| title = 10/01/2018 Vogtle Readiness Group (Vrg) Update (Presentation)
| title = Readiness Group (Vrg) Update (Presentation)
| author name = Ayegbusi O, Hall V
| author name = Ayegbusi O, Hall V
| author affiliation = NRC/NRO/DCIP
| author affiliation = NRC/NRO/DCIP

Latest revision as of 08:22, 30 November 2019

Readiness Group (Vrg) Update (Presentation)
ML18271A216
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 10/01/2018
From: Odunayo Ayegbusi, Victor Hall
Division of Construction Inspection and Operational Programs
To:
Webb M
References
Download: ML18271A216 (7)


Text

CIP Public Meeting October 1, 2018 Vogtle Readiness Group (VRG) Update Ayo Ayegbusi Victor Hall NRO/DCIP

Vogtle Readiness Group

- VRG serves as the focal point for project status and for coordination among Region II, NRO, NRR, NSIR, and OGC through commercial operation of Vogtle Units 3 and 4.

Oversee the Vogtle Units 3 and 4 Transition to Operations

- In addition, the VRG serves as the hub for communications with the Commission, the Executive Director for Operations and its office direct reports, the licensee, and other external stakeholders

- Identify and resolve any licensing, inspection, or regulatory challenges or gaps that could impact the schedule for completion of Vogtle Units 3 and 4.

2

Integrated Project Plan

- VRG directed the formation of an internal NRC working group to develop an Integrated Project Plan (IPP) scheduling tool

- The IPP lists the regulatory milestones for the transition of Vogtles construction to operations 3

Integrated Project Plan

- The tool will allow the working group to map the milestones inter-dependencies and ties to NRCs inspection schedule

- The VRG will use the IPP to track scheduled activities and identify potential critical path areas related to the completion of construction 4

Integrated Project Plan

- Innovative and technology driven

  • First of a kind at NRC
  • Uses Primavera software

- Enhances communication

  • Internal and external

- Reduces project risks

  • NRC internal processes are known
  • Increases stakeholder confidence 5

IPP, Vogtle U3 Status - 2018 Q3 Current NRC Fuel Load Status 10/14/2020 IMC 2503 IMC 2504 IMC 2514 Upcoming NRC Schedule Items

  • Continue to inspect construction activities
  • Finalize 103(g) sequence of events

Questions?