Letter Sequence RAI |
---|
TAC:MF2798, Clarify Application of Setpoint Methodology for LSSS Functions (Approved, Closed) |
|
MONTHYEARGNRO-2013/00012, Maximum Extended Load Line Limit Analysis Plus (Mellla+), License Amendment Request2013-09-25025 September 2013 Maximum Extended Load Line Limit Analysis Plus (Mellla+), License Amendment Request Project stage: Request ML13345A1822013-12-19019 December 2013 Supplemental Information Needed for Acceptance of Licensing Action, Request to Revise Technical Specification to Allow Operation in Expanded Maximum Extended Load Line Limit Analysis Plus (Mellla+) Domain Project stage: Acceptance Review ML13364A2862013-12-30030 December 2013 Maximum Extended Load Mine Limit Analysis Plus (Mella+) License Amendment Request-Responses to Requests for Supplemental Information Project stage: Supplement ML14023A5802014-01-23023 January 2014 NRR E-mail Capture - Acceptance Review of Grand Guld Nuclear Station License Amendment Request Regarding Maximum Extended Load Line Limit Analysis Plus Project stage: Acceptance Review ML14037A1492014-02-0606 February 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: RAI GNRO-2014/00024, Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 2/6/20142014-03-10010 March 2014 Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 2/6/2014 Project stage: Response to RAI ML14080A2722014-03-18018 March 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: RAI ML14119A0092014-04-28028 April 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Audit Plan Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: Other ML14101A0872014-05-0808 May 2014 Request for Withholding from Public Disclosure - 9/10/2013 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Nedc - 33612P, Revision 0 Project stage: Other ML14101A0432014-05-0808 May 2014 Request for Withholding from Public Disclosure - 12/19/2013 Affidavit Executed by L. Dolan, GE-Hitachi Nuclear Energy Americas LLC Related to Responses to Request for Supplemental Information Project stage: Other ML14140A3012014-05-19019 May 2014 NRR E-mail Capture - Grand Gulf Nuclear Station, Unit 1, Request for Additional Information Regarding Maximum Load Line Limit Analysis Plus Project stage: RAI ML14211A1362014-07-30030 July 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: RAI GNRO-2014/00051, Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request Dated 7/2/20142014-08-14014 August 2014 Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request Dated 7/2/2014 Project stage: Response to RAI GNRO-2014/00045, Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/20142014-08-26026 August 2014 Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/2014 Project stage: Response to RAI GNRO-2014/00064, Superseding Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 3/18/20142014-09-0404 September 2014 Superseding Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 3/18/2014 Project stage: Response to RAI GNRO-2014/00052, Response to Electronic Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 7/29/20142014-09-10010 September 2014 Response to Electronic Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 7/29/2014 Project stage: Request ML14265A4222014-10-23023 October 2014 Request for Withholding from Public Disclosure - 6/25/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 3 to GNRO-2014/00045 Dated 8/26/14 Project stage: Other ML14265A3842014-10-23023 October 2014 Request for Withholding from Public Disclosure - 6/19/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00045 Dated 8/26/14 Project stage: Other ML14265A3702014-10-23023 October 2014 Request for Withholding from Public Disclosure - 7/1/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00064 Dated 9/4/14 Project stage: Other ML14111A0582014-10-23023 October 2014 Request for Withholding from Public Disclosure - 3/4/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Enclosure to GNRO-2014/00024 Responses to Request for Additional Information Project stage: RAI ML14262A3972014-11-12012 November 2014 Request for Withholding from Public Disclosure - 7/22/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Enclosure 1 to GNRO-2014/00051 Dated 8/14/14 Project stage: Other ML14262A3722014-11-12012 November 2014 Request for Withholding from Public Disclosure - 8/20/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00052 Dated 9/10/14 Project stage: Other ML14260A1302014-11-25025 November 2014 April 23-25, 2014, Audit Report Regarding Maximum Extended Load Line Limit Analysis Plus Amendment Including Minimum Stable Film Boiling Temperature and Quench Model Project stage: Other GNRO-2014/00083, Traversing Incore Probe (TIP) Comparisons TIP Comparisons for Current Operating Conditions in Support of the Grand Gulf Nuclear Station (GGNS) Maximum Extended Load Line Limit Analysis Plus (Mellla+) License Amendment Request2014-12-15015 December 2014 Traversing Incore Probe (TIP) Comparisons TIP Comparisons for Current Operating Conditions in Support of the Grand Gulf Nuclear Station (GGNS) Maximum Extended Load Line Limit Analysis Plus (Mellla+) License Amendment Request Project stage: Request GNRO-2014/00088, Response to Item 20 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/20142015-01-20020 January 2015 Response to Item 20 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/2014 Project stage: Request