MONTHYEARML24137A2702024-05-16016 May 2024 NRR E-mail Capture - Entergy Fleet - Acceptance Review of License Amendment Request to Remove Obsolete License Conditions from Operating Licenses for GGNS, RBS, and WF3 (L-2024-LLA-0062) ML24108A1142024-04-17017 April 2024 June 2024 Emergency Preparedness Program Inspection - Request for Information ML23348A1222023-12-14014 December 2023 NRR E-mail Capture - Grand Gulf, River Bend, and Waterford, Unit 3 - 2nd Round of Official RAIs for RR EN-RR-22-001, Use ASME Code Case N-752, Risk Informed Categorization for Class 2 and 3 Systems ML23335A0652023-12-0101 December 2023 NRR E-mail Capture - GGNS - Audit Questions for LARs Associated with TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Init. 4b and 50.69, Risk-Informed Cat. and Treatment of SSCs for Nuclear Pwr Rx (L-2023-LLA-0081/0080) ML23240A3412023-08-28028 August 2023 NRR E-mail Capture - ANO-2, Grand Gulf, and River Bend - Acceptance Review of LAR Revising TSs to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23191A8662023-07-10010 July 2023 NRR E-mail Capture - Grand Gulf - Acceptance Review of LAR Adopting 10 CFR 50.69, Risk-Informed Categorization and Treatment of SSCs for Nuclear Power Reactors ML23191A2802023-07-10010 July 2023 NRR E-mail Capture - Grand Gulf - Acceptance Review for LAR Adopting TSTF-505, Rev. 2, Provide Risk-Informed Completion Times - RITSTF Initiative 4b ML23116A1462023-04-26026 April 2023 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Final RAI for Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23009B6912023-01-0909 January 2023 NRR E-mail Capture - Grand Gulf, Unit 1 and River, Unit 1 - Acceptance of Requested Licensing Action Request to Update ASME Code RR SE with NRC-Approved Revision of BWRVIP Guidelines ML22353A6122022-12-19019 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22206A0152022-07-21021 July 2022 NRR E-mail Capture - Entergy (Grand Gulf, River Bend, and Waterford-3) - Acceptance Review of the RR EN-RR-22-001, Case N-752, Risk-informed Cat & Treatment for Repair/Replacement Activities in Class 2 & 3 Systems ML22173A0372022-06-21021 June 2022 NRR E-mail Capture - Entergy (Grand Gulf and River Bend) - Acceptance Review of the License Amendment Request to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML22110A1172022-04-19019 April 2022 (GG) 2022 Emergency Preparedness (EP) Program Inspection RFI Sdh 041922 ML22075A3692022-03-0303 March 2022 Email Grand Gulf 2022 PI&R Request for Information ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21165A1352021-06-14014 June 2021 NRR E-mail Capture - Grand Gulf - Acceptance Review for Inserice Testing Program Relief Request VRR-GGNS-2021-1, Pressure Isolation Valve Testing Frequency ML21119A2152021-04-28028 April 2021 NRR E-mail Capture - Energy Harbor Fleet, Beaver Valley Units 1 and 2 and DAVIS-BESSE Unit 1 - Acceptance of Relief Request Proposed Alternative to Use ASME OM Code Case OMN-27 ML21109A2142021-04-19019 April 2021 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Rev. Est Hours for Review of Relief Request (RR) - ASME Code RR Safety Eval with NRC-Approved Rev of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML21109A2132021-03-23023 March 2021 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Relief Request (RR) Associated with ASME Code RR Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML21068A4092021-03-0909 March 2021 NRR E-mail Capture - Entergy Fleet (GGNS and RBS) -Approval of TSTF-501 LAR, Relocate Sored Fuel Oil and Lube Oil Volume Values to Licensee Control ML21015A3452021-01-14014 January 2021 NRR E-mail Capture - Grand Gulf and River Bend - Revised Estimated Hours for Relief Request Associated with ASME Code RR SEs with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20363A1462020-12-22022 December 2020 Request for Information: Grand Gulf EP Exercise Inspection - March 2021 ML20352A1192020-12-10010 December 2020 Email from Thomas Saporito 12-10-20 ML20329A1442020-11-20020 November 2020 Terrapower QAPD Preliminary Questions Email ML20323A4162020-11-18018 November 2020 Response to Choice Letter (EA-20-094) ML20337A2712020-11-0909 November 2020 Email - Grand Gulf Nuclear Station 050-00416, Requested Regulatory Conference ML20289A3542020-10-14014 October 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of TSTF-563 LAR, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML20258A0202020-09-0909 September 2020 EP Program Inspection RFI, Request for Information to Support and Prepare for Emergency Preparedness (EP) Program Inspection Scheduled to Occur the Week of November 16, 2020 ML20260H4422020-09-0808 September 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Official RAIs for RR Associated with Updating ASME Code RR SEs with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20176A4832020-06-22022 June 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of Relief Request Associated with ASME Code RR SE with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20150A6012020-05-29029 May 2020 NRR E-mail Capture - Grand Gulf - Official RAI for LAR Associated with Containment ILRT Interval Change from 10 Years to 15 Years ML20097B8032020-04-0303 April 2020 NRR E-mail Capture - Grand Gulf - Acceptance Review for the Exigent LAR Associated with One-Time Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies from 11.5 Years to 13.5 Years ML20093C3072020-04-0101 April 2020 NRR E-mail Capture - (External_Sender) Entergy Fleet - Performance-Based Cyber Security Testing Plan Fee Waiver Response Letter (EPID P-2020-PRF-0000; CAC No. 001648) ML20079D9302020-03-19019 March 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with Adopting TSTF-501, Relocate Stored Fuel Oil and Lube Oil Volumes to Licensee Control ML20076B6322020-03-16016 March 2020 NRR E-mail Capture - Grand Gulf - Acceptance Review for the LAR Associated with Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies ML20057G1752020-02-24024 February 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with TSTF-566, Revise Actions for Inoperable RHR-Shutdown Cooling Subsystems ML20057G1592020-02-24024 February 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML19242C0122019-08-29029 August 2019 2.206 Petitioner (No Public Meeting Required) ML19339H4362019-08-26026 August 2019 Request for Information IR 05000416/2019-004 ML19115A3512019-04-25025 April 2019 LTR-19-0177 Tom Gurdziel, E-mail a Matter of Fairness Entergy Grand Gulf Seems to Be Running Rather Steadily at 100 Percent ML19151A3312019-04-0303 April 2019 (OEDO-19-00053)10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station ML19095B7622019-04-0303 April 2019 Acceptance Review Results for License Amendment Request to Adopt TSTF-564, Revision 2, Safety Limit MCPR (Minimum Critical Power Ratio), for Grand Gulf Nuclear Station, Unit 1 and River Bend Station, Unit 1 (EPID L-22019-LLA-0051) ML19078A3772019-03-19019 March 2019 NRR E-mail Capture - Grand Gulf - Official Rais for Relief Request GG-ISI-023, Inservice Inspection Impracticality, Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval ML19059A1782019-02-28028 February 2019 Acceptance Review Results for Relief Request No. EN-19-RR-1 to Use ASME Code Case N-831-1 for Entergy Fleet ML19059A0292019-02-27027 February 2019 NRR E-mail Capture - Acceptance Review Results for License Amendment Request to Adopt TSTF-529, Revision 4, Clarify Use and Application Rules, for Entergy Fleet ML19053A7622019-02-22022 February 2019 NRR E-mail Capture - Grand Gulf - Acceptance of the LAR Associated with Revising TS 3.3.1.1 (RPS Instrumentation) and TS 3.3.4.1 (EOC-RPT Instrumentation) 2024-05-16
[Table view] |
See also: IR 05000416/2019004
Text
From: Carson, Louis
Sent: Monday, August 26, 2019 10:02 AM
To: ELLIS, DAVID R * GGNS
Cc: O'Donnell, John
Subject Wishlist: Occupational Radiation Safety Inspection Integrated Report 2019-004 at
Grand Gulf Nuclear Station (September 30- October 3, 2019)
Attachments: Wishlist GGNS 2019-004 IP 71124-01 and 03 8-26-2019.docx
GM Dave:
The following Items are requested for the OccupationaJ Radiation Safety Inspection
Integrated Report 2019-004 at Grand Gulf Nuclear Station (September 30- October 3, 2019)
Inspection areas are listed in the attachments below.
Please provide the requested information on or before September 20, 2019
Please submit this information using the same lettering system as below . For example, all contacts and phone
numbers for Inspection Procedure 71124.01 should be in a file/folder titled * 1- A," applicable organization
charts in file/folder "1- B," etc.
If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at least 30 days
later than the onsite inspection dates, so the inspectors will have access to the information while writing the
report.
Please have RP to identify RWPs for jobs, since June 2018, that were 1 person-rem or more since.
Th'X
Louis@
ML19339H436
1
The following items are requested for the
Occupational Radiation Safety Inspection
Integrated Report 2019-004
at
Grand Gulf Nuclear Station
(September 30- October 3, 2019)
Inspection areas are listed in the attachments below.
Please provide the requested information on or before September 20, 2019
Please submit this information using the same lettering system as below. For example, all
contacts and phone numbers for Inspection Procedure 71124.01 should be in a file/folder titled
"1-A," applicable organization charts in file/folder "1- B," etc.
If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at
least 30 days later than the onsite inspection dates, so the inspectors will have access to the
information while writing the report.
In addition to the corrective action document lists provided for each inspection procedure listed
below, please provide updated lists of corrective action documents at the entrance meeting.
The dates for these lists should range from the end dates of the original lists to the day of the
entrance meeting.
