Flood Hazard Reevaluation Report in Response to March 12, 2012 Information Request Regarding Flooding Aspects of Recommendation 2.1
ML13074A925
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 03/11/2013
From: Grecheck E
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML13318A090 List:
References
13-121
Download: ML13074A925 (2)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 March 11, 2013 U.S. Nuclear Regulatory Commission Serial No.13-121 Attention: Document Control Desk NL&OS/WDC RO Washington, DC 20555 Docket Nos. 50-338/339 License Nos. NPF-4/7 VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 AND 2 FLOOD HAZARD REEVALUTION REPORT IN RESPONSE TO MARCH 12, 2012 INFORMATION REQUEST REGARDING FLOODING ASPECTS OF RECOMMENDATION 2.1 On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued, "Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident," to all power reactor licensees and holders of construction permits in active or deferred status. Flooding Recommendation 2.1 requires licensees to perform a flood hazard reevaluation and provide a final report documenting the results, as well as pertinent site information and detailed analysis.

For Flooding Recommendation 2.1, Enclosure 2 of the letter states that in accordance with the NRC's prioritization plan, within 1-3 years from the date of the information request, submit the Hazard Reevaluation Report and include the interim action plan. In a letter dated May 11, 2012, the NRC issued their prioritization plan. The response date for North Anna Power Station (NAPS) Units 1 and 2 flood hazard reevaluation was identified as March 12, 2013, which corresponds to one year from the date of the March 12, 2012 Information Request. provides the NAPS Flooding Hazard Reevaluation Report. Attachment 2 provides the NAPS Initial Assessment of the Flooding Hazard Reevaluation Results and Interim Actions Plan.

If you have any questions regarding this information, please contact Mr. Thomas Shaub at (804) 273-2763.

Sincerely, Eugene S. Grecheck VICKI L.HULL Vice President Virina - Nuclear Engineering and Development PoerComan Eecrican - Notary Public Commonwealth of Virglinia COMMONWEALTH OF VIRGINIOA.,'",".O' COMMNWEATH O VIRINI V 140542 Commission Expires May 31. 2014 COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by Eugene S. Grecheck, who is Vice President -

Nuclear Engineering and Development of Virginia Electric and Power Company. He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of that company, and that the statements in the document are true to the best of his knowledge and belief.

(l" Acknowledged before me this day of ___ 2013.

My Commission Expires: A

- v ot~ry P~ublic

Serial No.13-121 Docket Nos. 50-338/339 Page 2 of 2 Commitments made in this letter: No new regulatory commitments Attachments:

1. Flooding Hazard Reevaluation Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.1: Flooding
2. North Anna NTTF 2.1: Flooding Hazard Reevaluation Initial Assessment of Flooding Hazard Reevaluation Results and Interim Actions Plan cc: U.S. Nuclear Regulatory Commission, Region II Regional Administrator Marquis One Tower 245 Peachtree Center Ave. NE Suite 1200 Atlanta, Georgia 30303-1257 Dr. V. Sreenivas Project Manager U.S. Nuclear Regulatory Commission One White Flint North, Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 K. R. Cotton Project Manager U.S. Nuclear Regulatory Commission One White Flint North, Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector North Anna Power Station J. E. Reasor, Jr.

Old Dominion Electric Cooperative Innsbrook Corporate Center, Suite 300 4201 Dominion Blvd.

Glen Allen, Virginia 23060