GNRO-2015/00003, Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus, Amendment Request, Dated 5/19/20142015-02-0909 February 2015 Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus, Amendment Request, Dated 5/19/2014 Project stage: Request GNRO-2015/00011, Supplement to License Amendment Request Application to Revise the Current Methodology from 0 EFPY Through the End of Extended Operations to a Single Fluence Method2015-02-18018 February 2015 Supplement to License Amendment Request Application to Revise the Current Methodology from 0 EFPY Through the End of Extended Operations to a Single Fluence Method Project stage: Supplement ML15050A0772015-02-19019 February 2015 Request to Convert Regulatory Commitments for Time Critical Operator Actions Listed in Letter GNRO-2015/00003, Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit. Project stage: Request GNRO-2015/00012, Response to License Amendment Request for Revision of Five Technical Specification Allowable Value Setpoints Request for Additional Information2015-03-0303 March 2015 Response to License Amendment Request for Revision of Five Technical Specification Allowable Value Setpoints Request for Additional Information Project stage: Request ML15040A1262015-03-19019 March 2015 Request for Withholding Information from Public Disclosure - 10/30/14 Affidavit Executed by James F. Harrison, GE-Hitachi Nuclear Energy Americas LLC, Related to Attachment 1 to GNRO-2014/00088 Dated 1/20/15 (TAC MF27 Project stage: Withholding Request Acceptance ML15085A2272015-04-14014 April 2015 October 15, 2014, Onsite Audit Report Regarding Maximum Extended Load Line Limit Analysis Plus Project stage: Other ML15040A0932015-06-24024 June 2015 Request for Withholding Information from Public Disclosure-10/12/14 Affidavit Executed by James F. Harrison, GE-Hitachi Nuclear Energy Amenricas LLC Related to Attachment 1 to GNRO-2014/00083 Dated 12/15/2014 (MF2798) Project stage: Withholding Request Acceptance GNRO-2015/00059, Submits Corrected Technical Specification Pages Regarding Maximum Extended Load Line Limit Plus License Amendment Request, Dated 9/25/20132015-08-14014 August 2015 Submits Corrected Technical Specification Pages Regarding Maximum Extended Load Line Limit Plus License Amendment Request, Dated 9/25/2013 Project stage: Request ML15229A2192015-08-31031 August 2015 Redacted, Issuance of Amendment Maximum Extended Load Line Limit Analysis Plus License Amendment Request Project stage: Approval 2014-07-30
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24289A1442024-10-15015 October 2024 NRR E-mail Capture - Acceptance Review - Entergy (Grand Gulf Nuclear Station and River Bend Station) - CNRO2024-00017 - Adopt TSTF-592 - CLIIP (L-2024-LLA-0133) ML24137A2702024-05-16016 May 2024 NRR E-mail Capture - Entergy Fleet - Acceptance Review of License Amendment Request to Remove Obsolete License Conditions from Operating Licenses for GGNS, RBS, and WF3 (L-2024-LLA-0062) ML24108A1142024-04-17017 April 2024 June 2024 Emergency Preparedness Program Inspection - Request for Information ML24088A0092024-03-27027 March 2024 NRR E-mail Capture - Entergy Fleet - Final Request for Confirmation of Information (RCI) Re Alternative Request EN-RR-22-001 Concerning ASME Code Case N-752 (L-2022-LLR-0054) ML23348A1222023-12-14014 December 2023 NRR E-mail Capture - Grand Gulf, River Bend, and Waterford, Unit 3 - 2nd Round of Official RAIs for RR EN-RR-22-001, Use ASME Code Case N-752, Risk Informed Categorization for Class 2 and 3 Systems ML23335A0652023-12-0101 December 2023 NRR E-mail Capture - GGNS - Audit Questions for LARs Associated with TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Init. 4b and 50.69, Risk-Informed Cat. and Treatment of SSCs for Nuclear Pwr Rx (L-2023-LLA-0081/0080) ML23240A3412023-08-28028 August 2023 NRR E-mail Capture - ANO-2, Grand Gulf, and River Bend - Acceptance Review of LAR Revising TSs to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23191A8662023-07-10010 July 2023 NRR E-mail Capture - Grand Gulf - Acceptance Review of LAR Adopting 10 CFR 50.69, Risk-Informed Categorization and Treatment of SSCs for Nuclear Power Reactors ML23191A2802023-07-10010 July 2023 NRR E-mail Capture - Grand Gulf - Acceptance Review for LAR Adopting TSTF-505, Rev. 2, Provide Risk-Informed Completion Times - RITSTF Initiative 4b ML23116A1462023-04-26026 April 2023 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Final RAI for Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23009B6912023-01-0909 January 2023 NRR E-mail Capture - Grand Gulf, Unit 1 and River, Unit 1 - Acceptance of Requested Licensing Action Request to Update ASME Code RR SE with NRC-Approved Revision of BWRVIP Guidelines ML22353A6122022-12-19019 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22206A0152022-07-21021 July 2022 NRR E-mail Capture - Entergy (Grand Gulf, River Bend, and Waterford-3) - Acceptance Review of the RR EN-RR-22-001, Case N-752, Risk-informed Cat & Treatment for Repair/Replacement Activities in Class 2 & 3 Systems ML22173A0372022-06-21021 June 2022 NRR E-mail Capture - Entergy (Grand Gulf and River Bend) - Acceptance Review of the License Amendment Request to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML22110A1172022-04-19019 April 2022 (GG) 2022 Emergency Preparedness (EP) Program Inspection RFI Sdh 041922 ML22075A3692022-03-0303 