| {{#Wiki_filter:Christopher R. Costanzo P.O. Box 63Vice President-Nine Mile Point Lycoming, New York 13093315.349.5200315.349.1321 FaxCENG.a joint venture ofNINE MILE POINTNUCLEAR STATIONFebruary 27, 2013U.S. Nuclear Regulatory CommissionWashington, DC 20555-0001ATTENTION: Document Control Desk | | {{#Wiki_filter:Christopher R. Costanzo P.O. Box 63 Vice President-Nine Mile Point Lycoming, New York 13093 315.349.5200 315.349.1321 Fax CENG.a joint venture of NINE MILE POINT NUCLEAR STATION February 27, 2013 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTENTION: |
| | Document Control Desk |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| Nine Mile Point Nuclear StationUnit No. 1; Docket No. 50-220License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805,Performance-Based Standard for Fire Protection for Light Water Reactor ElectricGenerating Plants (2001 Edition) -Response to NRC Request for AdditionalInformation (TAC No. ME8899) | | Nine Mile Point Nuclear Station Unit No. 1; Docket No. 50-220 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) -Response to NRC Request for Additional Information (TAC No. ME8899) |
|
| |
|
| ==REFERENCES:== | | ==REFERENCES:== |
| (a) Letter from K. Langdon (NMPNS) to Document Control Desk (NRC), datedJune 11, 2012, License Amendment Request Pursuant to 10 CFR 50.90:Adoption of NFPA 805, Performance-Based Standard for Fire Protection forLight Water Reactor Electric Generating Plants (2001 Edition)(b) Letter from B. Vaidya (NRC) to K. Langdon (NMPNS), dated January 3, 2013,Nine Mile Point Nuclear Station, Unit No. 1 -Request for AdditionalInformation Regarding License Amendment Request for Adoption of NFPA 805(TAC No. ME8899)Nine Mile Point Nuclear Station, LLC (NMPNS) hereby transmits supplemental information requested bythe NRC in support of a previously submitted request for amendment to Nine Mile Point Unit 1 (NMP1)Renewed Operating License DPR-63. The initial request, dated June 11, 2012 (Reference a), proposed theadoption of a new risk-informed performance-based (RI-PB) fire protection licensing basis whichcomplies with the requirements in 10 CFR 50.48(a) and 10 CFR 50.48(c); the guidance in RegulatoryGuide (RG) 1.205, "Risk-Informed Performance-Based Fire Protection for Existing Light-Water NuclearPower Plants," Revision 1; and National Fire Protection Association (NFPA) 805, "Performance-BasedStandard for Fire Protection for Light Water Reactor Electric Generating Plants," 2001 Edition. | | (a) Letter from K. Langdon (NMPNS) to Document Control Desk (NRC), dated June 11, 2012, License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition)(b) Letter from B. Vaidya (NRC) to K. Langdon (NMPNS), dated January 3, 2013, Nine Mile Point Nuclear Station, Unit No. 1 -Request for Additional Information Regarding License Amendment Request for Adoption of NFPA 805 (TAC No. ME8899)Nine Mile Point Nuclear Station, LLC (NMPNS) hereby transmits supplemental information requested by the NRC in support of a previously submitted request for amendment to Nine Mile Point Unit 1 (NMP1)Renewed Operating License DPR-63. The initial request, dated June 11, 2012 (Reference a), proposed the adoption of a new risk-informed performance-based (RI-PB) fire protection licensing basis which complies with the requirements in 10 CFR 50.48(a) and 10 CFR 50.48(c); |
| Document Control DeskFebruary 27, 2013Page 2The supplemental information, provided in Enclosures 2 and 3 to this letter, responds to the request foradditional information (RAI) documented in the NRC's letter dated January 3, 2013 (Reference b). Asstated in Reference (b), NMPNS agreed to provide responses to all of the RAIs contained in Reference (b)by March 1, 2013, with the following exceptions: (1) the responses to Fire Protection Engineering RAI 05and Safe Shutdown / Circuit Analysis RAI 06 will be provided by March 31, 2013; and (2) the responsesto Safe Shutdown / Circuit Analysis RAIs 01, 03, and 07 will be provided by April 30, 2013.This supplemental information does not affect the No Significant Hazards Determination analysisprovided by NMPNS in Reference (a). Pursuant to 10 CFR 50.91(b)(1), NMPNS has provided a copy ofthis supplemental information to the appropriate state representative. The regulatory commitmentscontained in this letter are listed in Enclosure 1.Should you have any questions regarding the information in this submittal, please contact J. J. Dosa,Director Licensing, at (315) 349-5219.I declare under penalty of perjury that the foregoing is true and correct. Executed on February 27, 2013.Very truly yours,CRC/DEV | | the guidance in Regulatory Guide (RG) 1.205, "Risk-Informed Performance-Based Fire Protection for Existing Light-Water Nuclear Power Plants," Revision 1; and National Fire Protection Association (NFPA) 805, "Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants," 2001 Edition. |
| | Document Control Desk February 27, 2013 Page 2 The supplemental information, provided in Enclosures 2 and 3 to this letter, responds to the request for additional information (RAI) documented in the NRC's letter dated January 3, 2013 (Reference b). As stated in Reference (b), NMPNS agreed to provide responses to all of the RAIs contained in Reference (b)by March 1, 2013, with the following exceptions: |
| | (1) the responses to Fire Protection Engineering RAI 05 and Safe Shutdown / Circuit Analysis RAI 06 will be provided by March 31, 2013; and (2) the responses to Safe Shutdown / Circuit Analysis RAIs 01, 03, and 07 will be provided by April 30, 2013.This supplemental information does not affect the No Significant Hazards Determination analysis provided by NMPNS in Reference (a). Pursuant to 10 CFR 50.91(b)(1), NMPNS has provided a copy of this supplemental information to the appropriate state representative. |
| | The regulatory commitments contained in this letter are listed in Enclosure 1.Should you have any questions regarding the information in this submittal, please contact J. J. Dosa, Director Licensing, at (315) 349-5219.I declare under penalty of perjury that the foregoing is true and correct. Executed on February 27, 2013.Very truly yours, CRC/DEV |
|
| |
|
| ==Enclosures:== | | ==Enclosures:== |
| 1. List of Regulatory Commitments2. Nine Mile Point Unit 1 -Response to NRC Request for Additional InformationRegarding the Proposed Adoption of NFPA 805 (2001 Edition)3. Nine Mile Point Unit 1 -Revised LAR Attachment L, NFPA 805 Chapter 3Requirements for Approval (10 CFR 50.48(c)(2)(vii))cc: Regional Administrator, Region I, NRCProject Manager, NRCResident Inspector, NRCA. L. Peterson, NYSERDA | | : 1. List of Regulatory Commitments |
| }} | | : 2. Nine Mile Point Unit 1 -Response to NRC Request for Additional Information Regarding the Proposed Adoption of NFPA 805 (2001 Edition)3. Nine Mile Point Unit 1 -Revised LAR Attachment L, NFPA 805 Chapter 3 Requirements for Approval (10 CFR 50.48(c)(2)(vii)) |
| | cc: Regional Administrator, Region I, NRC Project Manager, NRC Resident Inspector, NRC A. L. Peterson, NYSERDA}} |
Letter Sequence Response to RAI |
---|
|
|
MONTHYEARML12170A8692012-06-30030 June 2012 Transition to 10 CFR 50.48(c) - NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition Project stage: Request ML12221A0152012-08-0808 August 2012 Issuance of Amendments License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants. Project stage: Approval ML12222A0292012-08-0909 August 2012 Correction to Acceptance Letter - Nine Mile Point Nuclear Station, Unit No. 1 - License Amendment Request Pursuant to 10CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generat Project stage: Acceptance Review ML12319A2632012-11-13013 November 2012 ME8899 Draft RAIs License Amendment Request to Adopt NFPA-805 Project stage: Draft RAI ML13064A4662013-02-27027 February 2013 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) - Response to NRC RAI Project stage: Response to RAI ML13092A1392013-03-27027 March 2013 Response to NRC Request for Additional Information on License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Response to RAI ML13127A3952013-04-30030 April 2013 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) - Response to NRC Rai. Part 1 of 3 Project stage: Response to RAI ML13127A3972013-04-30030 April 2013 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) - Response to NRC Rai. Part 2 of 3 Project stage: Response to RAI ML13127A3982013-04-30030 April 2013 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) - Response to NRC Rai. Part 3 of 3 Project stage: Response to RAI ML13282A6292013-10-0909 October 2013 ME8899, Second Round of Request for Additional Information (Rais) License Amendment Request (LAR) to Adopt NFPA-805 Project stage: RAI ML13281A0102013-10-0909 October 2013 Second Round of Request for Additional Information Regarding License Amendment Request for Adoption of NFPA 805 Project stage: RAI ML13347B1872013-12-0909 December 2013 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) - Response to Nrc...... Project stage: Request ML14024A4162014-01-22022 January 2014 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Ed.) - Response to NRC Request for Additional.. Project stage: Request ML14030A3772014-02-12012 February 2014 Third Round of Request for Additional Information Regarding License Amendment Request for Adoption of NFPA 805 Project stage: RAI ML14085A1612014-03-14014 March 2014 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) - Response to NRC Request For.. Project stage: Request ML14087A2742014-03-28028 March 2014 ISFSI, Nine Mile Point Units 1 & 2 and R. E. Ginna - Pending NRC Actions Requested by Constellation Energy Nuclear Group, LLC Project stage: Request ML14113A1752014-04-15015 April 2014 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) - Response to NRC RAI Project stage: Response to RAI ML14132A1992014-05-0909 May 2014 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) - Response to Nrc. Project stage: Request ML14149A3562014-05-23023 May 2014 License Amendment Request, Per 10CFR50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition)-Supplemental Information Regarding Fire PRA Mode Project stage: Supplement ML14181B0862014-06-30030 June 2014 (NMP1), ME8899, Email from Licensee to Confirm the Change from Nine Mile Point Nuclear Station LLC, to Exelon Generation LAR to Adopt NFPA 805 Project stage: Other ML14126A0032014-06-30030 June 2014 Issuance of Amendment Regarding Transition to a Risk-Informed, Performance-Based Fire Protection Program in Accordance with 10 CFR 50.48(c) Project stage: Approval 2013-04-30
[Table View] |
|
---|
Category:Letter
MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2890, Submittal of Revision 26 to the USAR and Reference Figures, 10 CFR 50.59 Evaluation Summary Report, TS Bases, TRM Requirements Manual Changes, and 10 CFR 54.37(b) Aging Management Review (Excludes Attachment 6)2024-10-0404 October 2024 Submittal of Revision 26 to the USAR and Reference Figures, 10 CFR 50.59 Evaluation Summary Report, TS Bases, TRM Requirements Manual Changes, and 10 CFR 54.37(b) Aging Management Review (Excludes Attachment 6) IR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24190A0012024-09-26026 September 2024 Issuance of Amendment Nos. 252 and 197 Regarding the Revision to Technical Specification Design Features Section to Remove Nine Mile Point Unit 3 Project Designation NMP1L3608, Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-09-20020 September 2024 Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3603, Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan2024-08-20020 August 2024 Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 ML24215A3002024-08-0202 August 2024 Operator Licensing Examination Approval ML24213A1412024-07-31031 July 2024 Requalification Program Inspection NMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation NMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024 Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations ML24198A0852024-07-16016 July 2024 Senior Reactor and Reactor Operator Initial License Examinations RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 NMP1L3591, Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request2024-05-18018 May 2024 Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request NMP1L3589, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-05-16016 May 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable NMP1L3582, 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 22024-05-15015 May 2024 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 2 ML24158A2052024-05-15015 May 2024 Annual Radioactive Environmental Operating Report IR 05000220/20240012024-05-10010 May 2024 Integrated Inspection Report 05000220/2024001 and 05000410/2024001 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds 05000410/LER-2024-001, Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum2024-05-0101 May 2024 Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum NMP1L3581, Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report2024-04-30030 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2877, 2023 Annual Environmental Operating Report2024-04-19019 April 2024 2023 Annual Environmental Operating Report NMP2L2878, Core Operating Limits Report2024-04-16016 