(One intermediate revision by the same user not shown) |
Line 2: |
Line 2: |
| | number = ML112310086 | | | number = ML112310086 |
| | issue date = 08/18/2011 | | | issue date = 08/18/2011 |
| | title = Hatch Initial Exam 2011-301 General Correspondence | | | title = Initial Exam 2011-301 General Correspondence |
| | author name = | | | author name = |
| | author affiliation = NRC/RGN-II/DRS | | | author affiliation = NRC/RGN-II/DRS |
Line 16: |
Line 16: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:}} | | {{#Wiki_filter:Plant Hatch HLT-06 NRC Exam 2011-301 Seating Chart Classroom 172 Andy Beicher Russell Lewis Jimmy Collins Craig Moulton Kristi Taylor Rick Berry Phillip Cloud Kyle Routh Gary Brown Instructor Table Instructor Computer Station |
| | |
| | PROPOSES CHANGES TO QUESTIONS AFTER VALIDATION 3 Q#36 At 10:05 bullet, changed RB Bldg. to Rx. Bldg. for consistency in question. |
| | Reason; Editorial Q#37 Changed A Unit 2 is operating to Unit 2 is operating. |
| | Reason; Editorial Q#38 Changed Unit 2 is operating at 14% power when the following indications are observed: to: |
| | Unit 2 is operating at 14% power with RFPT 2A operating at 3600 rpm. |
| | The following indications are observed: |
| | Reason; If RFPT speed is <3500 rpm the RFPT will not trip on low vacuum, therefore stating the rpm value removes challenges later. |
| | Q#41 Changed 2 nd part from After the Main Turbine is tripped, without any additional to After the Main Turbine reaches zero (0) rpm, without any additional Reason; Define the time frame of Main Turbine speed to meet any permissive for auto start of TGOP, because TGOP will not start immediately since the Main Shaft Driven oil pump will still be providing oil. |
| | Q#64 Changed kV in 2 places to VAC. |
| | Reason; Editorial Q#79 Changed E21 to E41 in the D distractor. |
| | Reason; Editorial Q#80 Changed the l part from With 2A RFPT speed increasing to 5800 RPM, the response of 2N2 1-Fl 11.... to With 2A RFPT speed increasing to 5800 RPM, the above response of 2N2 1-Fl 11 Reason; We added the above response to 1 s1 part to ensure the applicant understands that we are talking about only these conditions, not how it would normally operate.}} |
Latest revision as of 16:55, 12 November 2019
Similar Documents at Hatch |
---|
Category:License-Operator
MONTHYEARML24005A1162024-01-0505 January 2024 301 Exam Comment 2 ML23206A0532023-07-25025 July 2023 2A, Exam Draft Items (Hatch 2021-301) ML23206A0332023-07-25025 July 2023 2B, Exam Administrative Items (Hatch 2021-301) NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. ML23123A2222023-05-0101 May 2023 Notification of Licensed Operator Initial Examination 05000321/2023301, and 05000366/2023301 ML21095A3132023-03-23023 March 2023 301 Final SRO Written Exam ML22213A0502022-08-0101 August 2022 2022 Requalification Program Inspection Notification Letter - Hatch Nuclear Station NL-22-0240, SNC Response to Regulatory Issue Summary 2022-01: Preparation and Scheduling of Operator Licensing Examinations2022-03-31031 March 2022 SNC Response to Regulatory Issue Summary 2022-01: Preparation and Scheduling of Operator Licensing Examinations ML21333A2762021-11-29029 November 2021 302 Exam Approval Letter ML21096A3312021-04-0505 April 2021 Corporate Notification Letter (Aka 210 Day) ML21095A3062021-04-0505 April 2021 301 Final RO Written Exam ML21057A2822021-02-24024 February 2021 301 Exam Approval Letter ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 NL-20-0265, SNC Response to Regulatory Issue Summary 2020-01: Preparation and Scheduling of Operator Licensing Examinations2020-03-16016 March 2020 SNC Response to Regulatory Issue Summary 2020-01: Preparation and Scheduling of Operator Licensing Examinations ML20007F7572020-01-0707 January 2020 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2020 ML19308A4592019-11-0404 November 2019 Exam Administrative Items (Normal Release) ML19275K8702019-10-0202 October 2019 301 Post Exam Comments ML19218A3792019-08-0606 August 2019 Operator Licensing Written Examination Approval 05000321/2019301 and 05000366/2019301 ML19099A2872019-04-0909 April 2019 2019 Schedule Confirmation for Hatch ML19018A0882019-01-17017 January 2019 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2019 NL-18-0550, Response to Regulatory Issue Summary 2018-02 - Preparation and Scheduling of Operator Licensing Examinations2018-04-23023 April 2018 Response to Regulatory Issue Summary 2018-02 - Preparation and Scheduling of Operator Licensing Examinations ML18057B0452018-02-26026 February 2018 NRC RO Written Exam with Answer Key and List of References (Delay Release 2 Yrs) ML18057B0512018-02-26026 February 2018 NRC SRO Written Exam with Answer Key and List of References (Delay Release 2 Yrs) ML18086B0442018-02-16016 February 2018 Facility Cover Letter - Rii - March 2018 - GFE ML18057B0802017-10-17017 October 2017 Operating Post Examination Comments NL-17-1767, Hatch 2017 301 Operating Post Examination Comments2017-10-17017 October 2017 Hatch 2017 301 Operating Post Examination Comments ML17187A2272017-07-0606 July 2017 Hat 2016-301 Exam Final Items - Delay Release 2 Yrs ML17187A2252017-07-0606 July 2017 Hat 2016-301 Exam Draft Items - Delay Release 2 Yrs ML17187A2292017-07-0606 July 2017 Hat 2016-301 Exam Administrative Items - Delay Release 2 Yrs ML17052A6842017-02-15015 February 2017 Notification of Licensed Operator Initial Examination 05000321/2017301 and 05000366/2017301 ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 IR 05000321/20163012016-09-0707 September 2016 NRC Operator License Examination Report 05000321/2016301 and 05000366/2016301 ML16214A1802016-08-0101 August 2016 Initial Exam 2016-301 Final RO Written Exam - Delay Release ML16214A1942016-08-0101 August 2016 Initial Exam 2016-301 Post Exam Comments - Delay Release ML16214A1892016-08-0101 August 2016 Initial Exam 2016-301 Final SRO Written - Delay Release ML16166A4392016-06-13013 June 2016 E.I. Hatch - Operator Licensing Written Examination Approval 05000321/2016301 and 05000366/2016301 ML15176A5702015-06-22022 June 2015 Initial Exam 2015-301 Final Simulator in Plant JPMs ML15176A5802015-06-22022 June 2015 Initial Exam 2015-301 Final Administrative JPMs ML15176A5432015-06-22022 June 2015 Initial Exam 2015-301 Final Simulator Scenarios ML15176A5412015-06-22022 June 2015 Initial Exam 2015-301 Final Administrative Documents ML15175A4632015-06-22022 June 2015 Initial Exam 2015-301 Draft Administrative JPMs ML15175A4622015-06-22022 June 2015 Initial Exam 2015-301 Draft Simulator In-plant JPMs ML15175A4582015-06-22022 June 2015 Initial Exam 2015-301 Draft Simulator Scenarios ML15175A4492015-06-22022 June 2015 Initial Exam 2015-301 Draft SRO Written Exam ML15175A4432015-06-22022 June 2015 Initial Exam 2015-301 Draft RO Written Exam ML15175A4292015-06-22022 June 2015 Initial Exam 2015-301 Draft Administrave Documents ML15223B3212015-05-21021 May 2015 Initial Exam 2011-301 Draft Simulator Scenarios ML15105A2902015-04-0909 April 2015 Initial Exam 2015-301 Final SRO Written Exam ML15105A2842015-04-0909 April 2015 Initial Exam 2015-301 Final RO Written Exam ML14344A3712014-12-0808 December 2014 Notification of Licensed Operator Initial Examination 05000321/05000321/2015301 and 05000366/2015301 2024-01-05
