{{#Wiki_filter:1 WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]
{{#Wiki_filter:WBN2Public Resource From:                             Boyd, Desiree L [dlboyd@tva.gov]
Sent: Thursday, June 13, 2013 9:07 AM To: Poole, Justin; Arent, Gordon; Br yan, Robert H Jr; Hon, Andrew Cc: Boyd, Desiree L
Sent:                             Thursday, June 13, 2013 9:07 AM To:                               Poole, Justin; Arent, Gordon; Bryan, Robert H Jr; Hon, Andrew Cc:                               Boyd, Desiree L


==Subject:==
==Subject:==
2012-6-13  -  WBN Project Plan - Unit 2.pdf Attachments:
2012-6 WBN Project Plan - Unit 2.pdf Attachments:                     2013-06 WBN Project Plan - Unit 2.pdf Please see attached for todays 9:15 phone call.
2013-06-13  -  WBN Project Plan - Unit 2.pdf Please see attached for today's 9:15 phone call.  
Thank you Désireé L. Boyd WBN Unit 2 Licensing EQB 1-B (Trailer NP70) dlboyd@tva.gov 423-365-8764 NOTICE: This electronic message transmission contains information which may be TVA SENSITIVE, TVA RESTRICTED, or TVA CONFIDENTIAL. Any misuse or unauthorized disclosure can result in civil penalties. If you are not the intended recipient, be aware that any disclosure, copying, distribution or use of the content of this information is prohibited. If you have receive this communication in error, please notify me immediately by e-mail and delete the original message.
1


Thank you Désireé L. Boyd WBN Unit 2 Licensing EQB 1-B (Trailer NP70)  
Hearing Identifier:      Watts_Bar_2_Operating_LA_Public Email Number:            826 Mail Envelope Properties      (7AB41F650F76BD44B5BCAB7C0CCABFAF44F31222)


dlboyd@tva.gov 423-365-8764 NOTICEThis electronic message transmission contains information which may be TVA SENSITIVE, TVA RESTRICTED, or TVA CONFIDENTIAL.
==Subject:==
Any misuse or unauthorized disclosure can result in civil penalties. If you are not the intended recipient, be aware that any disclosure, copying, distribution or use of the content of this information is prohibited. If you have receive this communication in error, please notify me immediately by e-mail and delete the original message
2012-6 WBN Project Plan - Unit 2.pdf Sent Date:              6/13/2013 9:06:52 AM Received Date:          6/13/2013 9:10:02 AM From:                    Boyd, Desiree L Created By:              dlboyd@tva.gov Recipients:
.
"Boyd, Desiree L" <dlboyd@tva.gov>
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 826  Mail Envelope Properties   (7AB41F650F76BD44B5BCAB7C0CCABFAF44F31222)
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Tracking Status: None "Arent, Gordon" <garent@tva.gov>
Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>
Tracking Status: None "Hon, Andrew" <Andrew.Hon@nrc.gov>
Tracking Status: None Post Office:            TVANUCXVS2.main.tva.gov Files                          Size                  Date & Time MESSAGE                        727                    6/13/2013 9:10:02 AM 2013-06 WBN Project Plan - Unit 2.pdf                          154507 Options Priority:                      Standard Return Notification:            No Reply Requested:                Yes Sensitivity:                    Normal Expiration Date:
Recipients Received:
 
WBN UNIT 2 PROJECT PLAN: 06/13/2013                                                  Page 2 of 42 I.      SUBMITTAL LOOK-AHEAD Item No.                                        Description                              Resp. Person          Due Date License Amendments / Technical Specifications
: 1. Common Service Station Transformer (CSST) A & B Credit                            Shea      August 1, 2013 SSER Open Item 32:
: 2.                                                                                    Hilmes      TBD Revise Diesel Generator Frequency Allowable Value.    [Commitment 113676066]
x Revised Proposal from Flowserve to Bechtel                                FlowServe    COMPLETE x Issue Purchase Order                                                        Wiggall    COMPLETE x Provide Runout Analysis                                                    FlowServe    COMPLETE x Westinghouse draft evaluation of analysis impacts                                        COMPLETE x Westinghouse final analysis impact evaluation                                Morgan      COMPLETE x Add Flowserve and Westinghouse evaluations to LAR write-up.              Wiggall/Hilmes May 15, 2013 x Finalize and Submit LAR to NRC.                                            Licensing    July 1, 2013
: 3. Fuel Storage                                                                      Bryan      June 27, 2013
: 4. RCS Dose Equivalent Iodine                                                        Bryan      June 12, 2013
: 5. CCS Maintenance                                                                  Bryan      June 12, 2013
: 6. EGTS Testing                                                                  Koontz/Bryan  August 1, 2013
: 7. Incorp U1 changes to TS 5.9.2                                                    Bryan      June 12, 2013 SOURCE: POD UPDATES, COMMITMENTS
 
WBN UNIT 2 PROJECT PLAN: 06/13/2013                                                      Page 3 of 42 Item No.                                          Description                                    Resp. Person    Due Date License Amendments / Technical Specifications The Unit 1 Environmental Protection Plan (EPP) is based on Supplement 1 of NUREG        Bushnell August 1, 2013 0498, Final Environmental Statement and references Supplement 1 in several places.
: 8. Since Supplement 2 of NUREG 0498 updates Supplement 1, an amendment needs to be processed to update the Unit 1 EPP for two unit operation.
SOURCE: POD UPDATES, COMMITMENTS
 
WBN UNIT 2 PROJECT PLAN: 06/13/2013                                                        Page 4 of 42 Item No.                                          Description                                  Resp. Person          Due Date SSER Appendix HH Open Items (requiring submittal)
SSER Open Item 1:
Following completion of cable pulls, submit letter to NRC either:
: 1.        Affirming no power assisted cable pulls were made, or                               Hilmes      January 17, 2014 Documenting any power assisted cable pulls.
[Commitment 113676047]
SSER Open Item 13:
: 2. Submit an ASME Section XI Inservice Test Program for the first ten year interval    McDonald / Crouch June 12, 2014 six months before receiving an Operating License. [Commitment NCO080008033:
Item 017 of Enclosure 2 of letter T90 080128 001]
SSER Open Item 37:
: 3. Submit changes to the Emergency Plan (REP) prior to fuel load.                       Detchemendy    November 15, 2013
[Commitment 111032952]
SSER Open Item 41:
Update the following to provide two unit capability:
: 4.                                                                                             Hilmes      November 15, 2013 x Plant design displays [Commitment 111033086], and x dose assessment models [Commitment 113841821]
SSER Open Item 43:
: 5. Submit Emergency Plan implementing procedures no less than 180 days before schedule   Detchemendy    November 15, 2013 issuance of Operating License. [Commitment 113841955]
SSER Open Item 61:
: 6. Fuel Thermal Conductivity Degradation Model (PAD Code) - Note: currently this is a      Koontz      August 7, 2013 License Condition - tracking PWROG activity to update code. [Commitment 113676152]
SOURCE: POD UPDATES, COMMITMENTS


==Subject:==
WBN UNIT 2 PROJECT PLAN: 06/13/2013                                                           Page 5 of 42 Item No.                                            Description                                      Resp. Person      Due Date SSER Appendix HH Open Items (requiring submittal)
2012-6-13  -  WBN Project Plan  -  Unit 2.pdf  Sent Date:   6/13/2013 9:06:52 AM  Received Date: 6/13/2013 9:10:02 AM From:    Boyd, Desiree L Created Bydlboyd@tva.gov Recipients:     "Boyd, Desiree L" <dlboyd@tva.gov>
SSER Open Item 79:
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Perform an EMI survey of the containment high range radiation monitors after they are
Tracking Status: None  "Arent, Gordon" <garent@tva.gov>  Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>  Tracking Status: None  "Hon, Andrew" <Andrew.Hon@nrc.gov>  Tracking Status: None Post Office:   TVANUCXVS2.main.tva.gov 
: 7.                                                                                                Hilmes    March 4, 2014 installed in WBN Unit 2, and submit the results to the NRC within two weeks of the survey being completed. [Commitment 112177753]
SSER Open Item 83:
: 8.                                                                                                Hilmes    August 30, 2013 Provide Letter verifying completion of data storm test on DCS.    [Commitment 113676093]
SSER Open Item 132:
Hilmes    COMPLETE
: a. Issue EDCR to add high VCT level alarm to the main control room annunciator system
: b. Submit letter documenting that plant modifications to add high VCT level alarm to main Arent   December 16, 2013 control room annunciator system have been completed. [Commitment 113111704]
: 9. c. Revise appropriate procedures (SOI, GO) to limit the number of operating pumps and isolate potential boron dilution paths as required by the Chapter 15 analysis. Also      Wallace   December 16, 2013 revise the ARIs and AOIs as needed to account for the new VCT high level alarm.
: d. Submit letter documenting that procedure changes associated with limiting the number of operating primary water pumps and isolating potential boron dilution paths have        Arent    January, 2014 been made. [Commitment 113111705]
SSER Open Item 134:
: 10. Modifications for Cherokee and Douglas Dams will be designed and implemented prior to        Williams July 1, 2014 WBN Unit 2 Startup. [Commitment 113880166]
SOURCE: POD UPDATES, COMMITMENTS
 
WBN UNIT 2 PROJECT PLAN: 06/13/2013                                                                    Page 6 of 42 Item No.                                              Description                                          Resp. Person          Due Date Other Submittals
: 1. As-Constructed Fire Protection Report        [Commitment 113461862]                                Hilmes    July 18, 2014
: 2. U2 FSAR With As-Constructed Figures          [Commitment 112068531]                                Arent      September 12, 2014 Prior to fuel load, a final report will be submitted following certain validation activities as
: 3.                                                                                                    Koontz / Enis July 18, 2014 described in the IPEEE Design Report (Enclosure 1). [Commitment 111027893]
: 4. Submit a merged U2 FSAR / U1 UFSAR              [Commitment 111360889]                            Licensing    April 2016
: 5. As-Constructed PRA        [Commitment 111029124]                                                Guey / Koontz July 18, 2014 x  Milestone - start PSA Update                                                                              Complete x  Data Update                                                                                              Apr 1, 2013- Oct 31, 2013 x  System Update                                                                                            Apr 1, 2013 - Feb 28, 2014 x  Human Reliability Analysis Update                                                                        Apr 1, 2013 - Feb 28, 2014 x  Draft Quantification                                                                                      Feb 28, 2014 - Mar 17, 2014 x  Independent review                                                                                        Mar 10, 2014 - April 4, 2014 x  Final Quantification                                                                                      Apr 4, 2014 - April 30, 2014 x  Summary Report                                                                                            Apr 25, 2014 - May 30, 2014 x  Milestone - Closure Submittal to NRC                                                                      June 16, 2014
: 6. TMI Commitment Review Letter            [Commitment 113967286]                                  Licensing    January 24, 2014 SOURCE: POD UPDATES, COMMITMENTS


