(OEDO-19-00053)10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station
ML19151A331
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 04/03/2019
From: Siva Lingam
Plant Licensing Branch IV
To: Troy Pruett
Entergy Operations, NRC Region 4
Lingam S, 301-415-1564
References
2.206, OEDO-19-00053
Download: ML19151A331 (3)


Text

From:

Lingam, Siva To:

Pruett, Troy Cc:

Pascarelli, Robert; Buckberg, Perry; Felts, Russell

Subject:

RE: 10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station (OEDO-19-00053)

Date:

Thursday, May 02, 2019 1:04:00 PM The PRB first meeting was held on April 29, 2019. No final decision was made, and at the direction of the PRB Chair, the PRB members are still evaluating your petition. Thank you for your patience.

From: Lingam, Siva Sent: Wednesday, April 03, 2019 4:04 PM To: Pruett, Troy <Troy.Pruett@nrc.gov>

Cc: Pascarelli, Robert <Robert.Pascarelli@nrc.gov>; Buckberg, Perry <Perry.Buckberg@nrc.gov>;

Felts, Russell <Russell.Felts@nrc.gov>

Subject:

RE: 10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station (OEDO-19-00053)

Thank you for your prompt reply. We will follow the latest revision of MD 8.11.

From: Pruett, Troy Sent: Wednesday, April 03, 2019 4:01 PM To: Lingam, Siva <Siva.Lingam@nrc.gov>

Subject:

RE: 10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station (OEDO-19-00053)

Either procedure is acceptable.

From: Lingam, Siva Sent: Wednesday, April 03, 2019 1:44 PM To: Pruett, Troy <Troy.Pruett@nrc.gov>

Cc: Pascarelli, Robert <Robert.Pascarelli@nrc.gov>; Buckberg, Perry <Perry.Buckberg@nrc.gov>;

Felts, Russell <Russell.Felts@nrc.gov>

Subject:

RE: 10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station (OEDO-19-00053)

I contacted you by email on February 13, 2019 to introduce myself as the Petition Manager, and to describe some of the early steps in the petition process. As a status update, internal petition review board (PRB) discussions have begun as PRB members continue to review your petition.

When your petition was submitted on January 23, 2019, the 2000 version of Management Directive (MD) 8.11, Review Process for 10 CFR2.206 Petitions was current. A revised MD 8.11 was issued on March 1, 2019. Besides being a better organized MD overall, procedurally the revised MD includes a more effective interaction between the PRB and petitioner prior to the PRB decision on whether or not to accept a petition for further review.

I am requesting if you have any objection in case the PRB likes to follow the procedure in the revised MD 8.11 as your petition is evaluated. Please advise

Thank you for your patience.

From: Pruett, Troy Sent: Wednesday, February 13, 2019 5:24 PM To: Lingam, Siva <Siva.Lingam@nrc.gov>

Subject:

RE: 10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station - Acknowledgement Email (OEDO-19-00053)

Thanks for the message. Im fine with corresponding thru NRC email and my NRC work number.

I do not have a need to present to the Board. I am available to answer questions the Board may have regarding my request for enforcement action.

Troy Pruett 817-200-1106

From: Lingam, Siva Sent: Wednesday, February 13, 2019 3:25 PM To: Pruett, Troy <Troy.Pruett@nrc.gov>

Cc: Pascarelli, Robert <Robert.Pascarelli@nrc.gov>; Buckberg, Perry <Perry.Buckberg@nrc.gov>;

Devlin-Gill, Stephanie <Stephanie.Devlin-Gill@nrc.gov>

Subject:

10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station - Acknowledgement Email (OEDO-19-00053)

I have been assigned as the Petition Manager for your 10 CFR 2.206 petition dated January 23, 2019, in which you submitted your concerns regarding Entergys Grand Gulf Nuclear Station Operations in Mississippi.

Section 2.206 of Title 10 of the Code of Federal Regulations describes the petition process

- the primary mechanism for the public to request enforcement action by the NRC in a public process. This process permits anyone to petition NRC to take enforcement-type action related to NRC licensees or licensed activities. Depending on the results of its evaluation, the NRC could modify, suspend or revoke an NRC-issued license or take any other appropriate enforcement action to resolve a problem. The NRC staffs guidance for the disposition of 2.206 petition requests is in Management Directive 8.11, which is publicly available through a link at https://www.nrc.gov/about-nrc/regulatory/enforcement/petition.html or under Agencywide Documents Access Management System (ADAMS) Accession No. ML041770328. The 2.206 process is separate from the allegations process, which affords individuals who raise safety concerns a degree of protection of their identity. In the 2.206 process, all of the information in your letter will be made public, including your identity.

Under MD 8.11, you have the opportunity to address the Petition Review Board, either in person at NRC headquarters in Rockville, MD, or by telephone conference before it meets to discuss your petition. I would appreciate if you could advise me by March 15, 2019, if you would like to address the Petition Review Board. If you would like to meet in person, I will need to schedule a formal public meeting at the NRC Headquarters. If you would prefer to address the Petition Review Board via phone, I will also work with you to coordinate a date/time during the upcoming weeks.

It is noted that the petition did not provide email and/or telephone number contact

information other than a post office box address. Therefore, please advise your preferred contact information such as private email and telephone number for all the communications. Otherwise, I will be using your business email and telephone number for the communication purpose.

The NRC added your submission to ADAMS (ADAMS Accession No. ML19037A160) as publicly-available document.

Thank you.

Siva P. Lingam U.S. Nuclear Regulatory Commission Project Manager Palo Verde Nuclear Generating Station, Units 1, 2, and 3 Grand Gulf Nuclear Station Location: O-9E22; Mail Stop: O-9E03 Telephone: 301-415-1564 E-mail address: Siva.Lingam@nrc.gov