ML19025A120: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(5 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML19025A120
| number = ML19025A120
| issue date = 01/24/2019
| issue date = 01/24/2019
| title = Calvert Cliffs, Fitzpatrick, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Response Organization Staffing
| title = NRR E-mail Capture - Calvert Cliffs, Fitzpatrick, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Response Organization Staffing
| author name = Purnell B A
| author name = Purnell B
| author affiliation = NRC/NRR/DORL/LPLIII
| author affiliation = NRC/NRR/DORL/LPLIII
| addressee name = Gropp R W
| addressee name = Gropp R
| addressee affiliation = Exelon Generation Co, LLC
| addressee affiliation = Exelon Generation Co, LLC
| docket = 05000220, 05000317, 05000318, 05000333, 05000410, 07200008, 07200012, 07201036
| docket = 05000220, 05000317, 05000318, 05000333, 05000410, 07200008, 07200012, 07201036
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST TO REVISE EMERGENCY RESPONSE ORGANIZATION STAFFING REQUIREMENTS CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2, JAMES A. FITZPATRICK NUCLEAR POWER PLANT, AND NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 DOCKET NOS. 50-317, 50-318, 72-8, 50-333, 72-012, 50-220, 50-410, AND 72-1036 By application dated August 31, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18249A096), Exelon Generation Company, LLC (Exelon, the licensee) submitted a license amendment request for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Calvert Cliffs); James A. FitzPatrick Nuclear Power Plant (FitzPatrick); and the Nine Mile Point Nuclear Station, Units 1 and 2 (NMP). The amendments would revise the emergency plans by changing the emergency response organization (ERO) staffing requirements for each of these facilities.
{{#Wiki_filter:NRR-DMPSPEm Resource From:                              Purnell, Blake Sent:                              Thursday, January 24, 2019 1:18 PM To:                                Gropp Jr, Richard W:(GenCo-Nuc)
Cc:                                Wrona, David; Gudger, David T:(GenCo-Nuc)


The U.S. Nuclear Regulatory Commission (NRC) has reviewed the application and determined that the information below is needed to complete its review.  
==Subject:==
Calvert Cliffs, FitzPatrick, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Response Organization Staffing (EPID L-2018-LLA-0240)
Attachments:                        Exelon NE ERO Staffing RAI.pdf Mr. Gropp:
By application dated August 31, 2018 (Agencywide Documents Access and Management System Accession No. ML18249A096), Exelon Generation Company, LLC submitted a license amendment request for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 James A. FitzPatrick Nuclear Power Plant; and the Nine Mile Point Nuclear Station, Units 1 and 2. The amendments would revise the emergency plans by changing the emergency response organization staffing requirements for each of these facilities.
The NRC staff has reviewed the application and determined that it needs additional information to complete its review.
A response to the attached request for additional information is requested to be provided within 30 days from the date of this email. If you have any questions, please contact me at (301) 415-1380.
Sincerely, Blake Purnell, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Docket Nos. 50-317, 50-318, 72-8, 50-333, 72-012, 50-220, 50-410, and 72-1036 OFFICE    NRR/DORL/LPL3/PM          NSIR/DPR/RDB/BC                NRR/DORL/LPL3/BC NAME      BPurnell                  JAnderson (MNorris for)        DWrona DATE      1/24/19                  1/18/19                        1/18/19 1


RAI-1 Enclosures 1, 2, and 3 of the application provided separate evaluations of the proposed changes for each site. Section 2.4 of each enclosure states, in part, that:
Hearing Identifier:    NRR_DMPS Email Number:          775 Mail Envelope Properties    (Blake.Purnell@nrc.gov20190124131801)
 
==Subject:==
Calvert Cliffs, FitzPatrick, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Response Organization Staffing (EPID L-2018-LLA-0240)
Sent Date:            1/24/2019 1:18:01 PM Received Date:        1/24/2019 1:18:01 PM From:                  Purnell, Blake Created By:            Blake.Purnell@nrc.gov Recipients:
"Wrona, David" <David.Wrona@nrc.gov>
Tracking Status: None "Gudger, David T:(GenCo-Nuc)" <David.Gudger@exeloncorp.com>
Tracking Status: None "Gropp Jr, Richard W:(GenCo-Nuc)" <Richard.Gropp@exeloncorp.com>
Tracking Status: None Post Office:
Files                          Size                        Date & Time MESSAGE                        1273                        1/24/2019 1:18:01 PM Exelon NE ERO Staffing RAI.pdf                            74214 Options Priority:                      Standard Return Notification:            No Reply Requested:                No Sensitivity:                    Normal Expiration Date:
Recipients Received:
 
REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST TO REVISE EMERGENCY RESPONSE ORGANIZATION STAFFING REQUIREMENTS CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2, JAMES A. FITZPATRICK NUCLEAR POWER PLANT, AND NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 DOCKET NOS. 50-317, 50-318, 72-8, 50-333, 72-012, 50-220, 50-410, AND 72-1036 By application dated August 31, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18249A096), Exelon Generation Company, LLC (Exelon, the licensee) submitted a license amendment request for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Calvert Cliffs); James A. FitzPatrick Nuclear Power Plant (FitzPatrick); and the Nine Mile Point Nuclear Station, Units 1 and 2 (NMP). The amendments would revise the emergency plans by changing the emergency response organization (ERO) staffing requirements for each of these facilities.
The U.S. Nuclear Regulatory Commission (NRC) has reviewed the application and determined that the information below is needed to complete its review.
 
===RAI-1===
Enclosures 1, 2, and 3 of the application provided separate evaluations of the proposed changes for each site. Section 2.4 of each enclosure states, in part, that:
Those ERO positions designated as Minimum Staffing in the [site] Emergency Plan are those required to activate their respective Emergency Response Facility (ERF). Specifically, these are the ERO positions that are the absolute minimum needed to implement the Emergency Plan (i.e., if any position or function is not staffed then the Emergency Plan may not be effectively implemented).
Those ERO positions designated as Minimum Staffing in the [site] Emergency Plan are those required to activate their respective Emergency Response Facility (ERF). Specifically, these are the ERO positions that are the absolute minimum needed to implement the Emergency Plan (i.e., if any position or function is not staffed then the Emergency Plan may not be effectively implemented).
Section 2.6 of each enclosure states, in part, that:  
Section 2.6 of each enclosure states, in part, that:
In addition, Exelon will institute a Minimum Staff drill to be conducted once per drill cycle. The drill will include participation from the Minimum Staff of the Emergency Operations Facility (EOF), the Joint Information Center (JIC), the Technical Support Center (TSC), and the Operations Support Center (OSC) from one of the affected Exelon stations which have implemented the approved ERO staffing change license amendment. This will allow Exelon to periodically demonstrate that the Standardized Emergency Plan continues to effectively implement the required Emergency Preparedness functions utilizing only the Minimum Staff defined in the Emergency Plan. Since the ERO Minimum Staff is the same for each station under the Exelon Standardized Emergency Plan, it is not necessary to perform the drill for each station in a drill cycle. The stations would select one station to demonstrate the effectiveness of the minimum staff


In addition, Exelon will institute a "Minimum Staff" drill to be conducted once per drill cycle. The drill will include participation from the Minimum Staff of the Emergency Operations Facility (EOF), the Joint Information Center (JIC), the Technical Support Center (TSC), and the Operations Support Center (OSC) from one of the affected Exelon stations which have implemented the approved ERO staffing change license amendment. This will allow Exelon to periodically demonstrate that the Standardized Emergency Plan continues to effectively implement the required Emergency Preparedness functions utilizing only the Minimum Staff defined in the Emergency Plan. Since the ERO Minimum Staff is the same for each station under the Exelon Standardized Emergency Plan, it is not necessary to perform the drill for each station in a drill cycle. The stations would select one station to demonstrate the effectiveness of the minimum staff ERO. Credit for the "Minimum Staff" drill will be given to all of the affected stations.
ERO. Credit for the Minimum Staff drill will be given to all of the affected stations.
Exelon has also submitted similar license amendment requests to change the ERO staffing requirements for its facilities in Illinois and Pennsylvania (ADAMS Package Accession Nos. ML18053A159 and ML18149A290). In a November 1, 2018 (ADAMS Accession No. ML18305B270), supplement to its license amendment request for its Pennsylvania facilities, Exelon stated, in part, that:
Exelon has also submitted similar license amendment requests to change the ERO staffing requirements for its facilities in Illinois and Pennsylvania (ADAMS Package Accession Nos. ML18053A159 and ML18149A290). In a November 1, 2018 (ADAMS Accession No. ML18305B270), supplement to its license amendment request for its Pennsylvania facilities, Exelon stated, in part, that:
Exelon will perform a Minimum Staff Drill for each Emergency Operations Facility once per drill cycle. Specifically, one site which utilizes the EOF will perform the drill and the other sites which share the EOF will take credit for the performance for that drill cycle. For example, if Limerick performs the Minimum Staff drill for the first drill cycle, then PBAPS would be able to take credit, but Exelon stations in Illinois or New York would not be able to credit the drill.
Exelon will perform a Minimum Staff Drill for each Emergency Operations Facility once per drill cycle. Specifically, one site which utilizes the EOF will perform the drill and the other sites which share the EOF will take credit for the performance for that drill cycle. For example, if Limerick performs the Minimum Staff drill for the first drill cycle, then PBAPS would be able to take credit, but Exelon stations in Illinois or New York would not be able to credit the drill.
Describe how Exelon plans to specifically evaluate the adequacy of the minimum staffing levels to perform required functions until full augmentation, with the proposed ERO staffing changes, to ensure continued effective implementation of the respective emergency plans for each site. Confirm that for Calvert Cliffs, FitzPatrick, and NMP that the minimum staffing drill will be performed at each EOF once per drill cycle, and that a site would not credit a drill conducted at another EOF.
Describe how Exelon plans to specifically evaluate the adequacy of the minimum staffing levels to perform required functions until full augmentation, with the proposed ERO staffing changes, to ensure continued effective implementation of the respective emergency plans for each site.
RAI-2 Section 2.6 of Enclosure 1, 2, and 3 to the application states, in part:
Confirm that for Calvert Cliffs, FitzPatrick, and NMP that the minimum staffing drill will be performed at each EOF once per drill cycle, and that a site would not credit a drill conducted at another EOF.
 