March 2022 Email Grand Gulf 2022 PI&R Request for Information ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21165A1352021-06-14014 June 2021 NRR E-mail Capture - Grand Gulf - Acceptance Review for Inserice Testing Program Relief Request VRR-GGNS-2021-1, Pressure Isolation Valve Testing Frequency ML21119A2152021-04-28028 April 2021 NRR E-mail Capture - Energy Harbor Fleet, Beaver Valley Units 1 and 2 and DAVIS-BESSE Unit 1 - Acceptance of Relief Request Proposed Alternative to Use ASME OM Code Case OMN-27 ML21109A2142021-04-19019 April 2021 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Rev. Est Hours for Review of Relief Request (RR) - ASME Code RR Safety Eval with NRC-Approved Rev of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML21109A2132021-03-23023 March 2021 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Relief Request (RR) Associated with ASME Code RR Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML21068A4092021-03-0909 March 2021 NRR E-mail Capture - Entergy Fleet (GGNS and RBS) -Approval of TSTF-501 LAR, Relocate Sored Fuel Oil and Lube Oil Volume Values to Licensee Control ML21015A3452021-01-14014 January 2021 NRR E-mail Capture - Grand Gulf and River Bend - Revised Estimated Hours for Relief Request Associated with ASME Code RR SEs with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20363A1462020-12-22022 December 2020 Request for Information: Grand Gulf EP Exercise Inspection - March 2021 ML20352A1192020-12-10010 December 2020 Email from Thomas Saporito 12-10-20 ML20329A1442020-11-20020 November 2020 Terrapower QAPD Preliminary Questions Email ML20323A4162020-11-18018 November 2020 Response to Choice Letter (EA-20-094) ML20337A2712020-11-0909 November 2020 Email - Grand Gulf Nuclear Station 050-00416, Requested Regulatory Conference ML20289A3542020-10-14014 October 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of TSTF-563 LAR, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML20258A0202020-09-0909 September 2020 EP Program Inspection RFI, Request for Information to Support and Prepare for Emergency Preparedness (EP) Program Inspection Scheduled to Occur the Week of November 16, 2020 ML20260H4422020-09-0808 September 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Official RAIs for RR Associated with Updating ASME Code RR SEs with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20176A4832020-06-22022 June 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of Relief Request Associated with ASME Code RR SE with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20150A6012020-05-29029 May 2020 NRR E-mail Capture - Grand Gulf - Official RAI for LAR Associated with Containment ILRT Interval Change from 10 Years to 15 Years ML20097B8032020-04-0303 April 2020 NRR E-mail Capture - Grand Gulf - Acceptance Review for the Exigent LAR Associated with One-Time Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies from 11.5 Years to 13.5 Years ML20093C3072020-04-0101 April 2020 NRR E-mail Capture - (External_Sender) Entergy Fleet - Performance-Based Cyber Security Testing Plan Fee Waiver Response Letter (EPID P-2020-PRF-0000; CAC No. 001648) ML20079D9302020-03-19019 March 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with Adopting TSTF-501, Relocate Stored Fuel Oil and Lube Oil Volumes to Licensee Control ML20076B6322020-03-16016 March 2020 NRR E-mail Capture - Grand Gulf - Acceptance Review for the LAR Associated with Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies ML20057G1592020-02-24024 February 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML20057G1752020-02-24024 February 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with TSTF-566, Revise Actions for Inoperable RHR-Shutdown Cooling Subsystems ML19242C0122019-08-29029 August 2019 2.206 Petitioner (No Public Meeting Required) ML19339H4362019-08-26026 August 2019 Request for Information IR 05000416/2019-004 ML19115A3512019-04-25025 April 2019 LTR-19-0177 Tom Gurdziel, E-mail a Matter of Fairness Entergy Grand Gulf Seems to Be Running Rather Steadily at 100 Percent ML19151A3312019-04-0303 April 2019 (OEDO-19-00053)10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station ML19095B7622019-04-0303 April 2019 Acceptance Review Results for License Amendment Request to Adopt TSTF-564, Revision 2, Safety Limit MCPR (Minimum Critical Power Ratio), for Grand Gulf Nuclear Station, Unit 1 and River Bend Station, Unit 1 (EPID L-22019-LLA-0051) ML19078A3772019-03-19019 March 2019 NRR E-mail Capture - Grand Gulf - Official Rais for Relief Request GG-ISI-023, Inservice Inspection Impracticality, Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval ML19059A1782019-02-28028 February 2019 Acceptance Review Results for Relief Request No. EN-19-RR-1 to Use ASME Code Case N-831-1 for Entergy Fleet 2024-05-16
[Table view] |
Text
NRR-PMDAPEm Resource From: Wang, Alan Sent: Thursday, February 06, 2014 8:29 AM To: SEITER, JEFFERY ALAN Cc: Burkhardt, Janet
Subject:
Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request (TAC MF2798)
- Jeff, By letter dated September 25, 2013 (Agencywide Document Access and Management System (ADAMS) Accession No. ML13269A140), Entergy Operations Inc. (Entergy, the licensee) submitted a license amendment request (LAR) to allow plant operation in the expanded maximum extended load line limit analysis plus (MELLLA+) domain.
