ML13092A139

From kanterella
Jump to navigation Jump to search

Response to NRC Request for Additional Information on License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants
ML13092A139
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 03/27/2013
From: Costanzo C
Constellation Energy Nuclear Group, EDF Group, Nine Mile Point
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML14119A079 List:
References
TAC ME8899
Download: ML13092A139 (2)


Text

Christopher R. Costanzo P.O. Box 63 Vice President-Nine Mile Point Lycoming, New York 13093 315.349.5200 315.349.1321 Fax CENG..

a joint venture of Energw  %'

NINE MILE POINT NUCLEAR STATION March 27, 2013 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTENTION: Document Control Desk

SUBJECT:

Nine Mile Point Nuclear Station Unit No. 1; Docket No. 50-220 License Amendment Request Pursuant to 10 CFR 50.90: Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) - Response to NRC Request for Additional Information (TAC No. ME8899)

REFERENCES:

(a) Letter from K. Langdon (NMPNS) to Document Control Desk (NRC), dated June 11, 2012, License Amendment Request Pursuant to 10 CFR 50.90:

Adoption of NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition)

(b) Letter from B. Vaidya (NRC) to K. Langdon (NMPNS), dated January 3, 2013, Nine Mile Point Nuclear Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request for Adoption of NFPA 805 (TAC No. ME8899)

Nine Mile Point Nuclear Station, LLC (NMPNS) hereby transmits supplemental information requested by the NRC in support of a previously submitted request for amendment to Nine Mile Point Unit 1 (NMP1)

Renewed Operating License DPR-63. The initial request, dated June 11, 2012 (Reference a), proposed the adoption of a new risk-informed performance-based (RI-PB) fire protection licensing basis which complies with the requirements in 10 CFR 50.48(a) and 10 CFR 50.48(c); the guidance in Regulatory Guide (RG) 1.205, "Risk-Informed Performance-Based Fire Protection for Existing Light-Water Nuclear Power Plants," Revision 1; and National Fire Protection Association (NFPA) 805, "Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants," 2001 Edition.

PiY

Document Control Desk March 27, 2013 Page 2 The supplemental information provided in Enclosure 1 to this letter responds to the following two requests for additional information (RAIs) documented in the NRC's letter dated January 3, 2013 (Reference b): Fire Protection Engineering RAI 05 and Safe Shutdown / Circuit Analysis RAI 06. As stated in Reference (b), NMPNS agreed to provide responses to these two RAIs by March 31, 2013. In addition, Enclosure 2 provides revisions to Attachment S of the license amendment request as submitted in Reference (a). The revisions modify the description of committed plant modifications summarized in Table S-1 of Attachment S based on ongoing reviews being performed to finalize the design changes.

This supplemental information does not affect the No Significant Hazards Determination analysis provided by NMPNS in Reference (a). Pursuant to 10 CFR 50.91 (b)(1), NMPNS has provided a copy of this supplemental information to the appropriate state representative. This letter contains no new regulatory commitments.

Should you have any questions regarding the information in this submittal, please contact J. J. Dosa, Director Licensing, at (315) 349-5219.

I declare under penalty of perjury that the foregoing is true and correct. Executed on March 27, 2013.

Very truly yours, CRC/DEV

Enclosures:

1. Nine Mile Point Unit 1 - Response to NRC Request for Additional Information Regarding the Proposed Adoption of NFPA 805 (2001 Edition)
2. Nine Mile Point Unit 1 - Revision to LAR Attachment S, Table S-1, Plant Modifications Committed cc: Regional Administrator, Region I, NRC Project Manager, NRC Resident Inspector, NRC A. L. Peterson, NYSERDA