ML24008A262

From kanterella
Jump to navigation Jump to search

Acceptance Review Determination for Relief Request I5R-12, Concerning Installation of a FSWOL on RPV Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld
ML24008A262
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 01/08/2024
From: Richard Guzman
NRC/NRR/DORL/LPL1
To: Tom Loomis
Constellation Energy Generation
References
EPID L-2023-LLR-0065
Download: ML24008A262 (1)


Text

From: Richard Guzman To: Loomis, Thomas R:(Constellation Nuclear)

Cc: RidsNRRLIC109 Resource; Reynolds, Ronnie J:(Constellation Nuclear)

Subject:

Nine Mile Point Nuclear Station, Unit No. 1 - Acceptance Review Determination: Relief Request I5R-12 [EPID: L-2023-LLR-0065]

Date: Monday, January 8, 2024 5:50:02 PM Mr. Loomis, By (32-WD-208)|letter dated December 4, 2023]] (ADAMS Accession No. ML23338A232), Constellation Energy Generation, LLC (the licensee) submitted Relief Request I5R-12, Revision 0, concerning the repair of the reactor pressure vessel recirculation inlet nozzle N2E safe end-to-nozzle dissimilar metal weld (32-WD-208) by installing a full structural weld overlay over the existing leakage barrier weld overlay at Nine Mile Nuclear Station, Unit No. 1.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this proposed licensing action. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR),

whenever a holder of an operating license under this part desires to amend the license, application for an amendment must be filed with the Commission fully describing the changes requested, and following, as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 130 hours0.0015 days <br />0.0361 hours <br />2.149471e-4 weeks <br />4.9465e-5 months <br /> to complete. The NRC staff expects to complete this review by July 8, 2024. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date (greater than a month) or significant changes in the forecasted hours (greater than 25%), the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may

occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

Please contact me if you have any questions. A copy of this email will be made publicly available in ADAMS.

Thanks, Rich Guzman Sr. PM, Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Office: O-9C7 l Phone: (301) 415-1030 Richard.Guzman@nrc.gov