Category:Legal-Correspondence/Miscellaneous
MONTHYEARML20059M1852020-02-28028 February 2020 Commission Notification Re Conforming Amendments ML20058J3132020-02-27027 February 2020 Notification of Emergence from Chapter 11 Bankruptcy ML19336C6142019-12-0202 December 2019 Commission Notification Re Issuance ML19325D5212019-11-21021 November 2019 Notification of Significant Licensing Action ML19325D5182019-11-21021 November 2019 Notification of Nsla ML19325D4892019-11-21021 November 2019 Notice of Appearance for Jeremy L. Wachutka ML15058A4692015-02-27027 February 2015 February 2015 Status Update Letter ML15030A1672015-01-30030 January 2015 January 2015 Status Update Letter ML14357A0032014-12-23023 December 2014 December 2014 Status Update Letter in the Matter of Davis Besse, Unit 1 ML14342A4782014-12-0808 December 2014 Notice of Appearance of Jeremy L. Wachutka on Behalf of the Us Nuclear Regulatory Commission in the Matter of Davis Besse ML14329A8242014-11-25025 November 2014 November 2014 Status Update Letter in the Matter of Davis-Besse, Unit 1 ML14303A1192014-10-30030 October 2014 October 2014 Status Update Letter in the Matter of Davis-Besse License Renewal ML14302A7202014-10-29029 October 2014 Notification of Document Related to the Davis Besse Shield Building ML14241A2462014-08-29029 August 2014 August 2014 Status Update Letter ML14211A0072014-07-30030 July 2014 July 2014 Status Update Letter ML14189A4522014-07-0808 July 2014 Notification of Documents Related to the Davis-Besse Shield Building ML14181A0242014-06-30030 June 2014 June 2014 Status Update Letter, in the Matter of Firstenergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1) ML14150A0042014-05-30030 May 2014 May 2014 Status Update Letter ML14120A0282014-04-30030 April 2014 NRC Staff April 2014 Status Update Letter in the Matter of Davis-Besse, Unit 1 ML14059A0052014-02-28028 February 2014 February 2014 Status Update Letter in the Matter of Davis-Besse, Units 1 License Renewal ML14030A4372014-01-30030 January 2014 NRC Staff January 2014 Status Update Letter in the Matter of Davis-Besse, Unit 1 License Renewal ML13364A0132013-12-30030 December 2013 December 2013 Status Update Letter in the Matter of Davis-Besse Nuclear Power Station, Unit 1 License Renewal ML13331A0062013-11-27027 November 2013 November 2013 Status Update Letter ML13304B4472013-10-31031 October 2013 October 2013 Status Update Letter ML13273A3742013-09-30030 September 2013 September 2013 Status Update Letter ML13242A2542013-08-30030 August 2013 NRC Staff Status Update Letter, August 2013 ML13231A2422013-08-19019 August 2013 Notice of Withdrawal for Lloyd Subin ML13231A2472013-08-19019 August 2013 Notice of Withdrawal for Lloyd Subin on Behalf of the U.S. Nuclear Regulatory Commission in the Matter of Davis-Besse, Unit 1 ML13211A2162013-07-30030 July 2013 NRC Staff'S July 2013 Status Update Letter in the Matter of Davis-Besse, Unit 1 ML13182A3482013-07-0101 July 2013 NRC Staff June 2013 Status Update Letter in the Matter of Davis-Besse, Unit 1 ML13165A2472013-06-14014 June 2013 Notice of Appearance of David W. Jenkins ML13165A0712013-06-14014 June 2013 Notice of Appearance of Jeremy L. Wachutka ML13162A7872013-06-11011 June 2013 Notice of Appearance of Lloyd B. Subin on Behalf of the U.S. Nuclear Regulatory Commission in the Matter of Davis-Besse, Unit 1 ML13149A0942013-05-29029 May 2013 May 2013 Status Update Letter ML13142A5372013-05-22022 May 2013 Memorandum Referring Davis-Besse Nuclear Power Station, Unit 1 Petition to Intervene and for an Adjudicatory Hearing of FENOC License Amendment Request Docket No. 50-346-LA to the Atomic Safety and Licensing Board ML13120A5452013-04-30030 April 2013 NRC Staff Status Update in the Matter of Firstenergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1) ML13088A0032013-03-29029 March 2013 NRC Staff'S Status Update Letter March 29, 2013 ML13059A8232013-02-28028 February 2013 NRC Staff Status Update Letter ML12325A9682012-11-20020 November 2012 Board Notification of Filing Related to Shield Building Laminar Cracking ML12153A4112012-06-0101 June 2012 Firstenergy Nuclear Operating Company, Davis-Besse, Unit 1, Notification of Filing Related to Proposed Shield Building Cracking Contention ML12138A3612012-05-17017 May 2012 Firstenergy Nuclear Operating Company, Davis-Besse Nuclear Power Station, Unit 1, Notification of Filing Related to Proposed Shield Building Cracking Contention ML12131A0312012-05-10010 May 2012 NRC Staff Transmittal of Inspection Report Regarding Cracks Found in the Shield Building for Davis-Besse, Unit 1 ML12097A2162012-04-0505 April 2012 Firstenergy Notification of Filing Related to Proposed Shield Building Cracking Contention ML12060A1912012-02-29029 February 2012 Notification Regarding Proposed Contention 5 ML12025A0072012-01-25025 January 2012 Schedule Update Letter to the Board ML12024A0242012-01-24024 January 2012 Notice of Withdrawal of Richard S. Harper in the Matter of Davis-Besse, Unit 1 License Renewal ML12012A1832012-01-12012 January 2012 Notice of Appearance from Catherine E. Kanatas for Nrc/Ogc Office ML12006A2192012-01-0606 January 2012 Notice of Appearance of Timothy P. Matthews on Behalf of Firstenergy Nuclear Operating Company in the Matter of Davis-Besse, Unit 1 ML11319A1592011-11-15015 November 2011 NRC Staff Projections for the Draft Supplemental Environmental Impact Statement and Final Supplemental Environmental Impact Statement in the Matter of First Energy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1) ML11314A1942011-11-10010 November 2011 Staff Letter to Licensing Board Correcting Caption 2020-02-28
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 November 15, 2011 In the Matter of FirstEnergy Nuclear Operating Co.
