| {{#Wiki_filter:ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Dresden Unit 2/3 Date of Examination: | | {{#Wiki_filter:ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Dresden Unit 2/3 Date of Examination: Aug 6-17, 2012 Developed by: Written - Facility NRC // Operating - Facility NRC Target Chief Date* Task Description (Reference) Examiners Initials 02/06/2012 1. Examination administration date confirmed (C.1.a; C.2.a and b) dwr 03/02/2012 2. NRC examiners and facility contact assigned (C.1.d; C.2.e) dwr 03/02/2012 3. Facility contact briefed on security and other requirements (C.2.c) dwr 03/02/2012 4. Corporate notification letter sent (C.2.d) Dwr 2/27/2012 N/A [5. Reference material due (C.1.e; C.3.c; Attachment 3)] N/A 04/06/2012 6. Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, dwr ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and 04/09/2012 ES-401-4, as applicable (C.1.e and f; C.3.d) 04/13/2012 {7. Examination outline(s) reviewed by NRC and feedback provided to facility dwr licensee (C.2.h; C.3.e)} 4/12/2012 06/15/2012 8. Proposed examinations (including written, walk-through JPMs, and dwr scenarios, as applicable), supporting documentation (including Forms 06/22/2012 ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d) 07/06/2012 9. Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; dwr ES-202) 7/09/2012 07/20/2012 10. Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; dwr ES-202) 7/23/2012 07/13/2012 11. Examination approved by NRC supervisor for facility licensee review dwr (C.2.h; C.3.f) 7/13/2012 07/20/2012 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) dwr 7/19/2012 07/27/2012 13. Written examinations and operating tests approved by NRC supervisor dwr (C.2.i; C.3.h) 7/27/2012 07/27/2012 14. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm dwr qualifications / eligibility; and examination approval and waiver letters sent 7/27/2012 (C.2.i; Attachment 5; ES-202, C.2.e; ES-204) 07/27/2012 15. Proctoring/written exam administration guidelines reviewed Dwr with facility licensee (C.3.k) 8/14//2012 07/27/2012 16. Approved scenarios, job performance measures, and questions Dwr distributed to NRC examiners (C.3.i) 7/27/2012 |
| Aug 6-17, 2012 Developed by: Written | | * Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee. |
| - Facility NRC // Operating | |
| - Facility NRC Target Date* Task Description (Reference) | |
| Chief Examiner's Initials 02/06/2012
| |
| : 1. Examination administration date confirmed (C.1.a; C.2.a and b) dwr 0 3/02/2012 2. NRC examiners and facility contact assigned (C.1.d; C.2.e) dwr 0 3/02/2012 3. Facility contact briefed on security and other requirements (C.2.c) dwr 0 3/02/2012 4. Corporate notification letter sent (C.2.d)
| |
| D wr 2/27/2012 N/A [5. Reference material due (C.1.e; C.3.c; Attachment 3)]
| |
| N/A 04/06/2012 6. Integrated examination outline(s) due, including Forms ES | |
| -201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and ES-401-4, as applicable (C.1.e and f; C.3.d) dwr 04/09/2012 04/13/2012 {7. Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e)} | |
| dwr 4/12/2012 06/15/2012 8. Proposed examinations (including written, walk
| |
| -through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d) dwr 06/22/2012 07/06/2012 | |
| : 9. Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g;
| |
| | |
| ES-202) dwr 7/09/2012 07/20/2012 | |
| : 10. Final license applications due and Form ES
| |
| -201-4 prepared (C.1.l; C.2.i; ES-202) dwr 7/23/2012 07/13/2012 11. Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f) dwr 7/13/2012 07/20/2012 | |
| : 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) dwr 7/19/2012 07/27/2012
| |
| : 13. Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h) dwr 7/27/2012 07/27/2012
| |
| : 14. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; Attachment 5; ES
| |
| -202, C.2.e; ES | |
| -204) dwr 7/27/2012 07/27/2012 | |
| : 15. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k)
| |
| D wr 8/14//2012 07/27/2012
| |
| : 16. Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i)
| |
| D wr 7/27/2012
| |
| * Target dates are generally based on facility | |
| -prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case | |
| -by-case basis in coordination with the facility licensee. | |
| [Applies only] {Does not apply} to examinations prepared by the NRC.}} | | [Applies only] {Does not apply} to examinations prepared by the NRC.}} |
|
---|
Category:License-Operator
MONTHYEARML24179A1752024-06-27027 June 2024 Form 5.1-1 Post Examination Check Sheet ML24179A1742024-06-11011 June 2024 Form 2.1-1 Examination Preparation Checklist ML24179A1732024-06-11011 June 2024 Form 1.3-1 - Exam Security Agreement ML24179A1722024-06-0707 June 2024 2024-301 Post Exam SVP Letter ML24120A2032024-04-29029 April 2024 Operator Licensing Exam Approval - Dresden Nuclear Power Station, May 2024 ML24179A2152024-04-25025 April 2024 Form 3.4-1 Events and Evolutions Checklist ML24179A2142024-04-25025 April 2024 Form 2.3-1 Examination Outline Quality Checklist ML24179A2242024-04-23023 April 2024 Form 2.3-2 - Operating Test Quality Checklist ML24179A2252024-04-22022 April 2024 Form 2.3-4 - Written Examination Quality Checklist ML24179A2232024-02-12012 February 2024 ILT 23-1 (2024-301) SVP Letter - 24-007 ILT Exam Submittal ML24179A2122023-11-0808 November 2023 ILT 23-1 (2024-301) Exam Outline Submittal SVP Letter 23-0036 ML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 ML22195A2342021-08-16016 August 2021 Nov 2021 Ile Operating Test Submittal Letter 08-16-2021 ML22195A2632021-06-26026 June 2021 Nov 2021 Ile Es 201-2 Outline Quality Checklist ML22195A2662021-06-26026 June 2021 Nov 2021 Ile Es 301-5 Transients and Events Checklist ML22195A2672021-06-0404 June 2021 Nov 2021 Ile Es 201-2 Outlines Submittal Email ML21139A2372021-05-21021 May 2021 Confirmation of Initial License Examination ML22215A2492021-05-14014 May 2021 April 2021 Form ES-401-6 ML22216A1902021-05-14014 May 2021 April 2021 Proposed Written Exam ML22236A3332021-05-14014 May 2021 Initial License Exam Forms ES-201-3 ML22236A3322021-05-14014 May 2021 Initial License Exam Form ES-403-1 ML22236A3302021-05-14014 May 2021 Initial License Exam Form ES-201-1 ML22236A3842021-05-14014 May 2021 Initial License Exam Letter 21-0029 ML22235A7572021-05-14014 May 2021 April 2021 Form ES-201-2 Written Outline Only ML22235A7562021-05-14014 May 2021 April 2021 Form ES-301-5 SVPLTR 21-0007, April 2021 Submittal Letter2021-05-14014 May 2021 April 2021 Submittal Letter 2024-06-07
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML24179A1752024-06-27027 June 2024 Form 5.1-1 Post Examination Check Sheet ML24179A1742024-06-11011 June 2024 Form 2.1-1 Examination Preparation Checklist ML24179A1732024-06-11011 June 2024 Form 1.3-1 - Exam Security Agreement ML24179A1722024-06-0707 June 2024 2024-301 Post Exam SVP Letter ML24120A2032024-04-29029 April 2024 Operator Licensing Exam Approval - Dresden Nuclear Power Station, May 2024 ML24179A2152024-04-25025 April 2024 Form 3.4-1 Events and Evolutions Checklist ML24179A2142024-04-25025 April 2024 Form 2.3-1 Examination Outline Quality Checklist ML24179A2242024-04-23023 April 2024 Form 2.3-2 - Operating Test Quality Checklist