ML11251A212: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(3 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML11251A212
| number = ML11251A212
| issue date = 09/08/2011
| issue date = 09/08/2011
| title = Palo Verde Nuclear Generating Station - Notification of Inspection (NRC Inspection Report 05000528-11-005, 05000529-11-005, and 05000530-11-005) and Request for Information
| title = Notification of Inspection (NRC Inspection Report 05000528-11-005, 05000529-11-005, and 05000530-11-005) and Request for Information
| author name = Farnholtz T R
| author name = Farnholtz T
| author affiliation = NRC/RGN-IV/DRS/EB-1
| author affiliation = NRC/RGN-IV/DRS/EB-1
| addressee name = Edington R K
| addressee name = Edington R
| addressee affiliation = Arizona Public Service Co
| addressee affiliation = Arizona Public Service Co
| docket = 05000528, 05000529, 05000530
| docket = 05000528, 05000529, 05000530
Line 14: Line 14:
| page count = 6
| page count = 6
}}
}}
See also: [[followed by::IR 05000528/2011005]]
See also: [[see also::IR 05000528/2011005]]


=Text=
=Text=
{{#Wiki_filter: September 8, 2011  
{{#Wiki_filter:UNITED STATES
Randall K. Edington, Executive  Vice President, Nuclear/CNO Arizona Public Service Company P.O. Box 52034, Mail Stop 7602 Phoenix, AZ 85072-2034  
                                  NU CLE AR RE G ULAT O RY CO M M I S S I O N
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION - NOTIFICATION OF INSPECTION (NRC INSPECTION REPORT 05000528/2011005, 05000529/2011005, AND 05000530/2011005) AND REQUEST FOR INFORMATION Dear Mr. Edington: The purpose of this letter is to notify you that on December 5, 2011, the U.S. Nuclear Regulatory Commission (NRC), Region IV staff will begin the onsite portion of the Gas  
                                                      R E GI ON I V
Accumulation Management in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Temporary Instruction at your Palo Verde Nuclear Generating Station. This inspection will be performed in accordance with NRC Temporary Instruction (TI) 2515/177. Experience has shown that this inspection is resource intensive both for the NRC inspectors and your staff. In order to minimize the impact to your onsite resources and to ensure a  
                                          612 EAST LAMAR BLVD , SU ITE 400
productive inspection, we have enclosed a request for documents needed for this inspection.   The documents have been divided into two groups. * The first group lists information necessary for our initial inspection scoping and in-office preparation activities. This information should be separated by information request number,  
                                            AR LIN GTON , TEXAS 76011-4125
especially if provided electronically (e.g., folder with the information request number). This information should be available to the inspector no later than November 21, 2011. Upon review of these documents, the inspectors will select additional documentation for review upon arrival. By December 1, 2011, the inspector will communicate the initial selected samples.   * The second group of documents requested is needed to support our onsite inspection activities. This set of documents should be available to the inspector on December 5, 2011. It is also requested that corrective action documents and responses to questions developed during the inspection be provided to the inspector as the documents are generated.   We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Del Elkinton of your licensing organization. If there are any questions about this inspection or the material requested, please contact either Abin Fairbanks, at (817) 860-8158 or by email at Abin.Fairbanks@nrc.gov, or Dustin Reinert, at (817) 860-8244 or by email at Dustin.Reinert@nrc.gov. UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 EAST LAMAR BLVD, SUITE 400ARLINGTON, TEXAS 76011-4125
                                          September 8, 2011
Arizona Public Service Company - 2 -  This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011.  The NRC may not conduct or sponsor, and a person is not required to respond to,
Randall K. Edington, Executive
a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.  In accordance with Code of Federal Regulations, Title 10, Part 2.390 of the NRC's Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).        Sincerely,        /RA/
   Vice President, Nuclear/CNO
      Thomas R. Farnholtz, Chief Engineering Branch 1      Division of Reactor Safety 
Arizona Public Service Company
Docket Nos.: 50-528, 50-529, 50-530 Licenses: NPF-41, NPF-51, NPF-74  Enclosure: INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION TEMPORARY INSPECTION DOCUMENT
P.O. Box 52034, Mail Stop 7602
REQUEST  CC:  Distribution via ListServ for Palo Verde   
Phoenix, AZ 85072-2034
SUBJECT:         PALO VERDE NUCLEAR GENERATING STATION - NOTIFICATION OF
 
