| number = ML12309A008
| number = ML12309A008
| issue date = 10/04/2012
| issue date = 10/04/2012
| title = 2012/10/04 Watts Bar 2 OL - TVA Letter to NRC_10-04-2012_Bulletin 88-08 Alternative Update
| title = OL - TVA Letter to NRC_10-04-2012_Bulletin 88-08 Alternative Update
| author name =  
| author name =  
| author affiliation = - No Known Affiliation
| author affiliation = - No Known Affiliation
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:1 WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]
{{#Wiki_filter:WBN2Public Resource From:                   Boyd, Desiree L [dlboyd@tva.gov]
Sent: Thursday, October 04, 2012 1:19 PM To: Epperson, Dan; Wilson, George; Poole, Justin Cc: Arent, Gordon; Hamill, Carol L; Boyd, Desiree L
Sent:                   Thursday, October 04, 2012 1:19 PM To:                     Epperson, Dan; Wilson, George; Poole, Justin Cc:                     Arent, Gordon; Hamill, Carol L; Boyd, Desiree L


==Subject:==
==Subject:==
TVA letter to NRC_10-04-2012_Bulletin 88-08 Alternative Update Attachments:
TVA letter to NRC_10-04-2012_Bulletin 88-08 Alternative Update Attachments:             10-04-2012_Bulletin 88-08 Alternative Update_Final.pdf Please see attached TVA letter that was sent to the NRC today.
10-04-2012_Bulletin 88-08 Alternative Update_Final.pdfPlease see attached TVA letter that was sent to the NRC today.  
Thank You,
~*~*~*~*~*~*~*~*~*~*~
Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764 1


Thank You,    ~*~*~*~*~*~*~*~*~*~*~
Hearing Identifier:     Watts_Bar_2_Operating_LA_Public Email Number:           747 Mail Envelope Properties     (7AB41F650F76BD44B5BCAB7C0CCABFAF33D04C1C)
Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764
 
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 747   Mail Envelope Properties   (7AB41F650F76BD44B5BCAB7C0CCABFAF33D04C1C)


==Subject:==
==Subject:==
TVA letter to NRC_10-04-2012_Bulletin 88-08 Alternative Update Sent Date:   10/4/2012 1:18:53 PM Received Date: 10/4/2012 1:22:33 PM From:   Boyd, Desiree L Created By:   dlboyd@tva.gov Recipients:     "Arent, Gordon" <garent@tva.gov>
TVA letter to NRC_10-04-2012_Bulletin 88-08 Alternative Update Sent Date:               10/4/2012 1:18:53 PM Received Date:           10/4/2012 1:22:33 PM From:                   Boyd, Desiree L Created By:             dlboyd@tva.gov Recipients:
Tracking Status: None "Hamill, Carol L" <clhamill@tva.gov>
"Arent, Gordon" <garent@tva.gov>
Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov> Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov> Tracking Status: None "Wilson, George" <George.Wilson@nrc.gov>
Tracking Status: None "Hamill, Carol L" <clhamill@tva.gov>
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov> Tracking Status: None  
Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov>
 
Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>
Post Office:   TVANUCXVS2.main.tva.gov Files     Size     Date & Time MESSAGE   274     10/4/2012 1:22:33 PM 10-04-2012_Bulletin 88-08 Alternative Update_Final.pdf   97157 Options Priority:     Standard   Return Notification:   No   Reply Requested:   Yes   Sensitivity:     Normal Expiration Date:     Recipients Received:
Tracking Status: None "Wilson, George" <George.Wilson@nrc.gov>
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
 
Tracking Status: None Post Office:             TVANUCXVS2.main.tva.gov Files                           Size                   Date & Time MESSAGE                         274                   10/4/2012 1:22:33 PM 10-04-2012_Bulletin 88-08 Alternative Update_Final.pdf                 97157 Options Priority:                       Standard Return Notification:             No Reply Requested:                 Yes Sensitivity:                     Normal Expiration Date:
October 4, 2012
Recipients Received:
 
10 CFR 50.4 U.S. Nuclear Regulatory Commission
 
ATTN:  Document Control Desk Washington, D.C. 20555-0001


Watts Bar Nuclear Plant, Unit 2   NRC Docket No. 50-391  
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 October 4, 2012 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391


==Subject:==
==Subject:==
WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 - NRC BULLETIN NO. 88-08, THERMAL STRESSES IN PIPING CONNECTED TO REACTOR COOLANT SYSTEMS (RCS) - CLARIFICATION  
WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 - NRC BULLETIN NO. 88-08, THERMAL STRESSES IN PIPING CONNECTED TO REACTOR COOLANT SYSTEMS (RCS) - CLARIFICATION


==References:==
==References:==
: 1. TVA letter dated March 29, 1994, Watts Bar Nuclear Plant (WBN) Units 1 and 2 - NRC Bulletin 88 Thermal Stresses in Piping Connected to  
: 1. TVA letter dated March 29, 1994, Watts Bar Nuclear Plant (WBN) Units 1 and 2 - NRC Bulletin 88 Thermal Stresses in Piping Connected to Reactor Coolant Systems (RCS)
 
Reactor Coolant Systems (RCS)
: 2. TVA letter dated August 15, 2012, Watts Bar Nuclear Plant (WBN) Unit 2 -
: 2. TVA letter dated August 15, 2012, Watts Bar Nuclear Plant (WBN) Unit 2 -
Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 8 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 8 (TAC No. MD8314)
Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 8 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 8 (TAC No. MD8314)
The purpose of this letter is to provide the current WBN Unit 2 plan for addressing NRC Bulletin 88-08. Based on analysis and experience gained from WBN Unit 1, WBN Unit 2 has developed an acoustic monitoring program similar to the one currently used on WBN Unit 1. provides the background and the basis for this action. The Regulatory Framework status for NRC Bulletin 88-08 shown in Reference 2 will be revised to reflect this change in the next update.  
The purpose of this letter is to provide the current WBN Unit 2 plan for addressing NRC Bulletin 88-08. Based on analysis and experience gained from WBN Unit 1, WBN Unit 2 has developed an acoustic monitoring program similar to the one currently used on WBN Unit 1. provides the background and the basis for this action. The Regulatory Framework status for NRC Bulletin 88-08 shown in Reference 2 will be revised to reflect this change in the next update. provides the new commitment made in this letter.
 
provides the new commitment made in this letter.
 
U.S. Nuclear Regulatory Commission Page 3 October 4, 2012 bcc (Enclosures):
 
Jessie Quichocho
 
U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North
 
11555 Rockville Pike
 
Rockville, Maryland 20852-2738
 
Fred Brown, Deputy Regional Administrator for Construction U. S. Nuclear Regulatory Commission Region II Marquis One Tower
 
245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257
 
ENCLOSURE 1 NRC BULLETIN 88-08, THERMAL STRESSES IN PIPING CONNECTED TO REACTOR COOLANT SYSTEMS (RCS) - CLARIFICATION E1-1  Background The purpose of NRC Bulletin 88-08 was to review the reactor coolant systems (RCS) to identify any connected, non-isolable piping that might be subjected to temperature distributions which result in unacceptable thermal stresses and to take action, where such piping is identified, to ensure that the piping will not be subjected to unacceptable thermal stresses.
In 1987 and 1988, thermal fatigue cracking and leakage in several PWR plants resulted
 
in the issuance of NRC Bulletin 88-08. In each of those events, the cracking was attributed to thermal cycling mechanisms not considered in initial plant design, and several actions were required of operating plants to assess susceptibility. The cracking was in normally stagnant non-isolable lines attached to RCS piping.
EPRI investigations into these events showed that two of the three cases described in the Bulletin could be attributed to in-leakage of cold water toward the RCS. Interaction of this leakage with turbulence/swirl penetration effects from the reactor coolant piping resulted in cyclic conditions of hot and cold water on the inside of the attached piping, eventually leading to thermal fatigue cracking and leakage. In the third case, the leakage was attributed to cyclic out-leakage past a normally closed valve. These events were summarized in an EPRI Materials Reliability Program (MRP). In none of these cases did the occurrence of thermal fatigue cracking result in a pipe rupture; however, leakage had occurred. For each of the events, the costs associated with evaluation, repair and plant unavailability were significant.  


