{{#Wiki_filter:From:Thadani, Mohan To:Harding Jr, Thomas Cc:Roundtree, Amy
==Subject:==
Physical Security Plan Change Per 10 CFR 50.54(p)(2)
Date:Tuesday, August 21, 2012 10:25:00 AM Attachments:
image001.png Tom: By letter dated July 31, 2012 (Agencywide Documents Access and Management System (ADAMS)Accession No. ML12215AA119)
, Constellation Energy Nuclear Group (the licensee) submitted the R.E Ginna Nuclear Power Plant's Physical Security Plan (PSP), Training and Qualification Plan (T&QP), and Safeguards Contingency Plan (SCP), Revision 9. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure.
The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(p)(2).
The NRC staff has determined that the additional information requested below is needed for the NRC staff to complete its review. 10 CFR 50.54(p)(2)
CHANGES TO SECURITY PLAN CONSTELLATION ENERGY NUCLEAR GROUP R.E. GINNA NUCLEAR POWER PLANT DOCKET NOS. 50-244 LICENSE NOS DPR- 18  1. In section 11.3 of the PSP, the licensee describes protected area (PA) perimeterbarriers.
Describe the assessment capabilities in the areas where the PA perimeter barrier is comprised of buildings, walls, or roofs in accordance with 10 CFR 73.55(e)(8)(iv) and10 CFR 73.55(i)(3)(ii).
Additionally, the licensee should make appropriate changes during the next revision of the site's PSP to ensure the language clearly describes the assessment capabilities in areas where buildings, walls, or roofs comprise a portion of the PA barrier in accordance with 10 CFR 73.55(e)(8)(iv).
I will appreciate if your staff can provide a response to the above RAI.
Thank you for your support. Mohan C Thadani Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov}}

Revision as of 21:57, 1 August 2018

Physical Security Plan Change Per 10 CFR 50.54(p)(2)
ML12234A517
Person / Time
Site: Ginna Constellation icon.png
Issue date: 08/21/2012
From: Thadani M C
Plant Licensing Branch 1
To: Harding T
Constellation Energy Nuclear Group
Thadani M
References
Download: ML12234A517 (2)


Text

From:Thadani, Mohan To:Harding Jr, Thomas Cc:Roundtree, Amy

Subject:

Physical Security Plan Change Per 10 CFR 50.54(p)(2)

Date:Tuesday, August 21, 2012 10:25:00 AM Attachments:

image001.png Tom: By letter dated July 31, 2012 (Agencywide Documents Access and Management System (ADAMS)Accession No. ML12215AA119)

, Constellation Energy Nuclear Group (the licensee) submitted the R.E Ginna Nuclear Power Plant's Physical Security Plan (PSP), Training and Qualification Plan (T&QP), and Safeguards Contingency Plan (SCP), Revision 9. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure.

The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(p)(2).

The NRC staff has determined that the additional information requested below is needed for the NRC staff to complete its review. 10 CFR 50.54(p)(2)

CHANGES TO SECURITY PLAN CONSTELLATION ENERGY NUCLEAR GROUP R.E. GINNA NUCLEAR POWER PLANT DOCKET NOS. 50-244 LICENSE NOS DPR- 18 1. In section 11.3 of the PSP, the licensee describes protected area (PA) perimeterbarriers.

Describe the assessment capabilities in the areas where the PA perimeter barrier is comprised of buildings, walls, or roofs in accordance with 10 CFR 73.55(e)(8)(iv) and10 CFR 73.55(i)(3)(ii).

Additionally, the licensee should make appropriate changes during the next revision of the site's PSP to ensure the language clearly describes the assessment capabilities in areas where buildings, walls, or roofs comprise a portion of the PA barrier in accordance with 10 CFR 73.55(e)(8)(iv).

I will appreciate if your staff can provide a response to the above RAI.

Thank you for your support. Mohan C Thadani Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov