ML120460019: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
(2 intermediate revisions by the same user not shown) | |||
Line 2: | Line 2: | ||
| number = ML120460019 | | number = ML120460019 | ||
| issue date = 02/15/2012 | | issue date = 02/15/2012 | ||
| title = Acceptance Review Email, Request for Alternative No. RI-ISI-INT3 to ASME Code Requirements for Class 1 and 2 Piping Welds, Third 10-Year Inservice Inspection Interval | | title = Acceptance Review Email, Request for Alternative No. RI-ISI-INT3 to ASME Code Requirements for Class 1 and 2 Piping Welds, Third 10-Year Inservice Inspection Interval | ||
| author name = Sebrosky J | | author name = Sebrosky J | ||
| author affiliation = NRC/NRR/DORL/LPLIV | | author affiliation = NRC/NRR/DORL/LPLIV | ||
| addressee name = Baldwin T, Soenen P | | addressee name = Baldwin T, Soenen P | ||
| addressee affiliation = Pacific Gas & Electric Co | | addressee affiliation = Pacific Gas & Electric Co | ||
| docket = 05000275, 05000323 | | docket = 05000275, 05000323 | ||
| license number = DPR-080, DPR-082 | | license number = DPR-080, DPR-082 | ||
| contact person = Sebrosky J | | contact person = Sebrosky J, NRR/DORL/LPL4, 415-1132 | ||
| case reference number = TAC ME7854, TAC ME7855 | | case reference number = TAC ME7854, TAC ME7855 | ||
| document type = E-Mail | | document type = E-Mail | ||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:From: Burkhardt, Janet Sent: Wednesday, February 15, 2012 6:45 AM To: Lent, Susan | {{#Wiki_filter:From: Burkhardt, Janet Sent: Wednesday, February 15, 2012 6:45 AM To: Lent, Susan | ||
==Subject:== | ==Subject:== | ||
FW: Acceptance of Diablo Canyon Request for Approval of an Alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section XI Examination Requirements for Class 1 and 2 Piping Welds. TAC #s are ME7854, ME7855 - | FW: Acceptance of Diablo Canyon Request for Approval of an Alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section XI Examination Requirements for Class 1 and 2 Piping Welds. | ||
From: Sebrosky, Joseph | TAC #s are ME7854, ME7855 - Ive entered a database entry under 4010 for you use when adding to ADAMS. | ||
From: Sebrosky, Joseph Sent: Wednesday, February 15, 2012 6:34 AM To: Baldwin, Thomas (DCPP); Soenen, Philippe R Cc: Wang, Alan; Lent, Susan; Burkhardt, Janet | |||
==Subject:== | ==Subject:== | ||
Acceptance of Diablo Canyon Request for Approval of an Alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section XI Examination Requirements for Class 1 and 2 Piping Welds. | Acceptance of Diablo Canyon Request for Approval of an Alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section XI Examination Requirements for Class 1 and 2 Piping Welds. | ||
Tom and Philippe, | Tom and Philippe, By letter dated January 20, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12025A084), Pacific Gas and Electric Company, (PG&E, the licensee) submitted a request in accordance with 10 CFR 50.55a(a)(3)(i) to the U.S. Nuclear Regulatory Commission (NRC) to use a risk-informed inservice inspection program for Class 1 and 2 pipe welds for the third inspection interval for the Diablo Canyon Power Plant Units 1 and 2. | ||
The purpose of this letter is to provide the results of the NRC staff's acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. | The purpose of this letter is to provide the results of the NRC staff's acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. | ||
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. | |||
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence. | The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence. | ||
If you have any questions, please contact me at (301) 415-1132. | If you have any questions, please contact me at (301) 415-1132. | ||
Sincerely, Joe Sebrosky Project Manager (Diablo Canyon Power Plant) Nuclear Regulatory Commission Division of Operating Reactor Licensing joseph.sebrosky@nrc.gov 301-415-1132}} | Sincerely, Joe Sebrosky Project Manager (Diablo Canyon Power Plant) | ||
Nuclear Regulatory Commission Division of Operating Reactor Licensing | |||
joseph.sebrosky@nrc.gov 301-415-1132}} |
Latest revision as of 17:50, 20 March 2020
ML120460019 | |
Person / Time | |
---|---|
Site: | Diablo Canyon |
Issue date: | 02/15/2012 |
From: | Joseph Sebrosky Plant Licensing Branch IV |
To: | Baldwin T, Soenen P Pacific Gas & Electric Co |
Sebrosky J, NRR/DORL/LPL4, 415-1132 | |
References | |
TAC ME7854, TAC ME7855 | |
Download: ML120460019 (1) | |
Text
From: Burkhardt, Janet Sent: Wednesday, February 15, 2012 6:45 AM To: Lent, Susan
Subject:
FW: Acceptance of Diablo Canyon Request for Approval of an Alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section XI Examination Requirements for Class 1 and 2 Piping Welds.
TAC #s are ME7854, ME7855 - Ive entered a database entry under 4010 for you use when adding to ADAMS.
From: Sebrosky, Joseph Sent: Wednesday, February 15, 2012 6:34 AM To: Baldwin, Thomas (DCPP); Soenen, Philippe R Cc: Wang, Alan; Lent, Susan; Burkhardt, Janet
Subject:
Acceptance of Diablo Canyon Request for Approval of an Alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section XI Examination Requirements for Class 1 and 2 Piping Welds.
Tom and Philippe, By letter dated January 20, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12025A084), Pacific Gas and Electric Company, (PG&E, the licensee) submitted a request in accordance with 10 CFR 50.55a(a)(3)(i) to the U.S. Nuclear Regulatory Commission (NRC) to use a risk-informed inservice inspection program for Class 1 and 2 pipe welds for the third inspection interval for the Diablo Canyon Power Plant Units 1 and 2.
The purpose of this letter is to provide the results of the NRC staff's acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
If you have any questions, please contact me at (301) 415-1132.
Sincerely, Joe Sebrosky Project Manager (Diablo Canyon Power Plant)
Nuclear Regulatory Commission Division of Operating Reactor Licensing
joseph.sebrosky@nrc.gov 301-415-1132