Letter Sequence Request |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
|
MONTHYEARNL-12-125, Response to Request for Additional Information for Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application Environmental Review - Compliance with Coastal Zone Management Act2012-09-11011 September 2012 Response to Request for Additional Information for Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application Environmental Review - Compliance with Coastal Zone Management Act Project stage: Response to RAI ML13032A2562013-01-31031 January 2013 NRR E-mail Capture - NMFS Final Biop for Indian Point 2 and 3 Project stage: Request ML13142A0142013-05-0606 May 2013 License Renewal Application-Completed Engineering Project Cost Estimates for SAMAs Previously Identified as Potentially Cost-Beneficial Project stage: Other ML13154A5332013-06-0303 June 2013 NRC Staffs 16th Status Report in Response to the Atomic Safety and Licensing Board'S Order of February 16, 2012 Project stage: Request 05000286/LER-2013-003, Regarding Technical Specification Prohibited Condition Due to Turbine Driven Auxiliary Feedwater Pump Failure to Meet Test Acceptance Criteria2013-06-24024 June 2013 Regarding Technical Specification Prohibited Condition Due to Turbine Driven Auxiliary Feedwater Pump Failure to Meet Test Acceptance Criteria Project stage: Request ML13182A7312013-07-0101 July 2013 NRC Staff'S 17th Status Report in Response to the Atomic Safety and Licensing Board'S Order of February 16, 2012 Project stage: Request NL-13-098, Response to Request for Additional Information for the Review of the Indian Point Nuclear Generating Units 2 and 3, License Renewal Application2013-07-24024 July 2013 Response to Request for Additional Information for the Review of the Indian Point Nuclear Generating Units 2 and 3, License Renewal Application Project stage: Response to RAI ML13213A4912013-08-0101 August 2013 NRC Staff'S 18th Status Report in Response to the Atomic Safety and Licensing Board'S Order of February 16, 2012 Project stage: Request 05000247/LER-2013-003, Manual Reactor Trip Due to Decreasing Steam Generator Water Levels Due to Loss of Main Feedwater (FW) Flow Caused by a Loss of Instrument Air to the FW Regulating Valves2013-08-27027 August 2013 Manual Reactor Trip Due to Decreasing Steam Generator Water Levels Due to Loss of Main Feedwater (FW) Flow Caused by a Loss of Instrument Air to the FW Regulating Valves Project stage: Request ML13246A3452013-09-0303 September 2013 NRC Staff'S 19th Status Report in Response to the Atomic Safety and Licensing Board'S Order of February 16, 2012 Project stage: Request ML13269A4522013-09-26026 September 2013 Lr Hearing - IPEC License Renewal - Amendment 14 to LRA and IP2 UFSAR Update Project stage: Other ML13274A6532013-10-0101 October 2013 NRC Staff 20th Status Report in Response to the Atomic Safety and Licensing Board'S Order of February 16, 2012 Project stage: Request ML13308B3822013-11-0101 November 2013 NRC Staff'S 21st Status Report in Response to the Atomic Safety and Licensing Board'S Order of February 16, 2012 Project stage: Request ML13341A0032013-12-0707 December 2013 List of Attachments Project stage: Request ML13357A2542013-12-23023 December 2013 Entergys Answer Opposing State of New York Motion to Reopen the Record and for Reconsideration of Contention NYS-12C Project stage: Request ML13364A0062013-12-23023 December 2013 Required Response for NTTF Recommendation 2.1: Flooding - Hazard Reevaluation Report Project stage: Request ML14121A4312014-05-0505 May 2014 Regulatory Audit Plan for May 27 - 30, 2014, Audit at the Indian Point Facility to Support Review of Near Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report (TAC MF3313 & MF3314) Project stage: Other ML14120A1712014-05-0505 May 2014 Request for Additional Information Regarding Planned Audit for Near Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report (Tac Nos. MF3313 and MF3314) Project stage: RAI ML14227A6722014-08-29029 August 2014 Regulatory Audit Report for May 27-30, 2014, Audit at the Indian Point Facility to Support Review of Near-Term Task Force Recommendation 2.1: Flooding Hazard Reevaluation Report Project stage: Approval ML15124A3402015-05-0606 May 2015 Nuclear Regulatory Commission Plan for the Audit of Entergy Nucleaer Operations, Incs. Flooding Hazard Reevaluation Report Submittal Relating to the Fukushima Near-Term Task Force Recommendation 2.1 - Flooding for Indian Point Nuclear Gener Project stage: Other 2013-06-03
[Table View] |
Text
aSEnterg Entergy Nuclear Northeast Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel 914 254 6700 John A Ventosa Site Vice President Administration NL-13-156 December 23, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
References:
Entergy's Required Response for NTTF Recommendation 2.1: Flooding -
Hazard Reevaluation Report Indian Point Unit Numbers 2 and 3 Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64
- 1.
NRC letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident, dated March 12, 2012 (ML12053A340)
- 2.
Entergy Letter to NRC (NL-1 3-053), Entergy's Required Response 2 for NTTF Recommendation 2.1: Flooding - Hazard Reevaluation Report, dated March 12, 2013
- 3.
NRC letter, Indian Point Nuclear Generating Station Unit Nos. 2 and 3 - Relaxation of Response Due Dates Regarding Flooding Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Forces Review of the Insights From the Fukushima Dai-lchi Accident, dated April 12, 2013 (ADAMS Accession ML13095A297)
Dear Sir or Madam:
On March 12, 2012, the NRC issued the Reference 1 requesting information to support the evaluation of the NRC staff recommendations for the Near-Term Task Force (NTTF) review of the accident at the Fukushima Dai-ichi nuclear facility. Recommendation 2.1 of the referenced letter requested a reevaluation of all appropriate external flooding sources and the submittal of a Hazard Evaluation Report. Entergy Nuclear Operations, Inc. (Entergy) requested a delay to submit the Hazard Evaluation Report (Reference 2) and the NRC granted a schedule delay until December 31, 2013 (Reference 3).
f~oo~
NL-13-156 Docket Nos. 50-247 and 50-289 Page 2 of 2 Enclosed is the Hazard Reevaluation Report for Indian Point Energy Center (IPEC). The analysis was performed per the guidance of NUREG/CR-7046 and JLD-ISG-2012-06.
The interim actions in Reference 2 protects the plant from extreme postulated storms (storms that are postulated to occur only once in 500,000 years).
Protecting the plant against the 500,000 year flood will protect IPEC against storms that could result in flooding levels in the lower Manhattan Battery about 25 percent higher (about 20.8 feet NADV88). This can be compared to Super-storm Sandy where the National Oceanic and Atmospheric Administration reported storm water levels at the battery in lower Manhattan of 11.28 feet NADV88 and at Ossining, about 10 miles south of the plant, of 9.0 feet NADV88.
Entergy will, in accordance with Reference 1, Recommendation 2.1, Item 2, perform an integrated assessment and submit to NRC an Integrated Assessment Report within two years.
This letter contains no new regulatory commitments. If you have any questions concerning this submittal, please contact Mr. Robert Walpole, Manager, Licensing at (914) 254-6710.
I declare under penalty of perjury that the foregoing is true and correct; executed on December 2-3 2013.
Respectfully, JAV/sp Enclosure Flood Hazard Reevaluation Report Required by 10 CFR 50.54(f) Near-Term Task Force Recommendation 2.1 cc:
Mr. Douglas V. Pickett, Senior Project Manager, NRC NRR DORL Mr. William M. Dean, Regional Administrator, NRC Region 1 NRC Resident Inspectors Office Mr. Francis J. Murray, Jr., President and CEO, NYSERDA Ms. Bridget Frymire, New York State Dept. of Public Service