===RAI-2===
Section 2.6 of Enclosure 1, 2, and 3 to the application states, in part:
As part of the implementation of these changes, a confirmation of the capabilities of the final Minimum Staff personnel will be performed through an EP drill to demonstrate that no loss of function will result due to the changes in the ERO. Additionally, the NRC will be invited to observe the drill.
As part of the implementation of these changes, a confirmation of the capabilities of the final Minimum Staff personnel will be performed through an EP drill to demonstrate that no loss of function will result due to the changes in the ERO. Additionally, the NRC will be invited to observe the drill.
Confirm that the corresponding States and the Federal Emergency Management Agency will be invited to observe the drill, or explain why an invitation is not needed.}}
Confirm that the corresponding States and the Federal Emergency Management Agency will be invited to observe the drill, or explain why an invitation is not needed.}}

Latest revision as of 13:03, 2 February 2020

NRR E-mail Capture - Calvert Cliffs, Fitzpatrick, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Response Organization Staffing
ML19025A120
Person / Time
Site: Calvert Cliffs, Nine Mile Point, FitzPatrick  Constellation icon.png
Issue date: 01/24/2019
From: Blake Purnell
Plant Licensing Branch III
To: Gropp R
Exelon Generation Co
References
L-2018-LLA-0240
Download: ML19025A120 (4)


Text

NRR-DMPSPEm Resource From: Purnell, Blake Sent: Thursday, January 24, 2019 1:18 PM To: Gropp Jr, Richard W:(GenCo-Nuc)

Cc: Wrona, David; Gudger, David T:(GenCo-Nuc)

Subject:

Calvert Cliffs, FitzPatrick, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Response Organization Staffing (EPID L-2018-LLA-0240)

Attachments: Exelon NE ERO Staffing RAI.pdf Mr. Gropp:

By application dated August 31, 2018 (Agencywide Documents Access and Management System Accession No. ML18249A096), Exelon Generation Company, LLC submitted a license amendment request for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 James A. FitzPatrick Nuclear Power Plant; and the Nine Mile Point Nuclear Station, Units 1 and 2. The amendments would revise the emergency plans by changing the emergency response organization staffing requirements for each of these facilities.

The NRC staff has reviewed the application and determined that it needs additional information to complete its review.

A response to the attached request for additional information is requested to be provided within 30 days from the date of this email. If you have any questions, please contact me at (301) 415-1380.

