| issue date = 07/09/2014
| issue date = 07/09/2014
| title = Requalification Program Inspection - Plant Hatch
| title = Requalification Program Inspection - Plant Hatch
| author name = Guthrie E F
| author name = Guthrie E
| author affiliation = NRC/RGN-II/DRS
| author affiliation = NRC/RGN-II/DRS
| addressee name = Vineyard D R
| addressee name = Vineyard D
| addressee affiliation = Southern Nuclear Operating Co, Inc
| addressee affiliation = Southern Nuclear Operating Co, Inc
| docket = 05000321, 05000366
| docket = 05000321, 05000366
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 July 9, 2014 Southern Nuclear Operating Company, Inc. ATTN: Mr. David R. Vineyard Vice President Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 July 9, 2014 Southern Nuclear Operating Company, Inc.
ATTN: Mr. David R. Vineyard Vice President Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513


==SUBJECT:==
==SUBJECT:==
REQUALIFICATION PROGRAM INSPECTION - PLANT HATCH  
REQUALIFICATION PROGRAM INSPECTION - PLANT HATCH


==Dear Mr. Vineyard:==
==Dear Mr. Vineyard:==


In a telephone conversation on July 7, 2014 Mr. David Lanyi, Operations Engineer, and Mr. Kip Wainwright, Operations Training Manager, made arrangements for the NRC to inspect the licensed operator requalification program at Plant Hatch. The inspection is planned for the week of August 18, 2014, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program. It is our understanding that you have committed to maintain your plant-referenced simulator in accordance with ANSI/ANS-3.5-1985, "American National Standard for Nuclear Power Plant  
In a telephone conversation on July 7, 2014 Mr. David Lanyi, Operations Engineer, and Mr. Kip Wainwright, Operations Training Manager, made arrangements for the NRC to inspect the licensed operator requalification program at Plant Hatch. The inspection is planned for the week of August 18, 2014, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program. It is our understanding that you have committed to maintain your plant-referenced simulator in accordance with ANSI/ANS-3.5-1985, American National Standard for Nuclear Power Plant Simulators for Use in Operator Training and Examination.
In accordance with 10 CFR 55.59, the NRC has requested that you submit by August 8, 2014, the material as specified in paragraph A of the Enclosure, in order to support the NRC's inspection program needs. The NRC has further requested that you have all items as specified in paragraph B of the Enclosure available for review for the inspectors on the first day they arrive on site. Mr. Wainwright has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number Part 55 (3150-0018), which expires on April 30, 2016.
The public reporting burden for this collection of information is estimated to average 4 hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, DC 20503.


Simulators for Use in Operator Training and Examination."
D. Vineyard                                    2 The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB approval number.
In accordance with 10 CFR 55.59, the NRC has requested that you submit by August 8, 2014, the material as specified in paragraph "A" of the Enclosure, in order to support the NRC's
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. (The Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding this inspection please contact Mr. Lanyi at (404) 997-4487, (Internet E-mail: david.lanyi@nrc.gov),
or me at (404) 997-4662, (Internet E-mail: eugene.guthrie@nrc.gov).
Sincerely,
                                              /RA: Malcolm T. Widmann for/
Eugene F. Guthrie, Chief Operations Branch Division of Reactor Safety Docket Nos.: 50-321, 50-366 License Nos.: DPR-57 and NPF-5


inspection program needs. The NRC has further requested that you have all items as specified in paragraph "B" of the Enclosure available for review for the inspectors on the first day they arrive on site. Mr. Wainwright has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.
==Enclosure:==
 
Materials Request List cc: Distribution via Listserv
This letter contains information collections that are subject to the Paperwork Reduction Act of
 
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number Part 55 (3150-0018), which expires on April 30, 2016.
The public reporting burden for this collection of information is estimated to average 4 hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-


0101), Office of Management and Budget, Washington, DC 20503.
D. Vineyard                                   2 The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB approval number.
D. Vineyard 2 The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB approval number.  
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. (The Public Electronic Reading Room).
 
