ML061930417: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:July 19, 2006Mr. R. T. Ridenoure Vice President - Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
{{#Wiki_filter:July 19, 2006 Mr. R. T. Ridenoure Vice President - Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
Post Office Box 550 Fort Calhoun, NE 68023-0550
Post Office Box 550 Fort Calhoun, NE 68023-0550


==SUBJECT:==
==SUBJECT:==
FORT CALHOUN STATION, UNIT 1 - REQUEST FOR ADDITIONALINFORMATION (RAI) RELATED TO REVISING THE FORT CALHOUN STATION UPDATED SAFETY ANALYSIS REPORT (TAC NO. MC8857)Dear Mr. Ridenoure
FORT CALHOUN STATION, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION (RAI) RELATED TO REVISING THE FORT CALHOUN STATION UPDATED SAFETY ANALYSIS REPORT (TAC NO. MC8857)
:By letter dated October 31, 2005, Omaha Public Power District (OPPD) submitted anamendment request to revise the Fort Calhoun Station, Unit 1, Updated Safety Analysis Reportfor the radiological consequences of events affected by the planned 2006 replacement of the steam generators and pressurizer.The U.S. Nuclear Regulatory Commission staff has reviewed OPPD's submittal and hasdetermined that additional information is needed to complete our review. A request for additional information is enclosed. This request was discussed with Thomas Matthews of your staff on July 5, 2006, and it was agreed that a response would be provided within 30 days of receipt of this letter.If you have any questions, please contact me at (301) 415-1445. Sincerely,
/RA/ Alan B. Wang, Project Manager  Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No.
50-285


==Enclosure:==
==Dear Mr. Ridenoure:==
RAIcc w/encl:  See next page July 19, 2006Mr. R. T. Ridenoure Vice President  - Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station  FC-2-4 Adm.
Post Office Box 550 Fort Calhoun, NE  68023-0550


==SUBJECT:==
By letter dated October 31, 2005, Omaha Public Power District (OPPD) submitted an amendment request to revise the Fort Calhoun Station, Unit 1, Updated Safety Analysis Report for the radiological consequences of events affected by the planned 2006 replacement of the steam generators and pressurizer.
FORT CALHOUN STATION, UNIT 1 - REQUEST FOR ADDITIONALINFORMATION (RAI) RELATED TO REVISING THE FORT CALHOUN STATION UPDATED SAFETY ANALYSIS REPORT (TAC NO. MC8857)Dear Mr. Ridenoure
The U.S. Nuclear Regulatory Commission staff has reviewed OPPDs submittal and has determined that additional information is needed to complete our review. A request for additional information is enclosed. This request was discussed with Thomas Matthews of your staff on July 5, 2006, and it was agreed that a response would be provided within 30 days of receipt of this letter.
:By letter dated October 31, 2005, Omaha Public Power District (OPPD) submitted anamendment request to revise the Fort Calhoun Station, Unit 1, Updated Safety Analysis Reportfor the radiological consequences of events affected by the planned 2006 replacement of the steam generators and pressurizer.The U.S. Nuclear Regulatory Commission staff has reviewed OPPD's submittal and hasdetermined that additional information is needed to complete our review. A request for additional information is enclosed. This request was discussed with Thomas Matthews of your staff on July 5, 2006, and it was agreed that a response would be provided within 30 days of receipt of this letter.If you have any questions, please contact me at (301) 415-1445. Sincerely,/RA/
If you have any questions, please contact me at (301) 415-1445.
Alan B. Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No.
Sincerely,
50-285
                                            /RA/
Alan B. Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285


==Enclosure:==
==Enclosure:==
RAIcc w/encl: See next pageDISTRIBUTION
RAI cc w/encl: See next page
:PUBLICLPLIV R/FRidsOgcRpRidsRgn4MailCenter(DGraves) RidsNrrLALFeizollahiRidsNrrPMAWangRidsAcrsAcnwMailCenterRidsNrrDorlLpl4 RidsNrrDorlDprADAMS ACCESSION NO.:  ML061930417OFFICELPL4/PMLPL4/LALPL4/BCNAMEAWangLFeizollahiDTeraoDATE07/17/0607/17/0607/19/06OFFICIAL RECORD COPY