Files    Size      Date & Time MESSAGE    727      6/13/2013 9:10:02 AM  2013-06-13  -  WBN Project Plan  -  Unit 2.pdf    154507 Options  Priority:    Standard  Return Notification:    No  Reply Requested:    Yes  Sensitivity:    Normal  Expiration Date:      Recipients Received:
WBN UNIT 2 PROJECT PLAN: 06/13/2013                                                         Page 7 of 42 Item No.                                             Description                                   Resp. Person       Due Date Other Submittals Letter to terminate Part 30/40 License after receipt of Part 50 License
WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 2 of 42 SOURCE: POD UPDATES, COMMITMENTS I. SUBMITTAL LOOK-AHEAD Item No. Description Resp. Person Due Date License Amendments / Technical Specifications
: 7.                                                                                             Licensing  December 4, 2015
: 1. Common Service Station Transformer (CSST) A & B Credit Shea August 1, 2013
[Commitment 113967302]
: 2. SSER Open Item 32: Revise Diesel Generator Frequency Allowable Value.    [Commitment 113676066]
: 8. ASME Section III N-3 Report      [Commitment 113967305]                                  Crouch    September 2014 Letter to NRC for notification of Vital Area Boundary Restoration
Hilmes TBD  Revised Proposal from Flowserve to Bechtel FlowServe COMPLETE  Issue Purchase Order Wiggall COMPLETE  Provide Runout Analysis FlowServe COMPLETE  Westinghouse draft evaluation of analysis impacts COMPLETE  Westinghouse final analysis impact evaluation Morgan COMPLETE  Add Flowserve and Westinghouse evaluations to LAR write-up. Wiggall/Hilmes May 15, 2013  Finalize and Submit LAR to NRC. Licensing July 1, 2013
: 9.                                                                                             Licensing January 24, 2014
: 3. Fuel Storage Bryan June 27, 2013
[Commitment 110850749]
: 4. RCS Dose Equivalent Iodine Bryan June 12, 2013
: 10. Unit 2 Completion Letter      [Commitment 113967311]                                      Licensing August 8, 2014
: 5. CCS Maintenance Bryan June 12, 2013
: 11. PAM variable Calculation for EOP reviews      [Commitment 113967317]                       Clark    November 1, 2013
: 6. EGTS Testing Koontz/Bryan August 1, 2013
: 12. TMI Action Item Status Letter                                                              Arent    April 30, 2014
: 7. Incorp U1 changes to TS 5.9.2 Bryan June 12, 2013 WBN UNIT 2 PROJECT PLAN:  06/13/2013 Page 3 of 42 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date  License Amendments / Technical Specifications
: 13. Facility Operating License No. NPF Unit 2                                                  Arent    December 12, 2013 SG Alternate Repair Criteria
: 8. The Unit 1 Environmental Protection Plan (EPP) is based on Supplement 1 of NUREG 0498, Final Environmental Statement and references Supplement 1 in several places.
: 14.                                                                                             Goetcheus January 7, 2015 Prepare Submittal & Submit to NRC Regulatory Framework Update [for status as of 06/30/2013]
Since Supplement 2 of NUREG 0498 updates Supplement 1, an amendment needs to be processed to update the Unit 1 EPP for two unit operation.
: 15.                                                                                               Elton    July 23, 2013
Bushnell August 1, 2013 WBN UNIT 2 PROJECT PLAN:  06/13/2013 Page 4 of 42 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date SSER Appendix HH Open Items (requiring submittal)
[Commitment 111027916 - 02
: 1. SSER Open Item 1: Following completion of cable pulls, submit letter to NRC either: Affirming no power assisted cable pulls were made, or  Documenting any power assisted cable pulls. [Commitment 113676047] Hilmes January 17, 2014
: 16. PST & IST Plans                                                                            Stockton  August 2013
: 2. SSER Open Item 13:
: 17. FSAR Amendment 110                                                                        Stockton  August 1, 2013 Submit a revised final report for CDR 390/84-36 and a final report for CDR 391/84-32 to
Submit an ASME Section XI Inservice Test Program for the first ten year interval six months before receiving an Operating License.    [Commitment NCO080008033: Item 017 of Enclosure 2 of letter T90 080128 001] McDonald / Crouch June 12, 2014
: 18.                                                                                             Bushnell  June 14, 2013 clarify that the applicable code is NFPA 13-1975 SOURCE: POD UPDATES, COMMITMENTS
: 3. SSER Open Item 37: Submit changes to the Emergency Plan (REP) prior to fuel load.    [Commitment 111032952] Detchemendy November 15, 2013
: 4. SSER Open Item 41:
Update the following to provide two unit capability:  Plant design displays [Commitment 111033086], and  dose assessment models [Commitment 113841821] Hilmes November 15, 2013
: 5. SSER Open Item 43: Submit Emergency Plan implementing procedures no less than 180 days before schedule issuance of Operating License.
[Commitment 113841955] Detchemendy November 15, 2013
: 6. SSER Open Item 61: Fuel Thermal Conductivity Degradation Model (PAD Code) - Note: currently this is a License Condition - tracking PWROG activity to update code.    [Commitment 113676152] Koontz August 7, 2013 WBN UNIT 2 PROJECT PLAN:  06/13/2013 Page 5 of 42 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date SSER Appendix HH Open Items (requiring submittal)
: 7. SSER Open Item 79: Perform an EMI survey of the containment high range radiation monitors after they are installed in WBN Unit 2, and submit the results to the NRC within two weeks of the survey being completed.    [Commitment 112177753] Hilmes March 4, 2014
: 8. SSER Open Item 83: Provide Letter verifying completion of data storm test on DCS.    [Commitment 113676093] Hilmes August 30, 2013
: 9. SSER Open Item 132: a. Issue EDCR to add high VCT level alarm to the main control room annunciator system Hilmes COMPLETE b. Submit letter documenting that plant modifications to add high VCT level alarm to main control room annunciator system have been completed.    [Commitment 113111704] Arent December 16, 2013 c. Revise appropriate procedures (SOI, GO) to limit the number of operating pumps and isolate potential boron dilution paths as required by the Chapter 15 analysis. Also revise the ARIs and AOIs as needed to account for the new VCT high level alarm. Wallace December 16, 2013 d. Submit letter documenting that procedure changes associated with limiting the number of operating primary water pumps and isolating potential boron dilution paths have been made.    [Commitment 113111705] Arent January, 2014
: 10. SSER Open Item 134: Modifications for Cherokee and Douglas Dams will be designed and implemented prior to WBN Unit 2 Startup.    [Commitment 113880166] Williams July 1, 2014


WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 6 of 42 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Other Submittals
WBN UNIT 2 PROJECT PLAN: 06/13/2013                                           Page 8 of 42 Item No.                                         Description                           Resp. Person       Due Date Regional Submittals
: 1. As-Constructed Fire Protection Report      [Commitment 113461862] Hilmes July 18, 2014
: 1. Unit Differences Update Letter  [Commitment 112145218 - 01]                 Stockton  June 27, 2013
: 2. U2 FSAR With As-Constructed Figures    [Commitment 112068531] Arent September 12, 2014
: 2. 10 CFR 50.55(e) Report - Instrument Line Slope (60 Day Update)              Bushnell June 28, 2013
: 3. Prior to fuel load, a final report will be submitted following certain validation activities as described in the IPEEE Design Report (Enclosure 1).
: 3. 10 CFR 50.55(e) Report - Commercial Grade Dedication Third Interim Report   Stockton July 18, 2013 SOURCE: POD UPDATES, COMMITMENTS
[Commitment 111027893]
Koontz / Enis July 18, 2014
: 4. Submit a merged U2 FSAR / U1 UFSAR    [Commitment 111360889] Licensing April 2016
: 5. As-Constructed PRA    [Commitment 111029124] Guey / Koontz July 18, 2014  Milestone - start PSA Update Complete Data Update Apr 1, 2013- Oct 31, 2013  System Update  Apr 1, 2013 - Feb 28, 2014 Human Reliability Analysis Update Apr 1, 2013 - Feb 28, 2014 Draft Quantification Feb 28, 2014 - Mar 17, 2014  Independent review Mar 10, 2014 - April 4, 2014  Final Quantification Apr 4, 2014 - April 30, 2014  Summary Report Apr 25, 2014 - May 30, 2014 Milestone - Closure Submittal to NRC June 16, 2014
: 6. TMI Commitment Review Letter      [Commitment 113967286] Licensing January 24, 2014 WBN UNIT 2 PROJECT PLAN:  06/13/2013 Page 7 of 42 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Other Submittals
: 7. Letter to terminate Part 30/40 License after receipt of Part 50 License    [Commitment 113967302] Licensing December 4, 2015
: 8. ASME Section III N-3 Report    [Commitment 113967305] Crouch September 2014
: 9. Letter to NRC for notification of Vital Area Boundary Restoration    [Commitment 110850749] Licensing January 24, 2014
: 10. Unit 2 Completion Letter    [Commitment 113967311] Licensing August 8, 2014
: 11. PAM variable Calculation for EOP reviews    [Commitment 113967317] Clark November 1, 2013
: 12. TMI Action Item Status Letter Arent April 30, 2014
: 13. Facility Operating License No. NPF Unit 2 Arent December 12, 2013
: 14. SG Alternate Repair Criteria Prepare Submittal & Submit to NRC Goetcheus January 7, 2015
: 15. Regulatory Framework Update [for status as of 06/30/2013]      [Commitment 111027916 - 02 Elton July 23, 2013
: 16. PST & IST Plans Stockton August 2013
: 17. FSAR Amendment 110 Stockton August 1, 2013
: 18. Submit a revised final report for CDR 390/84-36 and a final report for CDR 391/84-32 to clarify that the applicable code is NFPA 13-1975 Bushnell June 14, 2013


WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 8 of 42 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Regional Submittals
WBN UNIT 2 PROJECT PLAN: 06/13/2013                                                                   Page 9 of 42 Item No.                                         Description                                             Resp. Person         Due Date Fukushima NRC Order EA-12-049; Mitigating Strategies Order:
: 1. Unit Differences Update Letter    [Commitment 112145218 - 01] Stockton June 27, 2013
Licensees to develop, implement, and maintain guidance and strategies to maintain or                          NRC Update
: 2. 10 CFR 50.55(e) Report - Instrument Line Slope (60 Day Update) Bushnell June 28, 2013
: 1.                                                                                                   Williams/Spink restore core cooling, containment and SFP cooling capabilities following a beyond-design-                      August 28, 2013 basis external event. Must be implemented in all modes. [Commitment 113868651]
: 3. 10 CFR 50.55(e) Report - Commercial Grade Dedication Third Interim Report Stockton July 18, 2013  
NRC Order EA-12-049; Mitigating Strategies Order:
Strategies must be capable of mitigating a simultaneous loss of all alternating current (AC)                  NRC Update
: 2. power and loss of normal access to the ultimate heat sink and have adequate capacity to        Williams/Spink address challenges to core cooling, containment, and SFP cooling capabilities at all units                    August 28, 2013 on a site. [Commitment 113871962]
NRC Order EA-12-049; Mitigating Strategies Order:
Provide reasonable protection for the associated equipment from external events. Such                          NRC Update
: 3. protection must demonstrate that there is adequate capacity to address challenges to core      Williams/Spink cooling, containment, and SFP cooling capabilities at all units on a site.                                    August 28, 2013
[Commitment 113871973]
NRC Order EA-12-051; Order:
Licensees to provide instrumentation, able to withstand design-basis natural phenomena and remain reliable at temperature, humidity and radiation levels at saturation conditions, to                NRC Update
: 4. monitor SFP water level from the control room.                                                 Williams/Spink August 28, 2013 DCN 59683, Spent Fuel Pool Level Indication 10% of package
[Commitment 113872005]
10 CFR 50.54 F Letter Request for Information:
: 5.                                                                                                  Williams/Spink September 12, 2013 Submit Base Velocity and subsurface material response.        [Commitment 113872017]
SOURCE: POD UPDATES, COMMITMENTS


WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 9 of 42 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Fukushima
WBN UNIT 2 PROJECT PLAN: 06/13/2013                                                           Page 10 of 42 Item No.                                           Description                                     Resp. Person         Due Date Fukushima 10 CFR 50.54 F Letter Request for Information:
: 1. NRC Order EA-12-049; Mitigating Strategies Order: Licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment and SFP cooling capabilities following a beyond-design-basis external event. Must be implemented in all modes.    [Commitment 113868651] Williams/Spink NRC Update August 28, 2013
Licensees to reevaluate the flooding hazards at their sites against current NRC
: 2. NRC Order EA-12-049; Mitigating Strategies Order:  Strategies must be capable of mitigating a simultaneous loss of all alternating current (AC) power and loss of normal access to the ultimate heat sink and have adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site.    [Commitment 113871962] Williams/Spink NRC Update August 28, 2013
: 6.                                                                                            Williams/Spink March 2015 requirements and guidance, and if necessary, update the design basis and SSCs important to safety to protect against the updated hazards. [Commitment 113872029]
: 3. NRC Order EA-12-049; Mitigating Strategies Order:  Provide reasonable protection for the associated equipment from external events. Such protection must demonstrate that there is adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site.
10 CFR 50.54 F Letter Request for Information:
[Commitment 113871973] Williams/Spink NRC Update August 28, 2013
: 7. Recommendation 9.3 requires licensees to evaluate communication and staffing needs for   Williams/Spink October 30, 2013 multi-unit events. [Commitment 113872040]
: 4. NRC Order EA-12-051; Order: Licensees to provide instrumentation, able to withstand design-basis natural phenomena and remain reliable at temperature, humidity and radiation levels at saturation conditions, to monitor SFP water level from the control room. DCN 59683, Spent Fuel Pool Level Indication 10% of package    [Commitment 113872005] Williams/Spink NRC Update August 28, 2013
: 8. WBN-1 RAI NRC Target Dates                                                               Williams/Spink July 17, 2013
: 5. 10 CFR 50.54 F Letter Request for Information: Submit Base Velocity and subsurface material respon se.      [Commitment 113872017] Williams/Spink September 12, 2013 WBN UNIT 2 PROJECT PLAN:  06/13/2013 Page 10 of 42 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Fukushima
: 9. WBN SER NRC Target Dates                                                                 Williams/Spink October 11, 2013 SOURCE: POD UPDATES, COMMITMENTS
: 6. 10 CFR 50.54 F Letter Request for Information: Licensees to reevaluate the flooding hazards at their sites against current NRC requirements and guidance, and if necessary, update the design basis and SSCs important to safety to protect against the updated hazards.     [Commitment 113872029] Williams/Spink March 2015
: 7. 10 CFR 50.54 F Letter Request for Information: Recommendation 9.3 requires licensees to evaluate communication and staffing needs for multi-unit events.     [Commitment 113872040] Williams/Spink October 30, 2013
: 8. WBN-1 RAI NRC Target Dates Williams/Spink July 17, 2013
: 9. WBN SER NRC Target Dates Williams/Spink October 11, 2013  


WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 11 of 42 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Waste Confidence
WBN UNIT 2 PROJECT PLAN: 06/13/2013                                     Page 11 of 42 Item No.                                       Description                   Resp. Person           Due Date Waste Confidence TVA actions on Waste Confidence:
: 1. TVA actions on Waste Confidence: Finalize contractor outputs on reports for Waste Confidence Plan Vigluicci / Baker COMPLETE 2. Follow NRC Generic Effort Comment as appropriate September 2013  
: 1.                                                                    Vigluicci / Baker COMPLETE Finalize contractor outputs on reports for Waste Confidence Plan
: 2. Follow NRC Generic Effort Comment as appropriate                                   September 2013 SOURCE: POD UPDATES, COMMITMENTS


WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 12 of 42 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Significant New Regulatory Issues
WBN UNIT 2 PROJECT PLAN: 06/13/2013                               Page 12 of 42 Item No.                                     Description               Resp. Person           Due Date Significant New Regulatory Issues New Station Blackout Rule
: 1. New Station Blackout Rule  Ongoing rulemaking Hilmes Late 2014
: 1.                                                                   Hilmes       Late 2014 x Ongoing rulemaking 10 CFR 50.46 Rule Change x Oxidation limits
: 2. 10 CFR 50.46 Rule Change Oxidation limits Ongoing rulemaking NRC planning to tie to GSI-191 (Sump Issue) Koontz/Westinghouse February 28, 2016
: 2. x Ongoing rulemaking                                     Koontz/Westinghouse February 28, 2016 NRC planning to tie to GSI-191 (Sump Issue)
: 3. DOEL Reactor Vessel Issues   NRC issue Information Notice Hemmer May 2013
: 3. DOEL Reactor Vessel Issues NRC issue Information Notice       Hemmer       May 2013
: 4. 10 CFR 73 - Rulemaking on Firearms Reynolds/Baker End of 2014
: 4. 10 CFR 73 - Rulemaking on Firearms                         Reynolds/Baker   End of 2014
: 5. 10 CFR Part 37 Physical Protection of Byproduct Material Reynolds/Baker TBD}}
: 5. 10 CFR Part 37 Physical Protection of Byproduct Material   Reynolds/Baker   TBD SOURCE: POD UPDATES, COMMITMENTS}}

Revision as of 17:06, 4 November 2019

2013/06/13 Watts Bar 2 OL - 2012-6-13 - WBN Project Plan - Unit 2.pdf
ML13192A439
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 06/13/2013
From:
- No Known Affiliation
To:
Division of Operating Reactor Licensing
References
Download: ML13192A439 (13)


Text

WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]

Sent: Thursday, June 13, 2013 9:07 AM To: Poole, Justin; Arent, Gordon; Bryan, Robert H Jr; Hon, Andrew Cc: Boyd, Desiree L

Subject:

2012-6 WBN Project Plan - Unit 2.pdf Attachments: 2013-06 WBN Project Plan - Unit 2.pdf Please see attached for todays 9:15 phone call.

Thank you Désireé L. Boyd WBN Unit 2 Licensing EQB 1-B (Trailer NP70) dlboyd@tva.gov 423-365-8764 NOTICE: This electronic message transmission contains information which may be TVA SENSITIVE, TVA RESTRICTED, or TVA CONFIDENTIAL. Any misuse or unauthorized disclosure can result in civil penalties. If you are not the intended recipient, be aware that any disclosure, copying, distribution or use of the content of this information is prohibited. If you have receive this communication in error, please notify me immediately by e-mail and delete the original message.

1

Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 826 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF44F31222)

Subject:

2012-6 WBN Project Plan - Unit 2.pdf Sent Date: 6/13/2013 9:06:52 AM Received Date: 6/13/2013 9:10:02 AM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients:

"Boyd, Desiree L" <dlboyd@tva.gov>

Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>

Tracking Status: None "Arent, Gordon" <garent@tva.gov>

Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>

Tracking Status: None "Hon, Andrew" <Andrew.Hon@nrc.gov>

Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 727 6/13/2013 9:10:02 AM 2013-06 WBN Project Plan - Unit 2.pdf 154507 Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:

Recipients Received:

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 2 of 42 I. SUBMITTAL LOOK-AHEAD Item No. Description Resp. Person Due Date License Amendments / Technical Specifications

1. Common Service Station Transformer (CSST) A & B Credit Shea August 1, 2013 SSER Open Item 32:
2. Hilmes TBD Revise Diesel Generator Frequency Allowable Value. [Commitment 113676066]

x Revised Proposal from Flowserve to Bechtel FlowServe COMPLETE x Issue Purchase Order Wiggall COMPLETE x Provide Runout Analysis FlowServe COMPLETE x Westinghouse draft evaluation of analysis impacts COMPLETE x Westinghouse final analysis impact evaluation Morgan COMPLETE x Add Flowserve and Westinghouse evaluations to LAR write-up. Wiggall/Hilmes May 15, 2013 x Finalize and Submit LAR to NRC. Licensing July 1, 2013

3. Fuel Storage Bryan June 27, 2013
4. RCS Dose Equivalent Iodine Bryan June 12, 2013
5. CCS Maintenance Bryan June 12, 2013
6. EGTS Testing Koontz/Bryan August 1, 2013
7. Incorp U1 changes to TS 5.9.2 Bryan June 12, 2013 SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 3 of 42 Item No. Description Resp. Person Due Date License Amendments / Technical Specifications The Unit 1 Environmental Protection Plan (EPP) is based on Supplement 1 of NUREG Bushnell August 1, 2013 0498, Final Environmental Statement and references Supplement 1 in several places.

8. Since Supplement 2 of NUREG 0498 updates Supplement 1, an amendment needs to be processed to update the Unit 1 EPP for two unit operation.

SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 4 of 42 Item No. Description Resp. Person Due Date SSER Appendix HH Open Items (requiring submittal)

SSER Open Item 1:

Following completion of cable pulls, submit letter to NRC either:

1. Affirming no power assisted cable pulls were made, or Hilmes January 17, 2014 Documenting any power assisted cable pulls.

[Commitment 113676047]

SSER Open Item 13:

2. Submit an ASME Section XI Inservice Test Program for the first ten year interval McDonald / Crouch June 12, 2014 six months before receiving an Operating License. [Commitment NCO080008033:

Item 017 of Enclosure 2 of letter T90 080128 001]

SSER Open Item 37:

3. Submit changes to the Emergency Plan (REP) prior to fuel load. Detchemendy November 15, 2013

[Commitment 111032952]

SSER Open Item 41:

Update the following to provide two unit capability:

4. Hilmes November 15, 2013 x Plant design displays [Commitment 111033086], and x dose assessment models [Commitment 113841821]

SSER Open Item 43:

5. Submit Emergency Plan implementing procedures no less than 180 days before schedule Detchemendy November 15, 2013 issuance of Operating License. [Commitment 113841955]

SSER Open Item 61:

6. Fuel Thermal Conductivity Degradation Model (PAD Code) - Note: currently this is a Koontz August 7, 2013 License Condition - tracking PWROG activity to update code. [Commitment 113676152]

SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 5 of 42 Item No. Description Resp. Person Due Date SSER Appendix HH Open Items (requiring submittal)

SSER Open Item 79:

Perform an EMI survey of the containment high range radiation monitors after they are

7. Hilmes March 4, 2014 installed in WBN Unit 2, and submit the results to the NRC within two weeks of the survey being completed. [Commitment 112177753]

SSER Open Item 83:

8. Hilmes August 30, 2013 Provide Letter verifying completion of data storm test on DCS. [Commitment 113676093]

SSER Open Item 132:

Hilmes COMPLETE

a. Issue EDCR to add high VCT level alarm to the main control room annunciator system
b. Submit letter documenting that plant modifications to add high VCT level alarm to main Arent December 16, 2013 control room annunciator system have been completed. [Commitment 113111704]
9. c. Revise appropriate procedures (SOI, GO) to limit the number of operating pumps and isolate potential boron dilution paths as required by the Chapter 15 analysis. Also Wallace December 16, 2013 revise the ARIs and AOIs as needed to account for the new VCT high level alarm.
d. Submit letter documenting that procedure changes associated with limiting the number of operating primary water pumps and isolating potential boron dilution paths have Arent January, 2014 been made. [Commitment 113111705]

SSER Open Item 134:

10. Modifications for Cherokee and Douglas Dams will be designed and implemented prior to Williams July 1, 2014 WBN Unit 2 Startup. [Commitment 113880166]

SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 6 of 42 Item No. Description Resp. Person Due Date Other Submittals

1. As-Constructed Fire Protection Report [Commitment 113461862] Hilmes July 18, 2014
2. U2 FSAR With As-Constructed Figures [Commitment 112068531] Arent September 12, 2014 Prior to fuel load, a final report will be submitted following certain validation activities as
3. Koontz / Enis July 18, 2014 described in the IPEEE Design Report (Enclosure 1). [Commitment 111027893]
4. Submit a merged U2 FSAR / U1 UFSAR [Commitment 111360889] Licensing April 2016
5. As-Constructed PRA [Commitment 111029124] Guey / Koontz July 18, 2014 x Milestone - start PSA Update Complete x Data Update Apr 1, 2013- Oct 31, 2013 x System Update Apr 1, 2013 - Feb 28, 2014 x Human Reliability Analysis Update Apr 1, 2013 - Feb 28, 2014 x Draft Quantification Feb 28, 2014 - Mar 17, 2014 x Independent review Mar 10, 2014 - April 4, 2014 x Final Quantification Apr 4, 2014 - April 30, 2014 x Summary Report Apr 25, 2014 - May 30, 2014 x Milestone - Closure Submittal to NRC June 16, 2014
6. TMI Commitment Review Letter [Commitment 113967286] Licensing January 24, 2014 SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 7 of 42 Item No. Description Resp. Person Due Date Other Submittals Letter to terminate Part 30/40 License after receipt of Part 50 License

7. Licensing December 4, 2015

[Commitment 113967302]

8. ASME Section III N-3 Report [Commitment 113967305] Crouch September 2014 Letter to NRC for notification of Vital Area Boundary Restoration
9. Licensing January 24, 2014

[Commitment 110850749]

10. Unit 2 Completion Letter [Commitment 113967311] Licensing August 8, 2014
11. PAM variable Calculation for EOP reviews [Commitment 113967317] Clark November 1, 2013
12. TMI Action Item Status Letter Arent April 30, 2014
13. Facility Operating License No. NPF Unit 2 Arent December 12, 2013 SG Alternate Repair Criteria
14. Goetcheus January 7, 2015 Prepare Submittal & Submit to NRC Regulatory Framework Update [for status as of 06/30/2013]
15. Elton July 23, 2013

[Commitment 111027916 - 02

16. PST & IST Plans Stockton August 2013
17. FSAR Amendment 110 Stockton August 1, 2013 Submit a revised final report for CDR 390/84-36 and a final report for CDR 391/84-32 to
18. Bushnell June 14, 2013 clarify that the applicable code is NFPA 13-1975 SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 8 of 42 Item No. Description Resp. Person Due Date Regional Submittals

1. Unit Differences Update Letter [Commitment 112145218 - 01] Stockton June 27, 2013
2. 10 CFR 50.55(e) Report - Instrument Line Slope (60 Day Update) Bushnell June 28, 2013
3. 10 CFR 50.55(e) Report - Commercial Grade Dedication Third Interim Report Stockton July 18, 2013 SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 9 of 42 Item No. Description Resp. Person Due Date Fukushima NRC Order EA-12-049; Mitigating Strategies Order:

Licensees to develop, implement, and maintain guidance and strategies to maintain or NRC Update

1. Williams/Spink restore core cooling, containment and SFP cooling capabilities following a beyond-design- August 28, 2013 basis external event. Must be implemented in all modes. [Commitment 113868651]

NRC Order EA-12-049; Mitigating Strategies Order:

Strategies must be capable of mitigating a simultaneous loss of all alternating current (AC) NRC Update

2. power and loss of normal access to the ultimate heat sink and have adequate capacity to Williams/Spink address challenges to core cooling, containment, and SFP cooling capabilities at all units August 28, 2013 on a site. [Commitment 113871962]

NRC Order EA-12-049; Mitigating Strategies Order:

Provide reasonable protection for the associated equipment from external events. Such NRC Update

3. protection must demonstrate that there is adequate capacity to address challenges to core Williams/Spink cooling, containment, and SFP cooling capabilities at all units on a site. August 28, 2013

[Commitment 113871973]

NRC Order EA-12-051; Order:

Licensees to provide instrumentation, able to withstand design-basis natural phenomena and remain reliable at temperature, humidity and radiation levels at saturation conditions, to NRC Update

4. monitor SFP water level from the control room. Williams/Spink August 28, 2013 DCN 59683, Spent Fuel Pool Level Indication 10% of package

[Commitment 113872005]

10 CFR 50.54 F Letter Request for Information:

5. Williams/Spink September 12, 2013 Submit Base Velocity and subsurface material response. [Commitment 113872017]

SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 10 of 42 Item No. Description Resp. Person Due Date Fukushima 10 CFR 50.54 F Letter Request for Information:

Licensees to reevaluate the flooding hazards at their sites against current NRC

6. Williams/Spink March 2015 requirements and guidance, and if necessary, update the design basis and SSCs important to safety to protect against the updated hazards. [Commitment 113872029]

10 CFR 50.54 F Letter Request for Information:

7. Recommendation 9.3 requires licensees to evaluate communication and staffing needs for Williams/Spink October 30, 2013 multi-unit events. [Commitment 113872040]
8. WBN-1 RAI NRC Target Dates Williams/Spink July 17, 2013
9. WBN SER NRC Target Dates Williams/Spink October 11, 2013 SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 11 of 42 Item No. Description Resp. Person Due Date Waste Confidence TVA actions on Waste Confidence:

1. Vigluicci / Baker COMPLETE Finalize contractor outputs on reports for Waste Confidence Plan
2. Follow NRC Generic Effort Comment as appropriate September 2013 SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 06/13/2013 Page 12 of 42 Item No. Description Resp. Person Due Date Significant New Regulatory Issues New Station Blackout Rule

1. Hilmes Late 2014 x Ongoing rulemaking 10 CFR 50.46 Rule Change x Oxidation limits
2. x Ongoing rulemaking Koontz/Westinghouse February 28, 2016 NRC planning to tie to GSI-191 (Sump Issue)
3. DOEL Reactor Vessel Issues NRC issue Information Notice Hemmer May 2013
4. 10 CFR 73 - Rulemaking on Firearms Reynolds/Baker End of 2014
5. 10 CFR Part 37 Physical Protection of Byproduct Material Reynolds/Baker TBD SOURCE: POD UPDATES, COMMITMENTS