==SUBJECT:== | ==SUBJECT:== | ||
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION | SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION | ||
==Dear Mr. Mulligan:== | ==Dear Mr. Mulligan:== | ||
By letter dated October 28, 2011, Entergy Operations, Inc., submitted an application pursuant to Title 1 0 of the Code of Federal Regulations | By letter dated October 28, 2011, Entergy Operations, Inc., submitted an application pursuant to Title 1 0 of the Code of Federal Regulations ( 1 0 CFR) Part 51 and 1 0 CFR Part 54, to renew the Grand Gulf Nuclear Station, Unit 1 (GGNS), operating license NPF-29, for review by the U.S. Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the environmental review schedule for the GGNS license renewal review. Due to the current and projected workload of the NRC's publishing resources, the GGNS environmental review schedule has been updated to reflect a change in the date of the issuance of the draft supplemental environmental impact statement and subsequent environmental review milestones. | ||
( 1 0 CFR) Part 51 and 1 0 CFR Part 54, to renew the Grand Gulf Nuclear Station, Unit 1 (GGNS), operating license NPF-29, for review by the U.S. Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the environmental review schedule for the GGNS license renewal review. Due to the current and projected workload of the NRC's publishing resources, the GGNS environmental review schedule has been updated to reflect a change in the date of the issuance of the draft supplemental environmental impact statement and subsequent environmental review milestones. | |||
The revised schedule is enclosed. | The revised schedule is enclosed. | ||
If you have any questions related to this revised schedule, please contact Mr. David Drucker, senior project manager, for the review of the GGNS license renewal application, by telephone at 301-415-6223 or by e-mail at david.drucker@ | If you have any questions related to this revised schedule, please contact Mr. David Drucker, senior project manager, for the review of the GGNS license renewal application, by telephone at 301-415-6223 or by e-mail at david.drucker@ | ||
nrc.qov. | nrc.qov. Docket No. 50-416 | ||
Docket No. 50-416 | |||
==Enclosure:== | ==Enclosure:== | ||
Revised Schedule cc: Listserv Sincerely, | Revised Schedule cc: Listserv Sincerely, \;3---W-:Lub s *,Director Div ic;n of Lie se Renewal Office of Nuclear Reactor Regulation October 30, 2013 Mr. Kevin J. Mulligan Vice President, Site Entergy Operations, Inc. P.O. Box 756 Port Gibson, MS 39150 | ||
\;3---W-:Lub s *,Director Div ic;n of Lie se Renewal Office of Nuclear Reactor Regulation October 30, 2013 Mr. Kevin J. Mulligan Vice President, Site Entergy Operations, Inc. P.O. Box 756 Port Gibson, MS 39150 | |||
==SUBJECT:== | ==SUBJECT:== | ||
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION | SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION | ||
Line 46: | Line 41: | ||
The revised schedule is enclosed. | The revised schedule is enclosed. | ||
If you have any questions related to this revised schedule, please contact Mr. David Drucker, senior project manager, for the review of the GGNS license renewal application, by telephone at 301-415-6223 or by e-mail at david.drucker@ | If you have any questions related to this revised schedule, please contact Mr. David Drucker, senior project manager, for the review of the GGNS license renewal application, by telephone at 301-415-6223 or by e-mail at david.drucker@ | ||
nrc.qov. | nrc.qov. Docket No. 50-416 | ||
Docket No. 50-416 | |||
==Enclosure:== | ==Enclosure:== | ||
Line 54: | Line 48: | ||
See next page ADAMS Accession No | See next page ADAMS Accession No | ||
* ML 13297 A250 .. OFFICE LA:RPB2:DLR PM: RPB2:DLR NAME I King DDrucker DATE t 0/30/13 t 0/25/13 Sincerely, IRA! John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation | * ML 13297 A250 .. OFFICE LA:RPB2:DLR PM: RPB2:DLR NAME I King DDrucker DATE t 0/30/13 t 0/25/13 Sincerely, IRA! John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation | ||