                  INSPECTION (NRC INSPECTION REPORT 05000528/2011005,
Arizona Public Service Company - 3 -     
                  05000529/2011005, AND 05000530/2011005) AND REQUEST FOR
R\Reactors\PV\2011\Palo Verde TI-177 RFI.docx                                                  ML11251A212 ADAMS:    No      Yes  SUNSI Review Complete  Reviewer Initials:      Publicly Available  Non-Sensitive    Non-publicly Available  Sensitive DRS/RI DRS/RI DRS/Branch Chief  AFairbanks DReinert TFarnholtz  /RA/ /RA/ /RA/  09/07/2011 09/08/2011 09/08/2011  OFFICIAL RECORD COPY                                        T=Telephone          E=E-mail        F=Fax   
                  INFORMATION
INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION TEMPORARY INSPECTION DOCUMENT REQUEST  - 1 - Enclosure  Inspection Report:  05000528/2011005, 05000529/2011005, AND 05000530/2011005 Inspection Dates:  December 5 - 9, 2011 Inspection Procedure: TI 2515/177, "Management of Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems" Inspectors:  Abin Fairbanks  Dustin Reinert Reactor Inspector  Reactor Inspector      (817) 860-8158  (817) 860-8244      Abin.Fairbanks@nrc.gov  Dustin.Reinert@nrc.gov  I. Information Requested by November 21, 2011  The following information should be sent to the Region IV office in hard copy or electronic format (ims.certrec.com or compact disc, preferred), in care of Abin Fairbanks, or Dustin
Dear Mr. Edington:
Reinert, to facilitate the selection of specific items that will be reviewed during the onsite inspection week.  The inspectors will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection weeks.  Also, we request that you categorize the documents in your response with the numbered list below.  Please provide requested documentation electronically if possible.  If
The purpose of this letter is to notify you that on December 5, 2011, the U.S. Nuclear
requested documents are large and only hard copy formats are available, please inform the inspectors, and provide subject documentation during the first day of the onsite inspection.  If you have any questions regarding this information request, please call the inspectors as soon as possible. 
Regulatory Commission (NRC), Region IV staff will begin the onsite portion of the Gas
1. List of corrective action program documents (with a short description) associated with GL 2008-01, voids in piping, and pressure transients for the previous three years.  2. List of changes (with a short description and tracking number) to the final safety analysis report (FSAR), technical specifications, technical specification bases, and technical requirements manual associated with the resolution of GL 2008-01.  3. List of calculations associated with GL 2008-01, including calculations that have been changed or created in response to GL 2008-01 (with a short description of the calculation and the change).  4. List (with a short description) of gas intrusion mechanisms that apply to the plant and the affected system locations (e.g., identify the source, conditions, and expected void locations).  Also, include a short description of how each gas intrusion mechanism has been addressed (e.g., plant hardware modification, procedure change). 
Accumulation Management in Emergency Core Cooling, Decay Heat Removal, and
INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION TEMPORARY INSPECTION DOCUMENT REQUEST  - 2 - Enclosure 5. List of the suction piping sections identified as susceptible to gas accumulation (the list should identify the corresponding system).  6. List of the discharge piping sections identified as susceptible to gas accumulation (the list should identify the corresponding system).  7. Copies of isometric drawings of the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System (hard-copies are preferred).  8. Copies of piping and instrumentation diagrams (P&IDs) of the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System (hard-copies are preferred).  Please highlight any components that were part of hardware modifications installed as part of the resolution of GL 2008-01 and all high point vents that are monitored during void surveillances.  9. Copies of program documents and procedures developed to implement the resolution of GL 2008-01.  10. List of actions that were completed in response to GL 2008-01.  11. Copies of the modification packages for hardware modifications as part of the resolution of GL 2008-01.  12. Design basis documents of the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System.  13. Design basis documents of keep-full systems of the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System.  14. System walkdown reports associated with the resolution of GL 2008-01.  15. If applicable, provide a list of inaccessible locations where plant walkdowns of the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System have not been completed.  Include an explanation of why each area is considered inaccessible.  16. Copies of surveillance procedures associated with the resolution of GL 2008-01 (i.e., procedures used for detecting and determining void volumes) and the results of the last two surveillances for the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System.  17. Copies of procedures used for filling and venting.  18. Copies of trends of periodic venting results.  19. Copies of the engineering evaluations performed for all identified voids.   
Containment Spray Systems Temporary Instruction at your Palo Verde Nuclear Generating
INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION TEMPORARY INSPECTION DOCUMENT REQUEST  - 3 - Enclosure  20. Basis for the void acceptance criteria (e.g., calculation).  If applicable, provide the justification for any deviation from the void acceptance criteria established by the Office
Station. This inspection will be performed in accordance with NRC Temporary Instruction (TI)
of Nuclear Reactor Regulation (NRR).  21. Copies of the methodologies used for predicting void behavior and impact on system operability.    22. Copies of any void transport analyses.  23. Copies of vortexing calculations associated with systems under the scope of GL 2008-01.  24. Copies of self-assessments associated with the implementation of the GL 2008-01 program.  25. Copies of any training materials for gas-related concerns.    26. Copies of training modules and attendance records that ensure personnel are aware of gas-related concerns.  II.  Information Requested by December 5, 2011  27. Copies of the selected corrective action program documents. 
2515/177.
28. Copies of the selected licensing and design basis document changes.  29. Copies of the selected calculations.  30. Copies of corrective action program implementing procedures.  31. Electronic copies of the current technical specifications, technical specification bases, updated final safety analysis report, and technical requirements manual.  Inspector Contact Information:
Experience has shown that this inspection is resource intensive both for the NRC inspectors
Abin Fairbanks  Dustin Reinert Reactor Inspector  Reactor Inspector (817) 860-8158  (817) 860-8244 Abin.Fairbanks@nrc.gov  Dustin.Reinert@nrc.gov  Mailing Address:  Mailing Address:
and your staff. In order to minimize the impact to your onsite resources and to ensure a
U.S. NRC Region IV  U.S. NRC Region IV Attn:  Abin Fairbanks  Attn:  Dustin Reinert 612 E. Lamar Blvd., Suite 400 612 E. Lamar Blvd., Suite 400 Arlington, TX  76011-4125  Arlington, TX  76011-4125 
productive inspection, we have enclosed a request for documents needed for this inspection.
The documents have been divided into two groups.
* The first group lists information necessary for our initial inspection scoping and in-office
    preparation activities. This information should be separated by information request number,
    especially if provided electronically (e.g., folder with the information request number). This
    information should be available to the inspector no later than November 21, 2011. Upon
    review of these documents, the inspectors will select additional documentation for review
    upon arrival. By December 1, 2011, the inspector will communicate the initial selected
    samples.
* The second group of documents requested is needed to support our onsite inspection
    activities. This set of documents should be available to the inspector on December 5, 2011.
    It is also requested that corrective action documents and responses to questions developed
    during the inspection be provided to the inspector as the documents are generated.
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Del Elkinton of your licensing organization.
If there are any questions about this inspection or the material requested, please contact either
Abin Fairbanks, at (817) 860-8158 or by email at Abin.Fairbanks@nrc.gov, or Dustin Reinert, at
(817) 860-8244 or by email at Dustin.Reinert@nrc.gov.


Arizona Public Service Company                  -2-
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, control number
3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,
a request for information or an information collection requirement unless the requesting
document displays a currently valid Office of Management and Budget control number.
In accordance with Code of Federal Regulations, Title 10, Part 2.390 of the NRC's Rules of
Practice, a copy of this letter and its enclosure will be available electronically for public
inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)
component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web
site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
                                              Sincerely,
                                              /RA/
                                              Thomas R. Farnholtz, Chief
                                              Engineering Branch 1
                                              Division of Reactor Safety
Docket Nos.: 50-528, 50-529, 50-530
Licenses: NPF-41, NPF-51, NPF-74
Enclosure:            INFORMATION REQUEST FOR PALO VERDE NUCLEAR
                        GENERATING STATION TEMPORARY INSPECTION DOCUMENT
                        REQUEST
CC: Distribution via ListServ for Palo Verde
Arizona Public Service Company              -3-
R\Reactors\PV\2011\Palo Verde TI-177 RFI.docx                                ML11251A212
ADAMS:      No    7 Yes    7 SUNSI Review Complete          Reviewer Initials:
                              7 Publicly Available            7 Non-Sensitive
                                Non-publicly Available          Sensitive
DRS/RI                DRS/RI                DRS/Branch Chief
AFairbanks            DReinert              TFarnholtz
/RA/                  /RA/                  /RA/
09/07/2011            09/08/2011            09/08/2011
OFFICIAL RECORD COPY                                T=Telephone      E=E-mail    F=Fax
        INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION
                          TEMPORARY INSPECTION DOCUMENT REQUEST
  Inspection Report:              05000528/2011005, 05000529/2011005, AND 05000530/2011005
  Inspection Dates:                December 5 - 9, 2011
  Inspection Procedure:            TI 2515/177, Management of Gas Accumulation in Emergency
                                    Core Cooling, Decay Heat Removal, and Containment Spray
                                    Systems
  Inspectors:                      Abin Fairbanks                          Dustin Reinert
                                    Reactor Inspector                      Reactor Inspector
                                    (817) 860-8158                          (817) 860-8244
                                    Abin.Fairbanks@nrc.gov                  Dustin.Reinert@nrc.gov
I. Information Requested by November 21, 2011
  The following information should be sent to the Region IV office in hard copy or electronic
  format (ims.certrec.com or compact disc, preferred), in care of Abin Fairbanks, or Dustin
  Reinert, to facilitate the selection of specific items that will be reviewed during the onsite
  inspection week. The inspectors will select specific items from the information requested below
  and then request from your staff additional documents needed during the onsite inspection
  weeks. Also, we request that you categorize the documents in your response with the
  numbered list below. Please provide requested documentation electronically if possible. If
  requested documents are large and only hard copy formats are available, please inform the
  inspectors, and provide subject documentation during the first day of the onsite inspection. If
  you have any questions regarding this information request, please call the inspectors as soon
  as possible.
  1.      List of corrective action program documents (with a short description) associated with
            GL 2008-01, voids in piping, and pressure transients for the previous three years.
  2.      List of changes (with a short description and tracking number) to the final safety
            analysis report (FSAR), technical specifications, technical specification bases, and
            technical requirements manual associated with the resolution of GL 2008-01.
  3.      List of calculations associated with GL 2008-01, including calculations that have been
            changed or created in response to GL 2008-01 (with a short description of the
            calculation and the change).
  4.      List (with a short description) of gas intrusion mechanisms that apply to the plant and
            the affected system locations (e.g., identify the source, conditions, and expected void
            locations). Also, include a short description of how each gas intrusion mechanism has
