Letter Sequence RAI |
|---|
TAC:MF2798, Clarify Application of Setpoint Methodology for LSSS Functions (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement
Results
Other: GNRO-2013/00060, Entergys First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049), GNRO-2014/00011, Entergys Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses- with- Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), GNRO-2014/00060, Entergys Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, GNRO-2015/00004, Entergys Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mititgation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), ML14101A043, ML14101A087, ML14119A009, ML14260A130, ML14262A372, ML14262A397, ML14265A370, ML14265A384, ML14265A422, ML15085A227
|
MONTHYEARGNRO-2013/00060, Entergys First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2013-08-28028 August 2013 Entergys First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) Project stage: Other GNRO-2013/00012, Maximum Extended Load Line Limit Analysis Plus (Mellla+), License Amendment Request2013-09-25025 September 2013 Maximum Extended Load Line Limit Analysis Plus (Mellla+), License Amendment Request Project stage: Request ML13345A1822013-12-19019 December 2013 Supplemental Information Needed for Acceptance of Licensing Action, Request to Revise Technical Specification to Allow Operation in Expanded Maximum Extended Load Line Limit Analysis Plus (Mellla+) Domain Project stage: Acceptance Review ML13364A2862013-12-30030 December 2013 Maximum Extended Load Mine Limit Analysis Plus (Mella+) License Amendment Request-Responses to Requests for Supplemental Information Project stage: Supplement ML14023A5802014-01-23023 January 2014 NRR E-mail Capture - Acceptance Review of Grand Guld Nuclear Station License Amendment Request Regarding Maximum Extended Load Line Limit Analysis Plus Project stage: Acceptance Review ML14037A1492014-02-0606 February 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: RAI GNRO-2014/00011, Entergys Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses- with- Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-02-28028 February 2014 Entergys Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses- with- Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other GNRO-2014/00024, Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 2/6/20142014-03-10010 March 2014 Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 2/6/2014 Project stage: Response to RAI ML14080A2722014-03-18018 March 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: RAI ML14119A0092014-04-28028 April 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Audit Plan Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: Other ML14101A0432014-05-0808 May 2014 Request for Withholding from Public Disclosure - 12/19/2013 Affidavit Executed by L. Dolan, GE-Hitachi Nuclear Energy Americas LLC Related to Responses to Request for Supplemental Information Project stage: Other ML14101A0872014-05-0808 May 2014 Request for Withholding from Public Disclosure - 9/10/2013 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Nedc - 33612P, Revision 0 Project stage: Other ML14140A3012014-05-19019 May 2014 NRR E-mail Capture - Grand Gulf Nuclear Station, Unit 1, Request for Additional Information Regarding Maximum Load Line Limit Analysis Plus Project stage: RAI ML14211A1362014-07-30030 July 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: RAI GNRO-2014/00051, Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request Dated 7/2/20142014-08-14014 August 2014 Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request Dated 7/2/2014 Project stage: Response to RAI GNRO-2014/00045, Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/20142014-08-26026 August 2014 Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/2014 Project stage: Response to RAI GNRO-2014/00060, Entergys Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-08-26026 August 2014 Entergys Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other GNRO-2014/00064, Superseding Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 3/18/20142014-09-0404 September 2014 Superseding Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 3/18/2014 Project stage: Response to RAI GNRO-2014/00052, Response to Electronic Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 7/29/20142014-09-10010 September 2014 Response to Electronic Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 7/29/2014 Project stage: Request ML14111A0582014-10-23023 October 2014 Request for Withholding from Public Disclosure - 3/4/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Enclosure to GNRO-2014/00024 Responses to Request for Additional Information Project stage: RAI ML14265A3702014-10-23023 October 2014 Request for Withholding from Public Disclosure - 7/1/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00064 Dated 9/4/14 Project stage: Other ML14265A3842014-10-23023 October 2014 Request for Withholding from Public Disclosure - 6/19/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00045 Dated 8/26/14 Project stage: Other ML14265A4222014-10-23023 October 2014 Request for Withholding from Public Disclosure - 6/25/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 3 to GNRO-2014/00045 Dated 8/26/14 Project stage: Other ML14262A3722014-11-12012 November 2014 Request for Withholding from Public Disclosure - 8/20/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00052 Dated 9/10/14 Project stage: Other ML14262A3972014-11-12012 November 2014 Request for Withholding from Public Disclosure - 7/22/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Enclosure 1 to GNRO-2014/00051 Dated 8/14/14 Project stage: Other ML14260A1302014-11-25025 November 2014 April 23-25, 2014, Audit Report Regarding Maximum Extended Load Line Limit Analysis Plus Amendment Including Minimum Stable Film Boiling Temperature and Quench Model Project stage: Other GNRO-2014/00083, Traversing Incore Probe (TIP) Comparisons TIP Comparisons for Current Operating Conditions in Support of the Grand Gulf Nuclear Station (GGNS) Maximum Extended Load Line Limit Analysis Plus (Mellla+) License Amendment Request2014-12-15015 December 2014 Traversing Incore Probe (TIP) Comparisons TIP Comparisons for Current Operating Conditions in Support of the Grand Gulf Nuclear Station (GGNS) Maximum Extended Load Line Limit Analysis Plus (Mellla+) License Amendment Request Project stage: Request GNRO-2014/00090, Correction to Typographical Error in Entergy Letter GNRO-2014/00053 Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using Consolidated Line Item Improvement.2015-01-0606 January 2015 Correction to Typographical Error in Entergy Letter GNRO-2014/00053 Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using Consolidated Line Item Improvement. Project stage: Request GNRO-2014/00088, Response to Item 20 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/20142015-01-20020 January 2015 Response to Item 20 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/2014 Project stage: Request GNRO-2015/00003, Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus, Amendment Request, Dated 5/19/20142015-02-0909 February 2015 Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus, Amendment Request, Dated 5/19/2014 Project stage: Request GNRO-2015/00011, Supplement to License Amendment Request Application to Revise the Current Methodology from 0 EFPY Through the End of Extended Operations to a Single Fluence Method2015-02-18018 February 2015 Supplement to License Amendment Request Application to Revise the Current Methodology from 0 EFPY Through the End of Extended Operations to a Single Fluence Method Project stage: Supplement GNRO-2015/00013, Request to Convert Regulatory Commitments for Time Critical Operator Actions Listed in Letter GNRO-2015/00003, Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit2015-02-19019 February 2015 Request to Convert Regulatory Commitments for Time Critical Operator Actions Listed in Letter GNRO-2015/00003, Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit Project stage: Request GNRO-2015/00004, Entergys Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mititgation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-19019 February 2015 Entergys Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mititgation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other GNRO-2015/00012, Response to License Amendment Request for Revision of Five Technical Specification Allowable Value Setpoints Request for Additional Information2015-03-0303 March 2015 Response to License Amendment Request for Revision of Five Technical Specification Allowable Value Setpoints Request for Additional Information Project stage: Request ML15040A1262015-03-19019 March 2015 Request for Withholding Information from Public Disclosure - 10/30/14 Affidavit Executed by James F. Harrison, GE-Hitachi Nuclear Energy Americas LLC, Related to Attachment 1 to GNRO-2014/00088 Dated 1/20/15 (TAC MF27 Project stage: Withholding Request Acceptance ML15085A2272015-04-14014 April 2015 October 15, 2014, Onsite Audit Report Regarding Maximum Extended Load Line Limit Analysis Plus Project stage: Other ML15040A0932015-06-24024 June 2015 Request for Withholding Information from Public Disclosure-10/12/14 Affidavit Executed by James F. Harrison, GE-Hitachi Nuclear Energy Amenricas LLC Related to Attachment 1 to GNRO-2014/00083 Dated 12/15/2014 (MF2798) Project stage: Withholding Request Acceptance GNRO-2015/00059, Submits Corrected Technical Specification Pages Regarding Maximum Extended Load Line Limit Plus License Amendment Request, Dated 9/25/20132015-08-14014 August 2015 Submits Corrected Technical Specification Pages Regarding Maximum Extended Load Line Limit Plus License Amendment Request, Dated 9/25/2013 Project stage: Request ML15229A2192015-08-31031 August 2015 Redacted, Issuance of Amendment Maximum Extended Load Line Limit Analysis Plus License Amendment Request Project stage: Approval 2014-05-08
[Table View] |
Text
1 NRR-PMDAPEm Resource From:
Wang, Alan Sent:
Thursday, February 06, 2014 8:29 AM To:
SEITER, JEFFERY ALAN Cc:
Burkhardt, Janet
Subject:
Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request (TAC MF2798)
Jeff, By letter dated September 25, 2013 (Agencywide Document Access and Management System (ADAMS) Accession No. ML13269A140), Entergy Operations Inc. (Entergy, the licensee) submitted a license amendment request (LAR) to allow plant operation in the expanded maximum extended load line limit analysis plus (MELLLA+) domain.
Upon review of Attachment 4 to the submittal titled Safety Analysis Report for Grand Gulf Nuclear Station-Maximum Extended Load Line Limit Analysis Plus (ADAMS Accession No. ML13269A139),
the US Nuclear Regulatory Commission (NRC) staff has determined that the following additional information is needed to complete our review:
- 1. Section 9.3.3 of Attachment 4 states that zirconium credit will be used in the Shumway correlation. The NRC staff has reviewed the zirconium data described in letter dated September 9, 2013 (ADAMS Accession No. ML13253A105), from GE Hitachi Nuclear Energy and has the following questions
- a. Fresh fuel that has little or no oxide at the start of the transient and the fresh fuel is often in the more reactive part of the core; therefore, it is the data of interest. Figure 6 of the September 9, 2013, letter has many data sets provided together on it. Provide a plot showing clean zirconium separate from all the other data including SS, Inconel, zirconium oxide and any data that would be expected to have oxidized zirconium.
- b. In the September 9, 2013 letter, much of the Hoffman (FKZ) data that has a rapid cooling rate early in the experiment that may have been incorrectly interpreted as quench. A closer examination of the data shows this initial cooling was due to startup of the test and that quench occurred much later at significantly lower temperatures. In addition, because of high temperatures during the tests and pre-conditioning of the rods, the rods are likely have thick oxide layer thicknesses that are not representative of fuel in a commercial reactor undergoing an Anticipated Transient without Scram with Instability (ATWS-I) event. Provide a plot showing the data considered valid by the licensee for justifying Shumway as implemented in TRACG for the intended application (e.g. ATWS-I under MELLLA+). Textual justification to support the choice of the selected data and exclusion of the other data should be provided focusing on comparing the applicable test conditions to the plant application conditions to support a conclusion that the data is applicable.
- 2. Section 9.3.3 of Attachment 10 states:
The plant-specific ATWS stability calculation was performed using the NRC-approved neutronic and thermal-hydraulic codes TRACG04.
2 An error in the code was corrected by letter from GE Hitachi Nuclear Energy to the staff dated October 15, 2013 titled Updated TRACG Quench Front Model Description and Qualification, which is currently under staff review. In the October 15, 2013 letter, GE noted:
The quench front model has been updated to correct an error in the quench front heat transfer coefficient for bottom reflooding, and to better capture the heat transfer ahead of and behind the quench front.
Please clarify which quench model is being used in the application.
This RAI was discussed with Mr. Jeff Seiter on February 4, 2014, and it was agreed that a response would be provided within 30 days of receipt of this email. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1445 or via e-mail at Alan.Wang@nrc.gov.
Alan Wang Project Manager (Grand Gulf Nuclear Station)
Nuclear Regulatory Commission Division of Operating Reactor Licensing Alan.Wang@NRC.gov Tel: (301) 415-1445 Fax: (301) 415-1222
Hearing Identifier:
NRR_PMDA Email Number:
1069 Mail Envelope Properties (Alan.Wang@nrc.gov20140206082800)
Subject:
Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request (TAC MF2798)
Sent Date:
2/6/2014 8:28:36 AM Received Date:
2/6/2014 8:28:00 AM From:
Wang, Alan Created By:
Alan.Wang@nrc.gov Recipients:
"Burkhardt, Janet" <Janet.Burkhardt@nrc.gov>
Tracking Status: None "SEITER, JEFFERY ALAN" <jseiter@entergy.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 3888 2/6/2014 8:28:00 AM Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received: