ISFSI, Nine Mile Point Units 1 & 2 and R. E. Ginna - Pending NRC Actions Requested by Constellation Energy Nuclear Group, LLC
ML14087A274
Person / Time
Site: Calvert Cliffs, Nine Mile Point, Ginna  Constellation icon.png
Issue date: 03/28/2014
From: Jim Barstow
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
Download: ML14087A274 (2)


Text

March 28, 2014 u.s. Nuclear Regulatory Commission A TIN: Document Control Desk Washington, DC 20555

Subject:

Calvert Cliffs Nuclear Power Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-53 and DPR-69 NRC Docket Nos. 50-317 and 50-318 Calvert Cliffs Independent Spent Fuel Storage Installation Materials License No. SNM-2505 Docket No. 72-8 Nine Mile Point Nuclear Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-63 and NPF-69 NRC Docket Nos. 50-220 and 50-410 R. E. Ginna Nuclear Power Plant Renewed Facility Operating License No. DPR-18 NRC Docket No. 50-244 Pending NRC Actions Requested by Constellation Energy Nuclear Group, LLC

References:

(1)

NRC letter, Nadiyah S. Morgan (USNRC) to Mary G. Korsnick & Bryan P. Wright (CENG) "Order Approving Direct Transfer of Renewed Operating Licenses, Independent Spent Fuel Storage Installation License, and Conforming Amendments," dated March 24, 2014 (Calvert Cliffs Nuclear Power Plant)

(2)

NRC letter, Nadiyah S. Morgan (USNRC) to Mary G. Korsnick & Bryan P. Wright (CENG) "Order Approving Direct Transfer of Renewed Operating Licenses and Conforming License Amendments," dated March 25, 2014 (Nine Mile Point Nuclear Station)

(3)

NRC letter, Nadiyah S. Morgan (USNRC) to Mary G. Korsnick & Bryan P. Wright (CENG) "Order Approving Direct Transfer of Renewed Operating License and Conforming License Amendment," dated March 25, 2014 (Ginna Nuclear Power Plant)

In the Reference 1, 2 and 3 letters, the Nuclear Regulatory Commission (NRC) issued Orders approving the transfer of the above licenses from Constellation Energy Nuclear Group, LLC (CENG) to Exelon Generation Company, LLC (Exelon) and approving conforming amendments associated with these license transfers.

U. S. Nuclear Regulatory Commission March 28, 2014 Page 2 Prior to the license transfers, CENG made docketed submittals to the NRC that requested specific licensing actions, such as license amendment requests, relief requests, exemption requests, etc. Furthermore, in the application for the license transfers, Exelon stated that upon transfer of the licenses, Exelon would assume all current regulatory commitments made for these units. Accordingly, Exelon hereby adopts and endorses those docketed requests currently before the NRC for review and approval. Exelon requests that the NRC continue to process those pending actions on the schedules previously requested by CENG.

There are no new commitments or changes to existing commitments being made in this letter.

Should you have any questions regarding this matter, please contact David P. Helker at (610) 765-5525.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of March 2014.

Respectfully, a

Il\\hI1?, U-c~

James Barstow Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC cc:

Regional Administrator - NRC Region I Nadiyah S. Morgan NRC Project Manager, NRR - (CENG)

NRC Senior Resident Inspector - Calvert Cliffs Nuclear Power Plant NRC Senior Resident Inspector - Nine Mile Point Nuclear Station NRC Senior Resident Inspector - Ginna Nuclear Power Plant NRC Project Manager, NRR - Calvert Cliffs Nuclear Power Plant NRC Project Manager, NRR - Nine Mile Point Nuclear Station NRC Project Manager, NRR - Ginna Nuclear Power Plant