Sincerely, Blake Purnell, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Docket Nos. 50-317, 50-318, 72-8, 50-333,72-012, 50-220, 50-410, and 72-1036 OFFICE NRR/DORL/LPL3/PM NSIR/DPR/RDB/BC NRR/DORL/LPL3/BC NAME BPurnell JAnderson (MNorris for) DWrona DATE 1/24/19 1/18/19 1/18/19 1

Hearing Identifier: NRR_DMPS Email Number: 775 Mail Envelope Properties (Blake.Purnell@nrc.gov20190124131801)

Subject:

Calvert Cliffs, FitzPatrick, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Response Organization Staffing (EPID L-2018-LLA-0240)

Sent Date: 1/24/2019 1:18:01 PM Received Date: 1/24/2019 1:18:01 PM From: Purnell, Blake Created By: Blake.Purnell@nrc.gov Recipients:

"Wrona, David" <David.Wrona@nrc.gov>

Tracking Status: None "Gudger, David T:(GenCo-Nuc)" <David.Gudger@exeloncorp.com>

Tracking Status: None "Gropp Jr, Richard W:(GenCo-Nuc)" <Richard.Gropp@exeloncorp.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 1273 1/24/2019 1:18:01 PM Exelon NE ERO Staffing RAI.pdf 74214 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received:

REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST TO REVISE EMERGENCY RESPONSE ORGANIZATION STAFFING REQUIREMENTS CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2, JAMES A. FITZPATRICK NUCLEAR POWER PLANT, AND NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 DOCKET NOS. 50-317, 50-318, 72-8, 50-333,72-012, 50-220, 50-410, AND 72-1036 By application dated August 31, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18249A096), Exelon Generation Company, LLC (Exelon, the licensee) submitted a license amendment request for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Calvert Cliffs); James A. FitzPatrick Nuclear Power Plant (FitzPatrick); and the Nine Mile Point Nuclear Station, Units 1 and 2 (NMP). The amendments would revise the emergency plans by changing the emergency response organization (ERO) staffing requirements for each of these facilities.

The U.S. Nuclear Regulatory Commission (NRC) has reviewed the application and determined that the information below is needed to complete its review.

RAI-1

Enclosures 1, 2, and 3 of the application provided separate evaluations of the proposed changes for each site. Section 2.4 of each enclosure states, in part, that:

Those ERO positions designated as Minimum Staffing in the [site] Emergency Plan are those required to activate their respective Emergency Response Facility (ERF). Specifically, these are the ERO positions that are the absolute minimum needed to implement the Emergency Plan (i.e., if any position or function is not staffed then the Emergency Plan may not be effectively implemented).

Section 2.6 of each enclosure states, in part, that:

In addition, Exelon will institute a Minimum Staff drill to be conducted once per drill cycle. The drill will include participation from the Minimum Staff of the Emergency Operations Facility (EOF), the Joint Information Center (JIC), the Technical Support Center (TSC), and the Operations Support Center (OSC) from one of the affected Exelon stations which have implemented the approved ERO staffing change license amendment. This will allow Exelon to periodically demonstrate that the Standardized Emergency Plan continues to effectively implement the required Emergency Preparedness functions utilizing only the Minimum Staff defined in the Emergency Plan. Since the ERO Minimum Staff is the same for each station under the Exelon Standardized Emergency Plan, it is not necessary to perform the drill for each station in a drill cycle. The stations would select one station to demonstrate the effectiveness of the minimum staff

ERO. Credit for the Minimum Staff drill will be given to all of the affected stations.

Exelon has also submitted similar license amendment requests to change the ERO staffing requirements for its facilities in Illinois and Pennsylvania (ADAMS Package Accession Nos. ML18053A159 and ML18149A290). In a November 1, 2018 (ADAMS Accession No. ML18305B270), supplement to its license amendment request for its Pennsylvania facilities, Exelon stated, in part, that:

Exelon will perform a Minimum Staff Drill for each Emergency Operations Facility once per drill cycle. Specifically, one site which utilizes the EOF will perform the drill and the other sites which share the EOF will take credit for the performance for that drill cycle. For example, if Limerick performs the Minimum Staff drill for the first drill cycle, then PBAPS would be able to take credit, but Exelon stations in Illinois or New York would not be able to credit the drill.

Describe how Exelon plans to specifically evaluate the adequacy of the minimum staffing levels to perform required functions until full augmentation, with the proposed ERO staffing changes, to ensure continued effective implementation of the respective emergency plans for each site.

Confirm that for Calvert Cliffs, FitzPatrick, and NMP that the minimum staffing drill will be performed at each EOF once per drill cycle, and that a site would not credit a drill conducted at another EOF.

RAI-2

Section 2.6 of Enclosure 1, 2, and 3 to the application states, in part:

As part of the implementation of these changes, a confirmation of the capabilities of the final Minimum Staff personnel will be performed through an EP drill to demonstrate that no loss of function will result due to the changes in the ERO. Additionally, the NRC will be invited to observe the drill.

Confirm that the corresponding States and the Federal Emergency Management Agency will be invited to observe the drill, or explain why an invitation is not needed.