ML24179A2252024-04-22022 April 2024 Form 2.3-4 - Written Examination Quality Checklist ML24179A2232024-02-12012 February 2024 ILT 23-1 (2024-301) SVP Letter - 24-007 ILT Exam Submittal ML24179A2122023-11-0808 November 2023 ILT 23-1 (2024-301) Exam Outline Submittal SVP Letter 23-0036 ML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 ML22195A2342021-08-16016 August 2021 Nov 2021 Ile Operating Test Submittal Letter 08-16-2021 ML22195A2662021-06-26026 June 2021 Nov 2021 Ile Es 301-5 Transients and Events Checklist ML22195A2632021-06-26026 June 2021 Nov 2021 Ile Es 201-2 Outline Quality Checklist ML22195A2672021-06-0404 June 2021 Nov 2021 Ile Es 201-2 Outlines Submittal Email ML21139A2372021-05-21021 May 2021 Confirmation of Initial License Examination ML22236A6392021-05-14014 May 2021 April 2021 Initial License Exam Form ES-401-9 ML22215A1812021-05-14014 May 2021 April 2021 Administered JPMs ML22215A1852021-05-14014 May 2021 April 2021 Administered Scenarios ML22215A1862021-05-14014 May 2021 April 2021 Administered Written Exam ML22236A3332021-05-14014 May 2021 Initial License Exam Forms ES-201-3 ML22236A3322021-05-14014 May 2021 Initial License Exam Form ES-403-1 ML22236A3302021-05-14014 May 2021 Initial License Exam Form ES-201-1 ML22236A3842021-05-14014 May 2021 Initial License Exam Letter 21-0029 ML22235A7572021-05-14014 May 2021 April 2021 Form ES-201-2 Written Outline Only 2024-06-07
[Table view] |
Text
ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Dresden Unit 2/3 Date of Examination: Aug 6-17, 2012 Developed by: Written - Facility NRC // Operating - Facility NRC Target Chief Date* Task Description (Reference) Examiners Initials 02/06/2012 1. Examination administration date confirmed (C.1.a; C.2.a and b) dwr 03/02/2012 2. NRC examiners and facility contact assigned (C.1.d; C.2.e) dwr 03/02/2012 3. Facility contact briefed on security and other requirements (C.2.c) dwr 03/02/2012 4. Corporate notification letter sent (C.2.d) Dwr 2/27/2012 N/A [5. Reference material due (C.1.e; C.3.c; Attachment 3)] N/A 04/06/2012 6. Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, dwr ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and 04/09/2012 ES-401-4, as applicable (C.1.e and f; C.3.d) 04/13/2012 {7. Examination outline(s) reviewed by NRC and feedback provided to facility dwr licensee (C.2.h; C.3.e)} 4/12/2012 06/15/2012 8. Proposed examinations (including written, walk-through JPMs, and dwr scenarios, as applicable), supporting documentation (including Forms 06/22/2012 ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d) 07/06/2012 9. Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; dwr ES-202) 7/09/2012 07/20/2012 10. Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; dwr ES-202) 7/23/2012 07/13/2012 11. Examination approved by NRC supervisor for facility licensee review dwr (C.2.h; C.3.f) 7/13/2012 07/20/2012 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) dwr 7/19/2012 07/27/2012 13. Written examinations and operating tests approved by NRC supervisor dwr (C.2.i; C.3.h) 7/27/2012 07/27/2012 14. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm dwr qualifications / eligibility; and examination approval and waiver letters sent 7/27/2012 (C.2.i; Attachment 5; ES-202, C.2.e; ES-204) 07/27/2012 15. Proctoring/written exam administration guidelines reviewed Dwr with facility licensee (C.3.k) 8/14//2012 07/27/2012 16. Approved scenarios, job performance measures, and questions Dwr distributed to NRC examiners (C.3.i) 7/27/2012
- Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.
[Applies only] {Does not apply} to examinations prepared by the NRC.