ML081270200: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(2 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML081270200
| number = ML081270200
| issue date = 04/28/2008
| issue date = 04/28/2008
| title = North Anna, Units 1 and 2, Annual Environment Operating Report for 2007
| title = Annual Environment Operating Report for 2007
| author name = Stoddard D G
| author name = Stoddard D
| author affiliation = Virginia Electric & Power Co (VEPCO)
| author affiliation = Virginia Electric & Power Co (VEPCO)
| addressee name =  
| addressee name =  
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGIN1A 23261 April 28, 2008 United States Nuclear Regulatory Commission Serial No. 08-0126 Attention:
{{#Wiki_filter:VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGIN1A   23261 April 28, 2008 United States Nuclear Regulatory Commission                       Serial No. 08-0126 Attention: Document Control Desk                                 NAPS/JHL Washington, D. C.'20555                                           Docket Nos. 50-338 50-339 License Nos., NPF-4 NPF-7 Gentlemen:
Document Control Desk NAPS/JHL Washington, D. C.'20555 Docket Nos. 50-338 50-339 License Nos., NPF-4 NPF-7 Gentlemen:
VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
NORTH ANNA POWER STATION UNITS 1 AND 2 ANNUAL ENVIRONMENT OPERATING REPORT Enclosed is the Annual Environmental Operating Report for North Anna Power Station Units 1 and 2 for 2007, pursuant to Section 5.4.1 of the Technical Specifications, Appendix B -Environmental Protection Plan.If you have any questions or require additional information, please contact Page Kemp at (540) 894-2295.Very truly yours, Daniel G. Stoddard Site Vice President Enclosure cc: U. S. Nuclear Regulatory Commission Region II Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303 NRC Senior Resident Inspector North Anna Power Station  
NORTH ANNA POWER STATION UNITS 1 AND 2 ANNUAL ENVIRONMENT OPERATING REPORT Enclosed is the Annual Environmental Operating Report for North Anna Power Station Units 1 and 2 for 2007, pursuant to Section 5.4.1 of the Technical Specifications, Appendix B - Environmental Protection Plan.
,ý,- J I ý'VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
If you have any questions or require additional information, please contact Page Kemp at (540) 894-2295.
NORTH ANNA POWER STATION UNITS 1 AND 2 APPENDIX B ENVIRONMENTAL PROTECTION PLAN 2007 ANNUAL REPORT DOCKET NOS. 50-338 AND 50-339 INTRODUCTION This 2007, Environmental Operating Report for the North Anna Power Station is submitted by Virginia Electric and Power Company, as requiried under Section 5.4.1 of Appendix B, Environmental Protection Plan (EPP).The objective of the EPP is to verify that the North Anna Power Station is operated in an environmentally acceptable manner, consistent with NRC and other federal, state and local requirements as well as to keep the NRC informed of any environmental effects of facility construction or operation.
Very truly yours, Daniel G. Stoddard Site Vice President Enclosure cc:     U. S. Nuclear Regulatory Commission Region II Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303 NRC Senior Resident Inspector North Anna Power Station
During 2007, no significant adverse environmental impact occurred as a result of the operation of North Anna Power Station, Units 1 and 2. Aquatic issues are addressed in the licensee's VPDES permit (number VA 0052451) issued by the Virginia State Water Control Board. The VPDES permitting program is administered by the Department of Environmental Quality and the NRC relies on this agency for regulation of matters involving water quality and aquatic biota.Listed below are the summaries and analyses required by Subsection 4.2 of the EPP.PLANT DESIGN AND OPERATION (SECTION 3.1)A review of all changes in station design or operation, tests and experiments failed to reveal any potentially, significant, unreviewed, environmental issues.EROSION CONTROL INSPECTION  
 
-SITE (SECTION 4.2.2.1)Performance of Periodic Test Procedure, 1-PT-9.3, Erosion Control Inspection-Station Site, by the Civil/Design Engineering Department identified five (5) areas of concern that needed corrective action. One area involved minor soil erosion which was subsequently corrected with the addition of a silt fence and re-seeding.
,ý,- J I
One area involved an animal trail, which. was filled-in.
      ý'
Another area involved a clogged culvert, which was subsequently unclogged.
VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
The two final areas involved eroded areas which were filled in with either gravel or concrete.
NORTH ANNA POWER STATION UNITS 1 AND 2 APPENDIX B ENVIRONMENTAL PROTECTION PLAN 2007 ANNUAL REPORT DOCKET NOS. 50-338 AND 50-339
All corrective actions have been completed and none of the areas of concern impacted station safety or operability.
 