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML24005A1162024-01-0505 January 2024 301 Exam Comment 2 ML23206A0332023-07-25025 July 2023 2B, Exam Administrative Items (Hatch 2021-301) ML23206A0532023-07-25025 July 2023 2A, Exam Draft Items (Hatch 2021-301) NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. ML23123A2222023-05-0101 May 2023 Notification of Licensed Operator Initial Examination 05000321/2023301, and 05000366/2023301 ML21095A3132023-03-23023 March 2023 301 Final SRO Written Exam NL-22-0240, SNC Response to Regulatory Issue Summary 2022-01: Preparation and Scheduling of Operator Licensing Examinations2022-03-31031 March 2022 SNC Response to Regulatory Issue Summary 2022-01: Preparation and Scheduling of Operator Licensing Examinations ML21333A2762021-11-29029 November 2021 302 Exam Approval Letter ML21096A3312021-04-0505 April 2021 Corporate Notification Letter (Aka 210 Day) ML21095A3062021-04-0505 April 2021 301 Final RO Written Exam ML21057A2822021-02-24024 February 2021 301 Exam Approval Letter ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 NL-20-0265, SNC Response to Regulatory Issue Summary 2020-01: Preparation and Scheduling of Operator Licensing Examinations2020-03-16016 March 2020 SNC Response to Regulatory Issue Summary 2020-01: Preparation and Scheduling of Operator Licensing Examinations ML19308A4592019-11-0404 November 2019 Exam Administrative Items (Normal Release) ML19275K8702019-10-0202 October 2019 301 Post Exam Comments ML19218A3792019-08-0606 August 2019 Operator Licensing Written Examination Approval 05000321/2019301 and 05000366/2019301 ML19099A2872019-04-0909 April 2019 2019 Schedule Confirmation for Hatch NL-18-0550, Response to Regulatory Issue Summary 2018-02 - Preparation and Scheduling of Operator Licensing Examinations2018-04-23023 April 2018 Response to Regulatory Issue Summary 2018-02 - Preparation and Scheduling of Operator Licensing Examinations ML18057B0452018-02-26026 February 2018 NRC RO Written Exam with Answer Key and List of References (Delay Release 2 Yrs) ML18057B0512018-02-26026 February 2018 NRC SRO Written Exam with Answer Key and List of References (Delay Release 2 Yrs) ML18057B0802017-10-17017 October 2017 Operating Post Examination Comments NL-17-1767, Hatch 2017 301 Operating Post Examination Comments2017-10-17017 October 2017 Hatch 2017 301 Operating Post Examination Comments ML17187A2272017-07-0606 July 2017 Hat 2016-301 Exam Final Items - Delay Release 2 Yrs ML17187A2292017-07-0606 July 2017 Hat 2016-301 Exam Administrative Items - Delay Release 2 Yrs ML17187A2252017-07-0606 July 2017 Hat 2016-301 Exam Draft Items - Delay Release 2 Yrs ML17052A6842017-02-15015 February 2017 Notification of Licensed Operator Initial Examination 05000321/2017301 and 05000366/2017301 ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 IR 05000321/20163012016-09-0707 September 2016 NRC Operator License Examination Report 05000321/2016301 and 05000366/2016301 ML16214A1802016-08-0101 August 2016 Initial Exam 2016-301 Final RO Written Exam - Delay Release ML16214A1942016-08-0101 August 2016 Initial Exam 2016-301 Post Exam Comments - Delay