Thank you for your cooperation in this matter. If you have any questions regarding this inspection please contact Mr. Lanyi at (404) 997-4487, (Internet E-mail: david.lanyi@nrc.gov),
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice, " a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. (The Public Electronic Reading Room).
or me at (404) 997-4662, (Internet E-mail: eugene.guthrie@nrc.gov).
Thank you for your cooperation in this matter. If you have any questions regarding this inspection please contact Mr. Lanyi at (404) 997-4487, (Internet E-mail:
Sincerely,
david.lanyi@nrc.gov
                                                        /RA: Malcolm T. Widmann for/
), or me at (404) 997-4662, (Internet E-mail: eugene.guthrie@nrc.gov
Eugene F. Guthrie, Chief Operations Branch Division of Reactor Safety Docket Nos.: 50-321, 50-366 License Nos.: DPR-57 and NPF-5
).
Sincerely,       /RA: Malcolm T. Widmann for/
Eugene F. Guthrie, Chief       Operations Branch       Division of Reactor Safety  
 
Docket Nos.: 50-321, 50-366 License Nos.: DPR-57 and NPF-5  


==Enclosure:==
==Enclosure:==
Materials Request List cc: Distribution via Listserv  
Materials Request List cc: Distribution via Listserv x  PUBLICLY AVAILABLE            NON-PUBLICLY AVAILABLE                    SENSITIVE      x NON-SENSITIVE ADAMS: x    Yes  ACCESSION NUMBER:_ML14192B421_______________               SUNSI REVIEW COMPLETE       FORM 665 ATTACHED OFFICE         RII:DRS         RII:DRS SIGNATURE       DRL2 VIA EMAIL   MTW FOR NAME           LANYI           GUTHRIE DATE                 7/8/2014       7/9/2014     7/ /2014       7/   /2014       7/ /2014     7/ /2014     7/ /2014 E-MAIL COPY?     YES     NO      YES     NO   YES   NO     YES     NO      YES     NO     YES   NO     YES     NO OFFICIAL    RECORD    COPY       DOCUMENT    NAME:        G:\DRSII\OBII\SITES\HATCH\REQUAL    INSPECTION INPUTS\2014\CORRESPONDENCE\HATCH REQUAL LETTER FINAL.DOCX
 
_ML14192B421_______________
SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS     SIGNATURE DRL2 VIA EMAIL MTW FOR     NAME LANYI GUTHRIE     DATE 7/8/2014 7/9/2014 7/   /2014 7/   /2014 7/   /2014 7/   /2014 7/   /2014 E-MAIL COPY?    YES NO       YES NO       YES NO      YES NO       YES NO       YES NO      YES NO Enclosure Materials Request List
 
The items listed below are necessary to support the Licensed Operator Requalification Program inspection (IP-71111.11) in August, 2014 at Plant Hatch. Items listed under "In-office inspection material" must be received in the NRC Region II office by August 8 th, 2014. Items listed under "On-site inspection material" should be ready for review upon arrival of the inspectors on August 18, 2014.  


A. In-office inspection material:
Materials Request List The items listed below are necessary to support the Licensed Operator Requalification Program inspection (IP-71111.11) in August, 2014 at Plant Hatch. Items listed under In-office inspection material must be received in the NRC Region II office by August 8th, 2014. Items listed under On-site inspection material should be ready for review upon arrival of the inspectors on August 18, 2014.
A.     In-office inspection material:
: 1. Complete list of all licensed individuals (active and inactive; RO and SRO) including license restrictions.
: 1. Complete list of all licensed individuals (active and inactive; RO and SRO) including license restrictions.
: 2. Copy of an Organizational Chart for the training department including simulator staff.
: 2. Copy of an Organizational Chart for the training department including simulator staff.
Line 66: Line 62:
: 9. A copy of site procedure(s) governing simulator configuration control, maintenance, and fidelity, including all testing methods used to fulfill ANSI/ANS-3.5-1985 requirements.
: 9. A copy of site procedure(s) governing simulator configuration control, maintenance, and fidelity, including all testing methods used to fulfill ANSI/ANS-3.5-1985 requirements.
: 10. Copy of the program evaluation of the previous biennial requalification cycle.
: 10. Copy of the program evaluation of the previous biennial requalification cycle.
B. On-site inspection material:
B.     On-site inspection material:
: 1. Requalification training attendance records for the current biennial training cycle.
: 1. Requalification training attendance records for the current biennial training cycle.
: 2. Examination results since last requalification inspection (weekly operating & written examinations); copies of examinations with pass/failure rates outside the average.  
: 2. Examination results since last requalification inspection (weekly operating & written examinations); copies of examinations with pass/failure rates outside the average.
Enclosure