*concurred via email BC:RPB2:DLR D:DLR BWittick Jlubinski 10/28/13 10/30/13 OFFICIAL RECORD COPY GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION SCHEDULE REVISION Milestone Schedule Receive license renewal application (LRA) 11/1/2011 Publish Federal Register notice (FAN) -LRA availability 11/2011 Publish FAN -acceptance/rejection and opportunity for hearing 12/2011 Publish FAN -environmental seeping meeting 12/2011 Audit-Seeping & Screening Methodology 1/9/2012 Audit-Aging Management Programs 1/23/2012 Public Meeting License Renewal Overview and Environmental Seeping 1/3112012 meeting Deadline for filing hearing requests and petitions for intervention 2/2012 Environmental seeping period ends 2/2012 Audit-Environmental 3/26/2012 Inspection-Regional 8/2012 Issue safety evaluation report (SER) with open items 1/2013 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee TBD meetina Issue draft supplemental environmental impact statement (SEIS) 1/2014 U.S. Environmental Protection Agency FRN Published-draft SEIS 2/2014 available for comment Public Meeting-draft SEIS meeting 3/2014 End of draft SEIS comment period 3/2014 Issue final SER TBD ACRS full committee meeting TBD Issue final SEIS 9/2014 U.S. Environmental Protection Agency FRN Published-availability of final 1 0/2014 SEIS Decision- | *concurred via email BC:RPB2:DLR D:DLR BWittick Jlubinski 10/28/13 10/30/13 OFFICIAL RECORD COPY GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION SCHEDULE REVISION Milestone Schedule Receive license renewal application (LRA) 11/1/2011 Publish Federal Register notice (FAN) -LRA availability 11/2011 Publish FAN -acceptance/rejection and opportunity for hearing 12/2011 Publish FAN -environmental seeping meeting 12/2011 Audit-Seeping & Screening Methodology 1/9/2012 Audit-Aging Management Programs 1/23/2012 Public Meeting License Renewal Overview and Environmental Seeping 1/3112012 meeting Deadline for filing hearing requests and petitions for intervention 2/2012 Environmental seeping period ends 2/2012 Audit-Environmental 3/26/2012 Inspection-Regional 8/2012 Issue safety evaluation report (SER) with open items 1/2013 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee TBD meetina Issue draft supplemental environmental impact statement (SEIS) 1/2014 U.S. Environmental Protection Agency FRN Published-draft SEIS 2/2014 available for comment Public Meeting-draft SEIS meeting 3/2014 End of draft SEIS comment period 3/2014 Issue final SER TBD ACRS full committee meeting TBD Issue final SEIS 9/2014 U.S. Environmental Protection Agency FRN Published-availability of final 1 0/2014 SEIS Decision-Director, Office of Nuclear Reactor Regulation TBD Commission decision (if hearing is granted) TBD Actual 11/1/2011 11/17/2011 12/27/2011 12/29/2011 1/9/2012 1/23/2012 1/31/2012 2/27/2012 2/27/2012 3/27/2012-3/29/2012 8/6/2012 1/2013 ENCLOSURE Letter to K. Mulligan From J. Lubinski dated October 30, 2013 | ||
TBD Actual 11/1/2011 11/17/2011 12/27/2011 12/29/2011 1/9/2012 1/23/2012 1/31/2012 2/27/2012 2/27/2012 3/27/2012-3/29/2012 8/6/2012 1/2013 ENCLOSURE Letter to K. Mulligan From J. Lubinski dated October 30, 2013 | |||
==SUBJECT:== | ==SUBJECT:== | ||
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION DISTRIBUTION: | SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION DISTRIBUTION: | ||
HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRapb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource JDaily DDrucker OW rona BMizuno, OGC AWang, DORL RSmith, RIV BRice, RIV DAIIen, RIV DMclntyre, OPA}} | HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRapb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource JDaily DDrucker OW rona BMizuno, OGC AWang, DORL RSmith, RIV BRice, RIV DAIIen, RIV DMclntyre, OPA}} |
Revision as of 20:56, 13 July 2018
ML13297A250 | |
Person / Time | |
---|---|
Site: | Grand Gulf |
Issue date: | 10/30/2013 |
From: | Lubinski J W Division of License Renewal |
To: | Kevin Mulligan Entergy Nuclear Generation Co |
Drucker D M, 415-6223 | |
References | |
Download: ML13297A250 (4) | |
Text
Mr. Kevin J. Mulligan Vice President, Site Entergy Operations, Inc. P.O. Box 756 Port Gibson, MS 39150 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 October 30, 2013
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION
Dear Mr. Mulligan:
By letter dated October 28, 2011, Entergy Operations, Inc., submitted an application pursuant to Title 1 0 of the Code of Federal Regulations ( 1 0 CFR) Part 51 and 1 0 CFR Part 54, to renew the Grand Gulf Nuclear Station, Unit 1 (GGNS), operating license NPF-29, for review by the U.S. Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the environmental review schedule for the GGNS license renewal review. Due to the current and projected workload of the NRC's publishing resources, the GGNS environmental review schedule has been updated to reflect a change in the date of the issuance of the draft supplemental environmental impact statement and subsequent environmental review milestones.