EROSION AND SEDIMENT CONTROL PROGRAM -CORRIDOR RIGHTS-OF-WAY (SECTION 4.2.2.2)During 2007, all transmission line rights-of-way were patrolled to coordinate brush and tree work needed for maintenance of the lines. This work involved the following:
INTRODUCTION This 2007, Environmental Operating Report for the North Anna Power Station is submitted by Virginia Electric and Power Company, as requiried under Section 5.4.1 of Appendix B, Environmental Protection Plan (EPP).
* North Anna-to-Gordonsville corridor:
The objective of the EPP is to verify that the North Anna Power Station is operated in an environmentally acceptable manner, consistent with NRC and other federal, state and local requirements as well as to keep the NRC informed of any environmental effects of facility construction or operation.
The patrol revealed that there was no significant tree or brush work needed, and no significant erosion was observed.* North Anna-to-Morrisville corridor:
During 2007, no significant adverse environmental impact occurred as a result of the operation of North Anna Power Station, Units 1 and 2. Aquatic issues are addressed in the licensee's VPDES permit (number VA 0052451) issued by the Virginia State Water Control Board. The VPDES permitting program is administered by the Department of Environmental Quality and the NRC relies on this agency for regulation of matters involving water quality and aquatic biota.
A contract crew performed all brush and tree work for reliability as needed. A follow-up inspection was done as the work progressed.
Listed below are the summaries and analyses required by Subsection 4.2 of the EPP.
No significant erosion and sedimentation issues were observed.* North Anna to Ladysmith corridor:
PLANT DESIGN AND OPERATION (SECTION 3.1)
The patrol revealed that there was no significant tree or brush work needed, and no significant erosion was observed." North Anna to Midlothian corridor:
A review of all changes in station design or operation, tests and experiments failed to reveal any potentially, significant, unreviewed, environmental issues.
A contract crew performed all brush and tree work for reliability as needed. A follow-up inspection was done as the work progressed.
EROSION CONTROL INSPECTION - SITE (SECTION 4.2.2.1)
No significant erosion and sedimentation issues were observed.During all of the above-noted patrols and follow-up observations, no abnormal erosion conditions were observed on any of the above corridors associated with transmission line construction, modification, maintenance activities or the use of herbicides during 2007.NON-COMPLIANCE (SECTION 5.4.1)There were no non-compliances with the Environmental Protection Plan during 2007.NON-ROUTINE REPORTS (SECTION 5.4.2)On August 10, 2007, a permit exceedance letter was submitted to the Virginia Department of Environmental Quality (DEQ) due to exceeding the upper VPDES permit limits for Total Suspended Solids (TSS), pH and Oil and Grease for Outfall 013, on August 6, 2007. This was a result from an unusual discharge using the high capacity sump pumps for turbine building basement sump #2, while the oil/water separator was out of service for repair. Due to the proximity of the outfall to the circulating water intake structure, no adverse environmental impact to Lake Anna occurred.
Performance of Periodic Test Procedure, 1-PT-9.3, Erosion Control Inspection-Station Site, by the Civil/Design Engineering Department identified five (5) areas of concern that needed corrective action. One area involved minor soil erosion which was subsequently corrected with the addition of a silt fence and re-seeding. One area involved an animal trail, which. was filled-in. Another area involved a clogged culvert, which was subsequently unclogged. The two final areas involved eroded areas which were filled in with either gravel or concrete. All corrective actions have been completed and none of the areas of concern impacted station safety or operability.
A Letter of Warning was issued by the DEQ on October 3, 2007, however, the station did not receive a Notice of Violation.
EROSION AND SEDIMENT CONTROL PROGRAM                   - CORRIDOR RIGHTS-OF-WAY (SECTION 4.2.2.2)
The oil/ water separator was promptly repaired and placed back in service. No further discharges have occurred at Outfall 013. The new revision of the VPDES permit was issued to the station on October 29, 2007. The new permit allows sample data from the normal low capacity turbine building sump outfall (Outfall 104) which includes'the oil/water separator discharge, to represent emergency discharges to Outfall 013, when the high capacity sump pumps have to be used. This allows us to obtain a more representative sample of the sump wastewater stream, from a continuously flowing outfall, then what could be obtained from an outfall that is normally not flowing, except during an emergency high capacity sump pump discharge.}}
During 2007, all transmission line rights-of-way were patrolled to coordinate brush and tree work needed for maintenance of the lines. This work involved the following:
* North Anna-to-Gordonsville corridor: The patrol revealed that there was no significant tree or brush work needed, and no significant erosion was observed.
* North Anna-to-Morrisville corridor: A contract crew performed all brush and tree work for reliability as needed. A follow-up inspection was done as the work progressed.
No significant erosion and sedimentation issues were observed.
* North Anna to Ladysmith corridor: The patrol revealed that there was no significant tree or brush work needed, and no significant erosion was observed.
"   North Anna to Midlothian corridor: A contract crew performed all brush and tree work for reliability as needed. A follow-up inspection was done as the work progressed.
No significant erosion and sedimentation issues were observed.
During all of the above-noted patrols and follow-up observations, no abnormal erosion conditions were observed on any of the above corridors associated with transmission line construction, modification, maintenance activities or the use of herbicides during 2007.
NON-COMPLIANCE (SECTION 5.4.1)
There were no non-compliances with the Environmental Protection Plan during 2007.
NON-ROUTINE REPORTS (SECTION 5.4.2)
On August 10, 2007, a permit exceedance letter was submitted to the Virginia Department of Environmental Quality (DEQ) due to exceeding the upper VPDES permit limits for Total Suspended Solids (TSS), pH and Oil and Grease for Outfall 013, on August 6, 2007. This was a result from an unusual discharge using the high capacity sump pumps for turbine building basement sump #2, while the oil/water separator was out of service for repair. Due to the proximity of the outfall to the circulating water intake structure, no adverse environmental impact to Lake Anna occurred. A Letter of Warning was issued by the DEQ on October 3, 2007, however, the station did not receive a Notice of Violation. The oil/ water separator was promptly repaired and placed back in service. No further discharges have occurred at Outfall 013. The new revision of the VPDES permit was issued to the station on October 29, 2007. The new permit allows sample data from the normal low capacity turbine building sump outfall (Outfall 104) which includes'the oil/water separator discharge, to represent emergency discharges to Outfall 013, when the high capacity sump pumps have to be used. This allows us to obtain a more representative sample of the sump wastewater stream, from a continuously flowing outfall, then what could be obtained from an outfall that is normally not flowing, except during an emergency high capacity sump pump discharge.}}

Latest revision as of 17:08, 14 November 2019

Annual Environment Operating Report for 2007
ML081270200
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 04/28/2008
From: Stoddard D
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
08-0126
Download: ML081270200 (4)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGIN1A 23261 April 28, 2008 United States Nuclear Regulatory Commission Serial No. 08-0126 Attention: Document Control Desk NAPS/JHL Washington, D. C.'20555 Docket Nos. 50-338 50-339 License Nos., NPF-4 NPF-7 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)

NORTH ANNA POWER STATION UNITS 1 AND 2 ANNUAL ENVIRONMENT OPERATING REPORT Enclosed is the Annual Environmental Operating Report for North Anna Power Station Units 1 and 2 for 2007, pursuant to Section 5.4.1 of the Technical Specifications, Appendix B - Environmental Protection Plan.

If you have any questions or require additional information, please contact Page Kemp at (540) 894-2295.

Very truly yours, Daniel G. Stoddard Site Vice President Enclosure cc: U. S. Nuclear Regulatory Commission Region II Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303 NRC Senior Resident Inspector North Anna Power Station

,ý,- J I

ý'

VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)

NORTH ANNA POWER STATION UNITS 1 AND 2 APPENDIX B ENVIRONMENTAL PROTECTION PLAN 2007 ANNUAL REPORT DOCKET NOS. 50-338 AND 50-339

INTRODUCTION This 2007, Environmental Operating Report for the North Anna Power Station is submitted by Virginia Electric and Power Company, as requiried under Section 5.4.1 of Appendix B, Environmental Protection Plan (EPP).