April 2024 Core Operating Limits Report ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24092A3352024-04-0101 April 2024 NRC Office of Investigations Case No. 1-2023-002 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24074A2812024-03-14014 March 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3577, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-03-13013 March 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable IR 05000220/20230062024-02-28028 February 2024 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2, (Reports 05000220/2023006 and 05000410/2023006) NMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 05000410/LER-2023-001, Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater2024-01-30030 January 2024 Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000220/LER-2023-002, Average Power Range Monitors Declared Inoperable Due to Trip of Reactor Recirculation Pump 122023-12-15015 December 2023 Average Power Range Monitors Declared Inoperable Due to Trip of Reactor Recirculation Pump 12 IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 2024-09-04
[Table view] |
Text
Christopher R. Costanzo P.O. Box 63 Vice President-Nine Mile Point Lycoming, New York 13093 315.349.5200 315.349.1321 Fax CENG.a joint venture of NINE MILE POINT NUCLEAR STATION February 27, 2013 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTENTION:
Document Control Desk
SUBJECT:
Nine Mile Point Nuclear Station Unit No. 1; Docket No. 50-220 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) -Response to NRC Request for Additional Information (TAC No. ME8899)
REFERENCES:
(a) Letter from K. Langdon (NMPNS) to Document Control Desk (NRC), dated June 11, 2012, License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition)(b) Letter from B. Vaidya (NRC) to K. Langdon (NMPNS), dated January 3, 2013, Nine Mile Point Nuclear Station, Unit No. 1 -Request for Additional Information Regarding License Amendment Request for Adoption of NFPA 805 (TAC No. ME8899)Nine Mile Point Nuclear Station, LLC (NMPNS) hereby transmits supplemental information requested by the NRC in support of a previously submitted request for amendment to Nine Mile Point Unit 1 (NMP1)Renewed Operating License DPR-63. The initial request, dated June 11, 2012 (Reference a), proposed the adoption of a new risk-informed performance-based (RI-PB) fire protection licensing basis which complies with the requirements in 10 CFR 50.48(a) and 10 CFR 50.48(c);
the guidance in Regulatory Guide (RG) 1.205, "Risk-Informed Performance-Based Fire Protection for Existing Light-Water Nuclear Power Plants," Revision 1; and National Fire Protection Association (NFPA) 805, "Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants," 2001 Edition.
Document Control Desk February 27, 2013 Page 2 The supplemental information, provided in Enclosures 2 and 3 to this letter, responds to the request for additional information (RAI) documented in the NRC's letter dated January 3, 2013 (Reference b). As stated in Reference (b), NMPNS agreed to provide responses to all of the RAIs contained in Reference (b)by March 1, 2013, with the following exceptions:
(1) the responses to Fire Protection Engineering RAI 05 and Safe Shutdown / Circuit Analysis RAI 06 will be provided by March 31, 2013; and (2) the responses to Safe Shutdown / Circuit Analysis RAIs 01, 03, and 07 will be provided by April 30, 2013.This supplemental information does not affect the No Significant Hazards Determination analysis provided by NMPNS in Reference (a). Pursuant to 10 CFR 50.91(b)(1), NMPNS has provided a copy of this supplemental information to the appropriate state representative.
The regulatory commitments contained in this letter are listed in Enclosure 1.Should you have any questions regarding the information in this submittal, please contact J. J. Dosa, Director Licensing, at (315) 349-5219.I declare under penalty of perjury that the foregoing is true and correct. Executed on February 27, 2013.Very truly yours, CRC/DEV
Enclosures:
- 1. List of Regulatory Commitments
- 2. Nine Mile Point Unit 1 -Response to NRC Request for Additional Information Regarding the Proposed Adoption of NFPA 805 (2001 Edition)3. Nine Mile Point Unit 1 -Revised LAR Attachment L, NFPA 805 Chapter 3 Requirements for Approval (10 CFR 50.48(c)(2)(vii))
cc: Regional Administrator, Region I, NRC Project Manager, NRC Resident Inspector, NRC A. L. Peterson, NYSERDA