ML14227A672: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(8 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML14227A672
| number = ML14227A672
| issue date = 08/29/2014
| issue date = 08/29/2014
| title = Indian Point Nuclear Generating Units 2 and 3, Regulatory Audit Report for May 27-30, 2014, Audit at the Indian Point Facility to Support Review of Near-Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report
| title = Regulatory Audit Report for May 27-30, 2014, Audit at the Indian Point Facility to Support Review of Near-Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report
| author name = Kuntz R F
| author name = Kuntz R
| author affiliation = NRC/NRR/JLD
| author affiliation = NRC/NRR/JLD
| addressee name =  
| addressee name =  
Line 9: Line 9:
| docket = 05000247, 05000286
| docket = 05000247, 05000286
| license number =  
| license number =  
| contact person = Kuntz R F, NRR/JLD, 415-3733
| contact person = Kuntz R, NRR/JLD, 415-3733
| case reference number = TAC MF3313, TAC MF3314
| case reference number = TAC MF3313, TAC MF3314
| document type = Audit Report, Letter
| document type = Audit Report, Letter
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Vice President, Operations Entergy Nuclear Operations, Inc. Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 August 29, 2014
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 29, 2014 Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249


==SUBJECT:==
==SUBJECT:==
INDIAN POINT NUCLEAR GENERATING, UNIT NOS. 2 AND 3-REGULATORY AUDIT REPORT FOR MAY 27-30,2014, AUDIT AT THE INDIAN POINT FACILITY TO SUPPORT REVIEW OF NEAR TERM TASK FORCE RECOMMENDATION 2.1: FLOODING HAZARD REEVALUATION REPORT (TAC NOS. MF3313 AND MF3314)  
INDIAN POINT NUCLEAR GENERATING, UNIT NOS. 2 AND 3-REGULATORY AUDIT REPORT FOR MAY 27-30,2014, AUDIT AT THE INDIAN POINT FACILITY TO SUPPORT REVIEW OF NEAR TERM TASK FORCE RECOMMENDATION 2.1: FLOODING HAZARD REEVALUATION REPORT (TAC NOS. MF3313 AND MF3314)


==Dear Sir or Madam:==
==Dear Sir or Madam:==
By letter dated December 23, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 13364A006), Entergy Nuclear Operations, Inc. (Entergy or the licensee), submitted its required response for Indian Point Nuclear Generating, Unit Nos. 2 and 3 to Near Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report (FHRR), in response to the U.S.Nuclear Regulatory Commission's (NRC) letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident, dated March 12, 2012 ( ADAMS Accession No. ML 12053A340). The purpose of the May 27-30, 2014, audit at the IPEC facility in Buchanan, New York, was for the NRC staff to review the data, models, and methods applied in the licensee's flood hazard reevaluation, supporting documentation, and calculation packages; and to discuss these issues with the Entergy's subject matter experts, staff, and contractors. The Indian Point Energy Center (IPEC) FHRR relied on complex methodologies to estimate flooding hazards at the site. Several of the flooding scenarios evaluated are not in the current licensing basis (CLB), nor were they evaluated for the purposes of the Individual Plant Examination of External Events (IPEEE) analysis. Almost all of the analyses rely on numerically-based computer codes that were not available at the time that the analyses supporting the CLB or the IPEEE were performed. In many cases, engineering judgment was an important part of the IPEC FHRR. Consequently, decisions concerning modeling abstractions, the specification of boundary conditions, the def,nition of input parameters, or other assumptions can impact the calculated flood water height estimated by these analyses. Following a preliminary review of the IPEC FHRR submitted on December 23, 2013 (ADAMS Accession No. ML 13364A005), the NRC staff identified several questions concerning various aspects of the fiood hazard calculations for the site. For example, the staff observed that spec1fic details concerning many of the analyses and their attendant assumptions were not   sufficiently described in the main body of the IPEC FHRR document or in supporting references. Because this information is necessary for the NRC staff to perform its review of the IPEC FHRR analyses, the staff decided to conduct an audit of the report and the associated calculations. An audit was then conducted at the IPEC site on May 27-30, 2014. The plan for this audit, dated May 5, 2014, can be found in ADAMS at Accession No. ML 14121 A431. A copy of the audit report, reflecting the NRC staff's findings during the site audit, is enclosed herewith. Enclosure 1 is the audit report which identifies the NRC staff and contractors and subcontractors that participated in the audit, as well as their respective function and the specific objectives of the audit. Enclosure 2 contains the Entergy contractor and subcontractor responses to NRC staff requests, and the staff's observations from the audit. If you have any questions, please contact me at 301-415-3733 or via email at Robert. Kuntz@nrc.gov. Docket Nos. 50-24 7 and 50-286  
 
By letter dated December 23, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13364A006), Entergy Nuclear Operations, Inc. (Entergy or the licensee), submitted its required response for Indian Point Nuclear Generating, Unit Nos. 2 and 3 to Near Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report (FHRR), in response to the U.S.Nuclear Regulatory Commission's (NRC) letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f)
Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident, dated March 12, 2012 ( ADAMS Accession No. ML12053A340).
The purpose of the May 27-30, 2014, audit at the IPEC facility in Buchanan, New York, was for the NRC staff to review the data, models, and methods applied in the licensee's flood hazard reevaluation, supporting documentation, and calculation packages; and to discuss these issues with the Entergy's subject matter experts, staff, and contractors.
The Indian Point Energy Center (IPEC) FHRR relied on complex methodologies to estimate flooding hazards at the site. Several of the flooding scenarios evaluated are not in the current licensing basis (CLB), nor were they evaluated for the purposes of the Individual Plant Examination of External Events (IPEEE) analysis. Almost all of the analyses rely on numerically-based computer codes that were not available at the time that the analyses supporting the CLB or the IPEEE were performed. In many cases, engineering judgment was an important part of the IPEC FHRR. Consequently, decisions concerning modeling abstractions, the specification of boundary conditions, the def,nition of input parameters, or other assumptions can impact the calculated flood water height estimated by these analyses.
Following a preliminary review of the IPEC FHRR submitted on December 23, 2013 (ADAMS Accession No. ML13364A005), the NRC staff identified several questions concerning various aspects of the fiood hazard calculations for the site. For example, the staff observed that spec1fic details concerning many of the analyses and their attendant assumptions were not
 
sufficiently described in the main body of the IPEC FHRR document or in supporting references.
Because this information is necessary for the NRC staff to perform its review of the IPEC FHRR analyses, the staff decided to conduct an audit of the report and the associated calculations. An audit was then conducted at the IPEC site on May 27-30, 2014.
The plan for this audit, dated May 5, 2014, can be found in ADAMS at Accession No. ML14121A431. A copy of the audit report, reflecting the NRC staff's findings during the site audit, is enclosed herewith. Enclosure 1 is the audit report which identifies the NRC staff and contractors and subcontractors that participated in the audit, as well as their respective function and the specific objectives of the audit. Enclosure 2 contains the Entergy contractor and subcontractor responses to NRC staff requests, and the staff's observations from the audit.
If you have any questions, please contact me at 301-415-3733 or via email at Robert. Kuntz@nrc.gov.
rt F. Kuntz, S 1or Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-24 7 and 50-286


==Enclosures:==
==Enclosures:==
: 1. FHRR Audit Report 2. Audit Report -Information needs cc w/encls: Distribution via Listserv rt F. Kuntz, S 1or Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation AUDIT REPORT BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO NEAR-TERM TASK FORCE RECOMMENDATION 2.1 FLOODING HAZARD REEVALUATION REPORT ENTERGY NUCLEAR OPERATIONS. INC., INDIAN POINT NUCLEAR GENERATING. UNIT NOS. 2 AND 3 DOCKET NOS. 50-247 AND 50-286 BACKGROUND AND AUDIT BASIS By letter dated December 23, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 13364A006), Entergy Nuclear Operations, Inc. (Entergy or the licensee), submitted its required response for Indian Point Nuclear Generating, Unit Nos. 2 and 3 (Indian Point) to Near Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report (FHRR), in response to the U.S. Nuclear Regulatory Commission's (NRC's) letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) (hereafter referred to as the 50.54(f) letter) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident, dated March 12, 2012 (ADAMS at Accession No. ML 12053A340). The licensee's submittal relied on several methodologies, for which NRC staff guidance was not used or goes beyond the existing staff guidance. In using these methodologies, the data, models, and analytical methods can be extremely important and can have large effects on the resulting calculated flooding heights at the site. Some details of how Entergy applied these methodologies, which the NRC staff must understand to complete its review, are not present in the Indian Point Energy Center (IPEC) FHRR. In its initial review of the IPEC FHRR, the NRC staff has identified questions in four areas regarding the information submitted by the licensee: (1) storm surge analysis, (2) local intense precipitation (LIP), (3) riverine flooding (including dam failures) and (4) documentation contained in calculation packages and references in the electronic reading room (ERR). With respect to evaluation of probable maximum precipitation (PMP), which serves as input to local intense precipitation and riverine flooding evaluations, Entergy performed a "site-specific" evaluation rather than using previously accepted methodologies and guidance contained in the Standard Review Plan (SRP). This could result in substantially lower precipitation values that might be calculated using previously accepted methodlogies. The NRC staff required further information to develop a better understanding of how the licensee calculated and applied the PMP, and how the licensee's analysis compares to the standard methodology. Enclosure 1   In the area of storm surge analysis, Entergy performed a probabilistic storm surge analysis (PSSA), which is a different method than the methods previously reviewed by the NRC staff. The NRC staff determined that it needed more information about the methodology used to implement the PSSA; the licensee's use and interpretation of available data, models, and methods (including use of engineering judgment); computer codes; the identification, treatment, and propagation of uncertainties; and the basis for certain relevant modeling decisions. Accordingly, the NRC staff conducted an audit of the IPEC FHRR at the IPEC site. The purpose of the audit was for the NRC staff to review the data, models, and methods applied in the licensee's flood hazard reevaluation, supporting documentation, and calculation packages; and discuss these issues with Entergy's subject matter experts, staff, and contractors. The audit allowed the staff to better understand the modeling results, and will aid the staff as it continues its review of the licensee's 50.54(f) submittal in order to make conclusions as to: (1) whether the licensee had responded appropriately to the 50.54(f) letter, (2) whether the responses are sufficient to determine whether or not the reevaluated flood causing mechanisms are, or are not, bounded by the current design-basis flood hazard, and (3) whether the staff needs additional information from the licensee to complete its review. The audit also assisted the NRC staff in identifying any additional information that it may need, as it continues its review of the IPEC FHRR. At the beginning of the audit, the licensee and its contractors presented information on Entergy's approach to performing both the PSSA and the PMF analyses. The PSSA presentation described how the PSSA relied on the Joint Probability Method (JPM) to estimate storm surge at the IPEC site, including discussions about how: (1) the JPM process steps were implemented; (2) the JPM results were benchmarked (validated) against deterministic-based estimates of storm surge at the site; and (3) engineering judgment, and error and uncertainty analyses were incorporated in the analyses. The presentation on the PMF calculation for the IPEC site reviewed the following topics: probable maximum precipitation, local intense precipitation, snow-melt, dam failures, and probable maximum flood estimation. For each topic, the methodology used to evaluate the hazard was discussed, as well as the use of engineering judgment and the treatment of conservatism in its analysis. There was also a discussion concerning the use of the FL0-20 computer software to perform flood routing calculations at the site. Both presentations were extensive and provided valuable insights into the analyses upon which the FHRR was based. The presentation materials provided additional detail and context concerning how the respective flood hazard analyses were performed. As a consequence, the NRC staff's information needs identified in the audit plan were sufficiently resolved for staff to generally understand the licensee's FHRR methodology/analysis. However, as the staff's detailed review progresses, the staff may issue Requests for Additional Information, at a later date. During the audit, the NRC staff and its contractors were provided a walking tour of the IPEC site. This walkdown provided important physical context for the briefings and analyses that were performed. The walkdown covered several areas of the facility cite, including: (1) the main runoff route for local intense precipitation (e.g., the steep road leading down to the waterfront); (2) the transformer yard, alleyways, downspouts, and manholes, and their treatment   in FL0-20; (3) the switchgear rooms, diesel generators and auxiliary feedwater and makeup water pumps; (4) the site grade and discharge canal; and (5) the staging area for sandbags and portable tiger dams. At the end of the audit, Entergy agreed to place several additional documents in the ERR, including: (1) certain specific maps and high resolution figures of the IPEC site; (2) corrected references in the FHRR and other documents; (3) spreadsheets and summary tables that the staff had requested and used during its audit; and (4) additional references needed by the staff. As a result of the audit, the licensee also revised its FL0-20 analysis and submitted it on August 18, 2014. The staff is continuing its review of the licensee's FHRR and supporting analyses. Regulatory Audit Scope or Methodology The area of focus for the audit was the Indian Point Recommendation 2.1 Flood Hazard Reevaluation Report and supporting documentation. Audit Team Activities The onsite audit was conducted at the Indian Point facility from May 27, 2014, through May 30, 2014. The NRC audit team staff was as follows: Support: Kenneth Erwin, NRC Audit Team Lead Douglas Pickett, NRC Senior Project Manager Wayne Schmidt, Senior Reactor Analyst, Region I Storm Surge Methodology: Henry Jones, NRC Audit Team Member, Storm Surge Lead Michelle Bensi, NRC Audit Team Member Chris Bender, Taylor Engineering, Inc., NRC Audit Team Member Don Resio, Taylor Engineering, Inc., NRC Audit Team Member Local Intense Precipitation I Riverine Flooding I Dam Failure Methodology: Barbara Hayes, NRC Audit Team Member, PMP Lead Kevin Quinlan, NRC Audit Team Member Rajiv Prasad, PNNL, NRC Audit Team Member Steve Breithaupt, PNNL, NRC Audit Team Member Serial No. 1 2 INDIAN POINT ENERGY CENTER FLOOD HAZARD REEVALUATION REPORT MAY 2014 HYDROLOGY AUDIT INFORMATION NEEDS FHRR'
: 1. FHRR Audit Report
* Section FHRR (in general) FHRR (in general) Information Need(s) 1 There appear to be instances of incorrect references in the body of the flood hazard reevaluation report (FHRR) or missing/incorrect references in the reference list. Have available a copy of the FHRR with any incorrect references clearly identified and corrected. NRC staff notes: The licensee provided a revision of the FHRR during the audit. As a result, the staff teamed that revisions were made by the licensee (and its contractors) since docketing of the initial FHRR, that include, corrections to references as well as more substantive amendments (e.g., Figure 51 in the docketed FHRR was identified during the audit as being incorrect). Have available electronic copies of the calculation packages below; as well as the means to access them (preferably on licensee computers rather than through the use of the electronic reading room (ERR):
: 2. Audit Report -Information needs cc w/encls: Distribution via Listserv
* AREVA Document No. 32-9207390-000, "Probable Maximum Hurricane for Indian Point Energy Center [IPEC]," 2013.
 
* AREVA Document No. 38-9216321-000, "Acquisition of Coastal Flood Analysis Data from Federal Emergency Management Agency Region II Indian Point Energy Center Flooding Hazard Re-evaluation," August, 2013.
AUDIT REPORT BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO NEAR-TERM TASK FORCE RECOMMENDATION 2.1 FLOODING HAZARD REEVALUATION REPORT ENTERGY NUCLEAR OPERATIONS. INC.,
* AREVA Document No. 32-9196317-000, "Indian Point Energy Center Flood Hazard Re-evaluation -Probable Maximum Seiche"
INDIAN POINT NUCLEAR GENERATING. UNIT NOS. 2 AND 3 DOCKET NOS. 50-247 AND 50-286 BACKGROUND AND AUDIT BASIS By letter dated December 23, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13364A006), Entergy Nuclear Operations, Inc. (Entergy or the licensee), submitted its required response for Indian Point Nuclear Generating, Unit Nos. 2 and 3 (Indian Point) to Near Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report (FHRR), in response to the U.S. Nuclear Regulatory Commission's (NRC's) letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) (hereafter referred to as the 50.54(f) letter) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident, dated March 12, 2012 (ADAMS at Accession No. ML12053A340). The licensee's submittal relied on several methodologies, for which NRC staff guidance was not used or goes beyond the existing staff guidance. In using these methodologies, the data, models, and analytical methods can be extremely important and can have large effects on the resulting calculated flooding heights at the site. Some details of how Entergy applied these methodologies, which the NRC staff must understand to complete its review, are not present in the Indian Point Energy Center (IPEC)
* AREVA Document No. 32-9193356-000, "Flood Hazard Re-evaluation -Combined Effect Floods -Coastal Processes for Indian Point Energy Center''
FHRR.
* AREVA Document No. 32-9196319-000, "IPEC Deterministic Probable * * 'Ac:tion {Prist Audit) Following the audit, the licensee submitted a revised FHRR for the Indian Point site that includes both corrections and revisions identified by the staff during the audit. The calculation packages cited were made available in the licensee's ERR. The NRC staff plans to issue a request for additional information (RAI), as needed, to request that the licensee docket information contained in the calculation packages if it serves as a basis for conclusions documented in the staff assessment. 1 In this column of the NRC Staffs audit report, the staff's pre-audit information needs are reproduced (in normal font), followed by the staffs post-audit comments (in italics). Items identified for future action are shown in the final column ("Action (Post-Audit)"). Enclosure 2  Serial FliRR Information Need(s) 1 Action (Post Audit) . .
In its initial review of the IPEC FHRR, the NRC staff has identified questions in four areas regarding the information submitted by the licensee: (1) storm surge analysis, (2) local intense precipitation (LIP), (3) riverine flooding (including dam failures) and (4) documentation contained in calculation packages and references in the electronic reading room (ERR).
* I No. Section ' Maximum Storm Surge Calculation"
With respect to evaluation of probable maximum precipitation (PMP), which serves as input to local intense precipitation and riverine flooding evaluations, Entergy performed a "site-specific" evaluation rather than using previously accepted methodologies and guidance contained in the Standard Review Plan (SRP). This could result in substantially lower precipitation values that might be calculated using previously accepted methodlogies. The NRC staff required further information to develop a better understanding of how the licensee calculated and applied the PMP, and how the licensee's analysis compares to the standard methodology.
* AREVA Document No. 32-9213352-000, "Flood Hazard Re-evaluation-Probabilistic Storm Surge for Indian Point Energy Center'' NRC staff notes: The licensee's subject matter experts (SMEs) provided an overview of their approach to the probabilistic calculation of storm surge. During the break-out session that followed, the calculation packages identified above were made available by the licensee in CD format and were added to the ERR . NRC staff and the licensee's SMEs referred to the calculation packages, as necessary, to support discussions throughout the audit to better understand the approach/methodology used to calculate storm surge. 3 3.1: Local Intense Have available a clear description of the current licensing basis (CLB) related to The staff reviewed the material requested in the Audi1 Precipitation local intense precipitation (LIP). Also, have available a brief and clear description Plan. The information needs were sufficiently of the individual plant examination of external events (IPEEE) analysis related to resolved for the staff to understand the licensee's the LIP. methodology and analysis. The staff may issue RAis to address concerns. NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of LIP flooding. This issue was assessed and documented in /PEG's earlier IPEEE submittal. The Entergy team informed the NRC staff that LIP is not part of the plant's design/licensing basis. 4 3.1: Local Intense Have available the knowledgeable SMEs who performed the site-specific staff reviewed the material requested in the Precipitation probable maximum precipitation (PMP) analysis described in AREVA Document Plan. The information needs were sufficiently No. 32-9196314-000. Also, have available an example storm analysis (including resolved for the staff to understand the licensee's 3.2: Flooding in computation software and runs/simulations, if necessary) to walk the NRC staff methodology and analysis. The staff may issue Rivers and through the analysis. Be prepared to define terms used in the site-specific PMP RAis to address concerns. Streams analysis-e.g., "extreme rainfall event," "transpositionability," "maximum average dew point," and others. NRC staff notes: The licensee's SMEs provided an overview of their approach to ---  Serial FHRR Information Need(s) 1 Action* No. Section the estimation of a site-specific PMP for the site. During the break-out session, the licensee discussed how the site-specific PMP was estimated, as well as the meaning of certain specific technical terms. The AREVA document cited in the audit plan was also made available by the licensee during the audit to facilitate those discussions. 5 3.1: Local Intense Have available storm data that were used in the site-specific PMP analysis. staff reviewed the material requested in the Precipitation Have available a knowledgeable SME to explain how the storm data was Plan. The information needs were sufficiently analyzed, including details of any statistical analyses. Be prepared to explain resolved for the staff to understand how the 3.2: Flooding in how the storm data and/or results from storm data analyses were used in the licensee's FHRR methodology and analysis deviated Rivers and site-specific PMP estimation and how this varies from the storm data used in the rom HMR51. The staff may issue RAis to address Streams National Oceanic and Atmospheric Administration (NOAA)/National Weather concerns. Service (NWS) Hydrometeorological Report (HMR) HMR51. NRC staff notes: The licensee's SMEs provided an overview of their approach to the estimation of site-specific PMP values for the site. During the break-out session that followed, the licensee had SMEs available to describe the estimation of site-specific PMP and how that estimation deviated from the HMR51 methodology. 6 3.1: Local Intense Have available a list of assumptions that were made in the site-specific PMP The staff reviewed the material requested in the Precipitation analysis. Have available a knowledgeable SME to discuss the justifications Audit Plan and spoke to the licensee's SMEs. The and/or data supporting these assumptions. information needs were sufficiently resolved for staff 3.2: Flooding in o understand the licensee's PMP assumptions and Rivers and NRC staff notes: The licensee's SMEs provided an overview of their approach to *ustifications. Staff may issue RAis to address Streams the estimation of a site-specific PMP for the site. During the break-out session, vOncems. the licensee identified the assumptions associated with the estimation of a site-specific PMP as well as the reasoning behind those assumptions. The licensee's SMEs also discussed temporal rainfall issues among other things. 7 3.1: Local Intense Have available any references which describe the methodology used in the site-staff reviewed the material requested in the L____ ----
Enclosure 1
Serial No. 8 FHRR. *.Section Precipitation 3.2: Flooding in Rivers and Streams 3.1 Local Intense Precipitation Information Need(s) t. '. ,. . specific PMP estimation. Have available a knowledgeable SME to discuss the . differences between values resultant from the site-specific PMP estimation used in the FHRR, and values which would have been derived from the NOAA/NWS HMR methodology. Be prepared to discuss the level of conservativeness associated with these values and how these results could affect the flood hazard analysis at or near the IPEC site. NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to the estimation of a sffe-specific PMP for the site. During the break-out session, the licensee discussed the differences between the site-specific PMP methodology and the NOAAINWS HMR methodology. Wffh respect to the HMR methodology itself, the licensee's SMEs expressed the opinion that the Generic HMR 51152 methodology was not appropriate for the /PEG and that a case-specific PMP study was performed. Have available a knowledgeable SME to discuss how the hierarchical hazard assessment (HHA) approach described in NUREG/CR-7046 was applied to determine the LIP flood at and near the I PEG site. NRC staff notes: The licensee's SMEs provided an overview of how the HHA approach was used to estimate a LIP-based flood at the site. No analysis was done of results that would be associated with the PMP values that would be derived from HMR 51. During the break-out session, the LIP calculation using case 3 described in Appendix B of NUREG/CR-7046 "Design-Basis Flood Estimation for Site Characterization at Nuclear Power Plants in the Unffed States of America" was discussed. An issue was identified by the licensee's SMEs with FL0-2D modeling treatment of "rain on building." The licensee's SMEs noted that a corrective action is on -going to determine the impact. Action ' ,., !Audit Plan and spoke to the licensee's SMEs. The information needs were sufficiently resolved for staff o develop an improved understanding of the licensee's approach. Further staff review may be necessary to better-understand the level of in the licensee's site-specific analysis. he staff may issue RAis to address any further oncems. The staff reviewed the material requested in the Audit Plan. The staffs information needs were sufficiently resolved for the staff to better understand the licensee's approach. The staff may issue RAis to address concerns. 9 I 3.1: Local Intense I Have available a map of I PEG site and vicinity clearly showing topographic audit included meaningful discussion of key Precipitation and hydraulic features and structures that influence local site drainage. issues. Though staff did receive a  Serial FHRR ,, N 'Section Information Need(s) 1 Action(PostAudit)*** *, o. r.vatershed map related to riverine and dam failure ! NRC staff notes: Discussions of key topographic and hydraulic features that staff is awaiting detailed map relevant to influence local site drainage were discussed at the audit. In addition, a walking local drainage and will review in conjunction with tour of the site was conducted, in which key topographic features were identified. revised LIP analysis. The staff subsequently requested that the necessary higher-resolution maps (specifically computer graphics files) be added to the ERR and the licensee added this map to the ERR. 10 3.1: Local Intense Have available the FL0-20 documentation (input and output files; calculation The staff reviewed the material requested in the Audit Precipitation packages) and a knowledgeable SME to discuss: Plan and spoke to the licensee's SMEs. Based on
 
* Precipitation transformation hose discussions, the licensee determined it would
In the area of storm surge analysis, Entergy performed a probabilistic storm surge analysis (PSSA), which is a different method than the methods previously reviewed by the NRC staff.
* Building runoff resubmit a revised FL0-20 analysis as part of the
The NRC staff determined that it needed more information about the methodology used to implement the PSSA; the licensee's use and interpretation of available data, models, and methods (including use of engineering judgment); computer codes; the identification, treatment, and propagation of uncertainties; and the basis for certain relevant modeling decisions. Accordingly, the NRC staff conducted an audit of the IPEC FHRR at the IPEC site.
* Channel routing FHRR. This was submitted on August 18, 2014.
The purpose of the audit was for the NRC staff to review the data, models, and methods applied in the licensee's flood hazard reevaluation, supporting documentation, and calculation packages; and discuss these issues with Entergy's subject matter experts, staff, and contractors.
* Obstructions in the floodplain The staff conducted a clarification phone call with the
The audit allowed the staff to better understand the modeling results, and will aid the staff as it continues its review of the licensee's 50.54(f) submittal in order to make conclusions as to: (1) whether the licensee had responded appropriately to the 50.54(f) letter, (2) whether the responses are sufficient to determine whether or not the reevaluated flood causing mechanisms are, or are not, bounded by the current design-basis flood hazard, and (3) whether the staff needs additional information from the licensee to complete its review. The audit also assisted the NRC staff in identifying any additional information that it may need, as it continues its review of the IPEC FHRR.
* Hydraulic control structures licensee on 06/20/2014 to discuss the scope of the resubmittal. The staff understands that key features NRC staff notes: The licensee's SMEs provided an overview of their approach of the revised FL0-20 resubmittal will include to the calculation of a site-specific PMP using the FL0-2D computer code. discussion of the following issues: During the break-out session, the licensee's SMEs noted that precipitation
At the beginning of the audit, the licensee and its contractors presented information on Entergy's approach to performing both the PSSA and the PMF analyses. The PSSA presentation described how the PSSA relied on the Joint Probability Method (JPM) to estimate storm surge at the IPEC site, including discussions about how: (1) the JPM process steps were implemented; (2) the JPM results were benchmarked (validated) against deterministic-based estimates of storm surge at the site; and (3) engineering judgment, and error and uncertainty analyses were incorporated in the analyses.
The presentation on the PMF calculation for the IPEC site reviewed the following topics:
probable maximum precipitation, local intense precipitation, snow-melt, dam failures, and probable maximum flood estimation. For each topic, the methodology used to evaluate the hazard was discussed, as well as the use of engineering judgment and the treatment of conservatism in its analysis. There was also a discussion concerning the use of the FL0-20 computer software to perform flood routing calculations at the site.
Both presentations were extensive and provided valuable insights into the analyses upon which the FHRR was based. The presentation materials provided additional detail and context concerning how the respective flood hazard analyses were performed. As a consequence, the NRC staff's information needs identified in the audit plan were sufficiently resolved for staff to generally understand the licensee's FHRR methodology/analysis. However, as the staff's detailed review progresses, the staff may issue Requests for Additional Information, at a later date.
During the audit, the NRC staff and its contractors were provided a walking tour of the IPEC site. This walkdown provided important physical context for the briefings and analyses that were performed. The walkdown covered several areas of the facility cite, including: (1) the main runoff route for local intense precipitation (e.g., the steep road leading down to the waterfront); (2) the transformer yard, alleyways, downspouts, and manholes, and their treatment
 
in FL0-20; (3) the switchgear rooms, diesel generators and auxiliary feedwater and makeup water pumps; (4) the site grade and discharge canal; and (5) the staging area for sandbags and portable tiger dams.
At the end of the audit, Entergy agreed to place several additional documents in the ERR, including: (1) certain specific maps and high resolution figures of the IPEC site; (2) corrected references in the FHRR and other documents; (3) spreadsheets and summary tables that the staff had requested and used during its audit; and (4) additional references needed by the staff.
As a result of the audit, the licensee also revised its FL0-20 analysis and submitted it on August 18, 2014. The staff is continuing its review of the licensee's FHRR and supporting analyses.
Regulatory Audit Scope or Methodology The area of focus for the audit was the Indian Point Recommendation 2.1 Flood Hazard Reevaluation Report and supporting documentation.
Audit Team Activities The onsite audit was conducted at the Indian Point facility from May 27, 2014, through May 30, 2014. The NRC audit team staff was as follows:
Support:
Kenneth Erwin, NRC Audit Team Lead Douglas Pickett, NRC Senior Project Manager Wayne Schmidt, Senior Reactor Analyst, Region I Storm Surge Methodology:
Henry Jones, NRC Audit Team Member, Storm Surge Lead Michelle Bensi, NRC Audit Team Member Chris Bender, Taylor Engineering, Inc., NRC Audit Team Member Don Resio, Taylor Engineering, Inc., NRC Audit Team Member Local Intense Precipitation I Riverine Flooding I Dam Failure Methodology:
Barbara Hayes, NRC Audit Team Member, PMP Lead Kevin Quinlan, NRC Audit Team Member Rajiv Prasad, PNNL, NRC Audit Team Member Steve Breithaupt, PNNL, NRC Audit Team Member
 
INDIAN POINT ENERGY CENTER FLOOD HAZARD REEVALUATION REPORT MAY 2014 HYDROLOGY AUDIT REPORT-INFORMATION NEEDS Serial          FHRR'
* Information Need(s) 1                                         * * 'Ac:tion {Prist Audit)
No.          Section 1            FHRR          There appear to be instances of incorrect references in the body of the flood     Following the audit, the licensee submitted a (in general)    hazard reevaluation report (FHRR) or missing/incorrect references in the           revised FHRR for the Indian Point site that reference list. Have available a copy of the FHRR with any incorrect references   includes both corrections and revisions identified clearly identified and corrected.                                                 by the staff during the audit.
NRC staff notes: The licensee provided a revision of the FHRR during the audit.
As a result, the staff teamed that revisions were made by the licensee (and its contractors) since docketing of the initial FHRR, that include, corrections to references as well as more substantive amendments (e.g., Figure 51 in the docketed FHRR was identified during the audit as being incorrect).
2              FHRR          Have available electronic copies of the calculation packages below; as well as   The calculation packages cited were made (in general)      the means to access them (preferably on licensee computers rather than           available in the licensee's ERR. The NRC staff through the use of the electronic reading room (ERR):                           plans to issue a request for additional information
* AREVA Document No. 32-9207390-000, "Probable Maximum Hurricane                 (RAI), as needed, to request that the licensee for Indian Point Energy Center [IPEC]," 2013.                               docket information contained in the calculation
* AREVA Document No. 38-9216321-000, "Acquisition of Coastal Flood               packages if it serves as a basis for conclusions Analysis Data from Federal Emergency Management Agency Region II           documented in the staff assessment.
Indian Point Energy Center Flooding Hazard Re-evaluation," August, 2013.
* AREVA Document No. 32-9196317-000, "Indian Point Energy Center Flood Hazard Re-evaluation - Probable Maximum Seiche"
* AREVA Document No. 32-9193356-000, "Flood Hazard Re-evaluation -
Combined Effect Floods - Coastal Processes for Indian Point Energy Center''
* AREVA Document No. 32-9196319-000, "IPEC Deterministic Probable 1
In this column of the NRC Staffs audit report, the staff's pre-audit information needs are reproduced (in normal font), followed by the staffs post-audit comments (in italics). Items identified for future action are shown in the final column ("Action (Post-Audit)").
Enclosure 2
 
Serial      FliRR                                        Information Need(s) 1                                                Action (Post Audit) ..
* No.        Section                                                                                                                                            '     I Maximum Storm Surge Calculation"
* AREVA Document No. 32-9213352-000, "Flood Hazard Re-evaluation-Probabilistic Storm Surge for Indian Point Energy Center''
NRC staff notes: The licensee's subject matter experts (SMEs) provided an overview of their approach to the probabilistic calculation of storm surge. During the break-out session that followed, the calculation packages identified above were made available by the licensee in CD format and were added to the ERR .
NRC staff and the licensee's SMEs referred to the calculation packages, as necessary, to support discussions throughout the audit to better understand the approach/methodology used to calculate storm surge.
3    3.1: Local Intense Have available a clear description of the current licensing basis (CLB) related to    The staff reviewed the material requested in the Audi1 Precipitation  local intense precipitation (LIP). Also, have available a brief and clear description Plan. The information needs were sufficiently of the individual plant examination of external events (IPEEE) analysis related to   resolved for the staff to understand the licensee's the LIP.                                                                              methodology and analysis. The staff may issue RAis to address concerns.
NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of LIP flooding. This issue was assessed and documented in
                          /PEG's earlier IPEEE submittal. The Entergy team informed the NRC staff that LIP is not part of the plant's design/licensing basis.
4    3.1: Local Intense Have available the knowledgeable SMEs who performed the site-specific                ~he staff reviewed the material requested in the Precipitation  probable maximum precipitation (PMP) analysis described in AREVA Document            ~udit Plan. The information needs were sufficiently No. 32-9196314-000. Also, have available an example storm analysis (including        resolved for the staff to understand the licensee's 3.2: Flooding in computation software and runs/simulations, if necessary) to walk the NRC staff        methodology and analysis. The staff may issue Rivers and    through the analysis. Be prepared to define terms used in the site-specific PMP       RAis to address concerns.
Streams      analysis- e.g., "extreme rainfall event," "transpositionability," "maximum average dew point," and others.
NRC staff notes: The licensee's SMEs provided an overview of their approach to
 
Serial        FHRR                                        Information Need(s) 1                                                Action* (PostA~dit)
No.        Section the estimation of a site-specific PMP for the site. During the break-out session, the licensee discussed how the site-specific PMP was estimated, as well as the meaning of certain specific technical terms. The AREVA document cited in the audit plan was also made available by the licensee during the audit to facilitate those discussions.
5    3.1: Local Intense Have available storm data that were used in the site-specific PMP analysis.       ~he staff reviewed the material requested in the Precipitation  Have available a knowledgeable SME to explain how the storm data was              ~udit Plan. The information needs were sufficiently analyzed, including details of any statistical analyses. Be prepared to explain  resolved for the staff to understand how the 3.2: Flooding in how the storm data and/or results from storm data analyses were used in the       licensee's FHRR methodology and analysis deviated Rivers and    site-specific PMP estimation and how this varies from the storm data used in the   rom HMR51. The staff may issue RAis to address Streams      National Oceanic and Atmospheric Administration (NOAA)/National Weather          concerns.
Service (NWS) Hydrometeorological Report (HMR) HMR51.
NRC staff notes: The licensee's SMEs provided an overview of their approach to the estimation of site-specific PMP values for the site. During the break-out session that followed, the licensee had SMEs available to describe the estimation of site-specific PMP and how that estimation deviated from the HMR51 methodology.
6    3.1: Local Intense Have available a list of assumptions that were made in the site-specific PMP     The staff reviewed the material requested in the Precipitation  analysis. Have available a knowledgeable SME to discuss the justifications        Audit Plan and spoke to the licensee's SMEs. The and/or data supporting these assumptions.                                         information needs were sufficiently resolved for staff 3.2: Flooding in                                                                                    o understand the licensee's PMP assumptions and Rivers and    NRC staff notes: The licensee's SMEs provided an overview of their approach to   *ustifications. Staff may issue RAis to address Streams      the estimation of a site-specific PMP for the site. During the break-out session, vOncems.
the licensee identified the assumptions associated with the estimation of a site-specific PMP as well as the reasoning behind those assumptions. The licensee's SMEs also discussed temporal rainfall issues among other things.
7    3.1: Local Intense Have available any references which describe the methodology used in the site- ~he staff reviewed the material requested in the L____  ----
 
Serial      FHRR.
Information Need(s)        t.                                       Action (P~~JfAudit)
No.      *.Section                                                      '. '~'' ,. .                                                    '      ,.,
Precipitation  specific PMP estimation. Have available a knowledgeable SME to discuss the       !Audit Plan and spoke to the licensee's SMEs. The
                        .differences between values resultant from the site-specific PMP estimation used    information needs were sufficiently resolved for staff 3.2: Flooding in in the FHRR, and values which would have been derived from the NOAA/NWS              o develop an improved understanding of the Rivers and    HMR methodology. Be prepared to discuss the level of conservativeness              licensee's approach. Further staff review may be Streams      associated with these values and how these results could affect the flood hazard  necessary to better-understand the level of
                                                                                                            ~
analysis at or near the IPEC site.                                                   onservatism in the licensee's site-specific analysis.
he staff may issue RAis to address any further NRC staff notes: The licensee's SMEs provided an oveNiew of their approach         oncems.
to the estimation of a sffe-specific PMP for the site. During the break-out session, the licensee discussed the differences between the site-specific PMP methodology and the NOAAINWS HMR methodology. Wffh respect to the HMR methodology itself, the licensee's SMEs expressed the opinion that the Generic HMR 51152 methodology was not appropriate for the /PEG and that a case-specific PMP study was performed.
8    3.1 Local Intense    Have available a knowledgeable SME to discuss how the hierarchical hazard         The staff reviewed the material requested in the Precipitation    assessment (HHA) approach described in NUREG/CR-7046 was applied to               Audit Plan. The staffs information needs were determine the LIP flood at and near the IPEG site.                                 sufficiently resolved for the staff to better understand the licensee's approach. The staff NRC staff notes: The licensee's SMEs provided an overview of how the HHA             may issue RAis to address concerns.
approach was used to estimate a LIP-based flood at the site. No analysis was done of results that would be associated with the PMP values that would be derived from HMR 51. During the break-out session, the LIP calculation using case 3 described in Appendix B of NUREG/CR-7046 "Design-Basis Flood Estimation for Site Characterization at Nuclear Power Plants in the Unffed States of America" was discussed. An issue was identified by the licensee's SMEs with FL0-2D modeling treatment of "rain on building." The licensee's SMEs noted that a corrective action is on -going to determine the impact.
9 I 3.1: Local Intense I Have available a map of IPEG site and vicinity clearly showing topographic        ~he audit included meaningful discussion of key Precipitation    and hydraulic features and structures that influence local site drainage.        ~rainage issues. Though staff did receive a
 
Serial        FHRR No. .,~                                                  Information Need(s) 1                                                    Action(PostAudit)*** *,
            'Section r.vatershed map related to riverine and dam failure    !
NRC staff notes: Discussions of key topographic and hydraulic features that        ~ooding, staff is awaiting detailed map relevant to influence local site drainage were discussed at the audit. In addition, a walking local drainage and will review in conjunction with tour of the site was conducted, in which key topographic features were identified. revised LIP analysis.
The staff subsequently requested that the necessary higher-resolution maps (specifically computer graphics files) be added to the ERR and the licensee added this map to the ERR.
10      3.1: Local Intense   Have available the FL0-20 documentation (input and output files; calculation    The staff reviewed the material requested in the Audit Precipitation      packages) and a knowledgeable SME to discuss:                                  Plan and spoke to the licensee's SMEs. Based on
* Precipitation transformation                                                    hose discussions, the licensee determined it would
* Building runoff                                                              resubmit a revised FL0-20 analysis as part of the
* Channel routing                                                                FHRR. This was submitted on August 18, 2014.
* Obstructions in the floodplain                                                The staff conducted a clarification phone call with the licensee on 06/20/2014 to discuss the scope of the
* Hydraulic control structures                                                  resubmittal. The staff understands that key features NRC staff notes: The licensee's SMEs provided an overview of their approach       of the revised FL0-20 resubmittal will include to the calculation of a site-specific PMP using the FL0-2D computer code.         discussion of the following issues:
During the break-out session, the licensee's SMEs noted that precipitation
* Roof run-off issues transformed directly into runoff in FL0-2D and that no infiltration or
* Roof run-off issues transformed directly into runoff in FL0-2D and that no infiltration or
* Potential flow discontinuities in model abstractions were used. As a result of those discussions, the staff requested
* Potential flow discontinuities in model abstractions were used. As a result of those discussions, the staff requested
* Mesh resolution that certain specific references be added to the ERR including information
* Mesh resolution that certain specific references be added to the ERR including information
* Model configuration as it relates to complicated identifying the location of specific /PEG facility features including AutoCADIGIS flow areas data files for transformer yard doors as well as doors of other site critical
* Model configuration as it relates to complicated identifying the location of specific /PEG facility features including AutoCADIGIS         flow areas data files for transformer yard doors as well as doors of other site critical
* Flow near buildings features.
* Flow near buildings features.
* Criteria from the FL0-20 user's manual
* Criteria from the FL0-20 user's manual
* Any potential complications with supercritical flow conditions RAI(s) may be issued following the staff's review of he licensee's resubmittal and additional ERR references. ---------
* Any potential complications with supercritical flow conditions RAI(s) may be issued following the staff's review of he licensee's resubmittal and additional ERR references.
Serial **No. FHRR Section Information Need(s) 1 . Action (Post Audit) . 11 I 3.1: Local Intense I Have available the FL0-20 documentation (input and output files; calculation he staff reviewed the material requested in the Precipitation packages) and a knowledgeable SME to discuss: udit Plan and spoke to the licensee's SMEs. 12 3.1: Local Intense Precipitation Quality control checks Based on those discussions, the licensee Sub-grid scale flow balances etermined it would resubmit a revised FL0-20 nalysis as part of the FHRR (See item #1 0, above.) NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to he staff also determined that additional using the FL0-2D computer code. During the break-out session, the licensee's ocumentation was needed in the ERR. RAI(s) may SMEs noted that FL0-2D calculations were performed under an Appendix 8 be issued following the staffs review of licensee's approved QA program (safety related). The licensee noted that FL0-2D software resubmittal and additional ERR references. underwent a commercial grade dedication process. Relevant information was also made available by the licensee during the audit. Have available the FL0-20 documentation (input and output files; calculation packages) and a knowledgeable SME to discuss:
 
