| title = NRC Staff January 2014 Status Update Letter in the Matter of Davis-Besse, Unit 1 License Renewal
| title = NRC Staff January 2014 Status Update Letter in the Matter of Davis-Besse, Unit 1 License Renewal
| author name = Harris B G
| author name = Harris B
| author affiliation = NRC/OGC
| author affiliation = NRC/OGC
| addressee name = Froehlich W J, Kastenberg W E, Trikouros N G
| addressee name = Froehlich W, Kastenberg W, Trikouros N
| addressee affiliation = NRC/ASLBP
| addressee affiliation = NRC/ASLBP
| docket = 05000346
| docket = 05000346
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:U N I T E D S T A T E S N U C L E A R R E G U L A T O R Y C O M M I S S I O NWASHINGTON, DC 20555 - 0001 January 30, 2014
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 January 30, 2014 Administrative Judge                              Administrative Judge William J. Froehlich, Chair                      Nicholas G. Trikouros Atomic Safety and Licensing Board                Atomic Safety and Licensing Board Mail Stop: T-3F23                                Mail Stop: T-3F23 Washington, DC 20555-001                          Washington, DC 20555-0001 Administrative Judge Dr. William E. Kastenberg Atomic Safety and Licensing Board Mail Stop: T-3F23 Washington, DC 20555-0001 In the Matter of FirstEnergy Nuclear Operating Co.
(Davis-Besse Nuclear Power Station, Unit 1)
Docket No. 50-346-LR


In the Matter of FirstEnergy Nuclear Operating Co.
==Dear Administrative Judges:==
(Davis-Besse Nuclear Power Station, Unit 1)
Docket No. 50
-346-LR  Dear Administrative Judges
: Pursuant to the Atomic Safety and Licensing Board's ("Board") Memorandum and Order dated June 15, 2011
("Order") and Order (Granting Motion for Modification of Initial Scheduling Order) dated November 2, 2011, the staff of the Nuclear Regulatory Commission ("Staff") notes that the Safety Evaluation Report ("SER") with open items was published July 31, 2012. The Staff publish ed the SER on September 3, 2013. The Staff currently anticipates publication of the Draft Supplemental Environmental Impact Statement ("
DSEIS") in February 2014 and the Final SEIS in June 201 4.                  Respectfully submitted, 
        /signed (electronically) by/
Brian G. Harris Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O
-15 D21        Washington, DC 20555
-0001        (301) 415-1392        brian.harris@nrc.gov Administrative Judge William J. Froehlich, Chair Atomic Safety and Licensing Board Mail Stop: T
-3F23 Washington, DC 20555
-001  Administrative Judge Nicholas G. Trikouros Atomic Safety and Licensing Board Mail Stop: T
-3F23 Washington, DC 20555-0001  Administrative Judge Dr. William E. Kastenberg Atomic Safety and Licensing Board Mail Stop: T
-3F23 Washington, DC 20555
-0001 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of
    )        )  FIRSTENERGY NUCLEAR OPERATING CO.
  )  Docket No.
50-346-LRA ) (Davis-Besse Nuclear Power Station, Unit 1)
)          )  CERTIFICATE OF SERVICE


Pursuant to 10 C.F.R § 2.305 (revised), I hereby certify that copies of the January 30 , 2013 Letter from Brian G. Harris in the above
Pursuant to the Atomic Safety and Licensing Boards (Board) Memorandum and Order dated June 15, 2011 (Order) and Order (Granting Motion for Modification of Initial Scheduling Order) dated November 2, 2011, the staff of the Nuclear Regulatory Commission (Staff) notes that the Safety Evaluation Report (SER) with open items was published July 31, 2012. The Staff published the SER on September 3, 2013. The Staff currently anticipates publication of the Draft Supplemental Environmental Impact Statement (DSEIS) in February 2014 and the Final SEIS in June 2014.
-captioned proceeding have been served upon the Electronic Information Exchange, the NRC's E
Respectfully submitted,
-Filing System, in the above captioned proceeding, this 30 th day of January, 201 3.
                                                    /signed (electronically) by/
Signed (electronically) by Brian G. Harris Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O
Brian G. Harris Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-1392 brian.harris@nrc.gov
-15 D21       Washington, DC 20555
 
-0001       (301) 415-1392 brian.harris@nrc.gov}}
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of                                    )
                                                    )
FIRSTENERGY NUCLEAR OPERATING CO.                    )      Docket No. 50-346-LRA
                                                    )
(Davis-Besse Nuclear Power Station, Unit 1)          )
                                                    )
CERTIFICATE OF SERVICE Pursuant to 10 C.F.R § 2.305 (revised), I hereby certify that copies of the January 30, 2013 Letter from Brian G. Harris in the above-captioned proceeding have been served upon the Electronic Information Exchange, the NRCs E-Filing System, in the above captioned proceeding, this 30th day of January, 2013.
Signed (electronically) by Brian G. Harris Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-1392 brian.harris@nrc.gov}}

Latest revision as of 09:59, 4 November 2019

NRC Staff January 2014 Status Update Letter in the Matter of Davis-Besse, Unit 1 License Renewal
ML14030A437
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 01/30/2014
From: Harris B
NRC/OGC
To: William Froehlich, Kastenberg W, Nicholas Trikouros
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-346-LR, ASLBP 11-907-01-LR-BD01, RAS 25530
Download: ML14030A437 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 January 30, 2014 Administrative Judge Administrative Judge William J. Froehlich, Chair Nicholas G. Trikouros Atomic Safety and Licensing Board Atomic Safety and Licensing Board Mail Stop: T-3F23 Mail Stop: T-3F23 Washington, DC 20555-001 Washington, DC 20555-0001 Administrative Judge Dr. William E. Kastenberg Atomic Safety and Licensing Board Mail Stop: T-3F23 Washington, DC 20555-0001 In the Matter of FirstEnergy Nuclear Operating Co.

(Davis-Besse Nuclear Power Station, Unit 1)

Docket No. 50-346-LR

Dear Administrative Judges:

Pursuant to the Atomic Safety and Licensing Boards (Board) Memorandum and Order dated June 15, 2011 (Order) and Order (Granting Motion for Modification of Initial Scheduling Order) dated November 2, 2011, the staff of the Nuclear Regulatory Commission (Staff) notes that the Safety Evaluation Report (SER) with open items was published July 31, 2012. The Staff published the SER on September 3, 2013. The Staff currently anticipates publication of the Draft Supplemental Environmental Impact Statement (DSEIS) in February 2014 and the Final SEIS in June 2014.

Respectfully submitted,

/signed (electronically) by/

Brian G. Harris Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-1392 brian.harris@nrc.gov

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

FIRSTENERGY NUCLEAR OPERATING CO. ) Docket No. 50-346-LRA

)

(Davis-Besse Nuclear Power Station, Unit 1) )

)

CERTIFICATE OF SERVICE Pursuant to 10 C.F.R § 2.305 (revised), I hereby certify that copies of the January 30, 2013 Letter from Brian G. Harris in the above-captioned proceeding have been served upon the Electronic Information Exchange, the NRCs E-Filing System, in the above captioned proceeding, this 30th day of January, 2013.

Signed (electronically) by Brian G. Harris Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-1392 brian.harris@nrc.gov