The objective of the EPP is to verify that the North Anna Power Station is operated in an environmentally acceptable manner, consistent with NRC and other federal, state and local requirements as well as to keep the NRC informed of any environmental effects of facility construction or operation.

During 2007, no significant adverse environmental impact occurred as a result of the operation of North Anna Power Station, Units 1 and 2. Aquatic issues are addressed in the licensee's VPDES permit (number VA 0052451) issued by the Virginia State Water Control Board. The VPDES permitting program is administered by the Department of Environmental Quality and the NRC relies on this agency for regulation of matters involving water quality and aquatic biota.

Listed below are the summaries and analyses required by Subsection 4.2 of the EPP.

PLANT DESIGN AND OPERATION (SECTION 3.1)

A review of all changes in station design or operation, tests and experiments failed to reveal any potentially, significant, unreviewed, environmental issues.

EROSION CONTROL INSPECTION - SITE (SECTION 4.2.2.1)

Performance of Periodic Test Procedure, 1-PT-9.3, Erosion Control Inspection-Station Site, by the Civil/Design Engineering Department identified five (5) areas of concern that needed corrective action. One area involved minor soil erosion which was subsequently corrected with the addition of a silt fence and re-seeding. One area involved an animal trail, which. was filled-in. Another area involved a clogged culvert, which was subsequently unclogged. The two final areas involved eroded areas which were filled in with either gravel or concrete. All corrective actions have been completed and none of the areas of concern impacted station safety or operability.

EROSION AND SEDIMENT CONTROL PROGRAM - CORRIDOR RIGHTS-OF-WAY (SECTION 4.2.2.2)

During 2007, all transmission line rights-of-way were patrolled to coordinate brush and tree work needed for maintenance of the lines. This work involved the following:

  • North Anna-to-Gordonsville corridor: The patrol revealed that there was no significant tree or brush work needed, and no significant erosion was observed.
  • North Anna-to-Morrisville corridor: A contract crew performed all brush and tree work for reliability as needed. A follow-up inspection was done as the work progressed.

No significant erosion and sedimentation issues were observed.

  • North Anna to Ladysmith corridor: The patrol revealed that there was no significant tree or brush work needed, and no significant erosion was observed.

" North Anna to Midlothian corridor: A contract crew performed all brush and tree work for reliability as needed. A follow-up inspection was done as the work progressed.

No significant erosion and sedimentation issues were observed.

During all of the above-noted patrols and follow-up observations, no abnormal erosion conditions were observed on any of the above corridors associated with transmission line construction, modification, maintenance activities or the use of herbicides during 2007.

NON-COMPLIANCE (SECTION 5.4.1)

There were no non-compliances with the Environmental Protection Plan during 2007.

NON-ROUTINE REPORTS (SECTION 5.4.2)

On August 10, 2007, a permit exceedance letter was submitted to the Virginia Department of Environmental Quality (DEQ) due to exceeding the upper VPDES permit limits for Total Suspended Solids (TSS), pH and Oil and Grease for Outfall 013, on August 6, 2007. This was a result from an unusual discharge using the high capacity sump pumps for turbine building basement sump #2, while the oil/water separator was out of service for repair. Due to the proximity of the outfall to the circulating water intake structure, no adverse environmental impact to Lake Anna occurred. A Letter of Warning was issued by the DEQ on October 3, 2007, however, the station did not receive a Notice of Violation. The oil/ water separator was promptly repaired and placed back in service. No further discharges have occurred at Outfall 013. The new revision of the VPDES permit was issued to the station on October 29, 2007. The new permit allows sample data from the normal low capacity turbine building sump outfall (Outfall 104) which includes'the oil/water separator discharge, to represent emergency discharges to Outfall 013, when the high capacity sump pumps have to be used. This allows us to obtain a more representative sample of the sump wastewater stream, from a continuously flowing outfall, then what could be obtained from an outfall that is normally not flowing, except during an emergency high capacity sump pump discharge.