If more than one inspection procedure is to be conducted and the infonnation requests appear
to be redundant, there is no need to provide duplicate copies. Enter a note explaining in which
file the information can be found.
If you have any questions or comments, please contact Louis Carson at (817)200* 1221,
Louis. Carson@nrc. aov.
PAPERWORK REDUCTION ACT STATEMENT
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget,
control number 3150-0011.
1 Attachment 2
1. Radiological Hazard Assessment and Exposure Controls (71124.01) and
Performance Indicator Verification (71151)
Date of Last Inspection: April 27, 2018
A. List of contacts and telephone numbers for the Radiation Protection Organization Staff
and Technicians
B. Applicable organization charts
C. Audits, self-assessments, and LERs written since date of last inspection, related to this
inspection area
D. Procedure indexes for the radiation protection procedures
E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures may be requested by number after the inspector reviews
the procedure indexes.
1. Radiation Protection Program Description
2. Radiation Protection Conduct of Operations
3. Personnel Dosimetry Program
4. Posting of Radiological Areas
5. High Radiation Area Controls
6. RCA Access Controls and Radworker Instructions
7. Conduct of Radiological Surveys
8. Radioactive Source Inventory and Control
9. Declared Pregnant Worker Program
F. List of corrective action documents (including corporate and subtiered systems) since
date of last inspection
a. Initiated by the radiation protection organization
b. Assigned to the radiation protection organization
NOTE: The lists should indicate the significance level of each issue and the search
criteria used. Please provide in document fonnats which are "searchable" so that the
inspector can perform word searches.
If not covered above, a summary of corrective action documents since date of last
inspection involving unmonitored releases, unplanned releases, or releases in which any
dose limit or administrative dose limit was exceeded {for Public Radiation Safety
Performance Indicator verification in accordance with IP 71151)
G. List of radiologically significant work activities scheduled to be conducted during the
inspection period (If the inspection is scheduled during an outage, please also include a
list of work activities greater than 1 rem, scheduled during the outage with the dose
estimate for the work activity.)
C'
H. List of active radiation work permits
I. Radioactive source inventory list
a. All radioactive sources that are required to be leak tested
b. All radioactive sources that meet the 10 CFR Part 20, Appendix E, Category 2 and
above threshold. Please indicate the radioisotope, initial and current activity (w/assay
date), and storage location for each applicable source.
J. The last two leak test results for the radioactive sources inventoried and required to be
leak tested. If applicable, specifically provide a list of all radioactive source(s) that have
failed its leak test within the last two years
K. A current listing of any non-fuel items stored within your pools, and if available, their
appropriate dose rates (Contact I@ 30cm)
L. Computer printout of radiological controlled area entries greater than 100 millirems since
the previous inspection to the current inspection entrance date. The printout should
include the date of entry, some form of worker identification, the radiation work permit
used by the worker, dose accrued by the worker, and the electronic dosimeter dose
alarm setpoint used during the entry (for Occupational Radiation Safety Performance
Indicator verification in accordance with IP 71151 ).
3. ln*Plant Airborne Radioactivity Control and Mitigation (71124.03)
Date of Last Inspection: February 22, 2017
A List of contacts and telephone numbers for the following areas:
1. Respiratory Protection Program
2. Self contained breathing apparatus
B. Applicable organization charts
C. Copies of audits, self-assessments, vendor or NUPIC audits for contractor support
(SCBA), and LERs, written since date of last inspection related to:
1. Installed air filtration systems
2. Self contained breathing apparatuses
D. Procedure index for:
1. Use and operation of continuous air monitors
2. Use and operation of temporary air filtration units
3. Respiratory protection
E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures may be requested by number after the inspector reviews
the procedure indexes.
1. Respiratory protection program
2. Use of self contained breathing apparatuses
3. Air quality testing for SCBAs
4. Use of installed plant systems, such as containment purge, spent fuel pool
ventilation, and auxiliary building ventilation
F. A summary list of corrective action documents (including corporate and subtiered
systems) written since date of last inspection, related to the Airborne Monitoring program
including:
1. Continuous air monitors
2. Self contained breathing apparatuses
3. Respiratory protection program
NOTE: The lists should indicate the significance level of each issue and the search
criteria used. Please provide in document formats which are "searchable" so that the
inspector can perform word searches.
G. List of SCBA qualified personnel - reactor operators and emergency response personnel
H. Inspection records for self contained breathing apparatuses (SCBAs) staged in the plant
for use since date of last inspection.
I. SCBA training and qualification records for control room operators, shift supervisors,
STAs, and OSC personnel for the last year.
A selection of personnel may be asked to demonstrate proficiency in donning, doffing,
and perfonnance of functionality check for respiratory devices
J. List of respirators (available for use) by type (APR, SCBA, PAPR, etc.), manufacturer,
and model.
PAPERWORK REDUCTION ACT STATEMENT
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing infom,ation collection
requirements were approved by the Office of Management and Budget, control number 3150-
0011.