| title = Applicant'S Answer Opposing Motion to Amend Contention Out of Time and Motion to Reopen the Record by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia
| title = Applicants Answer Opposing Motion to Amend Contention Out of Time and Motion to Reopen the Record by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia
| author name = Bessette P, Blair W, Lighty R
| author name = Bessette P, Blair W, Lighty R
| author affiliation = Dominion Energy Services, Inc, Morgan, Lewis & Bockius, LLP, Virginia Electric & Power Co (VEPCO)
| author affiliation = Dominion Energy Services, Inc, Morgan, Lewis & Bockius, LLP, Virginia Electric & Power Co (VEPCO)
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION
{{#Wiki_filter:UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
                                              )
In the Matter of:                            )
                                              )  Docket Nos. 50-338-SLR and VIRGINIA ELECTRIC AND POWER COMPANY )                          50-339-SLR and OLD DOMINION ELECTRIC COOPERATIVE )
                                              )  October 25, 2021 (North Anna Power Station, Units 1 & 2)      )
                                              )
APPLICANTS ANSWER OPPOSING MOTION TO AMEND CONTENTION OUT OF TIME AND MOTION TO REOPEN THE RECORD BY BEYOND NUCLEAR, SIERRA CLUB, AND ALLIANCE FOR PROGRESSIVE VIRGINIA William S. Blair, Esq.                  Paul M. Bessette, Esq.
DOMINION ENERGY SERVICES, INC.          Ryan K. Lighty, Esq.
MORGAN, LEWIS & BOCKIUS LLP Counsel for Virginia Electric and Power Company


TABLE OF CONTENTS I. INTRODUCTION ................................................................................................................... 1 II. PROCEDURAL HISTORY .................................................................................................... 3 III. THE COMMISSION SHOULD DENY THE MOTION BECAUSE MOVANTS HAVE NOT SATISFIED THE COMMISSIONS STRICT STANDARDS ......................... 4 A. The Motion Is Not Accompanied by an Affidavit ....................................................... 5 B. The Motion Is Untimely .............................................................................................. 6 C. The Motion Fails to Demonstrate That It Is Based on Any Information That Is Both New and Materially Different, Much Less That It Raises a Significant Environmental Issue .................................................................................................... 8 D. The Motion Fails to Demonstrate That the Board Would Have Reached a Materially Different Result or That the Previously-Rejected Contention Is Somehow Now Admissible ................................................................................................................. 10 IV. CONCLUSION...................................................................................................................... 12
BEFORE THE COMMISSION
 
)
In the Matter of: )
) Docket Nos. 50-338-SLR and VIRGINIA ELECTRIC AND POWER COMPANY ) 50-339-SLR and OLD DOMINION ELECTRIC COOPERATIVE )
) October 25, 2021 (North Anna Power Station, Units 1 & 2) )
)
 
APPLICANTS ANSWER OPPOSING MOTION TO AMEND CONTENTION OUT OF TIME AND MOTION TO REOPEN THE RECORD BY BEYOND NUCLEAR, SIERRA CLUB, AND ALLIANCE FOR PROGRESSIVE VIRGINIA
 
William S. Blair, Esq. Paul M. Bessette, Esq.
DOMINION ENERGY SERVICES, INC. Ryan K. Lighty, Esq.
MORGAN, LEWIS & BOCKIUS LLP
 
Counsel for Virginia Electric and Power Company
 
TABLE OF CONTENTS
 
I. INTRODUCTION................................................................................................................... 1 II. PROCEDURAL HISTORY.................................................................................................... 3 III. THE COMMISSION SHOULD DENY THE MOTION BECAUSE MOVANTS HAVE NOT SATISFIED THE COMMISSIONS STRICT STANDARDS......................... 4 A. The Motion Is Not Accompanied by an Affidavit....................................................... 5 B. The Motion Is Untimely.............................................................................................. 6 C. The Motion Fails to Demonstrate That It Is Based on Any Information That Is Both New and Materially Different, Much Less That It Raises a Significant Environmental Issue.................................................................................................... 8 D. The Motion Fails to Demonstrate That the Board Would Have Reached a Materially Different Result or That the Previously-Rejected Contention Is Somehow Now Admissible................................................................................................................. 10 IV. CONCLUSI ON...................................................................................................................... 12
 
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
 
BEFORE THE COMMISSION
 
)
In the Matter of: )
) Docket Nos. 50-338-SLR and VIRGINIA ELECTRIC AND POWER COMPANY ) 50-339-SLR and OLD DOMINION ELECTRIC COOPERATIVE )
) October 25, 2021 (North Anna Power Station, Units 1 & 2) )
)
 
APPLICANTS ANSWER OPPOSING MOTION TO AMEND CONTENTION OUT OF TIME AND MOTION TO REOPEN THE RECORD BY BEYOND NUCLEAR, SIERRA CLUB, AND ALLIANCE FOR PROGRESSIVE VIRGINIA
 
I. INTRODUCTION
 
Pursuant to 10 C.F.R. §§ 2.309(i)(1) and 2.323(c), and the U.S. Nuclear Regulatory
 
Commission (NRC) Secretarys Order of October 8, 2021,1 Virginia Electric and Power
 
Company (Dominion Virginia Power or Dominion), on behalf of itself and Old Dominion
 
Electric Cooperative (collectively, Applicants) submit this Answer opposing the combined
 
Motion filed by Beyond Nuclear, Inc., Sierra Club, Inc., and Alliance for a Progressive Virginia,
 
Inc. (collectively, Movants) for leave to amend their contention out of time (Motion for
 
Leave) and to reopen the record (Motion to Reopen) (collectively, the Motion).2
 
Movants previously petitioned to intervene, requested a hearing, and proffered one
 
proposed contention in the above-captioned proceeding. In LBP-21-4, issued March 29, 2021,
 
1 NRC Secretary Order at 1 (Oct. 8, 2021) (unpublished) (ML21281A250).


UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION
                                                                        )
In the Matter of:                                                    )
                                                                        )    Docket Nos. 50-338-SLR and VIRGINIA ELECTRIC AND POWER COMPANY )                                                    50-339-SLR and OLD DOMINION ELECTRIC COOPERATIVE )
                                                                        )    October 25, 2021 (North Anna Power Station, Units 1 & 2)                              )
                                                                        )
APPLICANTS ANSWER OPPOSING MOTION TO AMEND CONTENTION OUT OF TIME AND MOTION TO REOPEN THE RECORD BY BEYOND NUCLEAR, SIERRA CLUB, AND ALLIANCE FOR PROGRESSIVE VIRGINIA I.          INTRODUCTION Pursuant to 10 C.F.R. §§ 2.309(i)(1) and 2.323(c), and the U.S. Nuclear Regulatory Commission (NRC) Secretarys Order of October 8, 2021,1 Virginia Electric and Power Company (Dominion Virginia Power or Dominion), on behalf of itself and Old Dominion Electric Cooperative (collectively, Applicants) submit this Answer opposing the combined Motion filed by Beyond Nuclear, Inc., Sierra Club, Inc., and Alliance for a Progressive Virginia, Inc. (collectively, Movants) for leave to amend their contention out of time (Motion for Leave) and to reopen the record (Motion to Reopen) (collectively, the Motion).2 Movants previously petitioned to intervene, requested a hearing, and proffered one proposed contention in the above-captioned proceeding. In LBP-21-4, issued March 29, 2021, 1
NRC Secretary Order at 1 (Oct. 8, 2021) (unpublished) (ML21281A250).
2 Beyond Nuclear, Inc., Sierra Club, Inc., and Alliance for a Progressive Virginia, Inc. Motion to Amend Contention Out of Time and to Reopen the Record (Sept. 29, 2021) (ML21272A386) (Motion). Despite this caption, Movants do not seek to amend their previously-rejected contention. Rather, they only seek to amend its basis statement. As an initial matter, it is unclear whether the Commissions regulations provide for a motion to admit an amended basis statement for a rejected contention, and Movants cite no authority for doing so.
2 Beyond Nuclear, Inc., Sierra Club, Inc., and Alliance for a Progressive Virginia, Inc. Motion to Amend Contention Out of Time and to Reopen the Record (Sept. 29, 2021) (ML21272A386) (Motion). Despite this caption, Movants do not seek to amend their previously-rejected contention. Rather, they only seek to amend its basis statement. As an initial matter, it is unclear whether the Commissions regulations provide for a motion to admit an amended basis statement for a rejected contention, and Movants cite no authority for doing so.
the Atomic Safety and Licensing Board (Board) denied those requests, finding that the
proposed contention was inadmissible, and terminated the proceeding.3
The Motion asks to reopen the record of that terminated proceeding and for leave to
amend the basis statement of the rejected contention. The proposed amendment relates to
allegedly new information in the NRC Staffs August 2021 draft supplemental environmental
impact statement (DSEIS).4 As explained below, the Motion must be rejected because it fails
to satisfy the Commissions strict standards for reopening the record and contentions out of time.
The Motion could be diplomatically described... as less than optimally organized or
articulated.5 In more direct terms, the Motion consists primarily of a recitation of the
procedural posture of the case and repetition of Movants original arguments (which the Board
rejected). Movants provide only a cursory discussion of the relevant legal standards. The crux
of Movants argument (i.e., the factual predicate for the Motion and the additional basis
statement they seek to add) is an assertion that, in the DSEIS, the NRC Staff allegedly
announced a sweeping new regulatory position claiming that the NRC expects many design-
basis accidents to occur. However, the DSEIS says no such thing. In fact, it says the opposite.
As explained below, Movants strained reading of the DSEIS is wholly unsupported and does not
remotely satisfy the Commissions stringent re quirements for reopening and filing contentions
out of time. Even assuming arguendo that Movants reading of the DSEIS were correctand it


the Atomic Safety and Licensing Board (Board) denied those requests, finding that the proposed contention was inadmissible, and terminated the proceeding.3 The Motion asks to reopen the record of that terminated proceeding and for leave to amend the basis statement of the rejected contention. The proposed amendment relates to allegedly new information in the NRC Staffs August 2021 draft supplemental environmental impact statement (DSEIS).4 As explained below, the Motion must be rejected because it fails to satisfy the Commissions strict standards for reopening the record and contentions out of time.
clearly is notMovants offer no cogent explanation as to how this statement regarding design
The Motion could be diplomatically described . . . as less than optimally organized or articulated.5 In more direct terms, the Motion consists primarily of a recitation of the procedural posture of the case and repetition of Movants original arguments (which the Board rejected). Movants provide only a cursory discussion of the relevant legal standards. The crux of Movants argument (i.e., the factual predicate for the Motion and the additional basis statement they seek to add) is an assertion that, in the DSEIS, the NRC Staff allegedly announced a sweeping new regulatory position claiming that the NRC expects many design-basis accidents to occur. However, the DSEIS says no such thing. In fact, it says the opposite.
 
As explained below, Movants strained reading of the DSEIS is wholly unsupported and does not remotely satisfy the Commissions stringent requirements for reopening and filing contentions out of time. Even assuming arguendo that Movants reading of the DSEIS were correctand it clearly is notMovants offer no cogent explanation as to how this statement regarding design 3
3 Va. Elec. & Power Co. (North Anna Power Station, Units 1 & 2), LBP-21-04, 93 NRC __ (Mar. 29, 2021) (slip op.) (ML21088A364) as modified by the Licensing Boards Memorandum and Order (Correcting Text of Decision) (Mar. 31, 2021) (ML21090A099).
Va. Elec. & Power Co. (North Anna Power Station, Units 1 & 2), LBP-21-04, 93 NRC __ (Mar. 29, 2021) (slip op.) (ML21088A364) as modified by the Licensing Boards Memorandum and Order (Correcting Text of Decision) (Mar. 31, 2021) (ML21090A099).
4 NUREG-1437, Generic Environmen tal Impact Statement for License Renewal of Nuclear Plants, Supplement 7, Second Renewal, Regarding Subsequent License Renewal for North Anna Power Station Units 1 and 2, Draft Report for Comment (Aug. 2021) (ML21228A084) (DSEIS).
4 NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 7, Second Renewal, Regarding Subsequent License Renewal for North Anna Power Station Units 1 and 2, Draft Report for Comment (Aug. 2021) (ML21228A084) (DSEIS).
5 Crow Butte Res., Inc. (N. Trend Expansion Proj.), CLI-09-12, 69 NRC 535, 552 (2009) (citation omitted).
5 Crow Butte Res., Inc. (N. Trend Expansion Proj.), CLI-09-12, 69 NRC 535, 552 (2009) (citation omitted).
2


basis accidents is remotely relevant (much less material) to the previously-rejected contention, which referenced a beyond design basis event. Thus, for any or all of these reasons, the Motion should be summarily denied.
2 basis accidents is remotely relevant (much less material) to the previously-rejected contention,
II.         PROCEDURAL HISTORY On August 24, 2020, Applicants filed with the NRC a subsequent license renewal application (SLRA) to renew the operating licenses for North Anna Power Station, Units 1 and 2 (North Anna) for an additional 20-year period.6 On December 14, 2020, Movants filed their Petition seeking to intervene in this proceeding, requesting a hearing, and proposing a single contention challenging Applicants Environmental Report (ER).7 The proposed contention alleged that the ER and the NRCs license renewal Generic Environmental Impact Statement (GEIS)8 discussion of Design Basis Accidents failed to consider the environmental significance of a 2011 earthquake in Mineral, Virginia that exceeded North Annas seismic design basis.9 Because the analysis of this issue was conducted generically by the NRC in the GEIS, and those findings were codified in NRC regulations, Movants also requested a waiver under 10 C.F.R. § 2.335(b) to challenge those regulations (Waiver Request).10 Following 6
 
See Letter from M. Sartain, Virginia Electric and Power Company, to NRC Document Control Desk, Virginia Electric and Power Company, North Anna Power Station Units 1 and 2, Application for Subsequent Renewed Operating Licenses (Aug. 24, 2020) (Package ML20246G703). The application package contains multiple enclosures. The SLRA is Enclosure 3, which consists of two files: the Main Report and Appendices A-D (ML20246G696) and Appendix E, which is the Environmental Report (ER) (ML20246G698).
which referenced a beyond design basis event. Thus, for any or all of these reasons, the Motion
 
should be summarily denied.
 
II. PROCEDURAL HISTORY
 
On August 24, 2020, Applicants filed with the NRC a subsequent license renewal
 
application (SLRA) to renew the operating licenses for North Anna Power Station, Units 1 and
 
2 (North Anna) for an additional 20-year period.6 On December 14, 2020, Movants filed their
 
Petition seeking to intervene in this proceeding, requesting a hearing, and proposing a single
 
contention challenging Applicants Environmental Report (ER).7 The proposed contention
 
alleged that the ER and the NRCs license renewal Generic Environmental Impact Statement
 
(GEIS)8 discussion of Design Basis Accidents failed to consider the environmental
 
significance of a 2011 earthquake in Mineral, Virginia that exceeded North Annas seismic
 
design basis.9 Because the analysis of this issue was conducted generically by the NRC in the
 
GEIS, and those findings were codified in NRC regulations, Movants also requested a waiver
 
under 10 C.F.R. § 2.335(b) to challenge those regulations (Waiver Request).10 Following
 
6 See Letter from M. Sartain, Virginia Electric and Power Company, to NRC Document Control Desk, Virginia Electric and Power Company, North Anna Power Station Units 1 and 2, Application for Subsequent Renewed Operating Licenses (Aug. 24, 2020) (Package ML20246G703). The application package contains multiple enclosures. The SLRA is Enclosure 3, which consists of two files: the Main Report and Appendices A-D (ML20246G696) and Appendix E, which is the Environmental Report (ER) (ML20246G698).
7 See generally Hearing Request and Petition to Intervene by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia and Petition for Waiver of 10 C.F.R. §§ 51.53(c)(3)(i), 51.71(d), and 51.95(c)(1) to Allow Consideration of Category 1 NEPA Issues (Dec. 14, 2020) (ML20349D952) (Petition).
7 See generally Hearing Request and Petition to Intervene by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia and Petition for Waiver of 10 C.F.R. §§ 51.53(c)(3)(i), 51.71(d), and 51.95(c)(1) to Allow Consideration of Category 1 NEPA Issues (Dec. 14, 2020) (ML20349D952) (Petition).
8 See NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (May 1996); Vol. 1, Main Report (ML040690705) (1996 GEIS); NUREG-1437, Rev. 1, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (June 2013); Vol. 1, Main Report (ML13106A241)
8 See NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (May 1996); Vol. 1, Main Report (ML040690705) (1996 GEIS); NUREG-1437, Rev. 1, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (June 2013); Vol. 1, Main Report (ML13106A241)
(GEIS).
(GEIS).
9 Petition at 13-14.
9 Petition at 13-14.
10 Id. at 30-37.
10 Id. at 30-37.
3


briefing11 and oral argument,12 the ASLB denied the Hearing Request and the Waiver Request and terminated the proceeding.13 In doing so, the Board found that Petitioners challenge to the Design Basis Accidents issue misinterprets the scope of the GEIS because beyond design basis events (such as the Mineral earthquake) were evaluated under the GEIS Severe Accidents issue, which Petitioners failed to dispute.14 Movants filed an Appeal of LBP-21-04 on April 23, 2021,15 and Applicants and the Staff both filed briefs opposing that Appeal.16 On September 29, 2021, while the Appeal is pending before the Commission, Movants filed the instant Motion. On October 8, 2021, the NRC Secretary clarified that the deadline for Answers to the Motion was October 25, 2021.17 Applicants hereby timely file their Answer.
3 briefing11 and oral argument,12 the ASLB denied the Hearing Request and the Waiver Request
III.         THE COMMISSION SHOULD DENY THE MOTION BECAUSE MOVANTS HAVE NOT SATISFIED THE COMMISSIONS STRICT STANDARDS The Motion is subject to two sets of standards: those for motions to reopen, under 10 C.F.R. § 2.326, and those for contentions out of time, under 10 C.F.R. § 2.309(c). Given Movants submission of a combined Motion, the discussion below addresses these standards 11 Applicants Answer Opposing Request for Hearing, Petition to Intervene, and Petition for Waiver Submitted by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (Jan. 8, 2021) (ML21008A531)
 
and terminated the proceeding.13 In doing so, the Board found that Petitioners challenge to the
 
Design Basis Accidents issue misinterprets the scope of the GEIS because beyond design basis
 
events (such as the Mineral earthquake) were evaluated under the GEIS Severe Accidents issue,
 
which Petitioners failed to dispute.14 Movants filed an Appeal of LBP-21-04 on April 23,
 
2021,15 and Applicants and the Staff both filed briefs opposing that Appeal.16 On September 29,
 
2021, while the Appeal is pending before the Commission, Movants filed the instant Motion. On
 
October 8, 2021, the NRC Secretary clarified that the deadline for Answers to the Motion was
 
October 25, 2021.17 Applicants hereby timely file their Answer.
 
III. THE COMMISSION SHOULD DENY THE MOTION BECAUSE MOVANTS HAVE NOT SATISFIED THE COMMISSIONS STRICT STANDARDS
 
The Motion is subject to two sets of standards: those for motions to reopen, under
 
10 C.F.R. § 2.326, and those for contentions out of time, under 10 C.F.R. § 2.309(c). Given
 
Movants submission of a combined Motion, the discussion below addresses these standards
 
11 Applicants Answer Opposing Request for Hearing, Petition to Intervene, and Petition for Waiver Submitted by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (Jan. 8, 2021) (ML21008A531)
(Applicants Answer to Petition); NRC Staff Answer to Hearing Request, Petition to Intervene and Petition for Waiver Filed by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (Jan. 8, 20201)
(Applicants Answer to Petition); NRC Staff Answer to Hearing Request, Petition to Intervene and Petition for Waiver Filed by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (Jan. 8, 20201)
(ML21008A593); Reply by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia to Oppositions to Hearing Request and Waiver Petition (Jan. 15, 2021) (ML21015A605).
(ML21008A593); Reply by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia to Oppositions to Hearing Request and Waiver Petition (Jan. 15, 2021) (ML21015A605).
Line 64: Line 186:
(ML21049A129).
(ML21049A129).
13 North Anna, LBP-21-04, 93 NRC at __ (slip op. at 36).
13 North Anna, LBP-21-04, 93 NRC at __ (slip op. at 36).
14 Id. at __ (slip op. at 25).
14 Id. at __ (slip op. at 25).
15 Brief on Appeal of LBP-21-04 by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (Apr. 23, 2021) (ML21113A317) (Appeal).
15 Brief on Appeal of LBP-21-04 by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (Apr. 23, 2021) (ML21113A317) (Appeal).
16 Applicants Brief in Opposition to Appeal of LBP-21-4 by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (May 18, 2021) (ML21138A894); NRC Staffs Brief in Response to Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginias Appeal of LBP-21-4 (May 18, 2021) (ML21138A942).
16 Applicants Brief in Opposition to Appeal of LBP-21-4 by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (May 18, 2021) (ML21138A894); NRC Staffs Brief in Response to Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginias Appeal of LBP-21-4 (May 18, 2021) (ML21138A942).
17 NRC Secretary Order at 1 (Oct. 8, 2021) (unpublished) (ML21281A250).
17 NRC Secretary Order at 1 (Oct. 8, 2021) (unpublished) (ML21281A250).
4


jointly. As a general matter, the Commission considers reopening the record to be an extraordinary action.18 As a result, the Commission imposes a deliberately heavy burden upon a participant seeking to reopen a closed record.19 As the Commission noted, [t]he level of support required for a motion to reopen is greater than that required for a contention under the general admissibility requirements of 10 C.F.R. § 2.309(f)(1).20 Bare assertions and speculation, even those supplied by an expert in an affidavit, do not supply the requisite support for such motions.21 As explained below, noneand certainly not allof the standards applicable to the instant Motion are satisfied here.
4 jointly. As a general matter, the Commission considers reopening the record to be an
A.       The Motion Is Not Accompanied by an Affidavit Section 2.326(b) specifies that reopening motions must be:
 
extraordinary action.18 As a result, the Commission imposes a deliberately heavy burden
 
upon a participant seeking to reopen a closed record.19 As the Commission noted, [t]he level of
 
support required for a motion to reopen is greater than that required for a contention under the
 
general admissibility requirements of 10 C.F.R. § 2.309(f)(1).20 Bare assertions and
 
speculation, even those supplied by an expert in an affidavit, do not supply the requisite
 
support for such motions.21 As explained below, noneand certainly not allof the standards
 
applicable to the instant Motion are satisfied here.
 
A. The Motion Is Not Accompanied by an Affidavit
 
Section 2.326(b) specifies that reopening motions must be:
 
accompanied by affidavits that set forth the factual and/or technical bases for the movants claim that the criteria of paragraph (a) of this section have been satisfied. Affidavits must be given by competent individuals with knowledge of the facts alleged, or by experts in the disciplines appropriate to the issues raised. Evidence contained in affidavits must meet the admissibility standards of this subpart.
accompanied by affidavits that set forth the factual and/or technical bases for the movants claim that the criteria of paragraph (a) of this section have been satisfied. Affidavits must be given by competent individuals with knowledge of the facts alleged, or by experts in the disciplines appropriate to the issues raised. Evidence contained in affidavits must meet the admissibility standards of this subpart.
Each of the criteria must be separately addressed, with a specific explanation of why it has been met. When multiple allegations are involved, the movant must identify with particularity each issue it seeks to litigate and specify the factual and/or technical bases which it believes support the claim that this issue meets the criteria in paragraph (a) of this section.22 18 Entergy Nuclear Vt. Yankee, LLC (Vt. Yankee Nuclear Power Station), CLI-11-2, 73 NRC 333, 337-38 (2011)
Each of the criteria must be separately addressed, with a specific explanation of why it has been met. When multiple allegations are involved, the movant must identify with particularity each issue it seeks to litigate and specify the factual and/or technical bases which it believes support the claim that this issue meets the criteria in paragraph (a) of this section.22
 
18 Entergy Nuclear Vt. Yankee, LLC (Vt. Yankee Nuclear Power Station), CLI-11-2, 73 NRC 333, 337-38 (2011)
(quotations and citation omitted).
(quotations and citation omitted).
19 Id. (quoting AmerGen Energy Co., LLC (Oyster Creek Nuclear Generating Station), CLI-08-28, 68 NRC 658, 674 (2008)). See also AmerGen Energy Co., LLC (Oyster Creek Nuclear Generating Station), CLI-09-7, 69 NRC 235, 287 (2009) (citing La. Power & Light Co. (Waterford Steam Elec. Station, Unit 3), CLI-86-1, 23 NRC 1, 5 (1986)).
19 Id. (quoting AmerGen Energy Co., LLC (Oyster Creek Nuclear Generating Station), CLI-08-28, 68 NRC 658, 674 (2008)). See also AmerGen Energy Co., LLC (Oyster Creek Nuclear Generating Station), CLI-09-7, 69 NRC 235, 287 (2009) (citing La. Power & Light Co. (Waterford Steam Elec. Station, Unit 3), CLI-86-1, 23 NRC 1, 5 (1986)).
20 DTE Elec. Co. (Fermi Nuclear Power Plant, Unit 2), CLI-17-07, 85 NRC 111, 116 (2017).
20 DTE Elec. Co. (Fermi Nuclear Power Plant, Unit 2), CLI-17-07, 85 NRC 111, 116 (2017).
21 Oyster Creek, CLI-08-28, 68 NRC at 674.
21 Oyster Creek, CLI-08-28, 68 NRC at 674.
22 10 C.F.R. § 2.326(b).
22 10 C.F.R. § 2.326(b).
5


No such affidavit accompanies the Motion here.23 Accordingly, on its face, and pursuant to the plain text of the regulation, the Motion must be denied for this reason alone.24 Movants purport to satisfy Section 2.326(b) through a cursory statement from counsel, in the Motion itself, that the factual statementsare true and correctand the legal conclusions are based on [Counsels] best understanding of applicable regulations and judicial precedents[.]25 This cursory statement, however, does not remotely satisfy the NRCs requirement for a competent and substantive technical or factual affidavit. As a general matter, the statement of counsel does little more than attest to the fact that counsel has read certain documents and (not surprisingly) agrees with her own statements and legal conclusions.
5 No such affidavit accompanies the Motion here.23 Accordingly, on its face, and pursuant to the
Moreover, this statement: fails to separately address each of the reopening criteria; does not remotely meet the admissibility standards in 10 C.F.R. § 2.337; and is not of sufficient quality as to be admissible into evidence at an evidentiary hearing. All of these things are required by Section 2.326(b),26 but remain unsatisfied here. Accordingly, the Motion must be denied.
 
B.       The Motion Is Untimely Motions to reopen and motions for leave to file new or amended contentions out of time must be timely.27 As Movants correctly explain, timeliness in this context generally requires that a motion be filed within 30 days of the availability of the information upon which the 23 The standing declarations attached to the Motion (see Motion at 13-14; id., Attachs. 1-8) do not purport to set forth the factual and/or technical bases for the Motion under 10 C.F.R. § 2.326(b).
plain text of the regulation, the Motion must be denied for this reason alone.24
 
Movants purport to satisfy Section 2.326(b) through a cursory statement from counsel, in
 
the Motion itself, that the factual statementsare true and correctand the legal conclusions
 
are based on [Counsels] best understanding of applicable regulations and judicial
 
precedents[.]25 This cursory statement, however, does not remotely satisfy the NRCs
 
requirement for a competent and substantive technical or factual affidavit. As a general matter,
 
the statement of counsel does little more than attest to the fact that counsel has read certain
 
documents and (not surprisingly) agrees with her own statements and legal conclusions.
 
Moreover, this statement: fails to separately address each of the reopening criteria; does not
 
remotely meet the admissibility st andards in 10 C.F.R. § 2.337; and is not of sufficient quality as
 
to be admissible into evidence at an evidentiary hearing. All of these things are required by
 
Section 2.326(b),26 but remain unsatisfied here. Accordingly, the Motion must be denied.
 
B. The Motion Is Untimely
 
Motions to reopen and motions for leave to file new or amended contentions out of time
 
must be timely.27 As Movants correctly explain, timeliness in this context generally requires
 
that a motion be filed within 30 days of the availability of the information upon which the
 
23 The standing declarations attached to the Motion (see Motion at 13-14; id., Attachs. 1-8) do not purport to set forth the factual and/or technical bases for the Motion under 10 C.F.R. § 2.326(b).
24 See, e.g., DTE Elec. Co. (Fermi Nuclear Power Plant, Unit 2), LBP-17-1, 85 NRC 3, 11 (2017) (Given that
24 See, e.g., DTE Elec. Co. (Fermi Nuclear Power Plant, Unit 2), LBP-17-1, 85 NRC 3, 11 (2017) (Given that
[the movant] attached no affidavit addressing the criteria in section 2.326(a), the Board must deny its Motion to Reopen), petition for review denied, CLI-17-07, 85 NRC 111 (2017).
[the movant] attached no affidavit addressing the criteria in section 2.326(a), the Board must deny its Motion to Reopen), petition for review denied, CLI-17-07, 85 NRC 111 (2017).
25 Motion at 12.
25 Motion at 12.
26 See, e.g., Holtec Int'l (HI-STORE Consolidated Interim Storage Facility), LBP-20-10, 92 NRC __, __ (Sept. 3, 2020) (slip op. at 6).
26 See, e.g., Holtec Int'l (HI-STORE Consolidated Interim Storage Facility), LBP-20-10, 92 NRC __, __ (Sept. 3, 2020) (slip op. at 6).
27 10 C.F.R. §§ 2.326(a)(1), 2.309(c)(1)(iii).
27 10 C.F.R. §§ 2.326(a)(1), 2.309(c)(1)(iii).
6


filing is based.28 Movants assert that their Motion is timely because it was submitted on September 29, 2021, within 30 days of receiving an e-mailed copy of the DSEIS from someone at the NRC on August 30, 2021.29 However, timeliness is not measured against the subjective threshold of when a movant received or became aware of the subject information rather, it is measured against the availability30 of that information. Under this well-settled standard, the Motion is untimely.
6 filing is based.28 Movants assert that their Motion is timely because it was submitted on
More specifically, the NRC publicly issued the DSEIS on August 19, 2021. According to the NRCs Agencywide Documents Access and Management System (ADAMS), the DSEIS became publicly available that day.31 Even generously assuming the appropriate timeliness trigger was the NRCs publication of the Federal Register notice on August 25, 2021, announcing the public availability of the DSEIS,32 corresponding motions were due no later than September 25, 2021. In contrast, Movants did not file their Motion until September 29, 2021.
 
September 29, 2021, within 30 days of receiving an e-mailed copy of the DSEIS from
 
someone at the NRC on August 30, 2021.29 However, timeliness is not measured against the
 
subjective threshold of when a movant received or became aware of the subject information
 
rather, it is measured against the availability 30 of that information. Under this well-settled
 
standard, the Motion is untimely.
 
More specifically, the NRC publicly issued the DSEIS on August 19, 2021. According to
 
the NRCs Agencywide Documents Access and Management System (ADAMS), the DSEIS
 
became publicly available that day.31 Even generously assuming the appropriate timeliness
 
trigger was the NRCs publication of the Federal Register notice on August 25, 2021,
 
announcing the public availability of the DSEIS,32 corresponding motions were due no later than
 
September 25, 2021. In contrast, Movants did not file their Motion until September 29, 2021.
 
By either measure, the Motion is untimely.
By either measure, the Motion is untimely.
Thus, the untimeliness of the Motion, coupled with the fact that Movants are represented by experienced nuclear counsel and do not allege any extraordinary and unanticipated circumstances that prevented timely filing, compels its rejection for failure to satisfy 10 C.F.R.
 
Thus, the untimeliness of the Motion, coupled with the fact that Movants are represented
 
by experienced nuclear counsel and do not allege any extraordinary and unanticipated
 
circumstances that prevented timely filing, compels its rejection for failure to satisfy 10 C.F.R.
 
§§ 2.309(c)(1)(iii) and 2.326(a)(1).
§§ 2.309(c)(1)(iii) and 2.326(a)(1).
28 Motion at 10 (quoting 10 C.F.R. § 2.309(c)(1)(iii) and citing Entergy Nuclear Vt. Yankee (Vt. Yankee Nuclear Power Station), LBP-07-15, 66 NRC 261, 266 n.11 (2007)).
28 Motion at 10 (quoting 10 C.F.R. § 2.309(c)(1)(iii) and citing Entergy Nuclear Vt. Yankee (Vt. Yankee Nuclear Power Station), LBP-07-15, 66 NRC 261, 266 n.11 (2007)).
29 Id. The referenced e-mail does not appear to be publicly available.
29 Id. The referenced e-mail does not appear to be publicly available.
30 10 C.F.R. § 2.309(c)(1)(iii).
30 10 C.F.R. § 2.309(c)(1)(iii).
31 See ADAMS profile for Accession No. ML21228A084 (Date Added field).
31 See ADAMS profile for Accession No. ML21228A084 (Date Added field).
32 Virginia Electric and Power Company, Dominion Energy Virginia, North Anna Power Station, Unit Nos. 1 and 2, Draft supplemental environmental impact statement, request for comment; 86 Fed. Reg. 47,525 (Aug. 25, 2021).
32 Virginia Electric and Power Company, Dominion Energy Virginia, North Anna Power Station, Unit Nos. 1 and 2, Draft supplemental environmental impact statement, request for comment; 86 Fed. Reg. 47,525 (Aug. 25, 2021).
7


C.       The Motion Fails to Demonstrate That It Is Based on Any Information That Is Both New and Materially Different, Much Less That It Raises a Significant Environmental Issue Motions for leave to file new or amended contentions must be based on new information that is materially different from information previously available.33 And motions to reopen must address a significant safety or environmental issue.34 To make the latter demonstration, a movant must show that the issue is so significant as to paint a seriously different picture of the environmental landscape.35 The Motion does none of these things.
7 C. The Motion Fails to Demonstrate That It Is Based on Any Information That Is Both New and Materially Different, Much Less That It Raises a Significant Environmental Issue
Movants claim satisfaction of these requirements based on certain language in the following paragraph that appears in a Background discussion regarding Design-Basis Accidents in Appendix F of the DSEIS:
 
Design-basis accidents are postulated accidents that a nuclear facility must be designed and built to withstand without loss to the systems, structures, and components necessary to ensure public health and safety. Planning for design-basis accidents ensures that the proposed plant can withstand normal transients (e.g., rapid changes in the reactor coolant system temperature or pressure, or rapid changes in reactor power), as well as a broad spectrum of postulated accidents without undue hazard to the health and safety of the public. Many of these design-basis accidents may occur, but are unlikely to occur, even once during the life of the plant; nevertheless, carefully evaluating each design-basis accident is crucial to establishing the design basis for the preventive and mitigative safety systems of the proposed nuclear power plant. Title 10 of the Code of Federal Regulations (10 CFR)
Motions for leave to file new or amended contentions must be based on new
Part 50, Domestic Licensing of 5 Production and Utilization Facilities, and 10 CFR Part 100, Reactor Site Criteria, describe the 6 NRCs acceptance criteria for design-basis accidents.36 More specifically, Movants rely on the following selective quotation of a partial sentence as the basis for their Motion: Many of these design-basis accidents may occur, but are unlikely to 33 10 C.F.R. § 2.309(c)(1)(i)-(ii).
 
information that is materially different from information previously available. 33 And motions
 
to reopen must address a significant safety or environmental issue.34 To make the latter
 
demonstration, a movant must show that the issue is so significant as to paint a seriously
 
different picture of the environmental landscape.35 The Motion does none of these things.
 
Movants claim satisfaction of these requirements based on certain language in the
 
following paragraph that appears in a Backgr ound discussion regarding Design-Basis
 
Accidents in Appendix F of the DSEIS:
 
Design-basis accidents are postulated accidents that a nuclear facility must be designed and built to withstand without loss to the systems, structures, and components necessary to ensure public health and safety. Planning for design-basis accidents ensures that th e proposed plant can withstand normal transients (e.g., rapid changes in the reactor coolant system temperature or pressure, or rapid changes in reactor power), as well as a broad spectrum of postulated accidents without undue hazard to the health and safety of the public. Many of these design-basis accidents may occur, but are unlikely to occur, even once during the life of the plant; nevertheless, carefully evaluating each design-basis accident is crucial to establishing the design basis for the preventive and mitigative safety systems of the proposed nuclear power plant. Title 10 of the Code of Federal Regulations (10 CFR)
Part 50, Domestic Licensing of 5 Production and Utilization Facilities, and 10 CFR Part 100, Reactor Site Criteria, describe the 6 NRCs acceptance criteria for design-basis accidents.36
 
More specifically, Movants rely on the following selective quotation of a partial sentence as the
 
basis for their Motion: Many of these design-basis accidents may occur, but are unlikely to
 
33 10 C.F.R. § 2.309(c)(1)(i)-(ii).
 
34 Id. § 2.326(a)(2).
34 Id. § 2.326(a)(2).
35 Private Fuel Storage, LLC (Indep. Spent Fuel Storage Installation), CLI-06-3, 63 NRC 19, 28 (2006)
35 Private Fuel Storage, LLC (Indep. Spent Fuel Storage Installation), CLI-06-3, 63 NRC 19, 28 (2006)
(quotations and citation omitted) (emphasis in original); see also Entergy Nuclear Generation Co. (Pilgrim Nuclear Power Station) LBP-11-23, 74 NRC 287, 301 (2011).
(quotations and citation omitted) (emphasis in original); see also Entergy Nuclear Generation Co. (Pilgrim Nuclear Power Station) LBP-11-23, 74 NRC 287, 301 (2011).
36 DSEIS, App. F at F-1 to F-2.
36 DSEIS, App. F at F-1 to F-2.
8


occur, even once during the life of the plant . . . . According to Movants, this phrase reveals that the NRC Staff has departed from decades of regulatory precedent and now takes the position that many design basis accidents are expected to occur.37 But Movants reading of the selected text is baselessand plainly incorrect. Indeed, the quoted language states precisely the oppositethat design basis accidents are unlikely to occur, even once during the life of the plant. Far from representing a startling new position that many such accidents are expected, as Movants claim, this background discussion squarely confirms that they are highly unlikely.
8 occur, even once during the life of the plant.... According to Movants, this phrase reveals
Movants also claim that the NRC has never stated, in either the context of NEPA or its Atomic Energy Act-based regulatory scheme, that it expects design-basis accidents to occur.38 This may be true, but Movants are incorrect to imply that the NRC has done so in the DSEIS.
 
Even assuming arguendo that Movants reading of the DSEIS were correctand it clearly is notMovants offer no comprehensible explanation as to how that partial sentence in the Background section of the DSEIS discussion of Design Basis Accidents is remotely relevant, much less material, to the previously-rejected contention. As is clear from the record of this proceeding, the issues raised in that contention related to beyond design basis external events (which is covered by a separate Severe Accidents discussion in the GEIS, not the Design Basis Accidents Movants discuss here). Any purported connection certainly remains unexplained here.
that the NRC Staff has departed from decades of regulatory precedent and now takes the position
 
that many design basis accidents are expected to occur.37 But Movants reading of the
 
selected text is baselessand plainly incorrect. Indeed, the quoted language states precisely the
 
oppositethat design basis accidents are unlikely to occur, even once during the life of the
 
plant. Far from representing a startling new position that many such accidents are
 
expected, as Movants claim, this background discussion squarely confirms that they are highly
 
unlikely.
 
Movants also claim that the NRC has never stated, in either the context of NEPA or its
 
Atomic Energy Act-based regulatory scheme, that it expects design-basis accidents to occur.38
 
This may be true, but Movants are incorrect to imply that the NRC has done so in the DSEIS.
 
Even assuming arguendo that Movants reading of the DSEIS were correctand it
 
clearly is notMovants offer no comprehensible explanation as to how that partial sentence in
 
the Background section of the DSEIS discussion of Design Basis Accidents is remotely
 
relevant, much less material, to the previously-rejected contention. As is clear from the record
 
of this proceeding, the issues raised in that contention related to beyond design basis external
 
events (which is covered by a separate Severe Accidents discussion in the GEIS, not the
 
Design Basis Accidents Movants discuss here). Any purported connection certainly remains
 
unexplained here.
 
37 Motion at 5.
37 Motion at 5.
38 Id. at 6 (emphasis added). See also id. at 11 (arguing that there is a significant environmental issue because the amended basis challenge[d] the legal validity of the NRCs key rationale for refusing to address the environmental significance of the 2011 Mineral Earthquake and by challenging a self-serving attempt by the NRC Staff to rewrite the NRCs well-established environmental analysis, inserting a whole new conceptual analytical approach that is neither consistent with the previous versions of the License Renewal GEIS or with the NRCs Atomic Energy Act-based regulatory regime for licensing of nuclear reactors.).
38 Id. at 6 (emphasis added). See also id. at 11 (arguing that there is a significant environmental issue because the amended basis challenge[d] the legal validity of the NRCs key rationale for refusing to address the environmental significance of the 2011 Mineral Earthquake and by challenging a self-serving attempt by the NRC Staff to rewrite the NRCs well-established environmental analysis, inserting a whole new conceptual analytical approach that is neither consistent with the previous versions of the License Renewal GEIS or with the NRCs Atomic Energy Act-based regulatory regime for licensing of nuclear reactors.).
9


By any reasonable measure, the DSEIS language does not identify any new information, much less anything materially different from previously available information.
9 By any reasonable measure, the DSEIS language does not identify any new
And it certainly does not raise a significant environmental issue capable of painting a seriously different picture of the environmental landscape. If anything, it paints the same picture presented in the GEIS, which is that design basis accidents are unlikely to occur during the life of an operating plant.39 At bottom, Movants flawed interpretation of a partial background statement regarding design basis accidents in the DSEIS is wholly insufficient to justify the extraordinary action of reopening the record and admitting an amended basis for a previously-rejected contention regarding beyond design basis accidents. Thus, the Motion must be denied for failure to satisfy 10 C.F.R. §§ 2.309(c)(1)(i)-(ii) and 2.326(a)(2).
 
D.       The Motion Fails to Demonstrate That the Board Would Have Reached a Materially Different Result or That the Previously-Rejected Contention Is Somehow Now Admissible Finally, any motion to reopen must demonstrate that a materially different result would be or would have been likely had the newly proffered evidence been considered initially.40 In the present context, this requirement largely parallels the corollary requirement that motions for leave to file new or amended contentions out of time include an admissible contention that meets all of the admissibility criteria in 10 C.F.R. § 2.309(f).41 Here, Movants do not advance any cogent arguments to make these mandatory demonstrations.
information, much less anything materially different from previously available information.
First, Movants fail to even address the requirement in 10 C.F.R. § 2.309(c)(4) to proffer an admissible contention that satisfies all six admissibility criteria in 10 C.F.R. § 2.309(f). They 39 See also 1996 GEIS at 5-1 (noting that the likelihood of beyond-design-basis events is lower than design basis events, thereby making clear that the GEIS has long acknowledged that the likelihood of design basis accidents, while exceptionally low, is not absolute zero as Movants appear to suggest).
 
And it certainly does not raise a significant environmental issue capable of painting a
 
seriously different picture of the environmental landscape. If anything, it paints the same
 
picture presented in the GEIS, which is that design basis accidents are unlikely to occur during
 
the life of an operating plant.39 At bottom, Movants flawed interpretation of a partial
 
background statement regarding design basis accidents in the DSEIS is wholly insufficient to
 
justify the extraordinary action of reopening the record and admitting an amended basis for a
 
previously-rejected contention regarding beyond design basis accidents. Thus, the Motion must
 
be denied for failure to satisfy 10 C.F.R. §§ 2.309(c)(1)(i)-(ii) and 2.326(a)(2).
 
D. The Motion Fails to Demonstrate That the Board Would Have Reached a Materially Different Result or That the Previously-Rejected Contention Is Somehow Now Admissible
 
Finally, any motion to reopen must demonstrate that a materially different result would
 
be or would have been likely had the newly proffered evidence been considered initially.40 In
 
the present context, this requirement largely para llels the corollary requirement that motions for
 
leave to file new or amended contentions out of time include an admissible contention that meets
 
all of the admissibility criteria in 10 C.F.R. § 2.309(f). 41 Here, Movants do not advance any
 
cogent arguments to make these mandatory demonstrations.
 
First, Movants fail to even address the requirement in 10 C.F.R. § 2.309(c)(4) to proffer
 
an admissible contention that satisfies all six admi ssibility criteria in 10 C.F.R. § 2.309(f). They
 
39 See also 1996 GEIS at 5-1 (noting that the likelihood of beyond-design-basis events is lower than design basis events, thereby making clear that the GEIS has long acknowledged that the likelihood of design basis accidents, while exceptionally low, is not absolute zero as Movants appear to suggest).
40 10 C.F.R. § 2.326(a)(3).
40 10 C.F.R. § 2.326(a)(3).
41 Id. § 2.309(c)(4).
41 Id. § 2.309(c)(4).
10


neither acknowledge the admissibility criteria nor explain how the previously-rejected contention, as supplemented by the amended basis, somehow satisfies each and every one of them. Movants bear the burden of demonstrating satisfaction of this requirement,42 yet make no attempt to provide that demonstration here.
10 neither acknowledge the admissibility criteria nor explain how the previously-rejected
Second, the only claim Movants offer towards satisfaction of the requirement to demonstrate a materially different result is that their amended basis would prevent the Commission from relying on a legally erroneous rationale to excuse the Staff from conducting a complete and thorough evaluation of the environmental significance of the Mineral Earthquake[.]43 The meaning of this statement is not clear to Applicants, and Movants certainly offer no explanation.
 
What is clear, however, is that Movants have not remotely demonstrated the likelihood of a different result (much less a material one) because they fail entirely to address the original result in LBP-21-4. Movants neither: acknowledge nor engage with the multitude of reasons the Board denied the contention in the first place;44 offer a single explanation as to how the Boards analysis purportedly would change based on Movants flawed interpretation of the DSEIS; nor explain how those revised analyses somehow would be sufficient to alter the Boards ultimate contention admissibility conclusion. And, as with their original petition, Movants provide no supporting factual or expert opinion to support their motion.
contention, as supplemented by the amended basis, somehow satisfies each and every one of
 
them. Movants bear the burden of demonstrating satisfaction of this requirement, 42 yet make no
 
attempt to provide that demonstration here.
 
Second, the only claim Movants offer towards satisfaction of the requirement to
 
demonstrate a materially different result is that their amended basis would prevent the
 
Commission from relying on a legally erroneous ra tionale to excuse the Staff from conducting a
 
complete and thorough evaluation of the environmental significance of the Mineral
 
Earthquake[.]43 The meaning of this statement is not clear to Appli cants, and Movants certainly
 
offer no explanation.
 
What is clear, however, is that Movants have not remotely demonstrated the likelihood of
 
a different result (much less a material one) because they fail entirely to address the original
 
result in LBP-21-4. Movants neither: acknowledge nor engage with the multitude of reasons the
 
Board denied the contention in the first place;44 offer a single explanation as to how the Boards
 
analysis purportedly would change based on Movants flawed interpretation of the DSEIS; nor
 
explain how those revised analyses somehow would be sufficient to alter the Boards ultimate
 
contention admissibility conclusion. And, as with their original petition, Movants provide no
 
supporting factual or expert opinion to support their motion.
 
42 Oyster Creek, CLI-09-7, 69 NRC at 287 (internal quotations and citation omitted).
42 Oyster Creek, CLI-09-7, 69 NRC at 287 (internal quotations and citation omitted).
43 Motion at 12.
43 Motion at 12.
44 See, e.g., North Anna, LBP-21-04, 93 NRC at __ (slip op. at 32-33) (finding that because Applicants ER did consider the environmental effects of design-basis and beyond-design-basis earthquakes in the SLR term and determined . . . that there was no post-2013 Revised GEIS new and significant information to incorporate into the ER that would change the GEIS conclusion that the environmental impacts of design-basis and severe accidents would be small . . . Petitioners generalized claims of missing or inadequate discussion, unsupported by any relevant technical analysis, fails to cross the threshold of providing sufficient factual or expert opinion support or of establishing a material dispute with the application[.]) (citations omitted).
11


Indeed, given the principle that licensing boards admit contentions, not bases[,]45 it is unclear how either standard could be satisfied here. The Motion seeks only to amend the basis statement of the Movants contention,46 not the contention itself.47 Because the Board rejected the contentionand it is the admissibility of the contention, not the basis, that must be determined48then, as a logical matter, an amended basis statement lacks the capacity to alter the admissibility determination. Movants certainly have not demonstrated otherwise.
44 See, e.g., North Anna, LBP-21-04, 93 NRC at __ (slip op. at 32-33) (finding that because Applicants ER did consider the environmental effects of design-basis and beyond-design-basis earthquakes in the SLR term and determined... that there was no post-2013 Revised GEIS new and significant information to incorporate into the ER that would change the GEIS conclusion that the environmental impacts of design-basis and severe accidents would be small... Petitioners generalized claims of missing or inadequate discussion, unsupported by any relevant technical analysis, fails to cross the threshold of providing sufficient factual or expert opinion support or of establishing a material dispute with the application[.]) (citations omitted).
Accordingly, the Motion must be rejected for the additional reason that it fails to satisfy 10 C.F.R. §§ 2.309(c)(4) and 2.326(a)(3).
 
IV.           CONCLUSION For the reasons set forth above, the Commission should deny the Motion for failure to meet the strict requirements of 10 C.F.R. §§ 2.326 and 2.309(c).
11 Indeed, given the principle that licensing boards admit contentions, not bases[,]45 it is
 
unclear how either standard could be satisfied here. The Motion seeks only to amend the basis
 
statement of the Movants contention,46 not the contention itself.47 Because the Board rejected
 
the contentionand it is the admissibility of the contention, not the basis, that must be
 
determined48then, as a logical matter, an amended basis statement lacks the capacity to alter
 
the admissibility determination. Movants certainly have not demonstrated otherwise.
 
Accordingly, the Motion must be rejected for the additional reason that it fails to satisfy
 
10 C.F.R. §§ 2.309(c)(4) and 2.326(a)(3).
 
IV. CONCLUSION
 
For the reasons set forth above, the Commissi on should deny the Motion for failure to
 
meet the strict requirements of 10 C.F.R. §§ 2.326 and 2.309(c).
 
45 Duke Energy Carolinas, LLC (William States Lee III Nuclear Station, Units 1 & 2), LBP-08-17, 68 NRC 431, 447 (2008) (citing Entergy Nuclear Vt. Yankee (Vt. Yankee Nuclear Power Station), LBP-04-28, 60 NRC 548, 557 (2004)). See also NextEra Energy Seabrook, LLC (Seabrook Station, Unit 1), LBP-11-02, 73 NRC 28, 56 (2011) (same).
45 Duke Energy Carolinas, LLC (William States Lee III Nuclear Station, Units 1 & 2), LBP-08-17, 68 NRC 431, 447 (2008) (citing Entergy Nuclear Vt. Yankee (Vt. Yankee Nuclear Power Station), LBP-04-28, 60 NRC 548, 557 (2004)). See also NextEra Energy Seabrook, LLC (Seabrook Station, Unit 1), LBP-11-02, 73 NRC 28, 56 (2011) (same).
46 Motion at 1.
46 Motion at 1.
47 See id. at 7 ([Movants] do not change their contention).
47 See id. at 7 ([Movants] do not change their contention).
48 Lee, LBP-08-17, 68 NRC at 447 (quoting Vt. Yankee, LBP-04-28, 60 NRC at 557) (emphasis added).
48 Lee, LBP-08-17, 68 NRC at 447 (quoting Vt. Yankee, LBP-04-28, 60 NRC at 557) (emphasis added).
12


Respectfully submitted, Executed in Accord with 10 C.F.R. § 2.304(d)   Executed in Accord with 10 C.F.R. § 2.304(d)
12 Respectfully submitted,
William S. Blair, Esq.                         Paul M. Bessette, Esq.
 
DOMINION ENERGY SERVICES, INC.                 MORGAN, LEWIS & BOCKIUS LLP 120 Tredegar Street, RS-2                     1111 Pennsylvania Avenue, N.W.
Executed in Accord with 10 C.F.R. § 2.304(d) Executed in Accord with 10 C.F.R. § 2.304(d)
Richmond, VA 23219                             Washington, D.C. 20004
 
+1.561.267.7459                               +1.202.739.5796 william.s.blair@dominionenergy.com             paul.bessette@morganlewis.com Signed (electronically) by Ryan K. Lighty Ryan K. Lighty, Esq.
William S. Blair, Esq. Paul M. Bessette, Esq.
 
DOMINION ENERGY SERVICES, INC. MORGAN, LEWIS & BOCKIUS LLP 120 Tredegar Street, RS-2 1111 Pennsylvania Avenue, N.W.
Richmond, VA 23219 Washington, D.C. 20004
+1.561.267.7459 +1.202.739.5796 william.s.blair@dominionenergy.com paul.bessette@morganlewis.com
 
Signed (electronically) by Ryan K. Lighty Ryan K. Lighty, Esq.
 
MORGAN, LEWIS & BOCKIUS LLP 1111 Pennsylvania Avenue, N.W.
MORGAN, LEWIS & BOCKIUS LLP 1111 Pennsylvania Avenue, N.W.
Washington, D.C. 20004
Washington, D.C. 20004
                                              +1.202.739.5274 ryan.lighty@morganlewis.com Dated in Washington, D.C.                     Counsel for Virginia Electric and Power this 25th day of October 2021                 Company 13
+1.202.739.5274 ryan.lighty@morganlewis.com
 
Dated in Washington, D.C. Counsel for Virginia Electric and Power this 25th day of October 2021 Company
 
13 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
 
BEFORE THE COMMISSION
 
)
In the Matter of: )
) Docket Nos. 50-338-SLR and VIRGINIA ELECTRIC AND POWER COMPANY ) 50-339-SLR and OLD DOMINION ELECTRIC COOPERATIVE )
) October 25, 2021 (North Anna Power Station, Units 1 & 2) )
 
CERTIFICATE OF SERVICE
 
I hereby certify that, on this date, a copy of Applicants Answer Opposing Motion to
 
Amend Contention Out of Time and Motion to Reopen the Record by Beyond Nuclear, Sierra
 
Club, and Alliance for Progressive Virginia was filed through the e-Filing system.


UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION
                                                            )
In the Matter of:                                          )
                                                            )    Docket Nos. 50-338-SLR and VIRGINIA ELECTRIC AND POWER COMPANY )                                        50-339-SLR and OLD DOMINION ELECTRIC COOPERATIVE )
                                                            )    October 25, 2021 (North Anna Power Station, Units 1 & 2)                    )
CERTIFICATE OF SERVICE I hereby certify that, on this date, a copy of Applicants Answer Opposing Motion to Amend Contention Out of Time and Motion to Reopen the Record by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia was filed through the e-Filing system.
Signed (electronically) by Ryan K. Lighty Ryan K. Lighty, Esq.
Signed (electronically) by Ryan K. Lighty Ryan K. Lighty, Esq.
MORGAN, LEWIS & BOCKIUS LLP 1111 Pennsylvania Avenue, N.W.
MORGAN, LEWIS & BOCKIUS LLP 1111 Pennsylvania Avenue, N.W.
Washington, D.C. 20004
Washington, D.C. 20004
                                                  +1.202.739.5274 ryan.lighty@morganlewis.com Counsel for Virginia Electric and Power Company DB1/ 124776218}}
+1.202.739.5274 ryan.lighty@morganlewis.com
 
Counsel for Virginia Electric and Power Company
 
DB1/ 124776218}}

Revision as of 15:53, 19 November 2024

Applicants Answer Opposing Motion to Amend Contention Out of Time and Motion to Reopen the Record by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia
ML21298A154
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 10/25/2021
From: Bessette P, Blair W, Lighty R
Dominion Energy Services, Morgan, Morgan, Lewis & Bockius, LLP, Virginia Electric & Power Co (VEPCO)
To:
NRC/OCM
SECY RAS
References
50-338-SLR, 50-339-SLR, ASLBP 21-970-01-SLR-01, RAS 56283
Download: ML21298A154 (16)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

BEFORE THE COMMISSION

)

In the Matter of: )

) Docket Nos. 50-338-SLR and VIRGINIA ELECTRIC AND POWER COMPANY ) 50-339-SLR and OLD DOMINION ELECTRIC COOPERATIVE )

) October 25, 2021 (North Anna Power Station, Units 1 & 2) )

)

APPLICANTS ANSWER OPPOSING MOTION TO AMEND CONTENTION OUT OF TIME AND MOTION TO REOPEN THE RECORD BY BEYOND NUCLEAR, SIERRA CLUB, AND ALLIANCE FOR PROGRESSIVE VIRGINIA

William S. Blair, Esq. Paul M. Bessette, Esq.

DOMINION ENERGY SERVICES, INC. Ryan K. Lighty, Esq.

MORGAN, LEWIS & BOCKIUS LLP

Counsel for Virginia Electric and Power Company

TABLE OF CONTENTS

I. INTRODUCTION................................................................................................................... 1 II. PROCEDURAL HISTORY.................................................................................................... 3 III. THE COMMISSION SHOULD DENY THE MOTION BECAUSE MOVANTS HAVE NOT SATISFIED THE COMMISSIONS STRICT STANDARDS......................... 4 A. The Motion Is Not Accompanied by an Affidavit....................................................... 5 B. The Motion Is Untimely.............................................................................................. 6 C. The Motion Fails to Demonstrate That It Is Based on Any Information That Is Both New and Materially Different, Much Less That It Raises a Significant Environmental Issue.................................................................................................... 8 D. The Motion Fails to Demonstrate That the Board Would Have Reached a Materially Different Result or That the Previously-Rejected Contention Is Somehow Now Admissible................................................................................................................. 10 IV. CONCLUSI ON...................................................................................................................... 12

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

BEFORE THE COMMISSION

)

In the Matter of: )

) Docket Nos. 50-338-SLR and VIRGINIA ELECTRIC AND POWER COMPANY ) 50-339-SLR and OLD DOMINION ELECTRIC COOPERATIVE )

) October 25, 2021 (North Anna Power Station, Units 1 & 2) )

)

APPLICANTS ANSWER OPPOSING MOTION TO AMEND CONTENTION OUT OF TIME AND MOTION TO REOPEN THE RECORD BY BEYOND NUCLEAR, SIERRA CLUB, AND ALLIANCE FOR PROGRESSIVE VIRGINIA

I. INTRODUCTION

Pursuant to 10 C.F.R. §§ 2.309(i)(1) and 2.323(c), and the U.S. Nuclear Regulatory

Commission (NRC) Secretarys Order of October 8, 2021,1 Virginia Electric and Power

Company (Dominion Virginia Power or Dominion), on behalf of itself and Old Dominion

Electric Cooperative (collectively, Applicants) submit this Answer opposing the combined

Motion filed by Beyond Nuclear, Inc., Sierra Club, Inc., and Alliance for a Progressive Virginia,

Inc. (collectively, Movants) for leave to amend their contention out of time (Motion for

Leave) and to reopen the record (Motion to Reopen) (collectively, the Motion).2

Movants previously petitioned to intervene, requested a hearing, and proffered one

proposed contention in the above-captioned proceeding. In LBP-21-4, issued March 29, 2021,

1 NRC Secretary Order at 1 (Oct. 8, 2021) (unpublished) (ML21281A250).

2 Beyond Nuclear, Inc., Sierra Club, Inc., and Alliance for a Progressive Virginia, Inc. Motion to Amend Contention Out of Time and to Reopen the Record (Sept. 29, 2021) (ML21272A386) (Motion). Despite this caption, Movants do not seek to amend their previously-rejected contention. Rather, they only seek to amend its basis statement. As an initial matter, it is unclear whether the Commissions regulations provide for a motion to admit an amended basis statement for a rejected contention, and Movants cite no authority for doing so.

the Atomic Safety and Licensing Board (Board) denied those requests, finding that the

proposed contention was inadmissible, and terminated the proceeding.3

The Motion asks to reopen the record of that terminated proceeding and for leave to

amend the basis statement of the rejected contention. The proposed amendment relates to

allegedly new information in the NRC Staffs August 2021 draft supplemental environmental

impact statement (DSEIS).4 As explained below, the Motion must be rejected because it fails

to satisfy the Commissions strict standards for reopening the record and contentions out of time.

The Motion could be diplomatically described... as less than optimally organized or

articulated.5 In more direct terms, the Motion consists primarily of a recitation of the

procedural posture of the case and repetition of Movants original arguments (which the Board

rejected). Movants provide only a cursory discussion of the relevant legal standards. The crux

of Movants argument (i.e., the factual predicate for the Motion and the additional basis

statement they seek to add) is an assertion that, in the DSEIS, the NRC Staff allegedly

announced a sweeping new regulatory position claiming that the NRC expects many design-

basis accidents to occur. However, the DSEIS says no such thing. In fact, it says the opposite.

As explained below, Movants strained reading of the DSEIS is wholly unsupported and does not

remotely satisfy the Commissions stringent re quirements for reopening and filing contentions

out of time. Even assuming arguendo that Movants reading of the DSEIS were correctand it

clearly is notMovants offer no cogent explanation as to how this statement regarding design

3 Va. Elec. & Power Co. (North Anna Power Station, Units 1 & 2), LBP-21-04, 93 NRC __ (Mar. 29, 2021) (slip op.) (ML21088A364) as modified by the Licensing Boards Memorandum and Order (Correcting Text of Decision) (Mar. 31, 2021) (ML21090A099).

4 NUREG-1437, Generic Environmen tal Impact Statement for License Renewal of Nuclear Plants, Supplement 7, Second Renewal, Regarding Subsequent License Renewal for North Anna Power Station Units 1 and 2, Draft Report for Comment (Aug. 2021) (ML21228A084) (DSEIS).

5 Crow Butte Res., Inc. (N. Trend Expansion Proj.), CLI-09-12, 69 NRC 535, 552 (2009) (citation omitted).

2 basis accidents is remotely relevant (much less material) to the previously-rejected contention,

which referenced a beyond design basis event. Thus, for any or all of these reasons, the Motion

should be summarily denied.