The revised schedule is enclosed.
If you have any questions related to this revised schedule, please contact Mr. David Drucker, senior project manager, for the review of the GGNS license renewal application, by telephone at 301-415-6223 or by e-mail at david.drucker@
nrc.qov. Docket No. 50-416
Enclosure:
Revised Schedule cc: Listserv Sincerely, \;3---W-:Lub s *,Director Div ic;n of Lie se Renewal Office of Nuclear Reactor Regulation October 30, 2013 Mr. Kevin J. Mulligan Vice President, Site Entergy Operations, Inc. P.O. Box 756 Port Gibson, MS 39150
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION
Dear Mr. Mulligan:
By letter dated October 28, 2011, Entergy Operations, Inc., submitted an application pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR) Part 51 and 10 CFR Part 54, to renew the Grand Gulf Nuclear Station, Unit 1 (GGNS), operating license NPF-29, for review by the U.S. Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the environmental review schedule for the GGNS license renewal review. Due to the current and projected workload of the NRC's publishing resources, the GGNS environmental review schedule has been updated to reflect a change in the date of the issuance ot the draft supplemental environmental impact statement and subsequent environmental review milestones.
The revised schedule is enclosed.
If you have any questions related to this revised schedule, please contact Mr. David Drucker, senior project manager, for the review of the GGNS license renewal application, by telephone at 301-415-6223 or by e-mail at david.drucker@
nrc.qov. Docket No. 50-416
Enclosure:
Revised Schedule cc: Listserv DISTRIBUTION:
See next page ADAMS Accession No
- ML 13297 A250 .. OFFICE LA:RPB2:DLR PM: RPB2:DLR NAME I King DDrucker DATE t 0/30/13 t 0/25/13 Sincerely, IRA! John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation
- concurred via email BC:RPB2:DLR D:DLR BWittick Jlubinski 10/28/13 10/30/13 OFFICIAL RECORD COPY GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION SCHEDULE REVISION Milestone Schedule Receive license renewal application (LRA) 11/1/2011 Publish Federal Register notice (FAN) -LRA availability 11/2011 Publish FAN -acceptance/rejection and opportunity for hearing 12/2011 Publish FAN -environmental seeping meeting 12/2011 Audit-Seeping & Screening Methodology 1/9/2012 Audit-Aging Management Programs 1/23/2012 Public Meeting License Renewal Overview and Environmental Seeping 1/3112012 meeting Deadline for filing hearing requests and petitions for intervention 2/2012 Environmental seeping period ends 2/2012 Audit-Environmental 3/26/2012 Inspection-Regional 8/2012 Issue safety evaluation report (SER) with open items 1/2013 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee TBD meetina Issue draft supplemental environmental impact statement (SEIS) 1/2014 U.S. Environmental Protection Agency FRN Published-draft SEIS 2/2014 available for comment Public Meeting-draft SEIS meeting 3/2014 End of draft SEIS comment period 3/2014 Issue final SER TBD ACRS full committee meeting TBD Issue final SEIS 9/2014 U.S. Environmental Protection Agency FRN Published-availability of final 1 0/2014 SEIS Decision-Director, Office of Nuclear Reactor Regulation TBD Commission decision (if hearing is granted) TBD Actual 11/1/2011 11/17/2011 12/27/2011 12/29/2011 1/9/2012 1/23/2012 1/31/2012 2/27/2012 2/27/2012 3/27/2012-3/29/2012 8/6/2012 1/2013 ENCLOSURE Letter to K. Mulligan From J. Lubinski dated October 30, 2013
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION DISTRIBUTION:
HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRapb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource JDaily DDrucker OW rona BMizuno, OGC AWang, DORL RSmith, RIV BRice, RIV DAIIen, RIV DMclntyre, OPA