In 1994, Aptech Engineering prepared a response to NRC Bulletin 88-08 for Watts Bar Nuclear Plant (WBN) Unit 2. Similar to Unit 1, RCS branch lines were assessed for
U.S. Nuclear Regulatory Commission Page 3 October 4, 2012 bcc (Enclosures):
Jessie Quichocho U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Fred Brown, Deputy Regional Administrator for Construction U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257


potential thermal fatigue concerns. For Unit 2, the Loop 1, boron safety injection (SI) branch line was identified as the only line requiring future action. One of the recommended actions for this line was for the SI check valve to be physically relocated such that the distance between the RCS connection and the check valve exceeded 25 branch diameters (i.e., an increase in the non-isolable section length). At that time, it was believed that this modification would render this branch line unsusceptible to swirl penetration cyclic stratification.
ENCLOSURE 1 NRC BULLETIN 88-08, THERMAL STRESSES IN PIPING CONNECTED TO REACTOR COOLANT SYSTEMS (RCS) - CLARIFICATION
In March 1999, the EPRI MRP Executive Group and Senior Representatives approved formation of the Thermal Fatigue Issue Task Group. Testing and evaluations were undertaken to better understand the thermal fatigue mechanisms that had been responsible for cracking in the non-isolable normally-stagnant branch lines. This


research culminated in the development of a methodology for evaluation of the phenomena that could lead to thermal cracking. Based on current understanding of the phenomenon and operating experience since 1994, the piping change described above would have no real influence on mitigating possible swirl penetration thermal fatigue.
===Background===
Thus, this modification is no longer recommended for mitigation of this thermal fatigue  
The purpose of NRC Bulletin 88-08 was to review the reactor coolant systems (RCS) to identify any connected, non-isolable piping that might be subjected to temperature distributions which result in unacceptable thermal stresses and to take action, where such piping is identified, to ensure that the piping will not be subjected to unacceptable thermal stresses.
 
In 1987 and 1988, thermal fatigue cracking and leakage in several PWR plants resulted in the issuance of NRC Bulletin 88-08. In each of those events, the cracking was attributed to thermal cycling mechanisms not considered in initial plant design, and several actions were required of operating plants to assess susceptibility. The cracking was in normally stagnant non-isolable lines attached to RCS piping.
mechanism.  
EPRI investigations into these events showed that two of the three cases described in the Bulletin could be attributed to in-leakage of cold water toward the RCS. Interaction of this leakage with turbulence/swirl penetration effects from the reactor coolant piping resulted in cyclic conditions of hot and cold water on the inside of the attached piping, eventually leading to thermal fatigue cracking and leakage. In the third case, the leakage was attributed to cyclic out-leakage past a normally closed valve. These events were summarized in an EPRI Materials Reliability Program (MRP). In none of these cases did the occurrence of thermal fatigue cracking result in a pipe rupture; however, leakage had occurred. For each of the events, the costs associated with evaluation, repair and plant unavailability were significant.
 
In 1994, Aptech Engineering prepared a response to NRC Bulletin 88-08 for Watts Bar Nuclear Plant (WBN) Unit 2. Similar to Unit 1, RCS branch lines were assessed for potential thermal fatigue concerns. For Unit 2, the Loop 1, boron safety injection (SI) branch line was identified as the only line requiring future action. One of the recommended actions for this line was for the SI check valve to be physically relocated such that the distance between the RCS connection and the check valve exceeded 25 branch diameters (i.e., an increase in the non-isolable section length). At that time, it was believed that this modification would render this branch line unsusceptible to swirl penetration cyclic stratification.
ENCLOSURE 1 NRC BULLETIN 88-08, THERMAL STRESSES IN PIPING CONNECTED TO REACTOR COOLANT SYSTEMS (RCS) - CLARIFICATION E1-2  WBN Unit 2 Action
In March 1999, the EPRI MRP Executive Group and Senior Representatives approved formation of the Thermal Fatigue Issue Task Group. Testing and evaluations were undertaken to better understand the thermal fatigue mechanisms that had been responsible for cracking in the non-isolable normally-stagnant branch lines. This research culminated in the development of a methodology for evaluation of the phenomena that could lead to thermal cracking. Based on current understanding of the phenomenon and operating experience since 1994, the piping change described above would have no real influence on mitigating possible swirl penetration thermal fatigue.
 