* Water surface elevation results
Serial       FHRR Information Need(s) 1                                               .Action (Post Audit) .
* Velocity results NRC staff notes: The licensee's SME's provided relevant information during the audit. During the break-out session, detailed discussions concerned FL0-2D as well as the issue related to the treatment of "rain on buildings" features. Other relevant information was also made available by the licensee during the The staff reviewed the material requested in the Audit Plan and spoke to the licensee's SMEs. Based on those discussions, the licensee determined it would resubmit a revised FL0-20 analysis as part of the FHRR; (See item #1 0 above). The staff also reviewed the material requested in the Audit Plan and determined that additional documentation was needed in the ERR. RAI(s) may be issued following the staffs Serial **No; 13 14 FHRR Section 3.2: Flooding in Rivers and Streams 3.2: Flooding in Rivers and Streams lnformationNeed(s} r audit. Have available a knowledgeable SME to discuss how the hierarchical hazard assessment (HHA) approach described in NUREG/CR-7046 was applied to determine the probable maximum flood (PMF) at and near the IPEC site. NRC staff notes: The licensee's SMEs provided an overview of how the HHA approach was applied to the calculation of the PM F. No analysis was done of results that would be associated with the PMP values that would be derived from HMR51. During the break-out session, the licensee's SMEs noted that the model parameters initially selected were vefY conservative regarding initial losses, neglecting most of the upstream dams and use of conservative starting pool elevations at spillway crest,. The licensee's SMEs also noted that one iteration was performed and once the PMF elevation was below site grade the process was ended. The licensee also had relevant background information available during these discussions. Have available a knowledgeable SME to discuss the selection of the centering and orientation for the basin-wide PMP storm for estimation of the PMF. Be prepared to present justifications and/or data support for this selection. NRC staff notes: For the purposes of the basin-wide PMF calculation discussion, the licensee's SMEs noted that the storm center was taken as the center of the watershed. The licensee's SMEs also noted that the HMR52 computer program internally computes storm orientation to maximize rainfall depth within the user -defined watershed. Evaluation of additional storm centers was judged not to provide additional value and the licensee's SMEs relied on expert judgment to determine that the one storm orientation used would produce the most severe flooding possible. The licensee had other relevant background information available during these discussions. ** Action (Post Audit} review of the licensee's resubmittal and additional ERR references. staff reviewed the material requested in the jAudit Plan and met with the SMEs. The staffs information needs were sufficiently resolved for the E_taff to better understand the licensee's approach. 11 he staff may issue RAis to address concerns. staff reviewed the material requested in the udit Plan and spoke to the licensee's SMEs. hese actions lead to partial resolution of the staffs arlier questions. Further staff review is necessary .o better understand the level of conservatism in the licensee's analysis approach. Thestaff may issue RAis to address concerns. 
**No.        Section 11 I 3.1: Local Intense I Have available the FL0-20 documentation (input and output files; calculation       he staff reviewed the material requested in the Precipitation     packages) and a knowledgeable SME to discuss:                                       udit Plan and spoke to the licensee's SMEs.
** FHRR No. .
Quality control checks                                                             Based on those discussions, the licensee Sub-grid scale flow balances                                                       etermined it would resubmit a revised FL0-20 nalysis as part of the FHRR (See item #1 0, above.)
* Section 15 I 3.2: Flooding in 16 17 Rivers and Streams 3.2: Flooding in Rivers and Streams 3.2: Flooding in Rivers and Streams ' /' ,\, *., '',' *<.'' Information Need(t;)J * * * * * ; Action (Post Audit) .. Have available a knowledgeable SME to discuss reasonable alternative centering he staff reviewed the material requested in the locations and orientations for the site-specific PMP storm for estimation of the udit Plan and spoke to the licensee's SMEs. PMF. Be prepared to discuss how these alternative centering locations could hese actions lead to partial resolution of the staffs affect the flood hazard at or near the IPEC site and the associated levels of arlier questions. Further staff review will be conservatism. necessary to better understand the level of onservatism in the licensee's analitical approach. NRC staff notes: No alternative centering locations or orientations for the site-hestaff may issue RAis to address concerns. specific PMP were used by the licensee's SMEs who relied upon expert judgment in determining that all other alternative locations would result in less severe flooding near the /PEG site. The licensee had SMEs available to discuss the issues. Relevant information was made available by the licensee during the audit. Have available a map of the domains used for Hydrologic Engineering Center Hydrologic Modeling System (HEC-HMS) and Hydrologic Engineering Center River Analysis System (HEC-RAS) that clearly shows rivers, tributaries, dams and other hydraulic structures, reservoirs, watershed boundaries, and the location of gage stations. The map should clearly show the domains used for HEC-HMS and HEC-RAS, as well as the locations of cross sections used for HEC-RAS analyses. NRC staff notes: The licensee's SMEs provided a large scale map during the audit showing the requested information. An electronic copy was also requested for the ERR and was subsequently provided. Have available the HEC-HMS documentation (input and output files; calculation packages) and a knowledgeable SME to discuss:
NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to he staff also determined that additional using the FL0-2D computer code. During the break-out session, the licensee's       ocumentation was needed in the ERR. RAI(s) may SMEs noted that FL0-2D calculations were performed under an Appendix 8             be issued following the staffs review of licensee's approved QA program (safety related). The licensee noted that FL0-2D software resubmittal and additional ERR references.
* Precipitation transformation
underwent a commercial grade dedication process. Relevant information was also made available by the licensee during the audit.
* Channel routing characteristics
12  3.1: Local Intense    Have available the FL0-20 documentation (input and output files; calculation       The staff reviewed the material requested in the Precipitation      packages) and a knowledgeable SME to discuss:                                     Audit Plan and spoke to the licensee's SMEs.
* Reservoir characteristics NRC staff notes: The licensee's SMEs provided an overview of the approach to The staff reviewed the material requested in the Audit Plan and found it sufficient. An electronic copy was later provided to the ERR as requested for follow-up. staff reviewed the material requested in the udit Plan and concluded that it still has questions. he staff subsequently requested that additional ocumentation be placed in the ERR concerning the HEC-HMS computer modeling. Upon receipt of the requested information in the ERR, the staff will review it and determine if it has any additional Serial No. 18 FHRR Section 3.2: Flooding in Rivers and Streams Information Action ** .*. *. the PMF calculation using the HEC-HMS computer code. Relevant information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff to review during the audit break-out session, and the SMEs were on hand to aid in the interpretation of that information. Specific points discussed included unit hydrograph parameters used, infiltration loss rates, channel routing methods and available dam data for selected dams. During the breakout session, the licensee's SMEs noted:
* Water surface elevation results                                                 Based on those discussions, the licensee
* Velocity results                                                                 determined it would resubmit a revised FL0-20 analysis as part of the FHRR; (See item #1 0 NRC staff notes: The licensee's SME's provided relevant information during         above). The staff also reviewed the material the audit. During the break-out session, detailed discussions concerned FL0-      requested in the Audit Plan and determined that 2D as well as the issue related to the treatment of "rain on buildings" features. additional documentation was needed in the Other relevant information was also made available by the licensee during the      ERR. RAI(s) may be issued following the staffs
 
Serial     FHRR lnformationNeed(s} r
* Action (Post Audit}
**No;     Section audit.                                                                           review of the licensee's resubmittal and additional ERR references.
13  3.2: Flooding in Have available a knowledgeable SME to discuss how the hierarchical hazard   ~he staff reviewed the material requested in the Rivers and    assessment (HHA) approach described in NUREG/CR-7046 was applied to         jAudit Plan and met with the SMEs. The staffs Streams      determine the probable maximum flood (PMF) at and near the IPEC site.         information needs were sufficiently resolved for the E_taff to better understand the licensee's approach.
NRC staff notes: The licensee's SMEs provided an overview of how the HHA     11 he staff may issue RAis to address concerns.
approach was applied to the calculation of the PMF. No analysis was done of results that would be associated with the PMP values that would be derived from HMR51. During the break-out session, the licensee's SMEs noted that the model parameters initially selected were vefY conservative regarding initial losses, neglecting most of the upstream dams and use of conservative starting pool elevations at spillway crest,. The licensee's SMEs also noted that one iteration was performed and once the PMF elevation was below site grade the process was ended. The licensee also had relevant background information available during these discussions.
he staff reviewed the material requested in the
                                                                                                    ~
14  3.2: Flooding in Have available a knowledgeable SME to discuss the selection of the centering Rivers and    and orientation for the basin-wide PMP storm for estimation of the PMF. Be       udit Plan and spoke to the licensee's SMEs.
Streams      prepared to present justifications and/or data support for this selection.       hese actions lead to partial resolution of the staffs arlier questions. Further staff review is necessary NRC staff notes: For the purposes of the basin-wide PMF calculation             .o better understand the level of conservatism in the discussion, the licensee's SMEs noted that the storm center was taken as the   licensee's analysis approach. Thestaff may issue center of the watershed. The licensee's SMEs also noted that the HMR52         RAis to address concerns.
computer program internally computes storm orientation to maximize rainfall depth within the user -defined watershed. Evaluation of additional storm centers was judged not to provide additional value and the licensee's SMEs relied on expert judgment to determine that the one storm orientation used would produce the most severe flooding possible. The licensee had other relevant background information available during these discussions.
 
Serial~**.
                                                                                                                            /'                 ,\, *., '',' *<.''
              ** FHRR                                                        ' '~                                                          ~'
No. .
* Section                                      Information Need(t;)J ** * **                ;                    Action (Post Audit) ..
15 I    3.2: Flooding in Have available a knowledgeable SME to discuss reasonable alternative centering he staff reviewed the material requested in the Rivers and    locations and orientations for the site-specific PMP storm for estimation of the  udit Plan and spoke to the licensee's SMEs.
Streams    PMF. Be prepared to discuss how these alternative centering locations could        hese actions lead to partial resolution of the staffs affect the flood hazard at or near the IPEC site and the associated levels of      arlier questions. Further staff review will be conservatism.                                                                    necessary to better understand the level of onservatism in the licensee's analitical approach.
NRC staff notes: No alternative centering locations or orientations for the site-  hestaff may issue RAis to address concerns.
specific PMP were used by the licensee's SMEs who relied upon expert judgment in determining that all other alternative locations would result in less severe flooding near the /PEG site. The licensee had SMEs available to discuss the issues. Relevant information was made available by the licensee during the audit.
16      3.2: Flooding in  Have available a map of the domains used for Hydrologic Engineering Center      The staff reviewed the material requested in the Rivers and      Hydrologic Modeling System (HEC-HMS) and Hydrologic Engineering Center          Audit Plan and found it sufficient. An electronic Streams      River Analysis System (HEC-RAS) that clearly shows rivers, tributaries, dams    copy was later provided to the ERR as requested and other hydraulic structures, reservoirs, watershed boundaries, and the        for follow-up.
location of gage stations. The map should clearly show the domains used for HEC-HMS and HEC-RAS, as well as the locations of cross sections used for HEC-RAS analyses.
NRC staff notes: The licensee's SMEs provided a large scale map during the audit showing the requested information. An electronic copy was also requested for the ERR and was subsequently provided.
he staff reviewed the material requested in the
                                                                                                              ~
17      3.2: Flooding in  Have available the HEC-HMS documentation (input and output files; Rivers and      calculation packages) and a knowledgeable SME to discuss:                         udit Plan and concluded that it still has questions.
Streams
* Precipitation transformation                                                  he staff subsequently requested that additional
* Channel routing characteristics                                               ocumentation be placed in the ERR concerning the
* Reservoir characteristics                                                     HEC-HMS computer modeling. Upon receipt of the requested information in the ERR, the staff will NRC staff notes: The licensee's SMEs provided an overview of the approach to     review it and determine if it has any additional
 
Serial      FHRR                                          Information N~d(s)1**.                                               Action (Po~fAudit) * .*.
No.      Section                                                        *.
the PMF calculation using the HEC-HMS computer code. Relevant information           ~uestions.
(i.e., the input/output files and calculation packages) was made available by the licensee for the staff to review during the audit break-out session, and the SMEs were on hand to aid in the interpretation of that information. Specific points discussed included unit hydrograph parameters used, infiltration loss rates, channel routing methods and available dam data for selected dams. During the breakout session, the licensee's SMEs noted:
* Precipitation transformation was performed via the Snyder Method with calibration and verification.
* Precipitation transformation was performed via the Snyder Method with calibration and verification.
* Routing was performed with Muskingum and Muskingum-Cunge.
* Routing was performed with Muskingum and Muskingum-Cunge.
Line 62: Line 188:
* Initial losses during the PMF were zero.
* Initial losses during the PMF were zero.
* Constant losses changed during calibration, and were initially estimated from the minimum published typical infiltration rate for each hydrologic soil group.
* Constant losses changed during calibration, and were initially estimated from the minimum published typical infiltration rate for each hydrologic soil group.
* 8-point cross-section was used for Muskingum-Cunge. Have available the HEC-HMS documentation (input and output files; calculation packages) and a knowledgeable SME to discuss:
* 8-point cross-section was used for Muskingum-Cunge.
* Quality control checks (if applicable)
he staff reviewed the material requested in the
* Model calibration NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of the PMF using the HEC-HMS computer code. Relevant information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff to review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information. Specific points noted by the licensee's SMEs during the break-out sessions staff reviewed the material requested in the udit Plan and concluded that it still has questions. he staff subsequently requested that additional ocumentation be placed in the ERR concerning the HEC-HMS computer modeling. Upon receipt of the requested information in the ERR, the staff will 1review it and determine if it has any additional Serial. No. 19 20 FHRR <Section 3.2: Flooding in Rivers and Streams 3.2: Flooding in Rivers and Streams . Information Need(s) 1 --included the following:
                                                                                                            ~
18  3.2: Flooding in    Have available the HEC-HMS documentation (input and output files; Rivers and      calculation packages) and a knowledgeable SME to discuss:                           udit Plan and concluded that it still has questions.
Streams
* Quality control checks (if applicable)                                             he staff subsequently requested that additional
* Model calibration                                                                 ocumentation be placed in the ERR concerning the HEC-HMS computer modeling. Upon receipt of the NRC staff notes: The licensee's SMEs provided an overview of their approach         requested information in the ERR, the staff will to the calculation of the PMF using the HEC-HMS computer code. Relevant             1review it and determine if it has any additional information (i.e., the input/output files and calculation packages) was made       ~uestions.
available by the licensee for the staff to review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information.
Specific points noted by the licensee's SMEs during the break-out sessions
 
                                                                                                                                                                                                                            ~  . '. *,'
Serial.     FHRR                                                                                                             ,_.: .'              ''} ,' ' /
                                                          . Information Need(s) 1                                             Action      (Post Audit).
No.      <Section                                                                                --
included the following:
* 19 sub-watersheds were included in the model, 12 of which were gaged and used for model calibration/verification.
* 19 sub-watersheds were included in the model, 12 of which were gaged and used for model calibration/verification.
* 3 calibration and 3 verification floods were used including: o 2011 modem flood of record downstream o most recent Green Island gage (previous peak 1936, no reliable data available)
* 3 calibration and 3 verification floods were used including:
* Calibration/verification fits are ultimately based on engineering judgment. Have available the HEC-HMS documentation (input and output files; calculation packages) and a knowledgeable SME to discuss:
o 2011 modem flood of record downstream o most recent Green Island gage (previous peak 1936, no reliable data available)
* Discharge results NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of the PMF using the HEC-HMS computer code. Relevant information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information. Specific points noted by the licensee's SMEs during the break-out sessions focused on zero initial losses. Watershed average verified constant loss Initial estimates of constant loss rates were based on the low end of values of typical loss rates for each hydrologic soil group Have available the HEC-RAS documentation (input and output files; calculation packages) and a knowledgeable SME to discuss:
* Calibration/verification fits are ultimately based on engineering judgment.
* Boundary conditions (upstream and downstream)
19    3.2: Flooding in    Have available the HEC-HMS documentation (input and output files;               The staff reviewed the material requested in the Rivers and      calculation packages) and a knowledgeable SME to discuss:                       Audit Plan. The staffs information needs were Streams
* Tributary and lateral inflows
* Discharge results                                                             sufficiently resolved for staff to better understand the licensee's approach. The staff may issue NRC staff notes: The licensee's SMEs provided an overview of their approach       RAis to address concerns.
* Channel routing characteristics NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of the PMF using the HEC-HMS computer code. Relevant ,_.: .' . '. *,' ''} ,' ' / Action (Post Audit). ,, '*'' ,. ,, The staff reviewed the material requested in the Audit Plan. The staffs information needs were sufficiently resolved for staff to better understand the licensee's approach. The staff may issue RAis to address concerns. The staff reviewed the material requested in the Audit Plan. The staffs information needs were sufficiently resolved for staff to better understand the licensee's approach. The staff may issue RAis to address concerns.
to the calculation of the PMF using the HEC-HMS computer code. Relevant information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information. Specific points noted by the licensee's SMEs during the break-out sessions focused on zero initial losses. Watershed average verified constant loss Initial estimates of constant loss rates were based on the low end of values of typical loss rates for each hydrologic soil group 20    3.2: Flooding in    Have available the HEC-RAS documentation (input and output files; calculation   The staff reviewed the material requested in the Rivers and      packages) and a knowledgeable SME to discuss:                                   Audit Plan. The staffs information needs were Streams
Serial 21 FHRR Section 3.2: Flooding in Rivers and Streams Information Need(s) 1 information was made available by the licensee for staff review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information. Specific points noted by the licensee during the break-out sessions focused on PMF hydraulics, including
* Boundary conditions (upstream and downstream)                                 sufficiently resolved for staff to better understand
* Tributary and lateral inflows                                                 the licensee's approach. The staff may issue
* Channel routing characteristics                                               RAis to address concerns.
NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of the PMF using the HEC-HMS computer code. Relevant
 
Serial     FHRR                                         Information Need(s) 1                                                 Action (Post Audit)
No~,      Section information was made available by the licensee for staff review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information. Specific points noted by the licensee during the break-out sessions focused on PMF hydraulics, including
* Flow was unsteady.
* Flow was unsteady.
* Very-high downstream boundary condition was used-higher than the 10% exceedance high tide (5.35 ft used vs. 4.5 ft calculated in deterministic storm surge calculation).
* Very-high downstream boundary condition was used- higher than the 10%
exceedance high tide (5.35 ft used vs. 4.5 ft calculated in deterministic storm surge calculation).
* Manning's coefficient selection was based on visual obseNation and FEMA flood studies, with limited calibration.
* Manning's coefficient selection was based on visual obseNation and FEMA flood studies, with limited calibration.
* No lateral inflows were used; all sub-watersheds achieve confluence with the Hudson River upstream of the /PEG model boundary (boundary is 24 miles upstream of /PEG; tidal boundary is at the Troy Lock and Dam 109 Miles upstream of /PEG) Have available the HEC-RAS documentation (input and output files; calculation packages) and a knowledgeable SME to discuss:
* No lateral inflows were used; all sub-watersheds achieve confluence with the Hudson River upstream of the /PEG model boundary (boundary is 24 miles upstream of /PEG; tidal boundary is at the Troy Lock and Dam 109 Miles upstream of /PEG)
* Quality control checks
                                                                                                              ~
* Model calibration NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to the PMF calculation using the HEC-HMS computer code. Relevant information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff to review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information. During the break-out session, the licensee's SMEs noted that model calibration was limited because of a lack of data and tidal characteristics. Two floods were used; the Manning's n value that resulted in the highest water surface elevation was selected for use in the model. The SMEs noted that they could not use Hurricane Irene (2011) data because the event had a very significant storm Action (Post Audit) staff reviewed the material requested in the udit Plan and spoke to the licensee's SMEs. hese actions lead to partial resolution of the staffs arlier questions. Further staff review is necessary o better-understand the level of conservatism in the licensee's analysis approach. The staff may issue RAis to address concerns.
21  3.2: Flooding in    Have available the HEC-RAS documentation (input and output files; calculation       he staff reviewed the material requested in the Rivers and      packages) and a knowledgeable SME to discuss:                                       udit Plan and spoke to the licensee's SMEs.
Serial No. 22 FHRR Section 3.2: Flooding in Rivers and Streams Information Need(s) 1 . *. -surge component; the same issue encountered for Hurricane Sandy. The SMEs also noted HEC-RAS cannot reliably model storm surges. Have available the HEC-RAS documentation (input and output files; calculation packages) and a knowledgeable SME to discuss:
Streams
* Water surface elevation results NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to the calculation of the PMF using the HEC-HMS computer code. Relevant information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff to review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information. >Action (Post Audit) staff reviewed the material requested in the Audi Plan and spoke to the licensee's SMEs. The staffs information needs were sufficiently resolved for the to better understand the licensee's approach. 23 I 3.3: Dam Have available a knowledgeable SME to discuss how the HHA approach he staff reviewed the material requested in the Audi and Failures I described in NUREG/CR-7046 was applied to determine the flooding from dam Plan and spoke to the licensee's SMEs. The staffs 24 3.3: Dam and Failures failure mechanisms at and near the IPEC site. information needs were sufficiently resolved for the taff to better understand the licensee's approach. NRC staff notes: The licensee's SMEs provided an overview of how the HHA he staff may issue RAis to address concerns. approach was applied to the PMF calculation attributed to dam failure. No analysis was done of results that would be associated with the PMP values that would be derived from HMR 51. During the break-out session, the licensee's SMEs discussed their HHA approach in more detail. The licensee also had relevant background infonnation available during those discussions. During the break-out session, the licensee's SMEs noted that no individual PMP centerings were used in order to maximize dam failure contribution. Have available a knowledgeable SME to discuss the centering and orientation for the basin-wide PMP storm used for estimation of the maximum flooding from the dam failure flood causing mechanism. Be prepared to present justifications and/or data support for this selection. The staff reviewed the material requested in the Audit Plan and spoke to the licensee's SMEs. These actions lead to partial resolution of the staffs earlier questions. Further staff review is necessary to better understand the level of
* Quality control checks                                                             hese actions lead to partial resolution of the staffs
.Serial No. FHRR Section* Information Need(s) 1' NRC staff notes: The licensee's SMEs provided an overview of their approach to the centering and orientation of the basin-wide PMP. During the break-out session, the licensee discussed the significance of reasonable alternative PMP centering and orientation on the PMF calculation and the potential for dam failure. The licensee also had relevant background information available during those discussions. During the break-out session, the licensee's SMEs noted the following:
* Model calibration                                                                 arlier questions. Further staff review is necessary o better-understand the level of conservatism in the NRC staff notes: The licensee's SMEs provided an oveNiew of their approach           licensee's analysis approach. The staff may issue to the PMF calculation using the HEC-HMS computer code. Relevant                     RAis to address concerns.
information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff to review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information.
During the break-out session, the licensee's SMEs noted that model calibration was limited because of a lack of data and tidal characteristics. Two floods were used; the Manning's n value that resulted in the highest water surface elevation was selected for use in the model. The SMEs noted that they could not use Hurricane Irene (2011) data because the event had a very significant storm
 
Serial       FHRR                                         Information Need(s) 1 . *.                                           >Action (Post Audit)
No.        Section                              -
surge component; the same issue encountered for Hurricane Sandy.             The SMEs also noted HEC-RAS cannot reliably model storm surges.
22      3.2: Flooding in    Have available the HEC-RAS documentation (input and output files; calculation   ~he staff reviewed the material requested in the Audi Rivers and      packages) and a knowledgeable SME to discuss:                                   Plan and spoke to the licensee's SMEs. The staffs Streams
* Water surface elevation results                                               information needs were sufficiently resolved for the
                                                                                                              ~taff to better understand the licensee's approach.
NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to the calculation of the PMF using the HEC-HMS computer code. Relevant information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff to review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information.
23 I 3.3: Dam Breache~ Have available a knowledgeable SME to discuss how the HHA approach                       he staff reviewed the material requested in the Audi and Failures   I described in NUREG/CR-7046 was applied to determine the flooding from dam Plan and spoke to the licensee's SMEs. The staffs failure mechanisms at and near the IPEC site.                                   information needs were sufficiently resolved for the taff to better understand the licensee's approach.
NRC staff notes: The licensee's SMEs provided an overview of how the HHA he staff may issue RAis to address concerns.
approach was applied to the PMF calculation attributed to dam failure.         No analysis was done of results that would be associated with the PMP values that would be derived from HMR 51. During the break-out session, the licensee's SMEs discussed their HHA approach in more detail. The licensee also had relevant background infonnation available during those discussions. During the break-out session, the licensee's SMEs noted that no individual PMP centerings were used in order to maximize dam failure contribution.
24  3.3: Dam Breache~ Have available a knowledgeable SME to discuss the centering and orientation           The staff reviewed the material requested in the and Failures      for the basin-wide PMP storm used for estimation of the maximum flooding           Audit Plan and spoke to the licensee's SMEs.
from the dam failure flood causing mechanism. Be prepared to present               These actions lead to partial resolution of the justifications and/or data support for this selection.                             staffs earlier questions. Further staff review is necessary to better understand the level of
 
                                                                                      .Serial       FHRR Information Need(s) 1'                                           Actiori (Post Audit)
No.        Section*
NRC staff notes: The licensee's SMEs provided an overview of their approach         conservatism in the licensee's analitical to the centering and orientation of the basin-wide PMP. During the break-out       approach. The staff may issue RAis to address session, the licensee discussed the significance of reasonable alternative PMP     concerns.
centering and orientation on the PMF calculation and the potential for dam failure. The licensee also had relevant background information available during those discussions. During the break-out session, the licensee's SMEs noted the following:
* Issue of centering PMP over individual dam watersheds would not provide appreciable value
* Issue of centering PMP over individual dam watersheds would not provide appreciable value
* Dam failure scenario forced a Conklingville dam failure and combined it with the PMP storm applied to the center of the watershed (Conklingville dam watershed is 8.3% of watershed above /PEG, and Ashokan and Rondaout are even smaller),
* Dam failure scenario forced a Conklingville dam failure and combined it with the PMP storm applied to the center of the watershed (Conklingville dam watershed is 8.3% of watershed above /PEG, and Ashokan and Rondaout are even smaller),
Line 88: Line 253:
* Initial screening criterion was dam breaches that would be 1,000,000 cfs (without attenuation) because most dams are far from /PEG (no dams on the Hudson River within 100 miles)
* Initial screening criterion was dam breaches that would be 1,000,000 cfs (without attenuation) because most dams are far from /PEG (no dams on the Hudson River within 100 miles)
* Due to Individual dam watersheds relative to overall watershed, PMP over centroid was considered to result tin highest calculated PMF based on expert judgment
* Due to Individual dam watersheds relative to overall watershed, PMP over centroid was considered to result tin highest calculated PMF based on expert judgment
* HHA was used--no attenuation was necessary. More severe combinations would have triggered use of additional detailed modeling (or USBR attenuation equations) to consider attenuation. 25 I 3.3: Dam Have available a knowledgeable SME to discuss reasonable alternative and Failures I centering locations for the site-specific PMP storm for estimation flooding from Actiori (Post Audit) conservatism in the licensee's analitical approach. The staff may issue RAis to address concerns. The staff reviewed the material requested in the Audit Plan and spoke to the licensee's SMEs.
* HHA was used-- no attenuation was necessary. More severe combinations would have triggered use of additional detailed modeling (or USBR attenuation equations) to consider attenuation.
Serial No. FHRR Section Information Need{s) 1 dam failures. Be prepared to discuss how these alternative centering locations could affect the flood hazard at or near the IPEC site. NRC staff notes: The licensee's SMEs provided an overview of their approach to analysis related to dam breaches and failures. The licensee's SMEs did not perform additional simulations of PMP storms centered over the centroid of watersheds upstream to individual dams. The licensee's SMEs determined that flooding at /PEG by such storms would not result in more severe flooding at the /PEG site based upon expert judgment. The licensee also had relevant background information available during those discussions. 26 I 3.3: Dam Have available a map of the domain that clearly shows the locations of dams 27 and Failures I and reservoirs considered in dam failure analysis, as well as the rivers and 3.3: Dam Breaches and Failures tributaries along which any flood resulting from dam failures would be routed. NRC staff notes: The licensee's SMEs provided an appropriate map and explained various features in the map. Have available the HEC-HMS and HEC-RAS documentation (input and output files; calculation packages) and a knowledgeable SME to discuss:
25 I 3.3: Dam Breache~    Have available a knowledgeable SME to discuss reasonable alternative             The staff reviewed the material requested in the and Failures I   centering locations for the site-specific PMP storm for estimation flooding from Audit Plan and spoke to the licensee's SMEs.
* Selection of reservoirs and dams for failure analysis
 
* Breach flood routing characteristics NRC staff notes: The licensee's SMEs provided an overview of their approach in using the HEC-HMS and HEC-RAS computer code in the dam failure analysis. Relevant information was made available by the licensee for the staff, including the rationale for the selection of certain dam modeling parameters, and SMEs were on hand to aid in the interpretation of that information. During the break-out sessions, the licensee's SMEs noted the following with respect to the dam modeling exercise:
Serial        FHRR Information Need{s) 1                                            Action (Post}\udit)
* No attenuation of dam breach flood flows. Action (Post}\udit) These actions lead to partial resolution of the staffs earlier questions. Further staff review is necessary to better understand the level of conservatism in the licensee's analitical approach. The staff may issue RAis during subsequent review of the licensee's submission. The staff reviewed the material requested in the Audit Plan and requested that an electronic copy of the map be placed in the ERR. An appropriate digital map was subsequently provided in the ERR. he staff reviewed the material requested in the udit Plan and concluded that it still had questions. he staff subsequently requested that additional ocumentation be placed in the ERR. Upon receipt f the requested information in the ERR, the staff will review it and determine if it has any additional Serial1 .No. FHRR Section Information Need(s) 1
No.         Section dam failures. Be prepared to discuss how these alternative centering locations  These actions lead to partial resolution of the could affect the flood hazard at or near the IPEC site.                         staffs earlier questions. Further staff review is necessary to better understand the level of NRC staff notes: The licensee's SMEs provided an overview of their approach     conservatism in the licensee's analitical to analysis related to dam breaches and failures. The licensee's SMEs did not   approach. The staff may issue RAis during perform additional simulations of PMP storms centered over the centroid of       subsequent review of the licensee's submission.
* Forced hydrologic failure of the Conklingville Dam (FERC regulated structure) although it did not overtop during the PMF. Selection of dams based on largest heights, storage volumes, and proximity to the /PEG site. Action (Post Audit) 28 I 3.4: Storm Surge I Have available the following documents and appropriate references, as well as a knowledgeable SME to discuss the methodology used for the deterministic characterization of storm surge, including:
watersheds upstream to individual dams. The licensee's SMEs determined that flooding at /PEG by such storms would not result in more severe flooding at the /PEG site based upon expert judgment. The licensee also had relevant background information available during those discussions.
* The application of the SLOSH model as a screening tool, including the here was partial resolution of the staff's earlier assumptions used to implement model simplifications, grid resolution near the uestions in this area. The staff may issue RAis Indian Point facility, and no river inflow at the upstream boundary requesting results from additional computer runs Comparisons of SLOSH model results with measurements to validate the one with the ADCIRC computer code to account for SLOSH model's ability to simulate storm surge near the Indian Point facility. limitations in the screening tool.
26 I 3.3: Dam Breache~ Have available a map of the domain that clearly shows the locations of dams       The staff reviewed the material requested in the and Failures I and reservoirs considered in dam failure analysis, as well as the rivers and     Audit Plan and requested that an electronic copy tributaries along which any flood resulting from dam failures would be routed. of the map be placed in the ERR. An appropriate digital map was subsequently provided in the NRC staff notes: The licensee's SMEs provided an appropriate map and           ERR.
* The development and application of probability distributions applied to here was partial resolution of the staff's earlier develop the SLOSH model input parameter combinations. As part of this uestions in this area. The staff may issue RAis discussion, provide information on the upper limits applied for the requesting additional justification of capping of PMH meteorological forcing parameters. If this upper limit involved the estimation ind fields as well as additional information on of an MPI central pressure, describe how this was done. If this was done via relation of Rmax as applied in WRT analysis and an upper limit derived based on Extreme Value Statistics, describe how this probability distribution development. The staff was done. Also, discuss the application of the Extreme Value Statistics (EVS) mayalso inquire if any comparisons of WRT Rmax performed to estimate the probability of strong storms in the study region. alues and data have been made. Include the probability distributions used for different storm parameters and any references to their previous application to this region. If there are no previous applications of the specific distributions used here, provide a plot of the data and the fit to the data provided by the specific distributions used in this effort.
explained various features in the map.
* The application of the ADCIRC model within the deterministic analysis and any modeling difficulty encountered (such as instability for strong storms). staff concluded that additional documentation in his area is still needed. Thestaff plans to issue an RAI requesting additional discussion of any ADCIRC  Serial FHRR Information 1 Action*(Post:Auditf No. . Section .<. model instability encountered running the deterministic or probabilistic storms and any vOrrective actions taken.
27  3.3: Dam Breaches Have available the HEC-HMS and HEC-RAS documentation (input and output            he staff reviewed the material requested in the and Failures    files; calculation packages) and a knowledgeable SME to discuss:                udit Plan and concluded that it still had questions.
* Comparisons of the SLOSH and ADCIRC results for similar storms and There was partial resolution of the staffs earlier whether the results indicate suitable model results for application of SLOSH questions in this area. The staff may issue RAis requesting results from additional computer runs done with the ADCIRC computer code to account for limitations in the screening tool.
* Selection of reservoirs and dams for failure analysis                          he staff subsequently requested that additional
* Comparisons of the ADCIRC tidal model results to confirm consistency The staffs information needs were sufficiently between the simulated and predicted tidal phasing, range, and amplitude. resolved for the staff to better understand the licensee's approach. The staff may issue RAis to address concerns.
* Breach flood routing characteristics                                          ocumentation be placed in the ERR. Upon receipt f the requested information in the ERR, the staff will NRC staff notes: The licensee's SMEs provided an overview of their approach      review it and determine if it has any additional in using the HEC-HMS and HEC-RAS computer code in the dam failure                ~uestions.
* The development of the still water elevation, wave crest elevation, and limit of The staffs information needs were sufficiently run-up for Combined Flood Event Alternatives 1, 2, and 3 resolved for the staff to better understand the licensee's approach. The staff may issue RAis to address concerns.
analysis. Relevant information was made available by the licensee for the staff, including the rationale for the selection of certain dam modeling parameters, and SMEs were on hand to aid in the interpretation of that information. During the break-out sessions, the licensee's SMEs noted the following with respect to the dam modeling exercise:
* Provide evidence that wave setup is not important at the site . There was partial resolution of the staffs earlier questions in this area. The staff may issue RAis requesting results from additional computer runs done with ADCIRC to account for limitation in screening tool.
* No attenuation of dam breach flood flows.
* Details of methods applied to develop the flow velocity and hydrodynamic The staffs information needs were sufficiently loads at the site resolved for the staff to better understand the licensee's approach. The staff may issue RAis to address concerns.
 
* Discuss the source of the bathymetry data and interpolation method applied in The staffs information needs were sufficiently Serial No. FHRR Section
Serial      FHRR                                        Information Need(s) 1                                                    Action (Post Audit)
* Information Need(s) t,,, ',;"';/ ;c,-the development of the A DCI RC model mesh. Discuss the scope of changes made to the Federal Emergency Management Agency (FEMA) Region II mesh to refine the area near the Indian Point facility. Provide input files necessary to recreate two of the SLOSH and ADCIRC model results in Tables 3.4-10 and 3.412. NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to the calculation of probabilistic storm surge at the IPEC site. During the break-out session, the licensee's SMEs noted the following:
.No. 1    Section
* Forced hydrologic failure of the Conklingville Dam (FERC regulated structure) although it did not overtop during the PMF.
Selection of dams based on largest heights, storage volumes, and proximity to the /PEG site.
28 I 3.4: Storm Surge I Have available the following documents and appropriate references, as well as a knowledgeable SME to discuss the methodology used for the deterministic characterization of storm surge, including:
* The application of the SLOSH model as a screening tool, including the             here was partial resolution of the staff's earlier assumptions used to implement model simplifications, grid resolution near the uestions in this area. The staff may issue RAis Indian Point facility, and no river inflow at the upstream boundary              requesting results from additional computer runs Comparisons of SLOSH model results with measurements to validate the              one with the ADCIRC computer code to account for SLOSH model's ability to simulate storm surge near the Indian Point facility. limitations in the screening tool.
* The development and application of probability distributions applied to            here was partial resolution of the staff's earlier develop the SLOSH model input parameter combinations. As part of this              uestions in this area. The staff may issue RAis discussion, provide information on the upper limits applied for the              requesting additional justification of capping of PMH meteorological forcing parameters. If this upper limit involved the estimation    ind fields as well as additional information on of an MPI central pressure, describe how this was done. If this was done via    relation of Rmax as applied in WRT analysis and an upper limit derived based on Extreme Value Statistics, describe how this      probability distribution development. The staff was done. Also, discuss the application of the Extreme Value Statistics (EVS)    mayalso inquire if any comparisons of WRT Rmax performed to estimate the probability of strong storms in the study region.       alues and data have been made.
Include the probability distributions used for different storm parameters and any references to their previous application to this region. If there are no previous applications of the specific distributions used here, provide a plot of the data and the fit to the data provided by the specific distributions used in this effort.
* The application of the ADCIRC model within the deterministic analysis and       ~he staff concluded that additional documentation in any modeling difficulty encountered (such as instability for strong storms).     his area is still needed. Thestaff plans to issue an RAI requesting additional discussion of any ADCIRC
 
Serial    FHRR Information  Ne~d(s) 1                                                  Action*(Post:Auditf            .<.
No.   . Section model instability encountered running the deterministic or probabilistic storms and any vOrrective actions taken.
* Comparisons of the SLOSH and ADCIRC results for similar storms and              There was partial resolution of the staffs earlier whether the results indicate suitable model results for application of SLOSH    questions in this area. The staff may issue RAis requesting results from additional computer runs done with the ADCIRC computer code to account for limitations in the screening tool.
* Comparisons of the ADCIRC tidal model results to confirm consistency            The staffs information needs were sufficiently between the simulated and predicted tidal phasing, range, and amplitude.         resolved for the staff to better understand the licensee's approach. The staff may issue RAis to address concerns.
* The development of the still water elevation, wave crest elevation, and limit of The staffs information needs were sufficiently run-up for Combined Flood Event Alternatives 1, 2, and 3                        resolved for the staff to better understand the licensee's approach. The staff may issue RAis to address concerns.
* Provide evidence that wave setup is not important at the site .                  There was partial resolution of the staffs earlier questions in this area. The staff may issue RAis requesting results from additional computer runs done with ADCIRC to account for limitation in screening tool.
* Details of methods applied to develop the flow velocity and hydrodynamic        The staffs information needs were sufficiently loads at the site                                                                resolved for the staff to better understand the licensee's approach. The staff may issue RAis to address concerns.
* Discuss the source of the bathymetry data and interpolation method applied in The staffs information needs were sufficiently
 
Serial  FHRR Information Need(s)          t,,,                                       ActiQn . (PostAud!t)
No. Section                                                    ',;"';/ ;c,-
the development of the ADCI RC model mesh. Discuss the scope of changes resolved for the staff to better understand the made to the Federal Emergency Management Agency (FEMA) Region II                licensee's approach. The staff may issue RAis to mesh to refine the area near the Indian Point facility.                            ddress concerns.
* Provide input files necessary to recreate two of the SLOSH and ADCIRC model results in Tables 3.4-10 and 3.412.                                      t  he staffs information needs were sufficiently esolved for the staff to better understand the licensee's approach. The staff may issue RAis to
                                                                                                    ~ddress concerns.
NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to the calculation of probabilistic storm surge at the IPEC site. During the break-out session, the licensee's SMEs noted the following:
* SLOSH model was used as a as a screening tool.
* SLOSH model was used as a as a screening tool.
* Model simplifications: grid resolution near the IPEC site was judged to have no impact because final runs were made in ADCIRC.
* Model simplifications: grid resolution near the IPEC site was judged to have no impact because final runs were made in ADCIRC.
Line 109: Line 297:
* No stability issues were experienced with ADCIRC.
* No stability issues were experienced with ADCIRC.
* Comparisons of the SLOSH and ADCIRC results were favorable for river surge results. Differences were found for results in the NY Harbor area.
* Comparisons of the SLOSH and ADCIRC results were favorable for river surge results. Differences were found for results in the NY Harbor area.
* Wave set-up is included in the empirically-based calculation for wave up. The component of wave set -up that was not included was deep water waves breaking at the IPEC bulkhead. For these waves, the licensee expressed the view that existing site conditions (flat areas, structures, etc.) are such that momentum is lost.
* Wave set-up is included in the empirically-based calculation for wave run-up. The component of wave set -up that was not included was deep water waves breaking at the IPEC bulkhead. For these waves, the licensee expressed the view that existing site conditions (flat areas, structures, etc.)
* Coupled ADCIRC and numerical wave model (e.g. SWAN, STWAVE) was not performed here for several reasons: o Wind and surge at the site are effectively decoupled activities; in particular with the assumption of steady state storm tracks. That is, most tracks will not result in significant waves at the site o Given the predicted inundation, most waves are depth limited. ActiQn .. (PostAud!t) resolved for the staff to better understand the licensee's approach. The staff may issue RAis to tddress concerns. he staffs information needs were sufficiently esolved for the staff to better understand the licensee's approach. The staff may issue RAis to concerns.
are such that momentum is lost.
Serial No. FHRR Section Information Need{s) 1 o It was decided that a more conservative approach would be to calculate deep water waves using simplified procedures, but assume the worst wind and worst fetch direction, and add to the highest surge still water elevation (including tide and river flood).
* Coupled ADCIRC and numerical wave model (e.g. SWAN, STWAVE) was not performed here for several reasons:
o Wind and surge at the site are effectively decoupled activities; in particular with the assumption of steady state storm tracks. That is, most tracks will not result in significant waves at the site o Given the predicted inundation, most waves are depth limited.
 