            been addressed (e.g., plant hardware modification, procedure change).
                                                  -1-                                        Enclosure
    INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION
                    TEMPORARY INSPECTION DOCUMENT REQUEST
5.    List of the suction piping sections identified as susceptible to gas accumulation (the list
      should identify the corresponding system).
6.    List of the discharge piping sections identified as susceptible to gas accumulation (the
      list should identify the corresponding system).
7.    Copies of isometric drawings of the Emergency Core Cooling System, Decay Heat
      Removal System, and Containment Spray System (hard-copies are preferred).
8.    Copies of piping and instrumentation diagrams (P&IDs) of the Emergency Core Cooling
      System, Decay Heat Removal System, and Containment Spray System (hard-copies
      are preferred). Please highlight any components that were part of hardware
      modifications installed as part of the resolution of GL 2008-01 and all high point vents
      that are monitored during void surveillances.
9.    Copies of program documents and procedures developed to implement the resolution
      of GL 2008-01.
10.    List of actions that were completed in response to GL 2008-01.
11.    Copies of the modification packages for hardware modifications as part of the resolution
      of GL 2008-01.
12.    Design basis documents of the Emergency Core Cooling System, Decay Heat Removal
      System, and Containment Spray System.
13.    Design basis documents of keep-full systems of the Emergency Core Cooling System,
      Decay Heat Removal System, and Containment Spray System.
14.    System walkdown reports associated with the resolution of GL 2008-01.
15.    If applicable, provide a list of inaccessible locations where plant walkdowns of the
      Emergency Core Cooling System, Decay Heat Removal System, and Containment
      Spray System have not been completed. Include an explanation of why each area is
      considered inaccessible.
16.    Copies of surveillance procedures associated with the resolution of GL 2008-01 (i.e.,
      procedures used for detecting and determining void volumes) and the results of the last
      two surveillances for the Emergency Core Cooling System, Decay Heat Removal
      System, and Containment Spray System.
17.    Copies of procedures used for filling and venting.
18.    Copies of trends of periodic venting results.
19.    Copies of the engineering evaluations performed for all identified voids.
                                            -2-                                      Enclosure
          INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION
                            TEMPORARY INSPECTION DOCUMENT REQUEST
    20.    Basis for the void acceptance criteria (e.g., calculation). If applicable, provide the
            justification for any deviation from the void acceptance criteria established by the Office
            of Nuclear Reactor Regulation (NRR).
    21.    Copies of the methodologies used for predicting void behavior and impact on system
            operability.
    22.    Copies of any void transport analyses.
    23.    Copies of vortexing calculations associated with systems under the scope of GL 2008-
            01.
    24.    Copies of self-assessments associated with the implementation of the GL 2008-01
            program.
    25.    Copies of any training materials for gas-related concerns.
    26.    Copies of training modules and attendance records that ensure personnel are aware of
            gas-related concerns.
II.  Information Requested by December 5, 2011
    27.    Copies of the selected corrective action program documents.
    28.    Copies of the selected licensing and design basis document changes.
    29.    Copies of the selected calculations.
    30.    Copies of corrective action program implementing procedures.
    31.    Electronic copies of the current technical specifications, technical specification bases,
            updated final safety analysis report, and technical requirements manual.
    Inspector Contact Information:
Abin Fairbanks                      Dustin Reinert
Reactor Inspector                    Reactor Inspector
(817) 860-8158                      (817) 860-8244
Abin.Fairbanks@nrc.gov              Dustin.Reinert@nrc.gov
Mailing Address:                    Mailing Address:
U.S. NRC Region IV                  U.S. NRC Region IV
Attn: Abin Fairbanks                Attn: Dustin Reinert
612 E. Lamar Blvd., Suite 400        612 E. Lamar Blvd., Suite 400
Arlington, TX 76011-4125            Arlington, TX 76011-4125
                                                  -3-                                          Enclosure
}}
}}

Latest revision as of 16:04, 12 November 2019

Notification of Inspection (NRC Inspection Report 05000528-11-005, 05000529-11-005, and 05000530-11-005) and Request for Information
ML11251A212
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 09/08/2011
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Edington R
Arizona Public Service Co
References
IR-11-005
Download: ML11251A212 (6)


See also: IR 05000528/2011005

Text

UNITED STATES

NU CLE AR RE G ULAT O RY CO M M I S S I O N

R E GI ON I V

612 EAST LAMAR BLVD , SU ITE 400

AR LIN GTON , TEXAS 76011-4125

September 8, 2011

Randall K. Edington, Executive

Vice President, Nuclear/CNO

Arizona Public Service Company

P.O. Box 52034, Mail Stop 7602

Phoenix, AZ 85072-2034

SUBJECT: PALO VERDE NUCLEAR GENERATING STATION - NOTIFICATION OF

INSPECTION (NRC INSPECTION REPORT 05000528/2011005,

05000529/2011005, AND 05000530/2011005) AND REQUEST FOR

INFORMATION

Dear Mr. Edington:

The purpose of this letter is to notify you that on December 5, 2011, the U.S. Nuclear

Regulatory Commission (NRC), Region IV staff will begin the onsite portion of the Gas

Accumulation Management in Emergency Core Cooling, Decay Heat Removal, and

Containment Spray Systems Temporary Instruction at your Palo Verde Nuclear Generating

Station. This inspection will be performed in accordance with NRC Temporary Instruction (TI)

2515/177.