REQUEST FOR ADDITIONAL INFORMATIONREGARDING UPDATED SAFETY ANALYSIS REPORTRADIOLOGICAL CONSEQUENCE ANALYSISOMAHA PUBLIC POWER DISTRICTFORT CALHOUN STATION, UNIT 1DOCKET NUMBER 50-285By letter dated October 31, 2005, Omaha Public Power District (OPPD) submitted anamendment request to revise the Fort Calhoun Station, Unit 1 (FCS), Updated Safety Analysis Report (USAR) for the radiological consequences of events affected by the planned 2006 replacement of the steam generator and pressurizer. The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed OPPD's submittal and has determined that the followingadditional information is needed to complete our review: 1.The NRC staff notes that the atmospheric dispersion factors (/Q values) provided in theOctober 31, 2005, license amendment request (LAR) are the same as those approved in the safety evaluation associated with FCS Amendment No. 201. Amendment No. 201 implements use of the alternative source term in the FCS design-basis accident dose assessments. Therefore, for each design-basis accident or event addressed in the October 31, 2005, LAR, please discuss any differences between the two sets of release scenarios. If there are differences, please justify how the differences do not impact the applicability of the /Q values associated with Amendment No. 201 to the doseassessment associated with the October 31, 2005, LAR.2.Which water mass inventories (both primary and secondary) were used in calculatingcoolant activities?  Please indicate if the used values are the minimum, nominal or maximum.3.The submitted S-RELAP5 analysis indicates 0 percent/0 percent fraction of failed/meltedfuel. Is this a change from the analysis of record?    4.Attachment 4 (AREVA document 86-5064251-00) describes the thermal-hydraulic inputin support of the consequence analysis. Please confirm that the main steam safety valves and atmospheric dump valves actuation setpoints used are those specified in thetechnical specifications.5.Presumably, the cumulative steam releases used in the Attachment 6 (Stone & Websterreport) came from the Attachment 4 (AREVA document). However, it is not immediately obvious which tables in Attachment 4 were used to generate Tables 7.6 - 7.9 in . Please clarify.
July 19, 2006 Mr. R. T. Ridenoure Vice President - Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
Post Office Box 550 Fort Calhoun, NE 68023-0550


April 2006Ft. Calhoun Station, Unit 1 cc:Winston & Strawn ATTN:  James R. Curtiss, Esq.
==SUBJECT:==
1700 K Street, N.W.
FORT CALHOUN STATION, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION (RAI) RELATED TO REVISING THE FORT CALHOUN STATION UPDATED SAFETY ANALYSIS REPORT (TAC NO. MC8857)
Washington, DC  20006-3817ChairmanWashington County Board of Supervisors


P.O. Box 466 Blair, NE  68008Mr. John Hanna, Resident InspectorU.S. Nuclear Regulatory Commission
==Dear Mr. Ridenoure:==


P.O. Box 310 Fort Calhoun, NE  68023Regional Administrator, Region IVU.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX  76011-4005Ms. Julia Schmitt, Manager Radiation Control Program Nebraska Health & Human Services R & L Public Health Assurance 301 Centennial Mall, South P.O. Box 95007 Lincoln, NE  68509-5007Mr. David J. Bannister, ManagerFort Calhoun Station Omaha Public Power District Fort Calhoun Station FC-1-1 Plant
By letter dated October 31, 2005, Omaha Public Power District (OPPD) submitted an amendment request to revise the Fort Calhoun Station, Unit 1, Updated Safety Analysis Report for the radiological consequences of events affected by the planned 2006 replacement of the steam generators and pressurizer.
The U.S. Nuclear Regulatory Commission staff has reviewed OPPDs submittal and has determined that additional information is needed to complete our review. A request for additional information is enclosed. This request was discussed with Thomas Matthews of your staff on July 5, 2006, and it was agreed that a response would be provided within 30 days of receipt of this letter.
If you have any questions, please contact me at (301) 415-1445.
Sincerely,
                                            /RA/
Alan B. Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285
 
==Enclosure:==
RAI cc w/encl: See next page DISTRIBUTION:
PUBLIC                  LPLIV R/F            RidsOgcRp                    RidsRgn4MailCenter(DGraves)
RidsNrrLALFeizollahi RidsNrrPMAWang          RidsAcrsAcnwMailCenter      RidsNrrDorlLpl4 RidsNrrDorlDpr ADAMS ACCESSION NO.: ML061930417 OFFICE              LPL4/PM                  LPL4/LA                  LPL4/BC NAME                AWang                    LFeizollahi              DTerao DATE                07/17/06                  07/17/06                07/19/06 OFFICIAL RECORD COPY


P.O. Box 550 Fort Calhoun, NE  68023-0550Mr. Joe L. McManisManager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
REQUEST FOR ADDITIONAL INFORMATION REGARDING UPDATED SAFETY ANALYSIS REPORT RADIOLOGICAL CONSEQUENCE ANALYSIS OMAHA PUBLIC POWER DISTRICT FORT CALHOUN STATION, UNIT 1 DOCKET NUMBER 50-285 By letter dated October 31, 2005, Omaha Public Power District (OPPD) submitted an amendment request to revise the Fort Calhoun Station, Unit 1 (FCS), Updated Safety Analysis Report (USAR) for the radiological consequences of events affected by the planned 2006 replacement of the steam generator and pressurizer. The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed OPPDs submittal and has determined that the following additional information is needed to complete our review:
: 1.      The NRC staff notes that the atmospheric dispersion factors (/Q values) provided in the October 31, 2005, license amendment request (LAR) are the same as those approved in the safety evaluation associated with FCS Amendment No. 201. Amendment No. 201 implements use of the alternative source term in the FCS design-basis accident dose assessments. Therefore, for each design-basis accident or event addressed in the October 31, 2005, LAR, please discuss any differences between the two sets of release scenarios. If there are differences, please justify how the differences do not impact the applicability of the /Q values associated with Amendment No. 201 to the dose assessment associated with the October 31, 2005, LAR.
: 2.      Which water mass inventories (both primary and secondary) were used in calculating coolant activities? Please indicate if the used values are the minimum, nominal or maximum.
: 3.      The submitted S-RELAP5 analysis indicates 0 percent/0 percent fraction of failed/melted fuel. Is this a change from the analysis of record?
: 4.      Attachment 4 (AREVA document 86-5064251-00) describes the thermal-hydraulic input in support of the consequence analysis. Please confirm that the main steam safety valves and atmospheric dump valves actuation setpoints used are those specified in the technical specifications.
: 5.      Presumably, the cumulative steam releases used in the Attachment 6 (Stone & Webster report) came from the Attachment 4 (AREVA document). However, it is not immediately obvious which tables in Attachment 4 were used to generate Tables 7.6 - 7.9 in Attachment 6. Please clarify.


P.O. Box 550 Fort Calhoun, NE  68023-0550Mr. Daniel K. McGheeBureau of Radiological Health Iowa Department of Public Health Lucas State Office Building, 5th Floor 321 East 12th Street Des Moines, IA 50319}}
Ft. Calhoun Station, Unit 1 cc:
Winston & Strawn                      Mr. Daniel K. McGhee ATTN: James R. Curtiss, Esq.          Bureau of Radiological Health 1700 K Street, N.W.                    Iowa Department of Public Health Washington, DC 20006-3817              Lucas State Office Building, 5th Floor 321 East 12th Street Chairman                              Des Moines, IA 50319 Washington County Board of Supervisors P.O. Box 466 Blair, NE 68008 Mr. John Hanna, Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 310 Fort Calhoun, NE 68023 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Ms. Julia Schmitt, Manager Radiation Control Program Nebraska Health & Human Services R & L Public Health Assurance 301 Centennial Mall, South P.O. Box 95007 Lincoln, NE 68509-5007 Mr. David J. Bannister, Manager Fort Calhoun Station Omaha Public Power District Fort Calhoun Station FC-1-1 Plant P.O. Box 550 Fort Calhoun, NE 68023-0550 Mr. Joe L. McManis Manager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
P.O. Box 550 Fort Calhoun, NE 68023-0550 April 2006}}

Latest revision as of 16:28, 23 November 2019

Request for Additional Information (RAI) Related to Revising the Fort Calhoun Station Updated Safety Analysis Report
ML061930417
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 07/19/2006
From: Wang A
NRC/NRR/ADRO/DORL/LPLIV
To: Ridenoure R
Omaha Public Power District
Wang A, NRR/DLPM, 415-1445
References
TAC MC8857
Download: ML061930417 (4)


Text

July 19, 2006 Mr. R. T. Ridenoure Vice President - Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

Post Office Box 550 Fort Calhoun, NE 68023-0550

SUBJECT:

FORT CALHOUN STATION, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION (RAI) RELATED TO REVISING THE FORT CALHOUN STATION UPDATED SAFETY ANALYSIS REPORT (TAC NO. MC8857)

Dear Mr. Ridenoure:

By letter dated October 31, 2005, Omaha Public Power District (OPPD) submitted an amendment request to revise the Fort Calhoun Station, Unit 1, Updated Safety Analysis Report for the radiological consequences of events affected by the planned 2006 replacement of the steam generators and pressurizer.

The U.S. Nuclear Regulatory Commission staff has reviewed OPPDs submittal and has determined that additional information is needed to complete our review. A request for additional information is enclosed. This request was discussed with Thomas Matthews of your staff on July 5, 2006, and it was agreed that a response would be provided within 30 days of receipt of this letter.

If you have any questions, please contact me at (301) 415-1445.