2 3. Simulator scenarios and JPMs (in-plant and simulator) that have been or will be administered for this requalification exam. (exam security related item)
2
: 3. Simulator scenarios and JPMs (in-plant and simulator) that have been or will be administered for this requalification exam. (exam security related item)
: 4. All training feedback forms since the last requalification inspection.
: 4. All training feedback forms since the last requalification inspection.
: 5. Documentation regarding all remedial training conducted for examination failures since the last requalification inspection.
: 5. Documentation regarding all remedial training conducted for examination failures since the last requalification inspection.
: 6. Complete list of all individuals that reactivated their licenses since the last requalification inspection.
: 6. Complete list of all individuals that reactivated their licenses since the last requalification inspection.
: 7. Records associated with license reactivation, including:
: 7. Records associated with license reactivation, including:
: a. Documentation of time on shift under instruction. b. Security system and HP/dosimetry records for plant areas toured by reactivating individual and accompanying licensed operator.
: a. Documentation of time on shift under instruction.
: b. Security system and HP/dosimetry records for plant areas toured by reactivating individual and accompanying licensed operator.
: 8. Records providing documentation of maintenance of active license status (time on shift) for all licensed operators since last requalification inspection.
: 8. Records providing documentation of maintenance of active license status (time on shift) for all licensed operators since last requalification inspection.
: 9. Medical records for all licensed (active and inactive) operators.
: 9. Medical records for all licensed (active and inactive) operators.
: 10. Simulator maintenance and testing records, including:
: 10. Simulator maintenance and testing records, including:
: a. List of all open simulator discrepancies b. List of all simulator discrepancies closed within the past 12 months c. List of simulator performance tests
: a. List of all open simulator discrepancies
: b. List of all simulator discrepancies closed within the past 12 months
: c. List of simulator performance tests
: d. Simulator performance testing records and associated documentation}}
: d. Simulator performance testing records and associated documentation}}

Latest revision as of 02:29, 4 November 2019

Requalification Program Inspection - Plant Hatch
ML14192B421
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 07/09/2014
From: Eugene Guthrie
Division of Reactor Safety II
To: Vineyard D
Southern Nuclear Operating Co
References
Download: ML14192B421 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 July 9, 2014 Southern Nuclear Operating Company, Inc.

ATTN: Mr. David R. Vineyard Vice President Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION - PLANT HATCH

Dear Mr. Vineyard:

In a telephone conversation on July 7, 2014 Mr. David Lanyi, Operations Engineer, and Mr. Kip Wainwright, Operations Training Manager, made arrangements for the NRC to inspect the licensed operator requalification program at Plant Hatch. The inspection is planned for the week of August 18, 2014, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program. It is our understanding that you have committed to maintain your plant-referenced simulator in accordance with ANSI/ANS-3.5-1985, American National Standard for Nuclear Power Plant Simulators for Use in Operator Training and Examination.

In accordance with 10 CFR 55.59, the NRC has requested that you submit by August 8, 2014, the material as specified in paragraph A of the Enclosure, in order to support the NRC's inspection program needs. The NRC has further requested that you have all items as specified in paragraph B of the Enclosure available for review for the inspectors on the first day they arrive on site. Mr. Wainwright has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number Part 55 (3150-0018), which expires on April 30, 2016.

The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, DC 20503.

D. Vineyard 2 The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB approval number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. (The Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection please contact Mr. Lanyi at (404) 997-4487, (Internet E-mail: david.lanyi@nrc.gov),

or me at (404) 997-4662, (Internet E-mail: eugene.guthrie@nrc.gov).