II. PROCEDURAL HISTORY

On August 24, 2020, Applicants filed with the NRC a subsequent license renewal

application (SLRA) to renew the operating licenses for North Anna Power Station, Units 1 and

2 (North Anna) for an additional 20-year period.6 On December 14, 2020, Movants filed their

Petition seeking to intervene in this proceeding, requesting a hearing, and proposing a single

contention challenging Applicants Environmental Report (ER).7 The proposed contention

alleged that the ER and the NRCs license renewal Generic Environmental Impact Statement

(GEIS)8 discussion of Design Basis Accidents failed to consider the environmental

significance of a 2011 earthquake in Mineral, Virginia that exceeded North Annas seismic

design basis.9 Because the analysis of this issue was conducted generically by the NRC in the

GEIS, and those findings were codified in NRC regulations, Movants also requested a waiver

under 10 C.F.R. § 2.335(b) to challenge those regulations (Waiver Request).10 Following

6 See Letter from M. Sartain, Virginia Electric and Power Company, to NRC Document Control Desk, Virginia Electric and Power Company, North Anna Power Station Units 1 and 2, Application for Subsequent Renewed Operating Licenses (Aug. 24, 2020) (Package ML20246G703). The application package contains multiple enclosures. The SLRA is Enclosure 3, which consists of two files: the Main Report and Appendices A-D (ML20246G696) and Appendix E, which is the Environmental Report (ER) (ML20246G698).

7 See generally Hearing Request and Petition to Intervene by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia and Petition for Waiver of 10 C.F.R. §§ 51.53(c)(3)(i), 51.71(d), and 51.95(c)(1) to Allow Consideration of Category 1 NEPA Issues (Dec. 14, 2020) (ML20349D952) (Petition).

8 See NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (May 1996); Vol. 1, Main Report (ML040690705) (1996 GEIS); NUREG-1437, Rev. 1, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (June 2013); Vol. 1, Main Report (ML13106A241)

(GEIS).

9 Petition at 13-14.

10 Id. at 30-37.

3 briefing11 and oral argument,12 the ASLB denied the Hearing Request and the Waiver Request

and terminated the proceeding.13 In doing so, the Board found that Petitioners challenge to the

Design Basis Accidents issue misinterprets the scope of the GEIS because beyond design basis

events (such as the Mineral earthquake) were evaluated under the GEIS Severe Accidents issue,

which Petitioners failed to dispute.14 Movants filed an Appeal of LBP-21-04 on April 23,

2021,15 and Applicants and the Staff both filed briefs opposing that Appeal.16 On September 29,

2021, while the Appeal is pending before the Commission, Movants filed the instant Motion. On

October 8, 2021, the NRC Secretary clarified that the deadline for Answers to the Motion was

October 25, 2021.17 Applicants hereby timely file their Answer.

III. THE COMMISSION SHOULD DENY THE MOTION BECAUSE MOVANTS HAVE NOT SATISFIED THE COMMISSIONS STRICT STANDARDS

The Motion is subject to two sets of standards: those for motions to reopen, under

10 C.F.R. § 2.326, and those for contentions out of time, under 10 C.F.R. § 2.309(c). Given

Movants submission of a combined Motion, the discussion below addresses these standards

11 Applicants Answer Opposing Request for Hearing, Petition to Intervene, and Petition for Waiver Submitted by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (Jan. 8, 2021) (ML21008A531)

(Applicants Answer to Petition); NRC Staff Answer to Hearing Request, Petition to Intervene and Petition for Waiver Filed by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (Jan. 8, 20201)

(ML21008A593); Reply by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia to Oppositions to Hearing Request and Waiver Petition (Jan. 15, 2021) (ML21015A605).

12 Official Transcript of Proceedings (proceedings held Feb. 4, 2021, transcript served Feb. 8, 2021)

(ML21039A546), as modified by the Licensing Boards Memorandum and Order (Adopting Transcript Corrections for Initial Prehearing Conference) (Feb. 25, 2021) (unpublished) (ML21056A213) (Tr.); see also Joint Motion for Correction of the Transcript for the Oral Argument Held on February 4, 2021 (Feb. 18, 2021)

(ML21049A129).

13 North Anna, LBP-21-04, 93 NRC at __ (slip op. at 36).

14 Id. at __ (slip op. at 25).

15 Brief on Appeal of LBP-21-04 by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (Apr. 23, 2021) (ML21113A317) (Appeal).

16 Applicants Brief in Opposition to Appeal of LBP-21-4 by Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia (May 18, 2021) (ML21138A894); NRC Staffs Brief in Response to Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginias Appeal of LBP-21-4 (May 18, 2021) (ML21138A942).

17 NRC Secretary Order at 1 (Oct. 8, 2021) (unpublished) (ML21281A250).

4 jointly. As a general matter, the Commission considers reopening the record to be an

extraordinary action.18 As a result, the Commission imposes a deliberately heavy burden

upon a participant seeking to reopen a closed record.19 As the Commission noted, [t]he level of

support required for a motion to reopen is greater than that required for a contention under the

general admissibility requirements of 10 C.F.R. § 2.309(f)(1).20 Bare assertions and

speculation, even those supplied by an expert in an affidavit, do not supply the requisite

support for such motions.21 As explained below, noneand certainly not allof the standards

applicable to the instant Motion are satisfied here.

A. The Motion Is Not Accompanied by an Affidavit

Section 2.326(b) specifies that reopening motions must be:

accompanied by affidavits that set forth the factual and/or technical bases for the movants claim that the criteria of paragraph (a) of this section have been satisfied. Affidavits must be given by competent individuals with knowledge of the facts alleged, or by experts in the disciplines appropriate to the issues raised. Evidence contained in affidavits must meet the admissibility standards of this subpart.

Each of the criteria must be separately addressed, with a specific explanation of why it has been met. When multiple allegations are involved, the movant must identify with particularity each issue it seeks to litigate and specify the factual and/or technical bases which it believes support the claim that this issue meets the criteria in paragraph (a) of this section.22

18 Entergy Nuclear Vt. Yankee, LLC (Vt. Yankee Nuclear Power Station), CLI-11-2, 73 NRC 333, 337-38 (2011)

(quotations and citation omitted).

19 Id. (quoting AmerGen Energy Co., LLC (Oyster Creek Nuclear Generating Station), CLI-08-28, 68 NRC 658, 674 (2008)). See also AmerGen Energy Co., LLC (Oyster Creek Nuclear Generating Station), CLI-09-7, 69 NRC 235, 287 (2009) (citing La. Power & Light Co. (Waterford Steam Elec. Station, Unit 3), CLI-86-1, 23 NRC 1, 5 (1986)).

20 DTE Elec. Co. (Fermi Nuclear Power Plant, Unit 2), CLI-17-07, 85 NRC 111, 116 (2017).

21 Oyster Creek, CLI-08-28, 68 NRC at 674.

22 10 C.F.R. § 2.326(b).

5 No such affidavit accompanies the Motion here.23 Accordingly, on its face, and pursuant to the

plain text of the regulation, the Motion must be denied for this reason alone.24

Movants purport to satisfy Section 2.326(b) through a cursory statement from counsel, in

the Motion itself, that the factual statementsare true and correctand the legal conclusions

are based on [Counsels] best understanding of applicable regulations and judicial

precedents[.]25 This cursory statement, however, does not remotely satisfy the NRCs

requirement for a competent and substantive technical or factual affidavit. As a general matter,

the statement of counsel does little more than attest to the fact that counsel has read certain

documents and (not surprisingly) agrees with her own statements and legal conclusions.

Moreover, this statement: fails to separately address each of the reopening criteria; does not

remotely meet the admissibility st andards in 10 C.F.R. § 2.337; and is not of sufficient quality as

to be admissible into evidence at an evidentiary hearing. All of these things are required by

Section 2.326(b),26 but remain unsatisfied here. Accordingly, the Motion must be denied.

B. The Motion Is Untimely

Motions to reopen and motions for leave to file new or amended contentions out of time

must be timely.27 As Movants correctly explain, timeliness in this context generally requires

that a motion be filed within 30 days of the availability of the information upon which the

23 The standing declarations attached to the Motion (see Motion at 13-14; id., Attachs. 1-8) do not purport to set forth the factual and/or technical bases for the Motion under 10 C.F.R. § 2.326(b).

24 See, e.g., DTE Elec. Co. (Fermi Nuclear Power Plant, Unit 2), LBP-17-1, 85 NRC 3, 11 (2017) (Given that

[the movant] attached no affidavit addressing the criteria in section 2.326(a), the Board must deny its Motion to Reopen), petition for review denied, CLI-17-07, 85 NRC 111 (2017).

25 Motion at 12.

26 See, e.g., Holtec Int'l (HI-STORE Consolidated Interim Storage Facility), LBP-20-10, 92 NRC __, __ (Sept. 3, 2020) (slip op. at 6).

27 10 C.F.R. §§ 2.326(a)(1), 2.309(c)(1)(iii).

6 filing is based.28 Movants assert that their Motion is timely because it was submitted on

September 29, 2021, within 30 days of receiving an e-mailed copy of the DSEIS from

someone at the NRC on August 30, 2021.29 However, timeliness is not measured against the

subjective threshold of when a movant received or became aware of the subject information

rather, it is measured against the availability 30 of that information. Under this well-settled

standard, the Motion is untimely.

More specifically, the NRC publicly issued the DSEIS on August 19, 2021. According to

the NRCs Agencywide Documents Access and Management System (ADAMS), the DSEIS

became publicly available that day.31 Even generously assuming the appropriate timeliness

trigger was the NRCs publication of the Federal Register notice on August 25, 2021,

announcing the public availability of the DSEIS,32 corresponding motions were due no later than

September 25, 2021. In contrast, Movants did not file their Motion until September 29, 2021.

By either measure, the Motion is untimely.

Thus, the untimeliness of the Motion, coupled with the fact that Movants are represented

by experienced nuclear counsel and do not allege any extraordinary and unanticipated

circumstances that prevented timely filing, compels its rejection for failure to satisfy 10 C.F.R.

§§ 2.309(c)(1)(iii) and 2.326(a)(1).

28 Motion at 10 (quoting 10 C.F.R. § 2.309(c)(1)(iii) and citing Entergy Nuclear Vt. Yankee (Vt. Yankee Nuclear Power Station), LBP-07-15, 66 NRC 261, 266 n.11 (2007)).

29 Id. The referenced e-mail does not appear to be publicly available.

30 10 C.F.R. § 2.309(c)(1)(iii).

31 See ADAMS profile for Accession No. ML21228A084 (Date Added field).

32 Virginia Electric and Power Company, Dominion Energy Virginia, North Anna Power Station, Unit Nos. 1 and 2, Draft supplemental environmental impact statement, request for comment; 86 Fed. Reg. 47,525 (Aug. 25, 2021).

7 C. The Motion Fails to Demonstrate That It Is Based on Any Information That Is Both New and Materially Different, Much Less That It Raises a Significant Environmental Issue

Motions for leave to file new or amended contentions must be based on new

information that is materially different from information previously available. 33 And motions

to reopen must address a significant safety or environmental issue.34 To make the latter

demonstration, a movant must show that the issue is so significant as to paint a seriously

different picture of the environmental landscape.35 The Motion does none of these things.

Movants claim satisfaction of these requirements based on certain language in the

following paragraph that appears in a Backgr ound discussion regarding Design-Basis

Accidents in Appendix F of the DSEIS:

Design-basis accidents are postulated accidents that a nuclear facility must be designed and built to withstand without loss to the systems, structures, and components necessary to ensure public health and safety. Planning for design-basis accidents ensures that th e proposed plant can withstand normal transients (e.g., rapid changes in the reactor coolant system temperature or pressure, or rapid changes in reactor power), as well as a broad spectrum of postulated accidents without undue hazard to the health and safety of the public. Many of these design-basis accidents may occur, but are unlikely to occur, even once during the life of the plant; nevertheless, carefully evaluating each design-basis accident is crucial to establishing the design basis for the preventive and mitigative safety systems of the proposed nuclear power plant. Title 10 of the Code of Federal Regulations (10 CFR)

Part 50, Domestic Licensing of 5 Production and Utilization Facilities, and 10 CFR Part 100, Reactor Site Criteria, describe the 6 NRCs acceptance criteria for design-basis accidents.36

More specifically, Movants rely on the following selective quotation of a partial sentence as the

basis for their Motion: Many of these design-basis accidents may occur, but are unlikely to

33 10 C.F.R. § 2.309(c)(1)(i)-(ii).

34 Id. § 2.326(a)(2).

35 Private Fuel Storage, LLC (Indep. Spent Fuel Storage Installation), CLI-06-3, 63 NRC 19, 28 (2006)

(quotations and citation omitted) (emphasis in original); see also Entergy Nuclear Generation Co. (Pilgrim Nuclear Power Station) LBP-11-23, 74 NRC 287, 301 (2011).

36 DSEIS, App. F at F-1 to F-2.

8 occur, even once during the life of the plant.... According to Movants, this phrase reveals

that the NRC Staff has departed from decades of regulatory precedent and now takes the position

that many design basis accidents are expected to occur.37 But Movants reading of the

selected text is baselessand plainly incorrect. Indeed, the quoted language states precisely the

oppositethat design basis accidents are unlikely to occur, even once during the life of the

plant. Far from representing a startling new position that many such accidents are

expected, as Movants claim, this background discussion squarely confirms that they are highly

unlikely.

Movants also claim that the NRC has never stated, in either the context of NEPA or its

Atomic Energy Act-based regulatory scheme, that it expects design-basis accidents to occur.38

This may be true, but Movants are incorrect to imply that the NRC has done so in the DSEIS.

Even assuming arguendo that Movants reading of the DSEIS were correctand it

clearly is notMovants offer no comprehensible explanation as to how that partial sentence in

the Background section of the DSEIS discussion of Design Basis Accidents is remotely

relevant, much less material, to the previously-rejected contention. As is clear from the record

of this proceeding, the issues raised in that contention related to beyond design basis external

events (which is covered by a separate Severe Accidents discussion in the GEIS, not the

Design Basis Accidents Movants discuss here). Any purported connection certainly remains

unexplained here.

37 Motion at 5.

38 Id. at 6 (emphasis added). See also id. at 11 (arguing that there is a significant environmental issue because the amended basis challenge[d] the legal validity of the NRCs key rationale for refusing to address the environmental significance of the 2011 Mineral Earthquake and by challenging a self-serving attempt by the NRC Staff to rewrite the NRCs well-established environmental analysis, inserting a whole new conceptual analytical approach that is neither consistent with the previous versions of the License Renewal GEIS or with the NRCs Atomic Energy Act-based regulatory regime for licensing of nuclear reactors.).

9 By any reasonable measure, the DSEIS language does not identify any new

information, much less anything materially different from previously available information.

And it certainly does not raise a significant environmental issue capable of painting a

seriously different picture of the environmental landscape. If anything, it paints the same

picture presented in the GEIS, which is that design basis accidents are unlikely to occur during

the life of an operating plant.39 At bottom, Movants flawed interpretation of a partial

background statement regarding design basis accidents in the DSEIS is wholly insufficient to

justify the extraordinary action of reopening the record and admitting an amended basis for a

previously-rejected contention regarding beyond design basis accidents. Thus, the Motion must

be denied for failure to satisfy 10 C.F.R. §§ 2.309(c)(1)(i)-(ii) and 2.326(a)(2).

D. The Motion Fails to Demonstrate That the Board Would Have Reached a Materially Different Result or That the Previously-Rejected Contention Is Somehow Now Admissible

Finally, any motion to reopen must demonstrate that a materially different result would

be or would have been likely had the newly proffered evidence been considered initially.40 In

the present context, this requirement largely para llels the corollary requirement that motions for

leave to file new or amended contentions out of time include an admissible contention that meets

all of the admissibility criteria in 10 C.F.R. § 2.309(f). 41 Here, Movants do not advance any

cogent arguments to make these mandatory demonstrations.

First, Movants fail to even address the requirement in 10 C.F.R. § 2.309(c)(4) to proffer

an admissible contention that satisfies all six admi ssibility criteria in 10 C.F.R. § 2.309(f). They

39 See also 1996 GEIS at 5-1 (noting that the likelihood of beyond-design-basis events is lower than design basis events, thereby making clear that the GEIS has long acknowledged that the likelihood of design basis accidents, while exceptionally low, is not absolute zero as Movants appear to suggest).

40 10 C.F.R. § 2.326(a)(3).

41 Id. § 2.309(c)(4).

10 neither acknowledge the admissibility criteria nor explain how the previously-rejected

contention, as supplemented by the amended basis, somehow satisfies each and every one of

them. Movants bear the burden of demonstrating satisfaction of this requirement, 42 yet make no

attempt to provide that demonstration here.

Second, the only claim Movants offer towards satisfaction of the requirement to

demonstrate a materially different result is that their amended basis would prevent the

Commission from relying on a legally erroneous ra tionale to excuse the Staff from conducting a

complete and thorough evaluation of the environmental significance of the Mineral

Earthquake[.]43 The meaning of this statement is not clear to Appli cants, and Movants certainly

offer no explanation.

What is clear, however, is that Movants have not remotely demonstrated the likelihood of

a different result (much less a material one) because they fail entirely to address the original

result in LBP-21-4. Movants neither: acknowledge nor engage with the multitude of reasons the

Board denied the contention in the first place;44 offer a single explanation as to how the Boards

analysis purportedly would change based on Movants flawed interpretation of the DSEIS; nor

explain how those revised analyses somehow would be sufficient to alter the Boards ultimate

contention admissibility conclusion. And, as with their original petition, Movants provide no

supporting factual or expert opinion to support their motion.

42 Oyster Creek, CLI-09-7, 69 NRC at 287 (internal quotations and citation omitted).

43 Motion at 12.

44 See, e.g., North Anna, LBP-21-04, 93 NRC at __ (slip op. at 32-33) (finding that because Applicants ER did consider the environmental effects of design-basis and beyond-design-basis earthquakes in the SLR term and determined... that there was no post-2013 Revised GEIS new and significant information to incorporate into the ER that would change the GEIS conclusion that the environmental impacts of design-basis and severe accidents would be small... Petitioners generalized claims of missing or inadequate discussion, unsupported by any relevant technical analysis, fails to cross the threshold of providing sufficient factual or expert opinion support or of establishing a material dispute with the application[.]) (citations omitted).

11 Indeed, given the principle that licensing boards admit contentions, not bases[,]45 it is

unclear how either standard could be satisfied here. The Motion seeks only to amend the basis

statement of the Movants contention,46 not the contention itself.47 Because the Board rejected

the contentionand it is the admissibility of the contention, not the basis, that must be

determined48then, as a logical matter, an amended basis statement lacks the capacity to alter

the admissibility determination. Movants certainly have not demonstrated otherwise.

Accordingly, the Motion must be rejected for the additional reason that it fails to satisfy

10 C.F.R. §§ 2.309(c)(4) and 2.326(a)(3).

IV. CONCLUSION

For the reasons set forth above, the Commissi on should deny the Motion for failure to

meet the strict requirements of 10 C.F.R. §§ 2.326 and 2.309(c).

45 Duke Energy Carolinas, LLC (William States Lee III Nuclear Station, Units 1 & 2), LBP-08-17, 68 NRC 431, 447 (2008) (citing Entergy Nuclear Vt. Yankee (Vt. Yankee Nuclear Power Station), LBP-04-28, 60 NRC 548, 557 (2004)). See also NextEra Energy Seabrook, LLC (Seabrook Station, Unit 1), LBP-11-02, 73 NRC 28, 56 (2011) (same).

46 Motion at 1.

47 See id. at 7 ([Movants] do not change their contention).

48 Lee, LBP-08-17, 68 NRC at 447 (quoting Vt. Yankee, LBP-04-28, 60 NRC at 557) (emphasis added).

12 Respectfully submitted,

Executed in Accord with 10 C.F.R. § 2.304(d) Executed in Accord with 10 C.F.R. § 2.304(d)

William S. Blair, Esq. Paul M. Bessette, Esq.

DOMINION ENERGY SERVICES, INC. MORGAN, LEWIS & BOCKIUS LLP 120 Tredegar Street, RS-2 1111 Pennsylvania Avenue, N.W.

Richmond, VA 23219 Washington, D.C. 20004

+1.561.267.7459 +1.202.739.5796 william.s.blair@dominionenergy.com paul.bessette@morganlewis.com

Signed (electronically) by Ryan K. Lighty Ryan K. Lighty, Esq.

MORGAN, LEWIS & BOCKIUS LLP 1111 Pennsylvania Avenue, N.W.

Washington, D.C. 20004

+1.202.739.5274 ryan.lighty@morganlewis.com

Dated in Washington, D.C. Counsel for Virginia Electric and Power this 25th day of October 2021 Company

13 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

BEFORE THE COMMISSION

)

In the Matter of: )

) Docket Nos. 50-338-SLR and VIRGINIA ELECTRIC AND POWER COMPANY ) 50-339-SLR and OLD DOMINION ELECTRIC COOPERATIVE )

) October 25, 2021 (North Anna Power Station, Units 1 & 2) )

CERTIFICATE OF SERVICE

I hereby certify that, on this date, a copy of Applicants Answer Opposing Motion to

Amend Contention Out of Time and Motion to Reopen the Record by Beyond Nuclear, Sierra

Club, and Alliance for Progressive Virginia was filed through the e-Filing system.

Signed (electronically) by Ryan K. Lighty Ryan K. Lighty, Esq.

MORGAN, LEWIS & BOCKIUS LLP 1111 Pennsylvania Avenue, N.W.

Washington, D.C. 20004

+1.202.739.5274 ryan.lighty@morganlewis.com

Counsel for Virginia Electric and Power Company