Letter Sequence Approval |
---|
|
|
MONTHYEARML21053A3422021-02-22022 February 2021 Proposed License Amendment Request to Clarify Shutdown Bank Technical Specification Requirements and Add Alternative Control Rod Position Monitoring Requirements Project stage: Request ML21084A0042021-03-25025 March 2021 3/25/2021 E-mail, Acceptance Review Determination, Proposed License Amendment Request to Revise Shutdown Bank TS Requirements and Add Alternate Control Rod Position Monitoring Requirements Project stage: Acceptance Review ML22020A4122022-01-11011 January 2022 1/11/2022 State Consultation E-mail, R. Guzman to J. Semancik Millstone Power Station, Unit 3 Planned Issuance of Amendment to Clarify Shutdown Bank TS and Add Alternate Control Rod Position Monitoring Requirements Project stage: Approval ML22007A1512022-02-16016 February 2022 Issuance of Amendment No. 282 Regarding Shutdown Bank Technical Specification Requirements and Alternate Control Rod Position Monitoring Requirements Project stage: Approval 2021-03-25
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24213A2602024-07-31031 July 2024 Request for Additional Information LAR to Support Implementation of Framatome Gaia Fuel ML24116A0112024-04-25025 April 2024 Acceptance Review Determination for Proposed Alternative Request IR-4-13 Regarding Steam Generator Channel Head Drain Modification ML24115A2622024-04-24024 April 2024 Acceptance Review Determination for Proposed Alternative Request IR-4-14 Regarding Pressurizer and Steam Generator Pressure-Retaining Welds and Full-Penetration Welded Nozzles ML24114A3192024-04-23023 April 2024 Acceptance Review Determination LAR to Extend Inspection Interval for Reactor Coolant Pump Flywheels (TSTF-421) Using the CLIIP ML24113A2502024-04-22022 April 2024 Request for Additional Information (e-mail 4/22/2024) License Renewal Commitment for Aging Management Program of Alloy 600 Components ML24092A1082024-04-0101 April 2024 3R22 RFO ISI Owners Activity Report Extension - NRC Staff Acknowledgement Email (4/1/2024) ML24065A3112024-03-0505 March 2024 Request for Additional Information (Redacted) (03/05/2025 E-mail from R. Guzman to S. Sinha) Framatome Gaia Fuel LOCA LAR ML24058A2322024-02-27027 February 2024 2/27/2024 E-mail from S. Sinha to R. Guzman P-8 Instrument Uncertainty in Support of LAR Framatome Gaia Fuel ML24032A4702024-02-0101 February 2024 Change in Estimated Review Schedule Revision to TS Design Features Section to Remove the Nine Mile Point Unit 3 Nuclear Project, LLC ML24024A2452024-01-24024 January 2024 1/24/2024 E-mail from R.Guzman to S.Sinha - Acknowledgement of Error in SE for Amendment No. 288 - Revision to Applicability Term for RCS Heatup and Cooldown Pressure-Temperature Limitations Figures ML24024A0202024-01-24024 January 2024 Correction to Safety Evaluation Associated Wit Amendment No. 288 - Revision to Applicability Term for RCS Heat-Up and Cooldown Pressure-Temperature Limitations Figures ML23326A0132023-11-22022 November 2023 Acceptance Review Determination LAR to Support Implementation of Framatome Gaia Fuel ML23318A0952023-11-14014 November 2023 Request for Additional Information (E-mail Dated 11/14/2023) LAR to Revise TSs Related to Framatome Gaia Fuel ML23317A0732023-11-13013 November 2023 Acceptance Review Determination - License Amendment Request Modification of TS SR 4.3.6.a ML23297A2312023-10-24024 October 2023 E-mail to File - Summary of September 13, 2023, Meeting with Dominion to Discuss Proposed LAR to Support Cycle Reloads Using Framatome Gaia Fuel ML23265A2302023-09-22022 September 2023 Acceptance Review Determination - License Amendment Request Revision to TS Design Features Section to Remove the Nine Mile Point Unit 3 Nuclear Project, LLC ML23258A0552023-08-31031 August 2023 Setup of Online Reference Portal and Audit Plan for the NRC Staff'S Review of LAR to Use Framatome Small Break and Realistic Large Break LOCA Methodologies (08/31/2023 e-mail) ML23199A2832023-07-18018 July 2023 Request for Additional Information (E-mail Dated 7/18/2023) LAR to Revise the Pressure-Temperature Limits ML23172A0752023-06-21021 June 2023 Acceptance Review Determination LAR to Revise TSs for Reactor Core Safety Limits, Fuel Assemblies, and COLR Related to Framatome Gaia Fuel ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23145A0052023-05-25025 May 2023 Acceptance Review Determination Exemption to Use Framatome Gaia Fuel Assemblies Containing Fuel Rods Fabricated with M5 Fuel Rod Cladding ML23145A0042023-05-25025 May 2023 Acceptance Review Determination LAR to Use Framatome Small Break and Realistic Large Break LOCA Methodologies ML23115A3022023-04-24024 April 2023 4/24/2023 E-mail from R.Guzman to S.Sinha - Acknowledgement of Error in Issuance of Amendments Adoption of TSTF-359, Increase Flexibility in Mode Restraints ML23089A1882023-03-29029 March 2023 Request for Additional Information (E-mail Dated 3/29/2023) Spring 2022 Steam Generator Tube Inspection Report ML23067A2162023-03-0707 March 2023 NRR E-mail Capture - RAI for North Anna, 1 & 2, Surry 1 & 2, Millstone, 2 & 3, Request for Approval of App. F Fleet Report DOM-NAF-2-P, Qual of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion VIPRE-D Computer Code ML23038A0152023-02-0707 February 2023 Acceptance Review Determination LAR to Revise the Applicability Term for RCS Heatup and Cooldown Pressure-Temperature Limitations Figures ML23024A1522023-01-24024 January 2023 Acceptance Review Determination LAR to Supplement Burnup Credit of Criticality Safety Analysis ML23018A0352023-01-17017 January 2023 NRR E-mail Capture - Acceptance Review for Fleet Report Re Appendix F of DOM-NAF-2-P (L-2022-LLT-0003) ML22320A5752022-11-16016 November 2022 E-mail to File - Summary of October 18, 2022, Meeting with Dominion to Discuss Requested Actions for Implementing Framatome Gaia Fuel ML22298A2052022-10-25025 October 2022 Acceptance Review Determination for Alternative Request for Extension of Examination Interval for Reactor Pressure Vessel Head Penetration Nozzles ML22292A3212022-10-19019 October 2022 Acceptance Review Determination for Alternative Request for Containment RSS Pump Periodic Verification Testing Program ML22297A1802022-10-0707 October 2022 Email Acknowledgement to Dominion Energy Nuclear Decommissioning Trust Fund Disbursement 30 Day Notification for Millstone Power Station Unit 1: Docket No 50-245 ML22278A0932022-10-0505 October 2022 E-mail to File - Summary of September 7, 2022, Meeting with Dominion to Discuss Proposed Supplement to the Spent Fuel Pool Criticality Safety Analysis (EPID L-2022-LRM-0059 ML22272A0332022-09-29029 September 2022 Memo E-mail to File - Summary of August 29, 2022, Meeting with Dominion to Discuss Proposed Alternative Request Post-peening follow-up Volumetric Exam of RPV Head Penetration Nozzle ML22252A1772022-09-0909 September 2022 Memo E-mail to File - Summary of August 9, 2022, Meeting with Dominion to Discuss Proposed Alternative Reqeust Recirculation Spray Pump Flow Testing (EPID L:2022-LRM-0057) ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22174A3552022-06-23023 June 2022 NRR E-mail Capture - Acceptance Review for Dominion Fleet LAR to Implement TSTF-554 (L-2022-LLA-0078) ML22123A0812022-05-0303 May 2022 Acceptance Review Determination for Proposed LAR for TS Change Applicable to TSTF-359, Increase Flexibility in Mode Restraints ML22069A7192022-03-10010 March 2022 E-mail from R. Guzman to S. Sinha - Millstone Unit 3 Steam Generator Outage Conference Call ML22020A4122022-01-11011 January 2022 1/11/2022 State Consultation E-mail, R. Guzman to J. Semancik Millstone Power Station, Unit 3 Planned Issuance of Amendment to Clarify Shutdown Bank TS and Add Alternate Control Rod Position Monitoring Requirements ML21348A7392021-12-14014 December 2021 E-mail - Acceptance Review Determination Alternative Request IR-4-09 for Use Alternative Brazed Joint Assessment Methodology for Class 3 Moderate Energy Piping ML21347A9412021-12-13013 December 2021 E-mail from R.Guzman to S.Sinha - Acknowledgement of Error in Safety Evaluation for Amendment No. 280 Measurement Uncertainy Recapture Power Uprate ML21334A1922021-11-30030 November 2021 NRR E-mail Capture - Audit Plan for Reactor Core Thermal-Hydraulics Using the VIPRE-D Appendix E Review ML21326A1502021-11-22022 November 2021 NRR E-mail Capture - Acceptance Review for Relocation of Unit Staff Requirements to the QAPD LAR (L-2021-LLA-0195) ML21306A3302021-11-0202 November 2021 NRR E-mail Capture - Acceptance Review for TSTF-569 LAR ML21297A0072021-10-19019 October 2021 E-mail from R. Guzman to S. Sinha - Acknowledgemnt of Error in SE for Millstone Power Station, Unit 3, Amendment No. 279 Addition of Analytical Methodology to the COLR for LBLOCA ML21286A7372021-10-13013 October 2021 Additional Element Included in the Implementation Plan for the Surry Fuel Melt Safety Limit (SL) LAR ML21223A3042021-08-11011 August 2021 Request for Withholding Information from Public Disclosure Proposed LAR to Add an Analytical Methodology to the COLR for a Large Break LOCA ML21200A2562021-07-19019 July 2021 7/19/2021 E-mail Pressurizer Steam Space Line Classification ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code 2024-07-31
[Table view] |
Text
From: Guzman, Richard To: Semancik, Jeffrey
Subject:
RE: Planned Issuance of Millstone Power Station, Unit 3 Proposed License Amendment to Clarify Shutdown Bank Technical Specification Requirements and Add Alternate Control Rod Position Monitoring Requirements (EPID L-2021-LLA-0023)
Date: Tuesday, January 11, 2022 10:08:00 AM Attachments: image001.png
- Jeff, Thanks for your reply. I agree that proposed amendment to TS 3.1.3.5 is a technical change and not administrative as the content of the TS limiting condition for operation (LCO), Actions and Surveillance requirements are being revised. The NRC staff considers the proposed change to TS 3.1.3.6 as administrative in nature in that it only revises the title of the TS requirement from Control Rod Insertion Limits," to "Control Bank Insertion Limits. The proposed revision to TS 3.1.3.6 does not change the technical content of LCO 3.1.3.6 for the rods (MPS3 TS page 3/4 1-27) or make any technical changes to the surveillance requirements governing the rods.
I appreciate your comments; it will be included for consideration in the staffs safety evaluation.
- Thanks, Rich Rich Guzman Sr. PM, Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Office: O-9C7 l Phone: (301) 415-1030 Richard.Guzman@nrc.gov From: Semancik, Jeffrey <Jeffrey.Semancik@ct.gov>
Sent: Monday, January 10, 2022 1:30 PM To: Guzman, Richard <Richard.Guzman@nrc.gov>
Subject:
[External_Sender] RE: Planned Issuance of Millstone Power Station, Unit 3 Proposed License Amendment to Clarify Shutdown Bank Technical Specification Requirements and Add Alternate Control Rod Position Monitoring Requirements (EPID L-2021-LLA-0023)
- Rich, I have reviewed the DENC proposed LA. I do not have any technical concerns or questions; however, in my opinion the proposed changes to 3.1.3.5 And 3.1.3.6 from individual rods to banks is a technical change not an administrative one. It is not a clarification, but rather a change from verifying each rod to verifying the bank demand.
V/R,
Jeff Jeffrey Semancik Director, Radiation Division Bureau of Air Management Connecticut Department of Energy and Environmental Protection 79 Elm Street, Hartford, CT 06106-5127 P: 860.424.4190 lC: 860.597.3628 lF: 860.706.5339 lE: jeffrey.semancik@ct.gov www.ct.gov/deep/radiation Conserving, improving and protecting our natural resources and environment; Ensuring a clean, affordable, reliable, and sustainable energy supply.
From: Guzman, Richard <Richard.Guzman@nrc.gov>
Sent: Friday, January 7, 2022 9:48 AM To: Semancik, Jeffrey <Jeffrey.Semancik@ct.gov>
Cc: Tifft, Doug <Doug.Tifft@nrc.gov>
Subject:
Planned Issuance of Millstone Power Station, Unit 3 Proposed License Amendment to Clarify Shutdown Bank Technical Specification Requirements and Add Alternate Control Rod Position Monitoring Requirements (EPID L-2021-LLA-0023)
EXTERNAL EMAIL: This email originated from outside of the organization. Do not click any links or open any attachments unless you trust the sender and know the content is safe.
Hello Jeff, The NRC staff is preparing the subject Millstone Unit 3 license amendment for issuance. A brief description of the license amendment request is provided below. Additional information can be found in the licensees submittal which is also referenced below by ADAMS Accession number.
Please let me know if you have any comments or questions regarding this licensing action by January 20th if possible. The projected issuance of this license amendment is by early to mid-February 2022.
Millstone Power Station, Unit No. 3 (MPS3) - License Amendment to Clarify Shutdown Bank Technical Specification Requirements and Add Alternate Control Rod Position Monitoring Requirements
Application Date:
February 22, 2021 (ADAMS Accession No. ML21053A342)
Brief Description of LAR:
The proposed license amendment would revise the MPS3 Technical Specification (TS) 3.1.3.2 to provide an alternative monitoring option for the condition where a maximum of one digital rod position indicator per bank is inoperable. Specifically, as an alternative to determining the position of the non-indicating rod(s) indirectly by the movable in-core detectors at a frequency of once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />, the change would allow rod position verification to be performed based on the occurrence of rod movement or power level change. This proposed revision is consistent with Technical Specification Task Force Traveler 547, Revision 1 (ADAMS Accession No. ML15365A610), and would provide alternate TS Actions to allow the position of the rod to be monitored by a means other than movable incore detectors. The proposed amendment would also revise TS 3.1.3.5 to replace shutdown "rods" with shutdown "banks," consistent with wording in the Standard TSs for Westinghouse Plants as provided in NUREG-1431, Revision 4 (ADAMS Accession No. ML12100A222). Finally, the proposed amendment would include administrative changes to revise the title of TS 3.1.3.6, to reflect that the requirements apply to control "banks," and modify TS 6.9.1.6.a and TS 6.9.1.6.b to cite the revised titles of TS 3.1.3.5 and TS 3.1.3.6.
FR Publish Date:
The LAR was published in the Federal Register (FR) on May 18, 2021 (86 FR 26953) https://www.govinfo.gov/content/pkg/FR-2021-05-18/pdf/2021-10374.pdf Thank you, Rich Guzman Sr. PM, Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Office: O-9C7 l Phone: (301) 415-1030 Richard.Guzman@nrc.gov