Sincerely,

/RA/

Alan B. Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285

Enclosure:

RAI cc w/encl: See next page

July 19, 2006 Mr. R. T. Ridenoure Vice President - Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

Post Office Box 550 Fort Calhoun, NE 68023-0550

SUBJECT:

FORT CALHOUN STATION, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION (RAI) RELATED TO REVISING THE FORT CALHOUN STATION UPDATED SAFETY ANALYSIS REPORT (TAC NO. MC8857)

Dear Mr. Ridenoure:

By letter dated October 31, 2005, Omaha Public Power District (OPPD) submitted an amendment request to revise the Fort Calhoun Station, Unit 1, Updated Safety Analysis Report for the radiological consequences of events affected by the planned 2006 replacement of the steam generators and pressurizer.

The U.S. Nuclear Regulatory Commission staff has reviewed OPPDs submittal and has determined that additional information is needed to complete our review. A request for additional information is enclosed. This request was discussed with Thomas Matthews of your staff on July 5, 2006, and it was agreed that a response would be provided within 30 days of receipt of this letter.

If you have any questions, please contact me at (301) 415-1445.

Sincerely,

/RA/

Alan B. Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285

Enclosure:

RAI cc w/encl: See next page DISTRIBUTION:

PUBLIC LPLIV R/F RidsOgcRp RidsRgn4MailCenter(DGraves)

RidsNrrLALFeizollahi RidsNrrPMAWang RidsAcrsAcnwMailCenter RidsNrrDorlLpl4 RidsNrrDorlDpr ADAMS ACCESSION NO.: ML061930417 OFFICE LPL4/PM LPL4/LA LPL4/BC NAME AWang LFeizollahi DTerao DATE 07/17/06 07/17/06 07/19/06 OFFICIAL RECORD COPY

REQUEST FOR ADDITIONAL INFORMATION REGARDING UPDATED SAFETY ANALYSIS REPORT RADIOLOGICAL CONSEQUENCE ANALYSIS OMAHA PUBLIC POWER DISTRICT FORT CALHOUN STATION, UNIT 1 DOCKET NUMBER 50-285 By letter dated October 31, 2005, Omaha Public Power District (OPPD) submitted an amendment request to revise the Fort Calhoun Station, Unit 1 (FCS), Updated Safety Analysis Report (USAR) for the radiological consequences of events affected by the planned 2006 replacement of the steam generator and pressurizer. The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed OPPDs submittal and has determined that the following additional information is needed to complete our review:

1. The NRC staff notes that the atmospheric dispersion factors (/Q values) provided in the October 31, 2005, license amendment request (LAR) are the same as those approved in the safety evaluation associated with FCS Amendment No. 201. Amendment No. 201 implements use of the alternative source term in the FCS design-basis accident dose assessments. Therefore, for each design-basis accident or event addressed in the October 31, 2005, LAR, please discuss any differences between the two sets of release scenarios. If there are differences, please justify how the differences do not impact the applicability of the /Q values associated with Amendment No. 201 to the dose assessment associated with the October 31, 2005, LAR.
2. Which water mass inventories (both primary and secondary) were used in calculating coolant activities? Please indicate if the used values are the minimum, nominal or maximum.
3. The submitted S-RELAP5 analysis indicates 0 percent/0 percent fraction of failed/melted fuel. Is this a change from the analysis of record?
4. Attachment 4 (AREVA document 86-5064251-00) describes the thermal-hydraulic input in support of the consequence analysis. Please confirm that the main steam safety valves and atmospheric dump valves actuation setpoints used are those specified in the technical specifications.
5. Presumably, the cumulative steam releases used in the Attachment 6 (Stone & Webster report) came from the Attachment 4 (AREVA document). However, it is not immediately obvious which tables in Attachment 4 were used to generate Tables 7.6 - 7.9 in Attachment 6. Please clarify.

Ft. Calhoun Station, Unit 1 cc:

Winston & Strawn Mr. Daniel K. McGhee ATTN: James R. Curtiss, Esq. Bureau of Radiological Health 1700 K Street, N.W. Iowa Department of Public Health Washington, DC 20006-3817 Lucas State Office Building, 5th Floor 321 East 12th Street Chairman Des Moines, IA 50319 Washington County Board of Supervisors P.O. Box 466 Blair, NE 68008 Mr. John Hanna, Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 310 Fort Calhoun, NE 68023 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Ms. Julia Schmitt, Manager Radiation Control Program Nebraska Health & Human Services R & L Public Health Assurance 301 Centennial Mall, South P.O. Box 95007 Lincoln, NE 68509-5007 Mr. David J. Bannister, Manager Fort Calhoun Station Omaha Public Power District Fort Calhoun Station FC-1-1 Plant P.O. Box 550 Fort Calhoun, NE 68023-0550 Mr. Joe L. McManis Manager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550 Fort Calhoun, NE 68023-0550 April 2006