Thus, this modification is no longer recommended for mitigation of this thermal fatigue mechanism.
In response to the experience gained from WBN Unit 1, the methodology used for WBN Unit 2 was to perform an engineering assessment of the RCS branch piping as described in MRP-146, "Management of Thermal Fatigue in Normally Stagnant Non-Isolable Reactor Coolant System Branch Lines."  Unit 2 Calculation 1100448.301 entitled "MRP-146 Assessment of Normally Stagnant Non-Isolable Branch Lines" was performed to determine the susceptibility of non-isolable and stagnant branch lines off the RCS to thermal cycling mechanisms. The results of this assessment identified four lines that are susceptible to turbulence/swirl penetration effects that could lead to thermal fatigue cracking and leakage.
E1-1


ENCLOSURE 1 NRC BULLETIN 88-08, THERMAL STRESSES IN PIPING CONNECTED TO REACTOR COOLANT SYSTEMS (RCS) - CLARIFICATION WBN Unit 2 Action In response to the experience gained from WBN Unit 1, the methodology used for WBN Unit 2 was to perform an engineering assessment of the RCS branch piping as described in MRP-146, "Management of Thermal Fatigue in Normally Stagnant Non-Isolable Reactor Coolant System Branch Lines." Unit 2 Calculation 1100448.301 entitled "MRP-146 Assessment of Normally Stagnant Non-Isolable Branch Lines" was performed to determine the susceptibility of non-isolable and stagnant branch lines off the RCS to thermal cycling mechanisms. The results of this assessment identified four lines that are susceptible to turbulence/swirl penetration effects that could lead to thermal fatigue cracking and leakage.
In compliance with NRC Bulletin 88-08, a susceptible drain line on each of the RCS Loops 1, 2, and 4 crossover legs was identified. Those three lines have been added to the augmented Pre-service Inspection Program WBN-2 PSI for baseline inspections of those areas deemed most susceptible to thermal fatigue cracking as noted in MRP-146.
In compliance with NRC Bulletin 88-08, a susceptible drain line on each of the RCS Loops 1, 2, and 4 crossover legs was identified. Those three lines have been added to the augmented Pre-service Inspection Program WBN-2 PSI for baseline inspections of those areas deemed most susceptible to thermal fatigue cracking as noted in MRP-146.
The RCS Loop 1 cold leg SI boron injection line is the fourth line identified which will be monitored for in-leakage. Cyclic stratification only occurs when in-leakage is present. Lack of in-leakage could reduce the need for future inspections.
The RCS Loop 1 cold leg SI boron injection line is the fourth line identified which will be monitored for in-leakage. Cyclic stratification only occurs when in-leakage is present.
Clarification For WBN Unit 2, TVA will utilize the WBN Unit 1 approach which utilizes an EPRI calculational methodology and an augmented Pre-service Inspection Program for the three Unit 2 drain lines.  
Lack of in-leakage could reduce the need for future inspections.
 
Clarification For WBN Unit 2, TVA will utilize the WBN Unit 1 approach which utilizes an EPRI calculational methodology and an augmented Pre-service Inspection Program for the three Unit 2 drain lines.
In addition, WBN Unit 2 has developed an acoustic monitoring program for the Unit 2 SI boron injection line governed by Procedure 2-TI-305, Acoustic Monitoring to Detect Leakage Through 2-FCV-63-25 & -26, which is similar to that used on WBN Unit 1 for monitoring its susceptible SI boron injection lines for in-leakage.  
In addition, WBN Unit 2 has developed an acoustic monitoring program for the Unit 2 SI boron injection line governed by Procedure 2-TI-305, Acoustic Monitoring to Detect Leakage Through 2-FCV-63-25 & -26, which is similar to that used on WBN Unit 1 for monitoring its susceptible SI boron injection lines for in-leakage.
E1-2


ENCLOSURE 2 LIST OF COMMITMENTS E2-1  1. The Regulatory Framework status for NRC Bulletin 88-08 shown in Reference 2 will be revised to reflect this change in the next update.}}
ENCLOSURE 2 LIST OF COMMITMENTS
: 1. The Regulatory Framework status for NRC Bulletin 88-08 shown in Reference 2 will be revised to reflect this change in the next update.
E2-1}}

Latest revision as of 18:22, 5 December 2019

OL - TVA Letter to NRC_10-04-2012_Bulletin 88-08 Alternative Update
ML12309A008
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 10/04/2012
From:
- No Known Affiliation
To:
Division of Operating Reactor Licensing
References
Download: ML12309A008 (8)


Text

WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]

Sent: Thursday, October 04, 2012 1:19 PM To: Epperson, Dan; Wilson, George; Poole, Justin Cc: Arent, Gordon; Hamill, Carol L; Boyd, Desiree L

Subject:

TVA letter to NRC_10-04-2012_Bulletin 88-08 Alternative Update Attachments: 10-04-2012_Bulletin 88-08 Alternative Update_Final.pdf Please see attached TVA letter that was sent to the NRC today.

Thank You,

~*~*~*~*~*~*~*~*~*~*~

Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764 1

Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 747 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF33D04C1C)

Subject:

TVA letter to NRC_10-04-2012_Bulletin 88-08 Alternative Update Sent Date: 10/4/2012 1:18:53 PM Received Date: 10/4/2012 1:22:33 PM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients:

"Arent, Gordon" <garent@tva.gov>

Tracking Status: None "Hamill, Carol L" <clhamill@tva.gov>

Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov>

Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>

Tracking Status: None "Wilson, George" <George.Wilson@nrc.gov>

Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>

Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 274 10/4/2012 1:22:33 PM 10-04-2012_Bulletin 88-08 Alternative Update_Final.pdf 97157 Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:

Recipients Received:

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 October 4, 2012 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391

Subject:

WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 - NRC BULLETIN NO. 88-08, THERMAL STRESSES IN PIPING CONNECTED TO REACTOR COOLANT SYSTEMS (RCS) - CLARIFICATION

References:

1. TVA letter dated March 29, 1994, Watts Bar Nuclear Plant (WBN) Units 1 and 2 - NRC Bulletin 88 Thermal Stresses in Piping Connected to Reactor Coolant Systems (RCS)
2. TVA letter dated August 15, 2012, Watts Bar Nuclear Plant (WBN) Unit 2 -

Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 8 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 8 (TAC No. MD8314)

The purpose of this letter is to provide the current WBN Unit 2 plan for addressing NRC Bulletin 88-08. Based on analysis and experience gained from WBN Unit 1, WBN Unit 2 has developed an acoustic monitoring program similar to the one currently used on WBN Unit 1. provides the background and the basis for this action. The Regulatory Framework status for NRC Bulletin 88-08 shown in Reference 2 will be revised to reflect this change in the next update. provides the new commitment made in this letter.

U.S. Nuclear Regulatory Commission Page 3 October 4, 2012 bcc (Enclosures):

Jessie Quichocho U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Fred Brown, Deputy Regional Administrator for Construction U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257

ENCLOSURE 1 NRC BULLETIN 88-08, THERMAL STRESSES IN PIPING CONNECTED TO REACTOR COOLANT SYSTEMS (RCS) - CLARIFICATION

Background

The purpose of NRC Bulletin 88-08 was to review the reactor coolant systems (RCS) to identify any connected, non-isolable piping that might be subjected to temperature distributions which result in unacceptable thermal stresses and to take action, where such piping is identified, to ensure that the piping will not be subjected to unacceptable thermal stresses.

In 1987 and 1988, thermal fatigue cracking and leakage in several PWR plants resulted in the issuance of NRC Bulletin 88-08. In each of those events, the cracking was attributed to thermal cycling mechanisms not considered in initial plant design, and several actions were required of operating plants to assess susceptibility. The cracking was in normally stagnant non-isolable lines attached to RCS piping.

EPRI investigations into these events showed that two of the three cases described in the Bulletin could be attributed to in-leakage of cold water toward the RCS. Interaction of this leakage with turbulence/swirl penetration effects from the reactor coolant piping resulted in cyclic conditions of hot and cold water on the inside of the attached piping, eventually leading to thermal fatigue cracking and leakage. In the third case, the leakage was attributed to cyclic out-leakage past a normally closed valve. These events were summarized in an EPRI Materials Reliability Program (MRP). In none of these cases did the occurrence of thermal fatigue cracking result in a pipe rupture; however, leakage had occurred. For each of the events, the costs associated with evaluation, repair and plant unavailability were significant.

In 1994, Aptech Engineering prepared a response to NRC Bulletin 88-08 for Watts Bar Nuclear Plant (WBN) Unit 2. Similar to Unit 1, RCS branch lines were assessed for potential thermal fatigue concerns. For Unit 2, the Loop 1, boron safety injection (SI) branch line was identified as the only line requiring future action. One of the recommended actions for this line was for the SI check valve to be physically relocated such that the distance between the RCS connection and the check valve exceeded 25 branch diameters (i.e., an increase in the non-isolable section length). At that time, it was believed that this modification would render this branch line unsusceptible to swirl penetration cyclic stratification.

In March 1999, the EPRI MRP Executive Group and Senior Representatives approved formation of the Thermal Fatigue Issue Task Group. Testing and evaluations were undertaken to better understand the thermal fatigue mechanisms that had been responsible for cracking in the non-isolable normally-stagnant branch lines. This research culminated in the development of a methodology for evaluation of the phenomena that could lead to thermal cracking. Based on current understanding of the phenomenon and operating experience since 1994, the piping change described above would have no real influence on mitigating possible swirl penetration thermal fatigue.

Thus, this modification is no longer recommended for mitigation of this thermal fatigue mechanism.

E1-1

ENCLOSURE 1 NRC BULLETIN 88-08, THERMAL STRESSES IN PIPING CONNECTED TO REACTOR COOLANT SYSTEMS (RCS) - CLARIFICATION WBN Unit 2 Action In response to the experience gained from WBN Unit 1, the methodology used for WBN Unit 2 was to perform an engineering assessment of the RCS branch piping as described in MRP-146, "Management of Thermal Fatigue in Normally Stagnant Non-Isolable Reactor Coolant System Branch Lines." Unit 2 Calculation 1100448.301 entitled "MRP-146 Assessment of Normally Stagnant Non-Isolable Branch Lines" was performed to determine the susceptibility of non-isolable and stagnant branch lines off the RCS to thermal cycling mechanisms. The results of this assessment identified four lines that are susceptible to turbulence/swirl penetration effects that could lead to thermal fatigue cracking and leakage.

In compliance with NRC Bulletin 88-08, a susceptible drain line on each of the RCS Loops 1, 2, and 4 crossover legs was identified. Those three lines have been added to the augmented Pre-service Inspection Program WBN-2 PSI for baseline inspections of those areas deemed most susceptible to thermal fatigue cracking as noted in MRP-146.

The RCS Loop 1 cold leg SI boron injection line is the fourth line identified which will be monitored for in-leakage. Cyclic stratification only occurs when in-leakage is present.

Lack of in-leakage could reduce the need for future inspections.

Clarification For WBN Unit 2, TVA will utilize the WBN Unit 1 approach which utilizes an EPRI calculational methodology and an augmented Pre-service Inspection Program for the three Unit 2 drain lines.

In addition, WBN Unit 2 has developed an acoustic monitoring program for the Unit 2 SI boron injection line governed by Procedure 2-TI-305, Acoustic Monitoring to Detect Leakage Through 2-FCV-63-25 & -26, which is similar to that used on WBN Unit 1 for monitoring its susceptible SI boron injection lines for in-leakage.

E1-2

ENCLOSURE 2 LIST OF COMMITMENTS

1. The Regulatory Framework status for NRC Bulletin 88-08 shown in Reference 2 will be revised to reflect this change in the next update.

E2-1