ML15342A202: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(6 intermediate revisions by the same user not shown) | |||
Line 2: | Line 2: | ||
| number = ML15342A202 | | number = ML15342A202 | ||
| issue date = 11/03/2015 | | issue date = 11/03/2015 | ||
| title = | | title = Partial Site Release References | ||
| author name = | | author name = Vannoordennen G | ||
| author affiliation = ZionSolutions, LLC | | author affiliation = ZionSolutions, LLC | ||
| addressee name = | | addressee name = | ||
Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter:}} | {{#Wiki_filter:ZIO NSOL UTIONSLL An EnorgySolutonsCom~pany 10 CFR 50.83(b) | ||
November 3, 2015 ZS-2015-0160 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-000 1 Zion Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-304 | |||
==Subject:== | |||
Zion Station Partial Site Release References | |||
==References:== | |||
: 1) Gerard van Noordernen, ZionSolutions, Letter to U.S. Nuclear Regulatory Commission, "Zion Station Request for Partial Site Release," dated August 27, 2015 ZionSolutions, the licensee for Zion Nuclear Power Station, submitted a request to the Nuclear Regulatory Commission (NRC) to remove a portion of the site from the Part 50 licenses (License No s. DPR-39 and DPR-48) in accordance with 10 CFR 50.83 (b), "Release of a power reactor facility or site for unrestricted use," as documented in Reference 1. Following initial NRC review, an e-mail Request for Additional Information was received on October 30, 2015 requesting the following information in support of the ongoing review: | |||
S"Zion Station Historical Site Assessment" (HSA) - September 2006 c ZionSolutions ZS-LT-02, "Characterization Survey Plan," Revision 3, July 6, 2015 ZionSolutionsZS-LT-0 1, "Quality Assurance Project Plan (for Characterization and FSS)" (QAPP), Revision 2, February 10, 2014 ZionSolutions ZS-LT-03, "Survey Plan, Non-Impacted Open Land Survey Units," | |||
Revision 1, June 11, 2013 ZionSolutions Technical Support Document 14-028, "Radiological Characterization Report," Revision 0, December 15, 2014 The QAPP has been revised since Reference 1 was submitted and the current document is Revision 4 dated October 16, 2015. The current revision is included in Enclosure 1 sent with this correspondence along with the remaining four documents. Enclosure 2 contains a preflight report identifying any noncompliance issues with NRC electronic submittal guidance that could not be resolved due to the source of the information being submitted. All submitted infornation is in legible format. | |||
101 Shioh Boulevard, Zion ,L60099 (224) 789-4016 Fax: (224) 789-4008 *www.zionsoiutionscompany.com | |||
ZionSolutions, LLC ZS-201 5-0160 Page 2 of 2 There are no regulatory commitments made in this submittal. If you should have any questions regarding this submittal, please contact Robert Yetter at (224) 789-4250. | |||
Respectfully, Gerard van Noordennen Vice President Regulatory Affairs | |||
==Enclosures:== | |||
: CD containing: | |||
* "Zion Station Historical Site Assessment" (HSA) - September 2006 | |||
* ZionSolutions ZS-LT-02, "Characterization Survey Plan," Revision 3, July 6, 2015 | |||
* ZionSolutions ZS-LT-01, "Quality Assurance Project Plan (for Characterization and FS S)" (QAPP), Revision 4, October 16, 2015 | |||
* ZionSolutions ZS-LT-03, "Survey Plan, Non-Impacted Open Land Survey Units," | |||
Revision 1, June 11, 2013 | |||
* ZionSolutions Technical Support Document 14-028, "Radiological Characterization Report," Revision 0, December 15, 2014 : Preflight Report for Enclosure 1 cc: John Hickman, U.S. NRC Senior Project Manager (2 CDs of the enclosures) | |||
Regional Administrator, U.S. NRC Region III (1 CD of the enclosures) | |||
Service List (Cover letter only, no enclosures) | |||
Zion Nuclear Power Station, Unit 1 and 2 License Transfer Service List cc: | |||