Experience has shown that this inspection is resource intensive both for the NRC inspectors

and your staff. In order to minimize the impact to your onsite resources and to ensure a

productive inspection, we have enclosed a request for documents needed for this inspection.

The documents have been divided into two groups.

  • The first group lists information necessary for our initial inspection scoping and in-office

preparation activities. This information should be separated by information request number,

especially if provided electronically (e.g., folder with the information request number). This

information should be available to the inspector no later than November 21, 2011. Upon

review of these documents, the inspectors will select additional documentation for review

upon arrival. By December 1, 2011, the inspector will communicate the initial selected

samples.

  • The second group of documents requested is needed to support our onsite inspection

activities. This set of documents should be available to the inspector on December 5, 2011.

It is also requested that corrective action documents and responses to questions developed

during the inspection be provided to the inspector as the documents are generated.

We have discussed the schedule for these inspection activities with your staff and understand

that our regulatory contact for this inspection will be Del Elkinton of your licensing organization.

If there are any questions about this inspection or the material requested, please contact either

Abin Fairbanks, at (817) 860-8158 or by email at Abin.Fairbanks@nrc.gov, or Dustin Reinert, at

(817) 860-8244 or by email at Dustin.Reinert@nrc.gov.

Arizona Public Service Company -2-

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control number

3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,

a request for information or an information collection requirement unless the requesting

document displays a currently valid Office of Management and Budget control number.

In accordance with Code of Federal Regulations, Title 10, Part 2.390 of the NRC's Rules of

Practice, a copy of this letter and its enclosure will be available electronically for public

inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)

component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web

site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos.: 50-528, 50-529, 50-530

Licenses: NPF-41, NPF-51, NPF-74

Enclosure: INFORMATION REQUEST FOR PALO VERDE NUCLEAR

GENERATING STATION TEMPORARY INSPECTION DOCUMENT

REQUEST

CC: Distribution via ListServ for Palo Verde

Arizona Public Service Company -3-

R\Reactors\PV\2011\Palo Verde TI-177 RFI.docx ML11251A212

ADAMS: No 7 Yes 7 SUNSI Review Complete Reviewer Initials:

7 Publicly Available 7 Non-Sensitive

Non-publicly Available Sensitive

DRS/RI DRS/RI DRS/Branch Chief

AFairbanks DReinert TFarnholtz

/RA/ /RA/ /RA/

09/07/2011 09/08/2011 09/08/2011

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION

TEMPORARY INSPECTION DOCUMENT REQUEST

Inspection Report: 05000528/2011005, 05000529/2011005, AND 05000530/2011005

Inspection Dates: December 5 - 9, 2011

Inspection Procedure: TI 2515/177, Management of Gas Accumulation in Emergency

Core Cooling, Decay Heat Removal, and Containment Spray

Systems

Inspectors: Abin Fairbanks Dustin Reinert

Reactor Inspector Reactor Inspector

(817) 860-8158 (817) 860-8244

Abin.Fairbanks@nrc.gov Dustin.Reinert@nrc.gov

I. Information Requested by November 21, 2011

The following information should be sent to the Region IV office in hard copy or electronic

format (ims.certrec.com or compact disc, preferred), in care of Abin Fairbanks, or Dustin

Reinert, to facilitate the selection of specific items that will be reviewed during the onsite

inspection week. The inspectors will select specific items from the information requested below

and then request from your staff additional documents needed during the onsite inspection

weeks. Also, we request that you categorize the documents in your response with the

numbered list below. Please provide requested documentation electronically if possible. If

requested documents are large and only hard copy formats are available, please inform the

inspectors, and provide subject documentation during the first day of the onsite inspection. If

you have any questions regarding this information request, please call the inspectors as soon

as possible.

1. List of corrective action program documents (with a short description) associated with

GL 2008-01, voids in piping, and pressure transients for the previous three years.

2. List of changes (with a short description and tracking number) to the final safety

analysis report (FSAR), technical specifications, technical specification bases, and

technical requirements manual associated with the resolution of GL 2008-01.

3. List of calculations associated with GL 2008-01, including calculations that have been

changed or created in response to GL 2008-01 (with a short description of the

calculation and the change).

4. List (with a short description) of gas intrusion mechanisms that apply to the plant and

the affected system locations (e.g., identify the source, conditions, and expected void

locations). Also, include a short description of how each gas intrusion mechanism has

been addressed (e.g., plant hardware modification, procedure change).

-1- Enclosure

INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION

TEMPORARY INSPECTION DOCUMENT REQUEST

5. List of the suction piping sections identified as susceptible to gas accumulation (the list

should identify the corresponding system).

6. List of the discharge piping sections identified as susceptible to gas accumulation (the

list should identify the corresponding system).

7. Copies of isometric drawings of the Emergency Core Cooling System, Decay Heat

Removal System, and Containment Spray System (hard-copies are preferred).

8. Copies of piping and instrumentation diagrams (P&IDs) of the Emergency Core Cooling

System, Decay Heat Removal System, and Containment Spray System (hard-copies

are preferred). Please highlight any components that were part of hardware

modifications installed as part of the resolution of GL 2008-01 and all high point vents

that are monitored during void surveillances.

9. Copies of program documents and procedures developed to implement the resolution

of GL 2008-01.

10. List of actions that were completed in response to GL 2008-01.

11. Copies of the modification packages for hardware modifications as part of the resolution

of GL 2008-01.

12. Design basis documents of the Emergency Core Cooling System, Decay Heat Removal

System, and Containment Spray System.

13. Design basis documents of keep-full systems of the Emergency Core Cooling System,

Decay Heat Removal System, and Containment Spray System.

14. System walkdown reports associated with the resolution of GL 2008-01.

15. If applicable, provide a list of inaccessible locations where plant walkdowns of the

Emergency Core Cooling System, Decay Heat Removal System, and Containment

Spray System have not been completed. Include an explanation of why each area is

considered inaccessible.

16. Copies of surveillance procedures associated with the resolution of GL 2008-01 (i.e.,

procedures used for detecting and determining void volumes) and the results of the last

two surveillances for the Emergency Core Cooling System, Decay Heat Removal

System, and Containment Spray System.

17. Copies of procedures used for filling and venting.

18. Copies of trends of periodic venting results.

19. Copies of the engineering evaluations performed for all identified voids.

-2- Enclosure

INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION

TEMPORARY INSPECTION DOCUMENT REQUEST

20. Basis for the void acceptance criteria (e.g., calculation). If applicable, provide the

justification for any deviation from the void acceptance criteria established by the Office

of Nuclear Reactor Regulation (NRR).

21. Copies of the methodologies used for predicting void behavior and impact on system

operability.

22. Copies of any void transport analyses.

23. Copies of vortexing calculations associated with systems under the scope of GL 2008-

01.

24. Copies of self-assessments associated with the implementation of the GL 2008-01

program.

25. Copies of any training materials for gas-related concerns.

26. Copies of training modules and attendance records that ensure personnel are aware of

gas-related concerns.

II. Information Requested by December 5, 2011

27. Copies of the selected corrective action program documents.

28. Copies of the selected licensing and design basis document changes.

29. Copies of the selected calculations.

30. Copies of corrective action program implementing procedures.

31. Electronic copies of the current technical specifications, technical specification bases,

updated final safety analysis report, and technical requirements manual.

Inspector Contact Information:

Abin Fairbanks Dustin Reinert

Reactor Inspector Reactor Inspector

(817) 860-8158 (817) 860-8244

Abin.Fairbanks@nrc.gov Dustin.Reinert@nrc.gov

Mailing Address: Mailing Address:

U.S. NRC Region IV U.S. NRC Region IV

Attn: Abin Fairbanks Attn: Dustin Reinert

612 E. Lamar Blvd., Suite 400 612 E. Lamar Blvd., Suite 400

Arlington, TX 76011-4125 Arlington, TX 76011-4125

-3- Enclosure