Upon review of Attachment 4 to the submittal titled Safety Analysis Report for Grand Gulf Nuclear Station- Maximum Extended Load Line Limit Analysis Plus (ADAMS Accession No. ML13269A139),
the US Nuclear Regulatory Commission (NRC) staff has determined that the following additional information is needed to complete our review:
- 1. Section 9.3.3 of Attachment 4 states that zirconium credit will be used in the Shumway correlation. The NRC staff has reviewed the zirconium data described in letter dated September 9, 2013 (ADAMS Accession No. ML13253A105), from GE Hitachi Nuclear Energy and has the following questions
- a. Fresh fuel that has little or no oxide at the start of the transient and the fresh fuel is often in the more reactive part of the core; therefore, it is the data of interest. Figure 6 of the September 9, 2013, letter has many data sets provided together on it. Provide a plot showing clean zirconium separate from all the other data including SS, Inconel, zirconium oxide and any data that would be expected to have oxidized zirconium.
- b. In the September 9, 2013 letter, much of the Hoffman (FKZ) data that has a rapid cooling rate early in the experiment that may have been incorrectly interpreted as quench. A closer examination of the data shows this initial cooling was due to startup of the test and that quench occurred much later at significantly lower temperatures. In addition, because of high temperatures during the tests and pre-conditioning of the rods, the rods are likely have thick oxide layer thicknesses that are not representative of fuel in a commercial reactor undergoing an Anticipated Transient without Scram with Instability (ATWS-I) event. Provide a plot showing the data considered valid by the licensee for justifying Shumway as implemented in TRACG for the intended application (e.g. ATWS-I under MELLLA+). Textual justification to support the choice of the selected data and exclusion of the other data should be provided focusing on comparing the applicable test conditions to the plant application conditions to support a conclusion that the data is applicable.
- 2. Section 9.3.3 of Attachment 10 states:
The plant-specific ATWS stability calculation was performed using the NRC-approved neutronic and thermal-hydraulic codes TRACG04.
1
An error in the code was corrected by letter from GE Hitachi Nuclear Energy to the staff dated October 15, 2013 titled Updated TRACG Quench Front Model Description and Qualification, which is currently under staff review. In the October 15, 2013 letter, GE noted:
The quench front model has been updated to correct an error in the quench front heat transfer coefficient for bottom reflooding, and to better capture the heat transfer ahead of and behind the quench front.
Please clarify which quench model is being used in the application.
This RAI was discussed with Mr. Jeff Seiter on February 4, 2014, and it was agreed that a response would be provided within 30 days of receipt of this email. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1445 or via e-mail at Alan.Wang@nrc.gov.
Alan Wang Project Manager (Grand Gulf Nuclear Station)
Nuclear Regulatory Commission Division of Operating Reactor Licensing Alan.Wang@NRC.gov Tel: (301) 415-1445 Fax: (301) 415-1222 2
Hearing Identifier: NRR_PMDA Email Number: 1069 Mail Envelope Properties (Alan.Wang@nrc.gov20140206082800)
Subject:
Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request (TAC MF2798)
Sent Date: 2/6/2014 8:28:36 AM Received Date: 2/6/2014 8:28:00 AM From: Wang, Alan Created By: Alan.Wang@nrc.gov Recipients:
"Burkhardt, Janet" <Janet.Burkhardt@nrc.gov>
Tracking Status: None "SEITER, JEFFERY ALAN" <jseiter@entergy.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 3888 2/6/2014 8:28:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: