E-mail from R.Guzman to S.Sinha - Acknowledgement of Error in Safety Evaluation for Amendment No. 280 Measurement Uncertainy Recapture Power Uprate
ML21347A941
Person / Time
Site: Millstone Dominion icon.png
Issue date: 12/13/2021
From: Richard Guzman
NRC/NRR/DORL/LPL1
To: Sinha S
Dominion Energy Nuclear Connecticut
Guzman R
References
EPID L-2020-LLS-0002
Download: ML21347A941 (3)


Text

From: Guzman, Richard To: Shayan.Sinha@dominionenergy.com

Subject:

RE: FW: Millstone Power Station, Unit No. 3 - Issuance of Amendment No. 280 Regarding Measurement Uncertainty Recapture Power Uprate (EPID L-2020-LLS-0002)

Date: Monday, December 13, 2021 2:04:09 PM Attachments: image001.png

Shayan, The NRC staff understands your comment below and agrees that on page 80 of the safety evaluation under Section 3.4.2.2 (ADAMS Accession No. ML21262A001), the correct power factor for the main generator rating is 0.90, not 0.95. Please consider this e-mail communication as the staffs acknowledgement of the error. This e-mail will be added to ADAMS as an official agency record.
Thanks, Richard V. Guzman Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Office: O-9C7 l Phone: (301) 415-1030 Richard.Guzman@nrc.gov From: Shayan.Sinha@dominionenergy.com <Shayan.Sinha@dominionenergy.com>

Sent: Thursday, December 09, 2021 1:44 PM To: Guzman, Richard <Richard.Guzman@nrc.gov>

Subject:

[External_Sender] FW: Millstone Power Station, Unit No. 3 - Issuance of Amendment No.

280 Regarding Measurement Uncertainty Recapture Power Uprate (EPID L-2020-LLS-0002)

Rich, DENC has reviewed the Enclosure 2 Safety Evaluation for the subject Amendment, and had one comment. Section 3.4.2.2 states:

The upgraded MG will be rated for 1500 MVA at a power factor of 0.95 and will operate well below its upgraded capacity since Millstone 3 will be limited by its licensed RTP for the MUR power uprate.

The wording above is not consistent with Attachment 4,Section V.1.F.i of the LAR submittal, which states:

Upon implementation of the MUR Power Uprate, the generator nameplate rating will be 1500 MVA, 24 kV, 60 Hz, 0.90 power factor and 1800 rpm at 75 psig hydrogen pressure.

Please note that the DENC Response to EEEB-RAI-9 mentioned a power factor of 0.95, but this was only related to reactive loading at the point of interconnection. The wording in Safety Evaluation Section 3.4.2.2 pertains to Main Generator rating, which is based on a power factor of 0.90.

If you have any questions, please let me know.

Thanks, Shayan Shayan Sinha Dominion Energy Nuclear Regulatory Affairs Shayan.sinha@dominionenergy.com (804) 273-4687 From: nrc_mail_2-2 Resource <nrc_mail_2-2.Resource@nrc.gov>

Sent: Tuesday, November 9, 2021 2:23 PM To: Shayan Sinha (Services - 6) <shayan.sinha@dominionenergy.com>

Subject:

[EXTERNAL] Millstone Power Station, Unit No. 3 - Issuance of Amendment No. 280 Regarding Measurement Uncertainty Recapture Power Uprate (EPID L-2020-LLS-0002)

CAUTION! This message was NOT SENT from DOMINION ENERGY Are you expecting this message to your DE email? Suspicious? Use PhishAlarm to report the message. Open a browser and type in the name of the trusted website instead of clicking on links. DO NOT click links or open attachments until you verify with the sender using a known-good phone number. Never provide your DE password.

Subject:

Millstone Power Station, Unit No. 3 - Issuance of Amendment No. 280 Regarding Measurement Uncertainty Recapture Power Uprate (EPID L-2020-LLS-0002)

ADAMS Accession No.: ML21262A001 ADAMS Hyperlink: https://adamswebsearch2.nrc.gov/webSearch2/main.jsp?

AccessionNumber=ML21262A001 Using Web-based ADAMS, select Advanced Search Under Property, select Accession Number Under Value, enter the Accession Number Click Search The attached document is being sent to you per your request to receive electronic mailings, if you wish to be removed follow the instructions below. The document is publicly available and will be accessible via the public web site Electronic Reading Room in the Agency Document Access and Management System (ADAMS),

http://www.nrc.gov/reading-rm/adams.html , generally within six days. To access this document use the ADAMS number provided in this email.

Documents containing proprietary or safeguards information are not publicly available and will not be sent using the electronic mailing system.

You are currently subscribed to millstone as: shayan.sinha@dominionenergy.com .

To unsubscribe: Please go to the NRC's public website http://www.nrc.gov/public-involve/listserver/plants-by-region.html Once at the site, type in your e-mail address in the space provided and check the box(es) that correspond to the list(s) you would like to unsubscribe from. Then click the Unsubscribe button.

or send an email to lyris@nrc.gov with the following information in the subject line unsubscribe millstone shayan.sinha@dominionenergy.com CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect. The information is intended solely for the individual or entity named above and access by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of the contents of this information is prohibited and may be unlawful. If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.