Release ML16214A1892016-08-0101 August 2016 Initial Exam 2016-301 Final SRO Written - Delay Release ML15175A4622015-06-22022 June 2015 Initial Exam 2015-301 Draft Simulator In-plant JPMs ML15176A5802015-06-22022 June 2015 Initial Exam 2015-301 Final Administrative JPMs ML15176A5702015-06-22022 June 2015 Initial Exam 2015-301 Final Simulator in Plant JPMs ML15176A5432015-06-22022 June 2015 Initial Exam 2015-301 Final Simulator Scenarios ML15176A5412015-06-22022 June 2015 Initial Exam 2015-301 Final Administrative Documents ML15175A4632015-06-22022 June 2015 Initial Exam 2015-301 Draft Administrative JPMs ML15175A4582015-06-22022 June 2015 Initial Exam 2015-301 Draft Simulator Scenarios ML15175A4492015-06-22022 June 2015 Initial Exam 2015-301 Draft SRO Written Exam ML15175A4292015-06-22022 June 2015 Initial Exam 2015-301 Draft Administrave Documents ML15175A4432015-06-22022 June 2015 Initial Exam 2015-301 Draft RO Written Exam ML15223B3212015-05-21021 May 2015 Initial Exam 2011-301 Draft Simulator Scenarios ML15105A2842015-04-0909 April 2015 Initial Exam 2015-301 Final RO Written Exam ML14344A3712014-12-0808 December 2014 Notification of Licensed Operator Initial Examination 05000321/05000321/2015301 and 05000366/2015301 IR 05000321/20050002014-12-0808 December 2014 Edwin I. Hatch - Notification of Licensed Operator Initial Examination 05000321/05000321/2015301 and 05000366/2015301 ML13324A6022013-11-18018 November 2013 Initial Exam 2013-301 Final Simulator Scenarios ML13324A2102013-11-18018 November 2013 Initial Exam 2013-301 Draft Administrative Documents ML13324A2282013-11-18018 November 2013 Initial Exam 2013-301 Draft RO Written Exams ML13324A2612013-11-18018 November 2013 Initial Exam 2013-301 Draft SRO Written Exams ML13324A5982013-11-18018 November 2013 Initial Exam 2013-301 Final Sim IN-plant JPMs 2024-01-05
[Table view] |
Text
Plant Hatch HLT-06 NRC Exam 2011-301 Seating Chart Classroom 172 Andy Beicher Russell Lewis Jimmy Collins Craig Moulton Kristi Taylor Rick Berry Phillip Cloud Kyle Routh Gary Brown Instructor Table Instructor Computer Station
PROPOSES CHANGES TO QUESTIONS AFTER VALIDATION 3 Q#36 At 10:05 bullet, changed RB Bldg. to Rx. Bldg. for consistency in question.
Reason; Editorial Q#37 Changed A Unit 2 is operating to Unit 2 is operating.
Reason; Editorial Q#38 Changed Unit 2 is operating at 14% power when the following indications are observed: to:
Unit 2 is operating at 14% power with RFPT 2A operating at 3600 rpm.
The following indications are observed:
Reason; If RFPT speed is <3500 rpm the RFPT will not trip on low vacuum, therefore stating the rpm value removes challenges later.
Q#41 Changed 2 nd part from After the Main Turbine is tripped, without any additional to After the Main Turbine reaches zero (0) rpm, without any additional Reason; Define the time frame of Main Turbine speed to meet any permissive for auto start of TGOP, because TGOP will not start immediately since the Main Shaft Driven oil pump will still be providing oil.
Q#64 Changed kV in 2 places to VAC.
Reason; Editorial Q#79 Changed E21 to E41 in the D distractor.
Reason; Editorial Q#80 Changed the l part from With 2A RFPT speed increasing to 5800 RPM, the response of 2N2 1-Fl 11.... to With 2A RFPT speed increasing to 5800 RPM, the above response of 2N2 1-Fl 11 Reason; We added the above response to 1 s1 part to ensure the applicant understands that we are talking about only these conditions, not how it would normally operate.