Serial       FHRR Information Need{s) 1                                                 Action (Post AlJdit).
No.        Section o   It was decided that a more conservative approach would be to calculate deep water waves using simplified procedures, but assume the worst wind and worst fetch direction, and add to the highest surge still water elevation (including tide and river flood).
* The input files necessary to recreate two of the SLOSH and ADCIRC model results were provided.
* The input files necessary to recreate two of the SLOSH and ADCIRC model results were provided.
* Bathymetry used with ADCIRC was provided by FEMA. Action (Post AlJdit). 29 I 3.4: Storm Surge I Have available appropriate documents and references, as well as an SME who is staff spoke to the licensee's SMEs. Based on knowledgeable about the probabilistic characterization of storm surge to discuss hose conversations, the staff may issue RAis to the following: urther address these issues. 30
* Bathymetry used with ADCIRC was provided by FEMA.
* Rationale for selecting 2 x 10*6 as the appropriate level to establish the reevaluated storm surge elevation
29 I 3.4: Storm Surge I Have available appropriate documents and references, as well as an SME who is ~he staff spoke to the licensee's SMEs.           Based on knowledgeable about the probabilistic characterization of storm surge to discuss hose conversations, the staff may issue RAis to the following:                                                                       urther address these issues.
* Interpretation of the hazard curve and annual exceedance probability (AEP) of 2 x 1 Q-6 light of the use of deterministic models and event combinations and any associated potential bias inherent in models employed as well as any uncertainties that were considered or neglected. NRC Staff notes: The licensee's SMEs provided an overview of their approach to the calculation of probabilistic storm surge at the /PEG site. Through the course of the audit, the SMEs stated that conservatisms in the probabilistic storm surge calculations provide justification for the selection of the 2 x 1 Q-6 number. The interpretation of the hazard curve (e.g., whether the hazard curve can be interpreted as a mean curve) and AEP of 2 x 1D-6 remains unclear due to the use of deterministic models and event combinations, associated potential bias inherent in models employed, as well as uncertainties that were neglected. 3.4: Storm Surge 1 Have available appropriate documents, codes, and references as well as an SME who is knowledgeable about the probabilistic characterization of storm surge to discuss the following:
6
* Characterization and propagation of relevant sources of aleatory variability staff spoke to the licensee's SMEs. Based on hose conversations, the licensee made presentation materials and supplemental written responses from he audit available to staff in the ERR. The staff plans Serial .. No; FHRR section Information Need(s) 1 (e.g., probability density functions associated with storm parameters and model errors).
* Rationale for selecting 2 x 10* as the appropriate level to establish the reevaluated storm surge elevation
* The means by which epistemic uncertainties in related data, models and methods were addressed, including, but not limited to, the following topics: o alternate technical interpretations of relevant data, including considerations of different means of selecting, interpreting, and filtering data from the HURDAT database. o alternate technical interpretations of relevant probability density (mass) functions used to characterize aleatory uncertainty associated with storm parameters (e.g., intensity, storm track, radius to maximum winds, and storm translational speed) o alternate technically defensible models and modeling decisions
* Interpretation of the hazard curve and annual exceedance probability (AEP) of 2 x 1Q-6 light of the use of deterministic models and event combinations and any associated potential bias inherent in models employed as well as any uncertainties that were considered or neglected.
* The means by which epistemic uncertainties were quantified and propagated (e.g., development of logic trees, if applicable}. NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of probabilistic storm surge at the /PEG site. During the break-out sessions that followed, an A REV A subcontractor (Dr. Emanuel) described the methods used to develop the probability distributions for storm parameters, including consideration of historic and synthetic data (with multiple geographic filters) as well as the use of nonparametric methods and extreme value analysis. The licensee described the consideration of epistemic uncertainty via "benchmarking" and justification for conservative assumptions. Epistemic uncertainties were not explicitly quantified or propagated. The licensee provided supplemental information in the form of presentation materials addressing the items listed above and written response to specific follow-up questions (e.g., questions related to bootstrap algorithms employed for verification analyses). Additionally, the licensee referenced a 2006 Emanuel paper that looked at probability distribution comparisons to historical data. Actioll.lPos(Audit) o issue RAis, as needed, to request that the licensee information contained in the presentation materials or supplemental materials if it serves as a asis for conclusions documented in the staff ssessment. The staff may also request additional o more detailed information regarding modeling 31 I 3.4: Storm Surge I Have available an electronic copy of the Excel spreadsheet !Staff may issue RAI requesting justification for Serial No: 32 FHRR Section . Information Need(s) 1 ' C,c (Post Audit) JPM_SLOSH_ADCIRC_1 03013.xlsx referenced in Appendix H of calculation in results near 2 x 10-6 level (may require package 32-9213352-000 as well as personnel knowledgeable in its contents dditional simulations to bolster confidence in the 2 and usage. 1 Q-6 values NRC staff notes: The subject spreadsheet identified in the audit plan was made available to the staff prior to the audit as part of an RAI response. The staff asked various questions related to the spreadsheet on topics such as treatment of probability mass associated with combinations of parameters assigned "-999" surge values, confidence in results near the 2 x 1 D-6 level and selection of computer runs for refinement using ADCIRC. As a result, the staff was able to develop an understanding of the spreadsheets' contents and usage. 3.4: Storm Surge I Have available relevant documentation and an SME who is knowledgeable about the probabilistic characterization of storm surge to discuss any sensitivity studies performed to support the probabilistic storm surge analysis (PSSA). NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of probabilistic storm surge at the /PEG site. Results of sensitivity studies were discussed. In addition, presentation materials were prepared summarizing parameter sensitivity (e.g., as low, moderate, or high). In addition, supplemental materials were presented related to sensitivity studies of parameter ranges and discretization considered in the joint probability method (JPM) integration. licensee has made presentation materials from he audit available to staff in the ERR. The staff plans to issue RAis, as needed, to request that the licensee docket information contained in the presentation materials if it serves as a basis for documented in the staff assessment. he staff may also request additional or more etailed information regarding sensitivity studies. 33 I 3.4: Storm Surge I Have available appropriate documents, codes, and references as well as an SME The staff will continue its review of information who is knowledgeable about the probabilistic characterization of storm surge to ontained in the ERR (e.g., calculation packages) discuss the following: ith the improved understanding afforded by the
NRC Staff notes: The licensee's SMEs provided an overview of their approach to the calculation of probabilistic storm surge at the /PEG site. Through the course of the audit, the SMEs stated that conservatisms in the probabilistic storm surge calculations provide justification for the selection of the 2 x 1Q-6 number. The interpretation of the hazard curve (e.g., whether the hazard curve can be interpreted as a mean curve) and AEP of 2 x 1D-6 remains unclear due to the use of deterministic models and event combinations, associated potential bias inherent in models employed, as well as uncertainties that were neglected.
* Probability distributions associated with storm parameters and error terms larifying information presented during the audit. The (as applicable) in the JPM integral. taft plans to issue RAis, as needed, to request that
30  3.4: Storm Surge 1 Have available appropriate documents, codes, and references as well as an           ~he staff spoke to the licensee's SMEs. Based on SME who is knowledgeable about the probabilistic characterization of storm           hose conversations, the licensee made presentation surge to discuss the following:                                                     materials and supplemental written responses from
* Basis for distribution models and parameters selected, including any he licensee docket information contained in the Serial No. FHRR Section Information Need(s) 1 , ' analyses performed using expert judgment, based on existing studies, or packages if it serves as a basis for based on available data (e.g., HURDAT) including selection, interpretation, onclusions documented in the staff assessment. If and filtering of available data. necessary, the staff may also request additional or detailed information regarding the datasets NRC staff notes: The licensee's SMEs provided an overview of their approach to tilized, judgments applied, and probability the calculation of probabilistic storm surge at the /PEG site. SMEs provided istributions ultimately selected. significant clarifying information regarding the methodology used to develop probability distributions associated with storm parameters in the JPM integral. A significant portion of the audit was spent discussing the basis for the distribution models selected (e.g., data and methods used to derive distributions, geographic filters applied to datasets, and the means by which temporal correlation in the datasets was addressed). The NRC staff was also afforded the opportunity to discuss the synthetic dataset with the external SME responsible for its development. 34 I 3.4: Storm Surge I Have available appropriate documents, codes, and references as well as an SME he licensee has made presentation materials from who is knowledgeable about the probabilistic characterization of storm surge to he audit available to staff in the ERR. The staff discuss the selected discretization shown in FHRR Tables 3.4-5 through 3.4-9, xpects to issue RAis related to the impact of including (but not limited to) discussion of the basis for the selected discretization iscretization, selected parameter ranges, and and the treatment of the contribution of probability mass associated with reatment of probability mass that was assigned to parameter values outside the range of parameters shown in Tables 3.4-5 through ombinations of parameters later deemed 3.4-9. meteorologically impossible. NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of probabilistic storm surge at the /PEG site. The SMEs prepared a supplemental presentation to illustrate the sensitivity of results to various decisions related to parameter ranges and discretization, including the impact of excluding probability mass outside the ranges of the parameters considered. The NRC staff also raised questions related to exclusion of probability mass assigned to parameter combinations that were later deemed meteorologically impossible.
* Characterization and propagation of relevant sources of aleatory variability       he audit available to staff in the ERR. The staff plans
Serial No *. 35 36 FHRR , Section 3.4: Storm Surge 3.4: Storm Surge
 
* Information Neect(s)1 '' ' ' : // ..?vf/ ,c Action (Post';Audit) ;* .. '* * .. rcc Have available relevant codes, references, and documentation as well as an he staff will continue its review of information SME who is knowledgeable about the probabilistic characterization of storm ontained in the ERR (e.g., calculation packages) surge to discuss the basis for the calculated omni-directional storm rate including ith the improved understanding afforded by the (but not limited to) the basis for the selected capture zone and any sensitivity larifying information presented during the audit. Thel studies that were performed or alternate methods that were considered. NRC taff plans to issue RAis, as needed, to request that also requests that the licensee have available a tabulation of the events he licensee docket information contained in the (including event dates) that were used to compute the omni-directional storm rate alculation packages if it serves as a basis for (as referenced in Section 6.2 of calculation package 32-9213352-000). onclusions documented in the staff assessment. If necessary, the staff may also request additional or NRC staff notes: The licensee's SMEs provided an overview of their approach to jmore detailed information regarding the evaluation the calculation of probabilistic storm surge at the /PEG site. The SMEs prepared the omni-directional rate. presentation materials related to the omni-directional storm rate and provided clarifying information relative to information contained in the calculation packages. The licensee also provided the tabulation of events used to compute the omni-directional rate. Lambda (the storm rate coefficient) was presented in documents using two different units for values presented. The licensee's SME reported that GZA (an AREVA subcontractor) reevaluated lambda to reflect geographic variability. Results are in terms of four shoreline segments (the limits of which were based on observed landfall trends). In general, lambda equal to 0.047 is expected to be appropriate for storms contributing to the 1 x 10-6 return period flood. Have available relevant documentation and an SME who is knowledgeable about he licensee has made presentation materials from the probabilistic characterization of storm surge to discuss the use and he audit available to the staff in the ERR. The staff interpretation of deterministic load combinations (e.g., a 25-year river flow in plans to issue RAis, as needed, to request that the conjunction with the storm surge event) in conjunction with the probabilistic licensee docket information contained in the characterization of storm surge and the basis for those decisions. alculation packages or presentation materials if it erves as a basis for conclusions documented in the NRC staff notes: The licensee's SMEs provided an overview of their approach to taff assessment. If necessary, the staff may also the calculation of probabilistic storm surge at the /PEG site. The SMEs described request additional or more detailed information the rationale for their judgment that the combination of a 25-year river flow in regarding deterministic load combinations. Serial FHRR Information Need(s) 1 Action (PostAudit) No. Section ''""' conjunction with a storm surge event is conservative. Their rationale was based on differences in characteristics between events that create large surges and events that deposit a large amount of rain on the watershed as well as considerations associated with the lack of coherence in the arrival of the peak surge and the arrival of a peak river flow. The licensee's SMEs noted that a 25-year flood was assumed to occur in conjunction with the PMSS. That rainfall event is considered to be conservative and as a further conservatism it is ! assumed to occur with the PMSS a probability of 1. Presentation materials presented during the audit provided graphics to support the rationale provided. 37 3.4: Storm Surge Have available relevant documentation and an SME who is knowledgeable about staff will continue its review of information the probabilistic characterization of storm surge to discuss components of the in the ERR (e.g., calculation packages) PSSA that relied on engineering judgment or experience, including (but not the improved understanding afforded by the limited to) the filtering of data, statistical methods used to develop probability information presented during the audit. density functions (PDFs), selected PDFs, event combinations considered (e.g., staff plans to issue RAis, as needed, to request treatment of concurrent tides and river flows), model selection, and model hat the licensee docket information contained in the parameters. calculation packages if it serves as a basis for documented in the staff assessment. If NRC staff notes: The licensee's SMEs provided an overview of their approach to necessary, the staff may also request additional or the calculation of probabilistic storm surge at the /PEG site. The SMEs identified more detailed information regarding judgments several places where engineering judgment was applied. Moreover, throughout applied during the analysis. the audit, the staff discussed the development of synthetic data, filtering of historic data, methods used to develop (or verify) probability density functions, treatment of tides and river flows, use of numerical models (SLOSH and ADCIRC), and other relevant decisions. Throughout the discussions, the staff further identified components of the analysis that utilized (explicitly or implicitly) engineering judgment or experience. Serial FHRR lnfonnation Need(s) 1 >>>'>> Action"(fiost<Audit) I No. Section >>' >>' '>;< ''1,>':,:">'<>, \c f_, <' ">;,,,,,> ', ' 38 3.4: Storm Surge Have available relevant codes, references, and documentation; and an SME who licensee has made supplemental material is knowledgeable about the probabilistic characterization of storm surge to (contained in presentations) from the audit available discuss the results of verification and validation exercises, including the means o the staff in the ERR. The staff plans to issue by which the Joint Probability Method (JPM) integration accounted for model RAis, as needed, to request that the licensee docket errors. information contained in the presentation materials if it serves as a basis for conclusions documented in NRC staff notes: Entergy contractors provided supplemental information he staff assessment. Pending the results of further describing the basis for exclusion of an error term from the JPM integral. The review, the staff may request additional or more bases provided were centered on a judgment that various modeling decisions detailed information regarding treatment of were conservative (e.g., based on benchmarking studies) or that verification uncertainties. studies showed results were sufficient that an error term was not required. -----
Serial .. FHRR                                           Information Need(s) 1 No;        section                                                                                                                Actioll.lPos(Audit)
(e.g., probability density functions associated with storm parameters and         o issue RAis, as needed, to request that the licensee ocket information contained in the presentation
                                                                                                                ~
model errors).
* The means by which epistemic uncertainties in related data, models and           materials or supplemental materials if it serves as a methods were addressed, including, but not limited to, the following topics:       asis for conclusions documented in the staff o alternate technical interpretations of relevant data, including                 ssessment. The staff may also request additional o considerations of different means of selecting, interpreting, and filtering more detailed information regarding modeling data from the HURDAT database.                                             ~ecisions.
o alternate technical interpretations of relevant probability density (mass) functions used to characterize aleatory uncertainty associated with storm parameters (e.g., intensity, storm track, radius to maximum winds, and storm translational speed) o alternate technically defensible models and modeling decisions
* The means by which epistemic uncertainties were quantified and propagated (e.g., development of logic trees, if applicable}.
NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of probabilistic storm surge at the /PEG site. During the break-out sessions that followed, an AREVA subcontractor (Dr. Emanuel) described the methods used to develop the probability distributions for storm parameters, including consideration of historic and synthetic data (with multiple geographic filters) as well as the use of nonparametric methods and extreme value analysis.
The licensee described the consideration of epistemic uncertainty via "benchmarking" and justification for conservative assumptions. Epistemic uncertainties were not explicitly quantified or propagated. The licensee provided supplemental information in the form of presentation materials addressing the items listed above and written response to specific follow-up questions (e.g.,
questions related to bootstrap algorithms employed for verification analyses).
Additionally, the licensee referenced a 2006 Emanuel paper that looked at probability distribution comparisons to historical data.
31 I 3.4: Storm Surge I Have      available    an  electronic  copy    of  the    Excel    spreadsheet  !Staff may issue RAI requesting justification for
 
Serial      FHRR                                                                              ' ~~ C,c Information Need(s) 1                                                  ~ctiQn. (Post Audit)
No:       Section .
JPM_SLOSH_ADCIRC_1 03013.xlsx referenced in Appendix H of calculation              ~onfidence in results near 2 x 10-6 level (may require package 32-9213352-000 as well as personnel knowledgeable in its contents            dditional simulations to bolster confidence in the 2 and usage.                                                                             1Q-6 values NRC staff notes: The subject spreadsheet identified in the audit plan was made available to the staff prior to the audit as part of an RAI response. The staff asked various questions related to the spreadsheet on topics such as treatment of probability mass associated with combinations of parameters assigned "-999" surge values, confidence in results near the 2 x 1D-6 level and selection of computer runs for refinement using ADCIRC. As a result, the staff was able to develop an understanding of the spreadsheets' contents and usage.
32  3.4: Storm Surge I Have available   relevant documentation and an SME who is knowledgeable           ~he licensee has made presentation materials from about the probabilistic characterization of storm surge to discuss any sensitivity he audit available to staff in the ERR. The staff studies performed to support the probabilistic storm surge analysis (PSSA).       plans to issue RAis, as needed, to request that the licensee docket information contained in the NRC staff notes: The licensee's SMEs provided an overview of their approach       presentation materials if it serves as a basis for
                                                                                                            ~
to the calculation of probabilistic storm surge at the /PEG site. Results of         onclusions documented in the staff assessment.
sensitivity studies were discussed. In addition, presentation materials were         he staff may also request additional or more prepared summarizing parameter sensitivity (e.g., as low, moderate, or high). In     etailed information regarding sensitivity studies.
addition, supplemental materials were presented related to sensitivity studies of parameter ranges and discretization considered in the joint probability method (JPM) integration.
33 I 3.4: Storm Surge I Have available appropriate documents, codes, and references as well as an SME The staff will continue its review of information who is knowledgeable about the probabilistic characterization of storm surge to     ontained in the ERR (e.g., calculation packages) discuss the following:                                                               ith the improved understanding afforded by the
* Probability distributions associated with storm parameters and error terms        larifying information presented during the audit. The (as applicable) in the JPM integral.                                           taft plans to issue RAis, as needed, to request that
* Basis for distribution models and parameters selected, including any              he licensee docket information contained in the
 
Serial      FHRR                                          Information Need(s) 1                                                , ~ctio~ (flo~tA~dit),,
No.       Section                                                                                                                         ' y*:~~)*~
analyses performed using expert judgment, based on existing studies, or ~alculation packages if it serves as a basis for based on available data (e.g., HURDAT) including selection, interpretation, onclusions documented in the staff assessment. If and filtering of available data.                                                 necessary, the staff may also request additional or
                                                                                                                ~
ore detailed information regarding the datasets NRC staff notes: The licensee's SMEs provided an overview of their approach to tilized, judgments applied, and probability the calculation of probabilistic storm surge at the /PEG site. SMEs provided istributions ultimately selected.
significant clarifying information regarding the methodology used to develop probability distributions associated with storm parameters in the JPM integral. A significant portion of the audit was spent discussing the basis for the distribution models selected (e.g., data and methods used to derive distributions, geographic filters applied to datasets, and the means by which temporal correlation in the datasets was addressed). The NRC staff was also afforded the opportunity to discuss the synthetic dataset with the external SME responsible for its development.
34 I 3.4: Storm Surge I Have available appropriate documents, codes, and references as well as an SME           he licensee has made presentation materials from who is knowledgeable about the probabilistic characterization of storm surge to         he audit available to staff in the ERR. The staff discuss the selected discretization shown in FHRR Tables 3.4-5 through 3.4-9,           xpects to issue RAis related to the impact of including (but not limited to) discussion of the basis for the selected discretization   iscretization, selected parameter ranges, and and the treatment of the contribution of probability mass associated with               reatment of probability mass that was assigned to parameter values outside the range of parameters shown in Tables 3.4-5 through           ombinations of parameters later deemed 3.4-9.                                                                                 meteorologically impossible.
NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of probabilistic storm surge at the /PEG site. The SMEs prepared a supplemental presentation to illustrate the sensitivity of results to various decisions related to parameter ranges and discretization, including the impact of excluding probability mass outside the ranges of the parameters considered. The NRC staff also raised questions related to exclusion of probability mass assigned to parameter combinations that were later deemed meteorologically impossible.
 
Serial       FHRR
* Information Neect(s)1               rcc                              Action (Post';Audit) ;*.. '* *.
No*.      , Section                                            '' ' ' *~ : // ~ ..?vf/ ,c 35    3.4: Storm Surge Have available relevant codes, references, and documentation as well as an           he staff will continue its review of information SME who is knowledgeable about the probabilistic characterization of storm           ontained in the ERR (e.g., calculation packages) surge to discuss the basis for the calculated omni-directional storm rate including   ith the improved understanding afforded by the (but not limited to) the basis for the selected capture zone and any sensitivity     larifying information presented during the audit. Thel studies that were performed or alternate methods that were considered. NRC           taff plans to issue RAis, as needed, to request that also requests that the licensee have available a tabulation of the events           he licensee docket information contained in the (including event dates) that were used to compute the omni-directional storm rate     alculation packages if it serves as a basis for (as referenced in Section 6.2 of calculation package 32-9213352-000).                 onclusions documented in the staff assessment. If necessary, the staff may also request additional or NRC staff notes: The licensee's SMEs provided an overview of their approach to jmore detailed information regarding the evaluation the calculation of probabilistic storm surge at the /PEG site. The SMEs prepared ~f the omni-directional rate.
presentation materials related to the omni-directional storm rate and provided clarifying information relative to information contained in the calculation packages. The licensee also provided the tabulation of events used to compute the omni-directional rate. Lambda (the storm rate coefficient) was presented in documents using two different units for values presented. The licensee's SME reported that GZA (an AREVA subcontractor) reevaluated lambda to reflect geographic variability. Results are in terms of four shoreline segments (the limits of which were based on observed landfall trends). In general, lambda equal to 0.047 is expected to be appropriate for storms contributing to the 1 x 10-6 return period flood.
36  3.4: Storm Surge Have available relevant documentation and an SME who is knowledgeable about           he licensee has made presentation materials from the probabilistic characterization of storm surge to discuss the use and             he audit available to the staff in the ERR. The staff interpretation of deterministic load combinations (e.g., a 25-year river flow in   plans to issue RAis, as needed, to request that the conjunction with the storm surge event) in conjunction with the probabilistic       licensee docket information contained in the characterization of storm surge and the basis for those decisions.                     alculation packages or presentation materials if it erves as a basis for conclusions documented in the NRC staff notes: The licensee's SMEs provided an overview of their approach to taff assessment. If necessary, the staff may also the calculation of probabilistic storm surge at the /PEG site. The SMEs described request additional or more detailed information the rationale for their judgment that the combination of a 25-year river flow in regarding deterministic load combinations.
 
Serial       FHRR                                       Information Need(s) 1                                                   Action (PostAudit)
No.       Section                                                                                                                         ''""'
conjunction with a storm surge event is conservative. Their rationale was based on differences in characteristics between events that create large surges and events that deposit a large amount of rain on the watershed as well as considerations associated with the lack of coherence in the arrival of the peak surge and the arrival of a peak river flow. The licensee's SMEs noted that a 25-year flood was assumed to occur in conjunction with the PMSS. That rainfall event is considered to be conservative and as a further conservatism it is                                                                 !
assumed to occur with the PMSS a probability of 1. Presentation materials presented during the audit provided graphics to support the rationale provided.
37   3.4: Storm Surge Have available relevant documentation and an SME who is knowledgeable about ~he staff will continue its review of information the probabilistic characterization of storm surge to discuss components of the ~ontained in the ERR (e.g., calculation packages)
PSSA that relied on engineering judgment or experience, including (but not ~ith the improved understanding afforded by the limited to) the filtering of data, statistical methods used to develop probability ~larifying information presented during the audit.
density functions (PDFs), selected PDFs, event combinations considered (e.g., ~he staff plans to issue RAis, as needed, to request treatment of concurrent tides and river flows), model selection, and model hat the licensee docket information contained in the parameters.                                                                           calculation packages if it serves as a basis for
                                                                                                              ~.;onclusions documented in the staff assessment. If NRC staff notes: The licensee's SMEs provided an overview of their approach to necessary, the staff may also request additional or the calculation of probabilistic storm surge at the /PEG site. The SMEs identified more detailed information regarding judgments several places where engineering judgment was applied. Moreover, throughout applied during the analysis.
the audit, the staff discussed the development of synthetic data, filtering of historic data, methods used to develop (or verify) probability density functions, treatment of tides and river flows, use of numerical models (SLOSH and ADCIRC), and other relevant decisions. Throughout the discussions, the staff further identified components of the analysis that utilized (explicitly or implicitly) engineering judgment or experience.
 
Serial       FHRR                                                                                   >>>'>>
lnfonnation    Need(s) 1                                                 Action"(fiost<Audit)
No.       Section             >>'                         \c f_, <'                    >>'     '>;<   ''1,>':,:">'<>,             ">;,,,,,> ', '               I 38   3.4: Storm Surge Have available relevant codes, references, and documentation; and an SME who           ~he licensee has made supplemental material is knowledgeable about the probabilistic characterization of storm surge to           (contained in presentations) from the audit available discuss the results of verification and validation exercises, including the means       o the staff in the ERR. The staff plans to issue by which the Joint Probability Method (JPM) integration accounted for model           RAis, as needed, to request that the licensee docket errors.                                                                               information contained in the presentation materials if it serves as a basis for conclusions documented in NRC staff notes: Entergy contractors provided supplemental information                 he staff assessment. Pending the results of further describing the basis for exclusion of an error term from the JPM integral. The         review, the staff may request additional or more bases provided were centered on a judgment that various modeling decisions            detailed information regarding treatment of were conservative (e.g., based on benchmarking studies) or that verification          uncertainties.
studies showed results were sufficient that an error term was not required.


ML 14227A672 KErwin, NRO BHayes, NRO Mlee, NRO MBensi, NRO EMiller, DORL ABurritt, R1 SStewart, R 1 OFFICE NRR/JLD/JHMB/PM NRR/JLD/LA NRO/DSEA/BC(A) NAME RKuntz Slent KErwin DATE 08/19/14 08/18/14 07/31/14 A) Acting NRR/JLD/JHMB/BC SWhaley 08/27/14}}
ML14227A672                                A) Acting OFFICE     NRR/JLD/JHMB/PM   NRR/JLD/LA     NRO/DSEA/BC(A)     NRR/JLD/JHMB/BC    NRR/JLD/JHMB/PM NAME       RKuntz             Slent           KErwin             SWhaley            RKuntz DATE       08/19/14           08/18/14       07/31/14           08/27/14          08/29/14}}

Latest revision as of 19:17, 5 February 2020

Regulatory Audit Report for May 27-30, 2014, Audit at the Indian Point Facility to Support Review of Near-Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report
ML14227A672
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 08/29/2014
From: Robert Kuntz
Japan Lessons-Learned Division
To:
Entergy Nuclear Operations
Kuntz R, NRR/JLD, 415-3733
References
TAC MF3313, TAC MF3314
Download: ML14227A672 (30)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 29, 2014 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249

SUBJECT:

INDIAN POINT NUCLEAR GENERATING, UNIT NOS. 2 AND 3-REGULATORY AUDIT REPORT FOR MAY 27-30,2014, AUDIT AT THE INDIAN POINT FACILITY TO SUPPORT REVIEW OF NEAR TERM TASK FORCE RECOMMENDATION 2.1: FLOODING HAZARD REEVALUATION REPORT (TAC NOS. MF3313 AND MF3314)

Dear Sir or Madam:

By letter dated December 23, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13364A006), Entergy Nuclear Operations, Inc. (Entergy or the licensee), submitted its required response for Indian Point Nuclear Generating, Unit Nos. 2 and 3 to Near Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report (FHRR), in response to the U.S.Nuclear Regulatory Commission's (NRC) letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f)

Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident, dated March 12, 2012 ( ADAMS Accession No. ML12053A340).

The purpose of the May 27-30, 2014, audit at the IPEC facility in Buchanan, New York, was for the NRC staff to review the data, models, and methods applied in the licensee's flood hazard reevaluation, supporting documentation, and calculation packages; and to discuss these issues with the Entergy's subject matter experts, staff, and contractors.

The Indian Point Energy Center (IPEC) FHRR relied on complex methodologies to estimate flooding hazards at the site. Several of the flooding scenarios evaluated are not in the current licensing basis (CLB), nor were they evaluated for the purposes of the Individual Plant Examination of External Events (IPEEE) analysis. Almost all of the analyses rely on numerically-based computer codes that were not available at the time that the analyses supporting the CLB or the IPEEE were performed. In many cases, engineering judgment was an important part of the IPEC FHRR. Consequently, decisions concerning modeling abstractions, the specification of boundary conditions, the def,nition of input parameters, or other assumptions can impact the calculated flood water height estimated by these analyses.

Following a preliminary review of the IPEC FHRR submitted on December 23, 2013 (ADAMS Accession No. ML13364A005), the NRC staff identified several questions concerning various aspects of the fiood hazard calculations for the site. For example, the staff observed that spec1fic details concerning many of the analyses and their attendant assumptions were not

sufficiently described in the main body of the IPEC FHRR document or in supporting references.

Because this information is necessary for the NRC staff to perform its review of the IPEC FHRR analyses, the staff decided to conduct an audit of the report and the associated calculations. An audit was then conducted at the IPEC site on May 27-30, 2014.

The plan for this audit, dated May 5, 2014, can be found in ADAMS at Accession No. ML14121A431. A copy of the audit report, reflecting the NRC staff's findings during the site audit, is enclosed herewith. Enclosure 1 is the audit report which identifies the NRC staff and contractors and subcontractors that participated in the audit, as well as their respective function and the specific objectives of the audit. Enclosure 2 contains the Entergy contractor and subcontractor responses to NRC staff requests, and the staff's observations from the audit.

If you have any questions, please contact me at 301-415-3733 or via email at Robert. Kuntz@nrc.gov.

rt F. Kuntz, S 1or Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-24 7 and 50-286

Enclosures:

1. FHRR Audit Report
2. Audit Report -Information needs cc w/encls: Distribution via Listserv

AUDIT REPORT BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO NEAR-TERM TASK FORCE RECOMMENDATION 2.1 FLOODING HAZARD REEVALUATION REPORT ENTERGY NUCLEAR OPERATIONS. INC.,

INDIAN POINT NUCLEAR GENERATING. UNIT NOS. 2 AND 3 DOCKET NOS. 50-247 AND 50-286 BACKGROUND AND AUDIT BASIS By letter dated December 23, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13364A006), Entergy Nuclear Operations, Inc. (Entergy or the licensee), submitted its required response for Indian Point Nuclear Generating, Unit Nos. 2 and 3 (Indian Point) to Near Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report (FHRR), in response to the U.S. Nuclear Regulatory Commission's (NRC's) letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) (hereafter referred to as the 50.54(f) letter) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident, dated March 12, 2012 (ADAMS at Accession No. ML12053A340). The licensee's submittal relied on several methodologies, for which NRC staff guidance was not used or goes beyond the existing staff guidance. In using these methodologies, the data, models, and analytical methods can be extremely important and can have large effects on the resulting calculated flooding heights at the site. Some details of how Entergy applied these methodologies, which the NRC staff must understand to complete its review, are not present in the Indian Point Energy Center (IPEC)

FHRR.

In its initial review of the IPEC FHRR, the NRC staff has identified questions in four areas regarding the information submitted by the licensee: (1) storm surge analysis, (2) local intense precipitation (LIP), (3) riverine flooding (including dam failures) and (4) documentation contained in calculation packages and references in the electronic reading room (ERR).

With respect to evaluation of probable maximum precipitation (PMP), which serves as input to local intense precipitation and riverine flooding evaluations, Entergy performed a "site-specific" evaluation rather than using previously accepted methodologies and guidance contained in the Standard Review Plan (SRP). This could result in substantially lower precipitation values that might be calculated using previously accepted methodlogies. The NRC staff required further information to develop a better understanding of how the licensee calculated and applied the PMP, and how the licensee's analysis compares to the standard methodology.

Enclosure 1

In the area of storm surge analysis, Entergy performed a probabilistic storm surge analysis (PSSA), which is a different method than the methods previously reviewed by the NRC staff.

The NRC staff determined that it needed more information about the methodology used to implement the PSSA; the licensee's use and interpretation of available data, models, and methods (including use of engineering judgment); computer codes; the identification, treatment, and propagation of uncertainties; and the basis for certain relevant modeling decisions. Accordingly, the NRC staff conducted an audit of the IPEC FHRR at the IPEC site.

The purpose of the audit was for the NRC staff to review the data, models, and methods applied in the licensee's flood hazard reevaluation, supporting documentation, and calculation packages; and discuss these issues with Entergy's subject matter experts, staff, and contractors.

The audit allowed the staff to better understand the modeling results, and will aid the staff as it continues its review of the licensee's 50.54(f) submittal in order to make conclusions as to: (1) whether the licensee had responded appropriately to the 50.54(f) letter, (2) whether the responses are sufficient to determine whether or not the reevaluated flood causing mechanisms are, or are not, bounded by the current design-basis flood hazard, and (3) whether the staff needs additional information from the licensee to complete its review. The audit also assisted the NRC staff in identifying any additional information that it may need, as it continues its review of the IPEC FHRR.

At the beginning of the audit, the licensee and its contractors presented information on Entergy's approach to performing both the PSSA and the PMF analyses. The PSSA presentation described how the PSSA relied on the Joint Probability Method (JPM) to estimate storm surge at the IPEC site, including discussions about how: (1) the JPM process steps were implemented; (2) the JPM results were benchmarked (validated) against deterministic-based estimates of storm surge at the site; and (3) engineering judgment, and error and uncertainty analyses were incorporated in the analyses.

The presentation on the PMF calculation for the IPEC site reviewed the following topics:

probable maximum precipitation, local intense precipitation, snow-melt, dam failures, and probable maximum flood estimation. For each topic, the methodology used to evaluate the hazard was discussed, as well as the use of engineering judgment and the treatment of conservatism in its analysis. There was also a discussion concerning the use of the FL0-20 computer software to perform flood routing calculations at the site.

Both presentations were extensive and provided valuable insights into the analyses upon which the FHRR was based. The presentation materials provided additional detail and context concerning how the respective flood hazard analyses were performed. As a consequence, the NRC staff's information needs identified in the audit plan were sufficiently resolved for staff to generally understand the licensee's FHRR methodology/analysis. However, as the staff's detailed review progresses, the staff may issue Requests for Additional Information, at a later date.

During the audit, the NRC staff and its contractors were provided a walking tour of the IPEC site. This walkdown provided important physical context for the briefings and analyses that were performed. The walkdown covered several areas of the facility cite, including: (1) the main runoff route for local intense precipitation (e.g., the steep road leading down to the waterfront); (2) the transformer yard, alleyways, downspouts, and manholes, and their treatment

in FL0-20; (3) the switchgear rooms, diesel generators and auxiliary feedwater and makeup water pumps; (4) the site grade and discharge canal; and (5) the staging area for sandbags and portable tiger dams.

At the end of the audit, Entergy agreed to place several additional documents in the ERR, including: (1) certain specific maps and high resolution figures of the IPEC site; (2) corrected references in the FHRR and other documents; (3) spreadsheets and summary tables that the staff had requested and used during its audit; and (4) additional references needed by the staff.

As a result of the audit, the licensee also revised its FL0-20 analysis and submitted it on August 18, 2014. The staff is continuing its review of the licensee's FHRR and supporting analyses.

Regulatory Audit Scope or Methodology The area of focus for the audit was the Indian Point Recommendation 2.1 Flood Hazard Reevaluation Report and supporting documentation.

Audit Team Activities The onsite audit was conducted at the Indian Point facility from May 27, 2014, through May 30, 2014. The NRC audit team staff was as follows:

Support:

Kenneth Erwin, NRC Audit Team Lead Douglas Pickett, NRC Senior Project Manager Wayne Schmidt, Senior Reactor Analyst, Region I Storm Surge Methodology:

Henry Jones, NRC Audit Team Member, Storm Surge Lead Michelle Bensi, NRC Audit Team Member Chris Bender, Taylor Engineering, Inc., NRC Audit Team Member Don Resio, Taylor Engineering, Inc., NRC Audit Team Member Local Intense Precipitation I Riverine Flooding I Dam Failure Methodology:

Barbara Hayes, NRC Audit Team Member, PMP Lead Kevin Quinlan, NRC Audit Team Member Rajiv Prasad, PNNL, NRC Audit Team Member Steve Breithaupt, PNNL, NRC Audit Team Member

INDIAN POINT ENERGY CENTER FLOOD HAZARD REEVALUATION REPORT MAY 2014 HYDROLOGY AUDIT REPORT-INFORMATION NEEDS Serial FHRR'

  • Information Need(s) 1 * * 'Ac:tion {Prist Audit)

No. Section 1 FHRR There appear to be instances of incorrect references in the body of the flood Following the audit, the licensee submitted a (in general) hazard reevaluation report (FHRR) or missing/incorrect references in the revised FHRR for the Indian Point site that reference list. Have available a copy of the FHRR with any incorrect references includes both corrections and revisions identified clearly identified and corrected. by the staff during the audit.

NRC staff notes: The licensee provided a revision of the FHRR during the audit.

As a result, the staff teamed that revisions were made by the licensee (and its contractors) since docketing of the initial FHRR, that include, corrections to references as well as more substantive amendments (e.g., Figure 51 in the docketed FHRR was identified during the audit as being incorrect).

2 FHRR Have available electronic copies of the calculation packages below; as well as The calculation packages cited were made (in general) the means to access them (preferably on licensee computers rather than available in the licensee's ERR. The NRC staff through the use of the electronic reading room (ERR): plans to issue a request for additional information

  • AREVA Document No. 32-9207390-000, "Probable Maximum Hurricane (RAI), as needed, to request that the licensee for Indian Point Energy Center [IPEC]," 2013. docket information contained in the calculation
  • AREVA Document No. 38-9216321-000, "Acquisition of Coastal Flood packages if it serves as a basis for conclusions Analysis Data from Federal Emergency Management Agency Region II documented in the staff assessment.

Indian Point Energy Center Flooding Hazard Re-evaluation," August, 2013.

  • AREVA Document No. 32-9196317-000, "Indian Point Energy Center Flood Hazard Re-evaluation - Probable Maximum Seiche"
  • AREVA Document No. 32-9193356-000, "Flood Hazard Re-evaluation -

Combined Effect Floods - Coastal Processes for Indian Point Energy Center

  • AREVA Document No. 32-9196319-000, "IPEC Deterministic Probable 1

In this column of the NRC Staffs audit report, the staff's pre-audit information needs are reproduced (in normal font), followed by the staffs post-audit comments (in italics). Items identified for future action are shown in the final column ("Action (Post-Audit)").

Enclosure 2

Serial FliRR Information Need(s) 1 Action (Post Audit) ..

  • No. Section ' I Maximum Storm Surge Calculation"
  • AREVA Document No. 32-9213352-000, "Flood Hazard Re-evaluation-Probabilistic Storm Surge for Indian Point Energy Center

NRC staff notes: The licensee's subject matter experts (SMEs) provided an overview of their approach to the probabilistic calculation of storm surge. During the break-out session that followed, the calculation packages identified above were made available by the licensee in CD format and were added to the ERR .

NRC staff and the licensee's SMEs referred to the calculation packages, as necessary, to support discussions throughout the audit to better understand the approach/methodology used to calculate storm surge.

3 3.1: Local Intense Have available a clear description of the current licensing basis (CLB) related to The staff reviewed the material requested in the Audi1 Precipitation local intense precipitation (LIP). Also, have available a brief and clear description Plan. The information needs were sufficiently of the individual plant examination of external events (IPEEE) analysis related to resolved for the staff to understand the licensee's the LIP. methodology and analysis. The staff may issue RAis to address concerns.

NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of LIP flooding. This issue was assessed and documented in

/PEG's earlier IPEEE submittal. The Entergy team informed the NRC staff that LIP is not part of the plant's design/licensing basis.

4 3.1: Local Intense Have available the knowledgeable SMEs who performed the site-specific ~he staff reviewed the material requested in the Precipitation probable maximum precipitation (PMP) analysis described in AREVA Document ~udit Plan. The information needs were sufficiently No. 32-9196314-000. Also, have available an example storm analysis (including resolved for the staff to understand the licensee's 3.2: Flooding in computation software and runs/simulations, if necessary) to walk the NRC staff methodology and analysis. The staff may issue Rivers and through the analysis. Be prepared to define terms used in the site-specific PMP RAis to address concerns.

Streams analysis- e.g., "extreme rainfall event," "transpositionability," "maximum average dew point," and others.

NRC staff notes: The licensee's SMEs provided an overview of their approach to

Serial FHRR Information Need(s) 1 Action* (PostA~dit)

No. Section the estimation of a site-specific PMP for the site. During the break-out session, the licensee discussed how the site-specific PMP was estimated, as well as the meaning of certain specific technical terms. The AREVA document cited in the audit plan was also made available by the licensee during the audit to facilitate those discussions.

5 3.1: Local Intense Have available storm data that were used in the site-specific PMP analysis. ~he staff reviewed the material requested in the Precipitation Have available a knowledgeable SME to explain how the storm data was ~udit Plan. The information needs were sufficiently analyzed, including details of any statistical analyses. Be prepared to explain resolved for the staff to understand how the 3.2: Flooding in how the storm data and/or results from storm data analyses were used in the licensee's FHRR methodology and analysis deviated Rivers and site-specific PMP estimation and how this varies from the storm data used in the rom HMR51. The staff may issue RAis to address Streams National Oceanic and Atmospheric Administration (NOAA)/National Weather concerns.

Service (NWS) Hydrometeorological Report (HMR) HMR51.

NRC staff notes: The licensee's SMEs provided an overview of their approach to the estimation of site-specific PMP values for the site. During the break-out session that followed, the licensee had SMEs available to describe the estimation of site-specific PMP and how that estimation deviated from the HMR51 methodology.

6 3.1: Local Intense Have available a list of assumptions that were made in the site-specific PMP The staff reviewed the material requested in the Precipitation analysis. Have available a knowledgeable SME to discuss the justifications Audit Plan and spoke to the licensee's SMEs. The and/or data supporting these assumptions. information needs were sufficiently resolved for staff 3.2: Flooding in o understand the licensee's PMP assumptions and Rivers and NRC staff notes: The licensee's SMEs provided an overview of their approach to *ustifications. Staff may issue RAis to address Streams the estimation of a site-specific PMP for the site. During the break-out session, vOncems.

the licensee identified the assumptions associated with the estimation of a site-specific PMP as well as the reasoning behind those assumptions. The licensee's SMEs also discussed temporal rainfall issues among other things.

7 3.1: Local Intense Have available any references which describe the methodology used in the site- ~he staff reviewed the material requested in the L____ ----

Serial FHRR.

Information Need(s) t. Action (P~~JfAudit)

No. *.Section '. '~ ,. . ' ,.,

Precipitation specific PMP estimation. Have available a knowledgeable SME to discuss the !Audit Plan and spoke to the licensee's SMEs. The

.differences between values resultant from the site-specific PMP estimation used information needs were sufficiently resolved for staff 3.2: Flooding in in the FHRR, and values which would have been derived from the NOAA/NWS o develop an improved understanding of the Rivers and HMR methodology. Be prepared to discuss the level of conservativeness licensee's approach. Further staff review may be Streams associated with these values and how these results could affect the flood hazard necessary to better-understand the level of

~

analysis at or near the IPEC site. onservatism in the licensee's site-specific analysis.

he staff may issue RAis to address any further NRC staff notes: The licensee's SMEs provided an oveNiew of their approach oncems.

to the estimation of a sffe-specific PMP for the site. During the break-out session, the licensee discussed the differences between the site-specific PMP methodology and the NOAAINWS HMR methodology. Wffh respect to the HMR methodology itself, the licensee's SMEs expressed the opinion that the Generic HMR 51152 methodology was not appropriate for the /PEG and that a case-specific PMP study was performed.

8 3.1 Local Intense Have available a knowledgeable SME to discuss how the hierarchical hazard The staff reviewed the material requested in the Precipitation assessment (HHA) approach described in NUREG/CR-7046 was applied to Audit Plan. The staffs information needs were determine the LIP flood at and near the IPEG site. sufficiently resolved for the staff to better understand the licensee's approach. The staff NRC staff notes: The licensee's SMEs provided an overview of how the HHA may issue RAis to address concerns.

approach was used to estimate a LIP-based flood at the site. No analysis was done of results that would be associated with the PMP values that would be derived from HMR 51. During the break-out session, the LIP calculation using case 3 described in Appendix B of NUREG/CR-7046 "Design-Basis Flood Estimation for Site Characterization at Nuclear Power Plants in the Unffed States of America" was discussed. An issue was identified by the licensee's SMEs with FL0-2D modeling treatment of "rain on building." The licensee's SMEs noted that a corrective action is on -going to determine the impact.

9 I 3.1: Local Intense I Have available a map of IPEG site and vicinity clearly showing topographic ~he audit included meaningful discussion of key Precipitation and hydraulic features and structures that influence local site drainage. ~rainage issues. Though staff did receive a

Serial FHRR No. .,~ Information Need(s) 1 Action(PostAudit)*** *,

'Section r.vatershed map related to riverine and dam failure  !

NRC staff notes: Discussions of key topographic and hydraulic features that ~ooding, staff is awaiting detailed map relevant to influence local site drainage were discussed at the audit. In addition, a walking local drainage and will review in conjunction with tour of the site was conducted, in which key topographic features were identified. revised LIP analysis.

The staff subsequently requested that the necessary higher-resolution maps (specifically computer graphics files) be added to the ERR and the licensee added this map to the ERR.

10 3.1: Local Intense Have available the FL0-20 documentation (input and output files; calculation The staff reviewed the material requested in the Audit Precipitation packages) and a knowledgeable SME to discuss: Plan and spoke to the licensee's SMEs. Based on

  • Precipitation transformation hose discussions, the licensee determined it would
  • Building runoff resubmit a revised FL0-20 analysis as part of the
  • Channel routing FHRR. This was submitted on August 18, 2014.
  • Obstructions in the floodplain The staff conducted a clarification phone call with the licensee on 06/20/2014 to discuss the scope of the
  • Hydraulic control structures resubmittal. The staff understands that key features NRC staff notes: The licensee's SMEs provided an overview of their approach of the revised FL0-20 resubmittal will include to the calculation of a site-specific PMP using the FL0-2D computer code. discussion of the following issues:

During the break-out session, the licensee's SMEs noted that precipitation

  • Roof run-off issues transformed directly into runoff in FL0-2D and that no infiltration or
  • Potential flow discontinuities in model abstractions were used. As a result of those discussions, the staff requested
  • Mesh resolution that certain specific references be added to the ERR including information
  • Model configuration as it relates to complicated identifying the location of specific /PEG facility features including AutoCADIGIS flow areas data files for transformer yard doors as well as doors of other site critical
  • Flow near buildings features.
  • Criteria from the FL0-20 user's manual
  • Any potential complications with supercritical flow conditions RAI(s) may be issued following the staff's review of he licensee's resubmittal and additional ERR references.

Serial FHRR Information Need(s) 1 .Action (Post Audit) .

    • No. Section 11 I 3.1: Local Intense I Have available the FL0-20 documentation (input and output files; calculation he staff reviewed the material requested in the Precipitation packages) and a knowledgeable SME to discuss: udit Plan and spoke to the licensee's SMEs.

Quality control checks Based on those discussions, the licensee Sub-grid scale flow balances etermined it would resubmit a revised FL0-20 nalysis as part of the FHRR (See item #1 0, above.)

NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to he staff also determined that additional using the FL0-2D computer code. During the break-out session, the licensee's ocumentation was needed in the ERR. RAI(s) may SMEs noted that FL0-2D calculations were performed under an Appendix 8 be issued following the staffs review of licensee's approved QA program (safety related). The licensee noted that FL0-2D software resubmittal and additional ERR references.

underwent a commercial grade dedication process. Relevant information was also made available by the licensee during the audit.

12 3.1: Local Intense Have available the FL0-20 documentation (input and output files; calculation The staff reviewed the material requested in the Precipitation packages) and a knowledgeable SME to discuss: Audit Plan and spoke to the licensee's SMEs.

  • Water surface elevation results Based on those discussions, the licensee
  • Velocity results determined it would resubmit a revised FL0-20 analysis as part of the FHRR; (See item #1 0 NRC staff notes: The licensee's SME's provided relevant information during above). The staff also reviewed the material the audit. During the break-out session, detailed discussions concerned FL0- requested in the Audit Plan and determined that 2D as well as the issue related to the treatment of "rain on buildings" features. additional documentation was needed in the Other relevant information was also made available by the licensee during the ERR. RAI(s) may be issued following the staffs

Serial FHRR lnformationNeed(s} r

  • Action (Post Audit}
    • No; Section audit. review of the licensee's resubmittal and additional ERR references.

13 3.2: Flooding in Have available a knowledgeable SME to discuss how the hierarchical hazard ~he staff reviewed the material requested in the Rivers and assessment (HHA) approach described in NUREG/CR-7046 was applied to jAudit Plan and met with the SMEs. The staffs Streams determine the probable maximum flood (PMF) at and near the IPEC site. information needs were sufficiently resolved for the E_taff to better understand the licensee's approach.

NRC staff notes: The licensee's SMEs provided an overview of how the HHA 11 he staff may issue RAis to address concerns.

approach was applied to the calculation of the PMF. No analysis was done of results that would be associated with the PMP values that would be derived from HMR51. During the break-out session, the licensee's SMEs noted that the model parameters initially selected were vefY conservative regarding initial losses, neglecting most of the upstream dams and use of conservative starting pool elevations at spillway crest,. The licensee's SMEs also noted that one iteration was performed and once the PMF elevation was below site grade the process was ended. The licensee also had relevant background information available during these discussions.

he staff reviewed the material requested in the

~

14 3.2: Flooding in Have available a knowledgeable SME to discuss the selection of the centering Rivers and and orientation for the basin-wide PMP storm for estimation of the PMF. Be udit Plan and spoke to the licensee's SMEs.

Streams prepared to present justifications and/or data support for this selection. hese actions lead to partial resolution of the staffs arlier questions. Further staff review is necessary NRC staff notes: For the purposes of the basin-wide PMF calculation .o better understand the level of conservatism in the discussion, the licensee's SMEs noted that the storm center was taken as the licensee's analysis approach. Thestaff may issue center of the watershed. The licensee's SMEs also noted that the HMR52 RAis to address concerns.

computer program internally computes storm orientation to maximize rainfall depth within the user -defined watershed. Evaluation of additional storm centers was judged not to provide additional value and the licensee's SMEs relied on expert judgment to determine that the one storm orientation used would produce the most severe flooding possible. The licensee had other relevant background information available during these discussions.

Serial~**.

/' ,\, *., ,' *<.

No. .

  • Section Information Need(t;)J ** * **  ; Action (Post Audit) ..

15 I 3.2: Flooding in Have available a knowledgeable SME to discuss reasonable alternative centering he staff reviewed the material requested in the Rivers and locations and orientations for the site-specific PMP storm for estimation of the udit Plan and spoke to the licensee's SMEs.

Streams PMF. Be prepared to discuss how these alternative centering locations could hese actions lead to partial resolution of the staffs affect the flood hazard at or near the IPEC site and the associated levels of arlier questions. Further staff review will be conservatism. necessary to better understand the level of onservatism in the licensee's analitical approach.

NRC staff notes: No alternative centering locations or orientations for the site- hestaff may issue RAis to address concerns.

specific PMP were used by the licensee's SMEs who relied upon expert judgment in determining that all other alternative locations would result in less severe flooding near the /PEG site. The licensee had SMEs available to discuss the issues. Relevant information was made available by the licensee during the audit.

16 3.2: Flooding in Have available a map of the domains used for Hydrologic Engineering Center The staff reviewed the material requested in the Rivers and Hydrologic Modeling System (HEC-HMS) and Hydrologic Engineering Center Audit Plan and found it sufficient. An electronic Streams River Analysis System (HEC-RAS) that clearly shows rivers, tributaries, dams copy was later provided to the ERR as requested and other hydraulic structures, reservoirs, watershed boundaries, and the for follow-up.

location of gage stations. The map should clearly show the domains used for HEC-HMS and HEC-RAS, as well as the locations of cross sections used for HEC-RAS analyses.

NRC staff notes: The licensee's SMEs provided a large scale map during the audit showing the requested information. An electronic copy was also requested for the ERR and was subsequently provided.

he staff reviewed the material requested in the

~

17 3.2: Flooding in Have available the HEC-HMS documentation (input and output files; Rivers and calculation packages) and a knowledgeable SME to discuss: udit Plan and concluded that it still has questions.

Streams

  • Precipitation transformation he staff subsequently requested that additional
  • Channel routing characteristics ocumentation be placed in the ERR concerning the
  • Reservoir characteristics HEC-HMS computer modeling. Upon receipt of the requested information in the ERR, the staff will NRC staff notes: The licensee's SMEs provided an overview of the approach to review it and determine if it has any additional

Serial FHRR Information N~d(s)1**. Action (Po~fAudit) * .*.

No. Section *.

the PMF calculation using the HEC-HMS computer code. Relevant information ~uestions.

(i.e., the input/output files and calculation packages) was made available by the licensee for the staff to review during the audit break-out session, and the SMEs were on hand to aid in the interpretation of that information. Specific points discussed included unit hydrograph parameters used, infiltration loss rates, channel routing methods and available dam data for selected dams. During the breakout session, the licensee's SMEs noted:

  • Precipitation transformation was performed via the Snyder Method with calibration and verification.
  • Routing was performed with Muskingum and Muskingum-Cunge.
  • Three dams were modeled based on publically-availab/e information and the Corps of Engineers' Phase I reports (no flood control dams were incorporated),
  • Initial losses during the PMF were zero.
  • Constant losses changed during calibration, and were initially estimated from the minimum published typical infiltration rate for each hydrologic soil group.
  • 8-point cross-section was used for Muskingum-Cunge.

he staff reviewed the material requested in the

~

18 3.2: Flooding in Have available the HEC-HMS documentation (input and output files; Rivers and calculation packages) and a knowledgeable SME to discuss: udit Plan and concluded that it still has questions.

Streams

  • Quality control checks (if applicable) he staff subsequently requested that additional
  • Model calibration ocumentation be placed in the ERR concerning the HEC-HMS computer modeling. Upon receipt of the NRC staff notes: The licensee's SMEs provided an overview of their approach requested information in the ERR, the staff will to the calculation of the PMF using the HEC-HMS computer code. Relevant 1review it and determine if it has any additional information (i.e., the input/output files and calculation packages) was made ~uestions.

available by the licensee for the staff to review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information.

Specific points noted by the licensee's SMEs during the break-out sessions

~ . '. *,'

Serial. FHRR ,_.: .' } ,' ' /

. Information Need(s) 1 Action (Post Audit).

No. <Section --

included the following:

  • 19 sub-watersheds were included in the model, 12 of which were gaged and used for model calibration/verification.
  • 3 calibration and 3 verification floods were used including:

o 2011 modem flood of record downstream o most recent Green Island gage (previous peak 1936, no reliable data available)

  • Calibration/verification fits are ultimately based on engineering judgment.

19 3.2: Flooding in Have available the HEC-HMS documentation (input and output files; The staff reviewed the material requested in the Rivers and calculation packages) and a knowledgeable SME to discuss: Audit Plan. The staffs information needs were Streams

  • Discharge results sufficiently resolved for staff to better understand the licensee's approach. The staff may issue NRC staff notes: The licensee's SMEs provided an overview of their approach RAis to address concerns.

to the calculation of the PMF using the HEC-HMS computer code. Relevant information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information. Specific points noted by the licensee's SMEs during the break-out sessions focused on zero initial losses. Watershed average verified constant loss Initial estimates of constant loss rates were based on the low end of values of typical loss rates for each hydrologic soil group 20 3.2: Flooding in Have available the HEC-RAS documentation (input and output files; calculation The staff reviewed the material requested in the Rivers and packages) and a knowledgeable SME to discuss: Audit Plan. The staffs information needs were Streams

  • Boundary conditions (upstream and downstream) sufficiently resolved for staff to better understand
  • Tributary and lateral inflows the licensee's approach. The staff may issue
  • Channel routing characteristics RAis to address concerns.

NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of the PMF using the HEC-HMS computer code. Relevant

Serial FHRR Information Need(s) 1 Action (Post Audit)

No~, Section information was made available by the licensee for staff review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information. Specific points noted by the licensee during the break-out sessions focused on PMF hydraulics, including

  • Flow was unsteady.
  • Very-high downstream boundary condition was used- higher than the 10%

exceedance high tide (5.35 ft used vs. 4.5 ft calculated in deterministic storm surge calculation).

  • Manning's coefficient selection was based on visual obseNation and FEMA flood studies, with limited calibration.
  • No lateral inflows were used; all sub-watersheds achieve confluence with the Hudson River upstream of the /PEG model boundary (boundary is 24 miles upstream of /PEG; tidal boundary is at the Troy Lock and Dam 109 Miles upstream of /PEG)

~

21 3.2: Flooding in Have available the HEC-RAS documentation (input and output files; calculation he staff reviewed the material requested in the Rivers and packages) and a knowledgeable SME to discuss: udit Plan and spoke to the licensee's SMEs.

Streams

  • Quality control checks hese actions lead to partial resolution of the staffs
  • Model calibration arlier questions. Further staff review is necessary o better-understand the level of conservatism in the NRC staff notes: The licensee's SMEs provided an oveNiew of their approach licensee's analysis approach. The staff may issue to the PMF calculation using the HEC-HMS computer code. Relevant RAis to address concerns.

information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff to review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information.

During the break-out session, the licensee's SMEs noted that model calibration was limited because of a lack of data and tidal characteristics. Two floods were used; the Manning's n value that resulted in the highest water surface elevation was selected for use in the model. The SMEs noted that they could not use Hurricane Irene (2011) data because the event had a very significant storm

Serial FHRR Information Need(s) 1 . *. >Action (Post Audit)

No. Section -

surge component; the same issue encountered for Hurricane Sandy. The SMEs also noted HEC-RAS cannot reliably model storm surges.

22 3.2: Flooding in Have available the HEC-RAS documentation (input and output files; calculation ~he staff reviewed the material requested in the Audi Rivers and packages) and a knowledgeable SME to discuss: Plan and spoke to the licensee's SMEs. The staffs Streams

  • Water surface elevation results information needs were sufficiently resolved for the

~taff to better understand the licensee's approach.

NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to the calculation of the PMF using the HEC-HMS computer code. Relevant information (i.e., the input/output files and calculation packages) was made available by the licensee for the staff to review during the audit break-out session and SMEs were on hand to aid in the interpretation of that information.

23 I 3.3: Dam Breache~ Have available a knowledgeable SME to discuss how the HHA approach he staff reviewed the material requested in the Audi and Failures I described in NUREG/CR-7046 was applied to determine the flooding from dam Plan and spoke to the licensee's SMEs. The staffs failure mechanisms at and near the IPEC site. information needs were sufficiently resolved for the taff to better understand the licensee's approach.

NRC staff notes: The licensee's SMEs provided an overview of how the HHA he staff may issue RAis to address concerns.

approach was applied to the PMF calculation attributed to dam failure. No analysis was done of results that would be associated with the PMP values that would be derived from HMR 51. During the break-out session, the licensee's SMEs discussed their HHA approach in more detail. The licensee also had relevant background infonnation available during those discussions. During the break-out session, the licensee's SMEs noted that no individual PMP centerings were used in order to maximize dam failure contribution.

24 3.3: Dam Breache~ Have available a knowledgeable SME to discuss the centering and orientation The staff reviewed the material requested in the and Failures for the basin-wide PMP storm used for estimation of the maximum flooding Audit Plan and spoke to the licensee's SMEs.

from the dam failure flood causing mechanism. Be prepared to present These actions lead to partial resolution of the justifications and/or data support for this selection. staffs earlier questions. Further staff review is necessary to better understand the level of

.Serial FHRR Information Need(s) 1' Actiori (Post Audit)

No. Section*

NRC staff notes: The licensee's SMEs provided an overview of their approach conservatism in the licensee's analitical to the centering and orientation of the basin-wide PMP. During the break-out approach. The staff may issue RAis to address session, the licensee discussed the significance of reasonable alternative PMP concerns.

centering and orientation on the PMF calculation and the potential for dam failure. The licensee also had relevant background information available during those discussions. During the break-out session, the licensee's SMEs noted the following:

  • Issue of centering PMP over individual dam watersheds would not provide appreciable value
  • Dam failure scenario forced a Conklingville dam failure and combined it with the PMP storm applied to the center of the watershed (Conklingville dam watershed is 8.3% of watershed above /PEG, and Ashokan and Rondaout are even smaller),
  • Conklingvil/e dam is 240 miles upstream of /PEG; breach flow from dams further upstream is likely to dissipate. Dams closer to /PEG are much smaller (combined volume max 1.4 million acre-ft vs. 1.8 million acre-ft).
  • No attenuation for the Conklingville dam failure therefore represents failure of dams that could contribute to /PEG PMF
  • Initial screening criterion was dam breaches that would be 1,000,000 cfs (without attenuation) because most dams are far from /PEG (no dams on the Hudson River within 100 miles)
  • Due to Individual dam watersheds relative to overall watershed, PMP over centroid was considered to result tin highest calculated PMF based on expert judgment
  • HHA was used-- no attenuation was necessary. More severe combinations would have triggered use of additional detailed modeling (or USBR attenuation equations) to consider attenuation.