Sincerely,

/RA: Malcolm T. Widmann for/

Eugene F. Guthrie, Chief Operations Branch Division of Reactor Safety Docket Nos.: 50-321, 50-366 License Nos.: DPR-57 and NPF-5

Enclosure:

Materials Request List cc: Distribution via Listserv

D. Vineyard 2 The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB approval number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. (The Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection please contact Mr. Lanyi at (404) 997-4487, (Internet E-mail: david.lanyi@nrc.gov),

or me at (404) 997-4662, (Internet E-mail: eugene.guthrie@nrc.gov).

Sincerely,

/RA: Malcolm T. Widmann for/

Eugene F. Guthrie, Chief Operations Branch Division of Reactor Safety Docket Nos.: 50-321, 50-366 License Nos.: DPR-57 and NPF-5

Enclosure:

Materials Request List cc: Distribution via Listserv x PUBLICLY AVAILABLE NON-PUBLICLY AVAILABLE SENSITIVE x NON-SENSITIVE ADAMS: x Yes ACCESSION NUMBER:_ML14192B421_______________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE DRL2 VIA EMAIL MTW FOR NAME LANYI GUTHRIE DATE 7/8/2014 7/9/2014 7/ /2014 7/ /2014 7/ /2014 7/ /2014 7/ /2014 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: G:\DRSII\OBII\SITES\HATCH\REQUAL INSPECTION INPUTS\2014\CORRESPONDENCE\HATCH REQUAL LETTER FINAL.DOCX

Materials Request List The items listed below are necessary to support the Licensed Operator Requalification Program inspection (IP-71111.11) in August, 2014 at Plant Hatch. Items listed under In-office inspection material must be received in the NRC Region II office by August 8th, 2014. Items listed under On-site inspection material should be ready for review upon arrival of the inspectors on August 18, 2014.

A. In-office inspection material:

1. Complete list of all licensed individuals (active and inactive; RO and SRO) including license restrictions.
2. Copy of an Organizational Chart for the training department including simulator staff.
3. Spreadsheets and/or test outlines which show the usage of written examination questions, JPMs, and simulator scenarios (i.e. outlines/sample plans).
4. Copy of the weekly examination schedules for the weeks that the 2014 annual operating exams will be administered, including a list of personnel scheduled for testing the week of August 18, 2014.
5. Copies of the written examinations that were administered for the last biennial requalification examination (for all weeks), including all re-take examinations.
6. Ten (10) job performance measures (JPMs), both simulator and in-plant, and six (6) simulator scenarios associated with the current annual operating test. The JPMs and scenarios to be reviewed should include those that will be administered the week of October 27, 2014, with any remaining JPMs and scenarios reviewed selected from other weeks of the annual operating test. (exam security related item)
7. Self-assessment reports, corrective action reports, and Licensee Event Reports, written since the last requalification inspection, resulting from or concerning human performance errors, including any examination security issues.
8. A copy of site procedure(s) governing the conduct (process and content) of license operator requalification training (classroom and simulator), examination development/administration, remedial training, and examination security.
9. A copy of site procedure(s) governing simulator configuration control, maintenance, and fidelity, including all testing methods used to fulfill ANSI/ANS-3.5-1985 requirements.
10. Copy of the program evaluation of the previous biennial requalification cycle.

B. On-site inspection material:

1. Requalification training attendance records for the current biennial training cycle.
2. Examination results since last requalification inspection (weekly operating & written examinations); copies of examinations with pass/failure rates outside the average.

Enclosure

2

3. Simulator scenarios and JPMs (in-plant and simulator) that have been or will be administered for this requalification exam. (exam security related item)
4. All training feedback forms since the last requalification inspection.
5. Documentation regarding all remedial training conducted for examination failures since the last requalification inspection.
6. Complete list of all individuals that reactivated their licenses since the last requalification inspection.
7. Records associated with license reactivation, including:
a. Documentation of time on shift under instruction.
b. Security system and HP/dosimetry records for plant areas toured by reactivating individual and accompanying licensed operator.
8. Records providing documentation of maintenance of active license status (time on shift) for all licensed operators since last requalification inspection.
9. Medical records for all licensed (active and inactive) operators.
10. Simulator maintenance and testing records, including:
a. List of all open simulator discrepancies
b. List of all simulator discrepancies closed within the past 12 months
c. List of simulator performance tests
d. Simulator performance testing records and associated documentation