ML112430301: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(3 intermediate revisions by the same user not shown) | |||
Line 2: | Line 2: | ||
| number = ML112430301 | | number = ML112430301 | ||
| issue date = 08/31/2011 | | issue date = 08/31/2011 | ||
| title = | | title = Supplemental Information Regarding Relocation of the TS Surveillance Frequencies | ||
| author name = Sanders C | | author name = Sanders C | ||
| author affiliation = NRC/NRR/DORL/LPLI-2 | | author affiliation = NRC/NRR/DORL/LPLI-2 | ||
| addressee name = Bartron W | | addressee name = Bartron W | ||
| addressee affiliation = Dominion Nuclear Connecticut, Inc | | addressee affiliation = Dominion Nuclear Connecticut, Inc | ||
| docket = 05000423 | | docket = 05000423 | ||
Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter:From: Sanders, Carleen Sent: Wednesday, August 31, 2011 12:33 PM To: 'William D Bartron' | {{#Wiki_filter:From: Sanders, Carleen Sent: Wednesday, August 31, 2011 12:33 PM To: 'William D Bartron' | ||
==Subject:== | ==Subject:== | ||
Millstone 3: | Millstone 3: Supplemental Information Regarding Request to Relocate the TS Surveillance Frequencies | ||
: Bill, Due to unforeseen circumstances (Hurricane Irene) over this past week, I understand that the equivalent of 3 business days were lost with respect to DNCs response to the request for supplemental information for the MPS3 acceptance review of LAR regarding relocation of TS surveillance frequencies. As such, I find it acceptable to extent the response date the equivalent of 3 business days. The new response date is September 12, 2011. | |||
Bill, | |||
Thank you, Carleen Sanders Millstone Project Manager 301-415-1603}} | Thank you, Carleen Sanders Millstone Project Manager 301-415-1603}} |
Latest revision as of 16:24, 12 November 2019
ML112430301 | |
Person / Time | |
---|---|
Site: | Millstone |
Issue date: | 08/31/2011 |
From: | Sanders C Plant Licensing Branch 1 |
To: | Bartron W Dominion Nuclear Connecticut |
Sandeers, Carleen, NRR/DORL, 415-1603 | |
References | |
Download: ML112430301 (1) | |
Text
From: Sanders, Carleen Sent: Wednesday, August 31, 2011 12:33 PM To: 'William D Bartron'
Subject:
Millstone 3: Supplemental Information Regarding Request to Relocate the TS Surveillance Frequencies
- Bill, Due to unforeseen circumstances (Hurricane Irene) over this past week, I understand that the equivalent of 3 business days were lost with respect to DNCs response to the request for supplemental information for the MPS3 acceptance review of LAR regarding relocation of TS surveillance frequencies. As such, I find it acceptable to extent the response date the equivalent of 3 business days. The new response date is September 12, 2011.
Thank you, Carleen Sanders Millstone Project Manager 301-415-1603