25 I 3.3: Dam Breache~ Have available a knowledgeable SME to discuss reasonable alternative The staff reviewed the material requested in the and Failures I centering locations for the site-specific PMP storm for estimation flooding from Audit Plan and spoke to the licensee's SMEs.

Serial FHRR Information Need{s) 1 Action (Post}\udit)

No. Section dam failures. Be prepared to discuss how these alternative centering locations These actions lead to partial resolution of the could affect the flood hazard at or near the IPEC site. staffs earlier questions. Further staff review is necessary to better understand the level of NRC staff notes: The licensee's SMEs provided an overview of their approach conservatism in the licensee's analitical to analysis related to dam breaches and failures. The licensee's SMEs did not approach. The staff may issue RAis during perform additional simulations of PMP storms centered over the centroid of subsequent review of the licensee's submission.

watersheds upstream to individual dams. The licensee's SMEs determined that flooding at /PEG by such storms would not result in more severe flooding at the /PEG site based upon expert judgment. The licensee also had relevant background information available during those discussions.

26 I 3.3: Dam Breache~ Have available a map of the domain that clearly shows the locations of dams The staff reviewed the material requested in the and Failures I and reservoirs considered in dam failure analysis, as well as the rivers and Audit Plan and requested that an electronic copy tributaries along which any flood resulting from dam failures would be routed. of the map be placed in the ERR. An appropriate digital map was subsequently provided in the NRC staff notes: The licensee's SMEs provided an appropriate map and ERR.

explained various features in the map.

27 3.3: Dam Breaches Have available the HEC-HMS and HEC-RAS documentation (input and output he staff reviewed the material requested in the and Failures files; calculation packages) and a knowledgeable SME to discuss: udit Plan and concluded that it still had questions.

  • Selection of reservoirs and dams for failure analysis he staff subsequently requested that additional
  • Breach flood routing characteristics ocumentation be placed in the ERR. Upon receipt f the requested information in the ERR, the staff will NRC staff notes: The licensee's SMEs provided an overview of their approach review it and determine if it has any additional in using the HEC-HMS and HEC-RAS computer code in the dam failure ~uestions.

analysis. Relevant information was made available by the licensee for the staff, including the rationale for the selection of certain dam modeling parameters, and SMEs were on hand to aid in the interpretation of that information. During the break-out sessions, the licensee's SMEs noted the following with respect to the dam modeling exercise:

  • No attenuation of dam breach flood flows.

Serial FHRR Information Need(s) 1 Action (Post Audit)

.No. 1 Section

  • Forced hydrologic failure of the Conklingville Dam (FERC regulated structure) although it did not overtop during the PMF.

Selection of dams based on largest heights, storage volumes, and proximity to the /PEG site.

28 I 3.4: Storm Surge I Have available the following documents and appropriate references, as well as a knowledgeable SME to discuss the methodology used for the deterministic characterization of storm surge, including:

  • The application of the SLOSH model as a screening tool, including the here was partial resolution of the staff's earlier assumptions used to implement model simplifications, grid resolution near the uestions in this area. The staff may issue RAis Indian Point facility, and no river inflow at the upstream boundary requesting results from additional computer runs Comparisons of SLOSH model results with measurements to validate the one with the ADCIRC computer code to account for SLOSH model's ability to simulate storm surge near the Indian Point facility. limitations in the screening tool.
  • The development and application of probability distributions applied to here was partial resolution of the staff's earlier develop the SLOSH model input parameter combinations. As part of this uestions in this area. The staff may issue RAis discussion, provide information on the upper limits applied for the requesting additional justification of capping of PMH meteorological forcing parameters. If this upper limit involved the estimation ind fields as well as additional information on of an MPI central pressure, describe how this was done. If this was done via relation of Rmax as applied in WRT analysis and an upper limit derived based on Extreme Value Statistics, describe how this probability distribution development. The staff was done. Also, discuss the application of the Extreme Value Statistics (EVS) mayalso inquire if any comparisons of WRT Rmax performed to estimate the probability of strong storms in the study region. alues and data have been made.

Include the probability distributions used for different storm parameters and any references to their previous application to this region. If there are no previous applications of the specific distributions used here, provide a plot of the data and the fit to the data provided by the specific distributions used in this effort.

  • The application of the ADCIRC model within the deterministic analysis and ~he staff concluded that additional documentation in any modeling difficulty encountered (such as instability for strong storms). his area is still needed. Thestaff plans to issue an RAI requesting additional discussion of any ADCIRC

Serial FHRR Information Ne~d(s) 1 Action*(Post:Auditf .<.

No. . Section model instability encountered running the deterministic or probabilistic storms and any vOrrective actions taken.

  • Comparisons of the SLOSH and ADCIRC results for similar storms and There was partial resolution of the staffs earlier whether the results indicate suitable model results for application of SLOSH questions in this area. The staff may issue RAis requesting results from additional computer runs done with the ADCIRC computer code to account for limitations in the screening tool.
  • Comparisons of the ADCIRC tidal model results to confirm consistency The staffs information needs were sufficiently between the simulated and predicted tidal phasing, range, and amplitude. resolved for the staff to better understand the licensee's approach. The staff may issue RAis to address concerns.
  • The development of the still water elevation, wave crest elevation, and limit of The staffs information needs were sufficiently run-up for Combined Flood Event Alternatives 1, 2, and 3 resolved for the staff to better understand the licensee's approach. The staff may issue RAis to address concerns.
  • Provide evidence that wave setup is not important at the site . There was partial resolution of the staffs earlier questions in this area. The staff may issue RAis requesting results from additional computer runs done with ADCIRC to account for limitation in screening tool.
  • Details of methods applied to develop the flow velocity and hydrodynamic The staffs information needs were sufficiently loads at the site resolved for the staff to better understand the licensee's approach. The staff may issue RAis to address concerns.
  • Discuss the source of the bathymetry data and interpolation method applied in The staffs information needs were sufficiently

Serial FHRR Information Need(s) t,,, ActiQn . (PostAud!t)

No. Section ',;"';/ ;c,-

the development of the ADCI RC model mesh. Discuss the scope of changes resolved for the staff to better understand the made to the Federal Emergency Management Agency (FEMA) Region II licensee's approach. The staff may issue RAis to mesh to refine the area near the Indian Point facility. ddress concerns.

  • Provide input files necessary to recreate two of the SLOSH and ADCIRC model results in Tables 3.4-10 and 3.412. t he staffs information needs were sufficiently esolved for the staff to better understand the licensee's approach. The staff may issue RAis to

~ddress concerns.

NRC staff notes: The licensee's SMEs provided an oveNiew of their approach to the calculation of probabilistic storm surge at the IPEC site. During the break-out session, the licensee's SMEs noted the following:

  • SLOSH model was used as a as a screening tool.
  • Model simplifications: grid resolution near the IPEC site was judged to have no impact because final runs were made in ADCIRC.
  • Sensitivity results were presented during the audit for parameter discretization sizes and ranges.
  • No stability issues were experienced with ADCIRC.
  • Comparisons of the SLOSH and ADCIRC results were favorable for river surge results. Differences were found for results in the NY Harbor area.
  • Wave set-up is included in the empirically-based calculation for wave run-up. The component of wave set -up that was not included was deep water waves breaking at the IPEC bulkhead. For these waves, the licensee expressed the view that existing site conditions (flat areas, structures, etc.)

are such that momentum is lost.

  • Coupled ADCIRC and numerical wave model (e.g. SWAN, STWAVE) was not performed here for several reasons:

o Wind and surge at the site are effectively decoupled activities; in particular with the assumption of steady state storm tracks. That is, most tracks will not result in significant waves at the site o Given the predicted inundation, most waves are depth limited.

Serial FHRR Information Need{s) 1 Action (Post AlJdit).

No. Section o It was decided that a more conservative approach would be to calculate deep water waves using simplified procedures, but assume the worst wind and worst fetch direction, and add to the highest surge still water elevation (including tide and river flood).

  • The input files necessary to recreate two of the SLOSH and ADCIRC model results were provided.
  • Bathymetry used with ADCIRC was provided by FEMA.

29 I 3.4: Storm Surge I Have available appropriate documents and references, as well as an SME who is ~he staff spoke to the licensee's SMEs. Based on knowledgeable about the probabilistic characterization of storm surge to discuss hose conversations, the staff may issue RAis to the following: urther address these issues.

6

  • Rationale for selecting 2 x 10* as the appropriate level to establish the reevaluated storm surge elevation
  • Interpretation of the hazard curve and annual exceedance probability (AEP) of 2 x 1Q-6 light of the use of deterministic models and event combinations and any associated potential bias inherent in models employed as well as any uncertainties that were considered or neglected.

NRC Staff notes: The licensee's SMEs provided an overview of their approach to the calculation of probabilistic storm surge at the /PEG site. Through the course of the audit, the SMEs stated that conservatisms in the probabilistic storm surge calculations provide justification for the selection of the 2 x 1Q-6 number. The interpretation of the hazard curve (e.g., whether the hazard curve can be interpreted as a mean curve) and AEP of 2 x 1D-6 remains unclear due to the use of deterministic models and event combinations, associated potential bias inherent in models employed, as well as uncertainties that were neglected.

30 3.4: Storm Surge 1 Have available appropriate documents, codes, and references as well as an ~he staff spoke to the licensee's SMEs. Based on SME who is knowledgeable about the probabilistic characterization of storm hose conversations, the licensee made presentation surge to discuss the following: materials and supplemental written responses from

  • Characterization and propagation of relevant sources of aleatory variability he audit available to staff in the ERR. The staff plans

Serial .. FHRR Information Need(s) 1 No; section Actioll.lPos(Audit)

(e.g., probability density functions associated with storm parameters and o issue RAis, as needed, to request that the licensee ocket information contained in the presentation

~

model errors).

  • The means by which epistemic uncertainties in related data, models and materials or supplemental materials if it serves as a methods were addressed, including, but not limited to, the following topics: asis for conclusions documented in the staff o alternate technical interpretations of relevant data, including ssessment. The staff may also request additional o considerations of different means of selecting, interpreting, and filtering more detailed information regarding modeling data from the HURDAT database. ~ecisions.

o alternate technical interpretations of relevant probability density (mass) functions used to characterize aleatory uncertainty associated with storm parameters (e.g., intensity, storm track, radius to maximum winds, and storm translational speed) o alternate technically defensible models and modeling decisions

  • The means by which epistemic uncertainties were quantified and propagated (e.g., development of logic trees, if applicable}.

NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of probabilistic storm surge at the /PEG site. During the break-out sessions that followed, an AREVA subcontractor (Dr. Emanuel) described the methods used to develop the probability distributions for storm parameters, including consideration of historic and synthetic data (with multiple geographic filters) as well as the use of nonparametric methods and extreme value analysis.

The licensee described the consideration of epistemic uncertainty via "benchmarking" and justification for conservative assumptions. Epistemic uncertainties were not explicitly quantified or propagated. The licensee provided supplemental information in the form of presentation materials addressing the items listed above and written response to specific follow-up questions (e.g.,

questions related to bootstrap algorithms employed for verification analyses).

Additionally, the licensee referenced a 2006 Emanuel paper that looked at probability distribution comparisons to historical data.

31 I 3.4: Storm Surge I Have available an electronic copy of the Excel spreadsheet !Staff may issue RAI requesting justification for

Serial FHRR ' ~~ C,c Information Need(s) 1 ~ctiQn. (Post Audit)

No: Section .

JPM_SLOSH_ADCIRC_1 03013.xlsx referenced in Appendix H of calculation ~onfidence in results near 2 x 10-6 level (may require package 32-9213352-000 as well as personnel knowledgeable in its contents dditional simulations to bolster confidence in the 2 and usage. 1Q-6 values NRC staff notes: The subject spreadsheet identified in the audit plan was made available to the staff prior to the audit as part of an RAI response. The staff asked various questions related to the spreadsheet on topics such as treatment of probability mass associated with combinations of parameters assigned "-999" surge values, confidence in results near the 2 x 1D-6 level and selection of computer runs for refinement using ADCIRC. As a result, the staff was able to develop an understanding of the spreadsheets' contents and usage.

32 3.4: Storm Surge I Have available relevant documentation and an SME who is knowledgeable ~he licensee has made presentation materials from about the probabilistic characterization of storm surge to discuss any sensitivity he audit available to staff in the ERR. The staff studies performed to support the probabilistic storm surge analysis (PSSA). plans to issue RAis, as needed, to request that the licensee docket information contained in the NRC staff notes: The licensee's SMEs provided an overview of their approach presentation materials if it serves as a basis for

~

to the calculation of probabilistic storm surge at the /PEG site. Results of onclusions documented in the staff assessment.

sensitivity studies were discussed. In addition, presentation materials were he staff may also request additional or more prepared summarizing parameter sensitivity (e.g., as low, moderate, or high). In etailed information regarding sensitivity studies.

addition, supplemental materials were presented related to sensitivity studies of parameter ranges and discretization considered in the joint probability method (JPM) integration.

33 I 3.4: Storm Surge I Have available appropriate documents, codes, and references as well as an SME The staff will continue its review of information who is knowledgeable about the probabilistic characterization of storm surge to ontained in the ERR (e.g., calculation packages) discuss the following: ith the improved understanding afforded by the

  • Probability distributions associated with storm parameters and error terms larifying information presented during the audit. The (as applicable) in the JPM integral. taft plans to issue RAis, as needed, to request that
  • Basis for distribution models and parameters selected, including any he licensee docket information contained in the

Serial FHRR Information Need(s) 1 , ~ctio~ (flo~tA~dit),,

No. Section ' y*:~~)*~

analyses performed using expert judgment, based on existing studies, or ~alculation packages if it serves as a basis for based on available data (e.g., HURDAT) including selection, interpretation, onclusions documented in the staff assessment. If and filtering of available data. necessary, the staff may also request additional or

~

ore detailed information regarding the datasets NRC staff notes: The licensee's SMEs provided an overview of their approach to tilized, judgments applied, and probability the calculation of probabilistic storm surge at the /PEG site. SMEs provided istributions ultimately selected.

significant clarifying information regarding the methodology used to develop probability distributions associated with storm parameters in the JPM integral. A significant portion of the audit was spent discussing the basis for the distribution models selected (e.g., data and methods used to derive distributions, geographic filters applied to datasets, and the means by which temporal correlation in the datasets was addressed). The NRC staff was also afforded the opportunity to discuss the synthetic dataset with the external SME responsible for its development.

34 I 3.4: Storm Surge I Have available appropriate documents, codes, and references as well as an SME he licensee has made presentation materials from who is knowledgeable about the probabilistic characterization of storm surge to he audit available to staff in the ERR. The staff discuss the selected discretization shown in FHRR Tables 3.4-5 through 3.4-9, xpects to issue RAis related to the impact of including (but not limited to) discussion of the basis for the selected discretization iscretization, selected parameter ranges, and and the treatment of the contribution of probability mass associated with reatment of probability mass that was assigned to parameter values outside the range of parameters shown in Tables 3.4-5 through ombinations of parameters later deemed 3.4-9. meteorologically impossible.

NRC staff notes: The licensee's SMEs provided an overview of their approach to the calculation of probabilistic storm surge at the /PEG site. The SMEs prepared a supplemental presentation to illustrate the sensitivity of results to various decisions related to parameter ranges and discretization, including the impact of excluding probability mass outside the ranges of the parameters considered. The NRC staff also raised questions related to exclusion of probability mass assigned to parameter combinations that were later deemed meteorologically impossible.

Serial FHRR

  • Information Neect(s)1 rcc Action (Post';Audit) ;*.. '* *.

No*. , Section ' ' *~ : // ~ ..?vf/ ,c 35 3.4: Storm Surge Have available relevant codes, references, and documentation as well as an he staff will continue its review of information SME who is knowledgeable about the probabilistic characterization of storm ontained in the ERR (e.g., calculation packages) surge to discuss the basis for the calculated omni-directional storm rate including ith the improved understanding afforded by the (but not limited to) the basis for the selected capture zone and any sensitivity larifying information presented during the audit. Thel studies that were performed or alternate methods that were considered. NRC taff plans to issue RAis, as needed, to request that also requests that the licensee have available a tabulation of the events he licensee docket information contained in the (including event dates) that were used to compute the omni-directional storm rate alculation packages if it serves as a basis for (as referenced in Section 6.2 of calculation package 32-9213352-000). onclusions documented in the staff assessment. If necessary, the staff may also request additional or NRC staff notes: The licensee's SMEs provided an overview of their approach to jmore detailed information regarding the evaluation the calculation of probabilistic storm surge at the /PEG site. The SMEs prepared ~f the omni-directional rate.

presentation materials related to the omni-directional storm rate and provided clarifying information relative to information contained in the calculation packages. The licensee also provided the tabulation of events used to compute the omni-directional rate. Lambda (the storm rate coefficient) was presented in documents using two different units for values presented. The licensee's SME reported that GZA (an AREVA subcontractor) reevaluated lambda to reflect geographic variability. Results are in terms of four shoreline segments (the limits of which were based on observed landfall trends). In general, lambda equal to 0.047 is expected to be appropriate for storms contributing to the 1 x 10-6 return period flood.

36 3.4: Storm Surge Have available relevant documentation and an SME who is knowledgeable about he licensee has made presentation materials from the probabilistic characterization of storm surge to discuss the use and he audit available to the staff in the ERR. The staff interpretation of deterministic load combinations (e.g., a 25-year river flow in plans to issue RAis, as needed, to request that the conjunction with the storm surge event) in conjunction with the probabilistic licensee docket information contained in the characterization of storm surge and the basis for those decisions. alculation packages or presentation materials if it erves as a basis for conclusions documented in the NRC staff notes: The licensee's SMEs provided an overview of their approach to taff assessment. If necessary, the staff may also the calculation of probabilistic storm surge at the /PEG site. The SMEs described request additional or more detailed information the rationale for their judgment that the combination of a 25-year river flow in regarding deterministic load combinations.

Serial FHRR Information Need(s) 1 Action (PostAudit)

No. Section ""'

conjunction with a storm surge event is conservative. Their rationale was based on differences in characteristics between events that create large surges and events that deposit a large amount of rain on the watershed as well as considerations associated with the lack of coherence in the arrival of the peak surge and the arrival of a peak river flow. The licensee's SMEs noted that a 25-year flood was assumed to occur in conjunction with the PMSS. That rainfall event is considered to be conservative and as a further conservatism it is  !

assumed to occur with the PMSS a probability of 1. Presentation materials presented during the audit provided graphics to support the rationale provided.

37 3.4: Storm Surge Have available relevant documentation and an SME who is knowledgeable about ~he staff will continue its review of information the probabilistic characterization of storm surge to discuss components of the ~ontained in the ERR (e.g., calculation packages)

PSSA that relied on engineering judgment or experience, including (but not ~ith the improved understanding afforded by the limited to) the filtering of data, statistical methods used to develop probability ~larifying information presented during the audit.

density functions (PDFs), selected PDFs, event combinations considered (e.g., ~he staff plans to issue RAis, as needed, to request treatment of concurrent tides and river flows), model selection, and model hat the licensee docket information contained in the parameters. calculation packages if it serves as a basis for

~.;onclusions documented in the staff assessment. If NRC staff notes: The licensee's SMEs provided an overview of their approach to necessary, the staff may also request additional or the calculation of probabilistic storm surge at the /PEG site. The SMEs identified more detailed information regarding judgments several places where engineering judgment was applied. Moreover, throughout applied during the analysis.

the audit, the staff discussed the development of synthetic data, filtering of historic data, methods used to develop (or verify) probability density functions, treatment of tides and river flows, use of numerical models (SLOSH and ADCIRC), and other relevant decisions. Throughout the discussions, the staff further identified components of the analysis that utilized (explicitly or implicitly) engineering judgment or experience.

Serial FHRR >>>'>>

lnfonnation Need(s) 1 Action"(fiost<Audit)

No. Section >>' \c f_, <' >>' '>;< 1,>':,:">'<>, ">;,,,,,> ', ' I 38 3.4: Storm Surge Have available relevant codes, references, and documentation; and an SME who ~he licensee has made supplemental material is knowledgeable about the probabilistic characterization of storm surge to (contained in presentations) from the audit available discuss the results of verification and validation exercises, including the means o the staff in the ERR. The staff plans to issue by which the Joint Probability Method (JPM) integration accounted for model RAis, as needed, to request that the licensee docket errors. information contained in the presentation materials if it serves as a basis for conclusions documented in NRC staff notes: Entergy contractors provided supplemental information he staff assessment. Pending the results of further describing the basis for exclusion of an error term from the JPM integral. The review, the staff may request additional or more bases provided were centered on a judgment that various modeling decisions detailed information regarding treatment of were conservative (e.g., based on benchmarking studies) or that verification uncertainties.

studies showed results were sufficient that an error term was not required.

ML14227A672 A) Acting OFFICE NRR/JLD/JHMB/PM NRR/JLD/LA NRO/DSEA/BC(A) NRR/JLD/JHMB/BC NRR/JLD/JHMB/PM NAME RKuntz Slent KErwin SWhaley RKuntz DATE 08/19/14 08/18/14 07/31/14 08/27/14 08/29/14