(Davis-Besse Nuclear Power Station, Unit 1)
Docket No. 50-346-LR
Dear Administrative Judges:
In accordance with the Atomic Safety and Licensing Boards (Board) June 15, 2011, Memorandum and Order, the staff of the Nuclear Regulatory Commission (Staff) currently expects to issue the Draft Supplemental Environmental Impact Statement (DSEIS), Final Supplemental Environmental Impact Statement (FSEIS), the Safety Evaluation Report (SER) with Open Items, and the Final SER as indicated in the table below.
Document Projected Issue Date DSEIS January 2012 FSEIS May 2012 SER with Open Items To be determined SER July 2012 Administrative Judge William J. Froehlich, Chair Atomic Safety and Licensing Board Mail Stop: T-3F23 Washington, DC 20555-001 Administrative Judge Nicholas G. Trikouros Atomic Safety and Licensing Board Mail Stop: T-3F23 Washington, DC 20555-0001 Administrative Judge Dr. William E. Kastenberg Atomic Safety and Licensing Board Mail Stop: T-3F23 Washington, DC 20555-0001 The Staff is not currently able to provide an updated projected date for issuing the SER with Open Items. The Staff anticipates that it will be able to provide the Board a projected date for issuing the SER with Open items in its next scheduled update in December 2011.
Respectfully submitted, Brian G. Harris
/signed (electronically) by/
Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-1392 Brian.harris@nrc.gov
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of
)
)
FIRSTENERGY NUCLEAR OPERATING CO.
)
Docket No. 50-346-LRA
)
(Davis-Besse Nuclear Power Station, Unit 1)
)
)
CERTIFICATE OF SERVICE I hereby certify that copies of the Letter from Brian G. Harris to the Board, dated November 15, 2011, in the above-captioned proceeding have been served on the following by Electronic Information Exchange this 15th day of November, 2011.
William J. Froehlich, Chair Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: william.froehlich@nrc.gov Office of Commission Appellate Adjudication Mail Stop: O-16G4 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: OCAAmail.resource@nrc.gov Nicholas G. Trikouros, Administrative Judge Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: nicholas.trikorous@nrc.gov Office of the Secretary Attn: Rulemakings and Adjudications Staff Mail Stop: O-16G4 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: hearingdocket@nrc.gov William E. Kastenberg, Administrative Judge Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: william.kastenberg@nrc.gov David W. Jenkins, Esq.
First Energy Service Company Mail Stop A-GO-15 76 South Main Street Akron, OH 44308 E-mail: djenkins@firstenergycorp.com
Hillary Cain, Law Clerk Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: hillary.cain@nrc.gov Morgan, Lewis & Bockius Pennsylvania Avenue, NW Washington, D.C. 20004 Stephen Burdick, Esq.
E-mail: sburdick@morganlewis.com Alex Polonsky, Esq.
E-mail: apolonsky@morganlewis.com Kathryn M. Sutton, Esq.
E-mail: ksutton@morganlewis.com Timothy Matthews, Esq.
E-mail: tmatthews@morganlewis.com Mary Freeze, Legal Secretary E-mail: mfreeze@morganlewis.com Morgan, Lewis & Bockius LLP 1000 Louisiana Street Suite 4000 Houston, TX 77002 Martin J. ONeill E-mail: martin.oneill@morganlewis.com Michael Keegan Dont Waste Michigan 811 Harrison Street Monroe, Michigan 48161 E-mail:
Beyond Nuclear mkeeganj@comcast.net 6930 Carroll Avenue, Suite 400 Takoma Park, MD 20912 Paul Gunter E-mail: paul@beyondnuclear.com Kevin Kamps Email: Kevin@beyondnuclear.com Anita Rios Green Party of Ohio 2626 Robinwood Avenue Toledo, Ohio 43610 Email: rhannon@toast.net Derek Coronado Citizens Environmental Alliance (CEA) of Southwestern Ontario 1950 Ottawa Street Windsor, Ontario Canada N8Y 197 Email: dcoronado@cogeco.net Terry Lodge Counsel for Citizens Environmental Alliance, Dont Waste Michigan and Green Party of Ohio 316 N. Michigan Street, Suite 520 Toledo, OH 43604 E-mail: tjlodge50@yahoo.com Brian G. Harris
/Signed (electronically) by/
Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-1392 E-mail: Brian.Harris@nrc.gov