Ken Robuck Alwyn C. Settles President Logistics Processing and Section Head, Nuclear Facility Inspection Disposal Group .NBureau of Nuclear Facility Safety EnergySolutions. Illinois Emergency Management Agency 299 South Main Street, 17th Floor 1011 Nordh Street, P0 Box 250 Salt Lake City, UT 84111 Mazon, IL 60444 John Sauger Kelly F. Grahn Executive VP & General Manager Senior Health Physicist, Unit Supervisor ZionSolutions, LLC Illinois Emergency Management Agency 101 Shiloh Boulevard Bureau of Radiation Safety, Environmental Zion, IL 60099 Management 245 W Roosevelt Road, Building 8, Suite 55 Gerard van Noordennen West Chicago, IL 60185 VP Regulatory Affairs ZionSolutions, LLC Kent McKenzie 101 Shiloh Boulevard Emergency Management Coordinator Zion, IL 60099 Lake County Emergency Management Agency 1303 N. Milwaukee Avenue Anthony Orawiec Libertyville, IL 60048-1308 Decommissioning Plant Manager ZionSolutions, LLC John E. Matthews 101 Shiloh Boulevard Morgan, Lewis & Bockius LLP Zion, IL 60099 1111 Pennsylvania Avenue, NW Washington, DC 20004 Dan Shrum Senior VP Regulatory Affairs EnergySolutions 299 South Main Street, 17th Floor Salt Lake City, UT 84111 Russ Workman General Counsel EnergySolutions 299 South Main Street, 17th Floor Salt Lake City, UT 84111 | |||
Enclosure 2 Preflight Report for to ZS-20 15-0160 | |||
ZionSolutions, LLC ZS-2015-0160: Enclosure 2 Page 1 of 1 This document serves as preflight report for Enclosure 1 to the letter ZS-2015-0160. The following files do not pass pre-flight criteria or do not meet NRC criteria, but text is word searchable with clarity/legibility of high quality. | |||
File Name Preflight Reso Status Rao TSD-14-028, Rev 0_Radiological Characterization Eror / Failed Document contains logos, color maps signatures, and Report scanned pages < 300 ppi, clear and legible Document contains logos, color maps (unembedded ZS-LT-0 1, Rev 4_QAPP for Characterization and FRS Error I Failed fonts), signatures, and scanned pages < 300 ppi, clear and legible Document contains logos, color maps (unembedded ZS-LT-02, Rev 3_Characterization Survey Plan Error I Failed fonts), signatures, and scanned pages < 300 ppi, clear and legible ZS-LT-03, Rev 1_Survey Plan-Non Impacted Open Err/Fie cne ae 30pi la n eil Land Survey UnitsEro/Fald Sandpgs<30piceradlgbe Document contains logos, color maps signatures, and 2006 Zion Station Historical Site Assessment Error / Failed scnepas<30piclradlgbe 2006 HSA Supplemental Documents Characterization Data Summary Report Passed Listing of Documents Reviewed Passed Listing of Survey Units Passed Summary of Results by Survey Passed | |||
ZIO NSOL UTIONSLL An EnorgySolutonsCom~pany 10 CFR 50.83(b) | |||
November 3, 2015 ZS-2015-0160 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-000 1 Zion Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-304 | |||
==Subject:== | |||
Zion Station Partial Site Release References | |||
==References:== | |||
: 1) Gerard van Noordernen, ZionSolutions, Letter to U.S. Nuclear Regulatory Commission, "Zion Station Request for Partial Site Release," dated August 27, 2015 ZionSolutions, the licensee for Zion Nuclear Power Station, submitted a request to the Nuclear Regulatory Commission (NRC) to remove a portion of the site from the Part 50 licenses (License No s. DPR-39 and DPR-48) in accordance with 10 CFR 50.83 (b), "Release of a power reactor facility or site for unrestricted use," as documented in Reference 1. Following initial NRC review, an e-mail Request for Additional Information was received on October 30, 2015 requesting the following information in support of the ongoing review: | |||
S"Zion Station Historical Site Assessment" (HSA) - September 2006 c ZionSolutions ZS-LT-02, "Characterization Survey Plan," Revision 3, July 6, 2015 ZionSolutionsZS-LT-0 1, "Quality Assurance Project Plan (for Characterization and FSS)" (QAPP), Revision 2, February 10, 2014 ZionSolutions ZS-LT-03, "Survey Plan, Non-Impacted Open Land Survey Units," | |||
Revision 1, June 11, 2013 ZionSolutions Technical Support Document 14-028, "Radiological Characterization Report," Revision 0, December 15, 2014 The QAPP has been revised since Reference 1 was submitted and the current document is Revision 4 dated October 16, 2015. The current revision is included in Enclosure 1 sent with this correspondence along with the remaining four documents. Enclosure 2 contains a preflight report identifying any noncompliance issues with NRC electronic submittal guidance that could not be resolved due to the source of the information being submitted. All submitted infornation is in legible format. | |||
101 Shioh Boulevard, Zion ,L60099 (224) 789-4016 Fax: (224) 789-4008 *www.zionsoiutionscompany.com | |||
ZionSolutions, LLC ZS-201 5-0160 Page 2 of 2 There are no regulatory commitments made in this submittal. If you should have any questions regarding this submittal, please contact Robert Yetter at (224) 789-4250. | |||
Respectfully, Gerard van Noordennen Vice President Regulatory Affairs | |||
==Enclosures:== | |||
: CD containing: | |||
* "Zion Station Historical Site Assessment" (HSA) - September 2006 | |||
* ZionSolutions ZS-LT-02, "Characterization Survey Plan," Revision 3, July 6, 2015 | |||
* ZionSolutions ZS-LT-01, "Quality Assurance Project Plan (for Characterization and FS S)" (QAPP), Revision 4, October 16, 2015 | |||
* ZionSolutions ZS-LT-03, "Survey Plan, Non-Impacted Open Land Survey Units," | |||
Revision 1, June 11, 2013 | |||
* ZionSolutions Technical Support Document 14-028, "Radiological Characterization Report," Revision 0, December 15, 2014 : Preflight Report for Enclosure 1 cc: John Hickman, U.S. NRC Senior Project Manager (2 CDs of the enclosures) | |||
Regional Administrator, U.S. NRC Region III (1 CD of the enclosures) | |||
Service List (Cover letter only, no enclosures) | |||
Zion Nuclear Power Station, Unit 1 and 2 License Transfer Service List cc: | |||
Ken Robuck Alwyn C. Settles President Logistics Processing and Section Head, Nuclear Facility Inspection Disposal Group .NBureau of Nuclear Facility Safety EnergySolutions. Illinois Emergency Management Agency 299 South Main Street, 17th Floor 1011 Nordh Street, P0 Box 250 Salt Lake City, UT 84111 Mazon, IL 60444 John Sauger Kelly F. Grahn Executive VP & General Manager Senior Health Physicist, Unit Supervisor ZionSolutions, LLC Illinois Emergency Management Agency 101 Shiloh Boulevard Bureau of Radiation Safety, Environmental Zion, IL 60099 Management 245 W Roosevelt Road, Building 8, Suite 55 Gerard van Noordennen West Chicago, IL 60185 VP Regulatory Affairs ZionSolutions, LLC Kent McKenzie 101 Shiloh Boulevard Emergency Management Coordinator Zion, IL 60099 Lake County Emergency Management Agency 1303 N. Milwaukee Avenue Anthony Orawiec Libertyville, IL 60048-1308 Decommissioning Plant Manager ZionSolutions, LLC John E. Matthews 101 Shiloh Boulevard Morgan, Lewis & Bockius LLP Zion, IL 60099 1111 Pennsylvania Avenue, NW Washington, DC 20004 Dan Shrum Senior VP Regulatory Affairs EnergySolutions 299 South Main Street, 17th Floor Salt Lake City, UT 84111 Russ Workman General Counsel EnergySolutions 299 South Main Street, 17th Floor Salt Lake City, UT 84111 | |||
Enclosure 2 Preflight Report for to ZS-20 15-0160 | |||
ZionSolutions, LLC ZS-2015-0160: Enclosure 2 Page 1 of 1 This document serves as preflight report for Enclosure 1 to the letter ZS-2015-0160. The following files do not pass pre-flight criteria or do not meet NRC criteria, but text is word searchable with clarity/legibility of high quality. | |||
File Name Preflight Reso Status Rao TSD-14-028, Rev 0_Radiological Characterization Eror / Failed Document contains logos, color maps signatures, and Report scanned pages < 300 ppi, clear and legible Document contains logos, color maps (unembedded ZS-LT-0 1, Rev 4_QAPP for Characterization and FRS Error I Failed fonts), signatures, and scanned pages < 300 ppi, clear and legible Document contains logos, color maps (unembedded ZS-LT-02, Rev 3_Characterization Survey Plan Error I Failed fonts), signatures, and scanned pages < 300 ppi, clear and legible ZS-LT-03, Rev 1_Survey Plan-Non Impacted Open Err/Fie cne ae 30pi la n eil Land Survey UnitsEro/Fald Sandpgs<30piceradlgbe Document contains logos, color maps signatures, and 2006 Zion Station Historical Site Assessment Error / Failed scnepas<30piclradlgbe 2006 HSA Supplemental Documents Characterization Data Summary Report Passed Listing of Documents Reviewed Passed Listing of Survey Units Passed Summary of Results by Survey Passed}} |
Latest revision as of 04:39, 31 October 2019
ML15342A202 | |
Person / Time | |
---|---|
Site: | Zion File:ZionSolutions icon.png |
Issue date: | 11/03/2015 |
From: | Gerard van Noordennen ZionSolutions |
To: | Document Control Desk, Office of Nuclear Material Safety and Safeguards |
Shared Package | |
ML15342A256 | List: |
References | |
ZS-2015-0160 | |
Download: ML15342A202 (5) | |
Text
ZIO NSOL UTIONSLL An EnorgySolutonsCom~pany 10 CFR 50.83(b)
November 3, 2015 ZS-2015-0160 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-000 1 Zion Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-304
Subject:
Zion Station Partial Site Release References
References:
- 1) Gerard van Noordernen, ZionSolutions, Letter to U.S. Nuclear Regulatory Commission, "Zion Station Request for Partial Site Release," dated August 27, 2015 ZionSolutions, the licensee for Zion Nuclear Power Station, submitted a request to the Nuclear Regulatory Commission (NRC) to remove a portion of the site from the Part 50 licenses (License No s. DPR-39 and DPR-48) in accordance with 10 CFR 50.83 (b), "Release of a power reactor facility or site for unrestricted use," as documented in Reference 1. Following initial NRC review, an e-mail Request for Additional Information was received on October 30, 2015 requesting the following information in support of the ongoing review:
S"Zion Station Historical Site Assessment" (HSA) - September 2006 c ZionSolutions ZS-LT-02, "Characterization Survey Plan," Revision 3, July 6, 2015 ZionSolutionsZS-LT-0 1, "Quality Assurance Project Plan (for Characterization and FSS)" (QAPP), Revision 2, February 10, 2014 ZionSolutions ZS-LT-03, "Survey Plan, Non-Impacted Open Land Survey Units,"
Revision 1, June 11, 2013 ZionSolutions Technical Support Document 14-028, "Radiological Characterization Report," Revision 0, December 15, 2014 The QAPP has been revised since Reference 1 was submitted and the current document is Revision 4 dated October 16, 2015. The current revision is included in Enclosure 1 sent with this correspondence along with the remaining four documents. Enclosure 2 contains a preflight report identifying any noncompliance issues with NRC electronic submittal guidance that could not be resolved due to the source of the information being submitted. All submitted infornation is in legible format.
101 Shioh Boulevard, Zion ,L60099 (224) 789-4016 Fax: (224) 789-4008 *www.zionsoiutionscompany.com
ZionSolutions, LLC ZS-201 5-0160 Page 2 of 2 There are no regulatory commitments made in this submittal. If you should have any questions regarding this submittal, please contact Robert Yetter at (224) 789-4250.
Respectfully, Gerard van Noordennen Vice President Regulatory Affairs
Enclosures:
- CD containing:
- "Zion Station Historical Site Assessment" (HSA) - September 2006
- ZionSolutions ZS-LT-02, "Characterization Survey Plan," Revision 3, July 6, 2015
- ZionSolutions ZS-LT-01, "Quality Assurance Project Plan (for Characterization and FS S)" (QAPP), Revision 4, October 16, 2015
- ZionSolutions ZS-LT-03, "Survey Plan, Non-Impacted Open Land Survey Units,"
Revision 1, June 11, 2013
- ZionSolutions Technical Support Document 14-028, "Radiological Characterization Report," Revision 0, December 15, 2014 : Preflight Report for Enclosure 1 cc: John Hickman, U.S. NRC Senior Project Manager (2 CDs of the enclosures)
Regional Administrator, U.S. NRC Region III (1 CD of the enclosures)
Service List (Cover letter only, no enclosures)
Zion Nuclear Power Station, Unit 1 and 2 License Transfer Service List cc:
Ken Robuck Alwyn C. Settles President Logistics Processing and Section Head, Nuclear Facility Inspection Disposal Group .NBureau of Nuclear Facility Safety EnergySolutions. Illinois Emergency Management Agency 299 South Main Street, 17th Floor 1011 Nordh Street, P0 Box 250 Salt Lake City, UT 84111 Mazon, IL 60444 John Sauger Kelly F. Grahn Executive VP & General Manager Senior Health Physicist, Unit Supervisor ZionSolutions, LLC Illinois Emergency Management Agency 101 Shiloh Boulevard Bureau of Radiation Safety, Environmental Zion, IL 60099 Management 245 W Roosevelt Road, Building 8, Suite 55 Gerard van Noordennen West Chicago, IL 60185 VP Regulatory Affairs ZionSolutions, LLC Kent McKenzie 101 Shiloh Boulevard Emergency Management Coordinator Zion, IL 60099 Lake County Emergency Management Agency 1303 N. Milwaukee Avenue Anthony Orawiec Libertyville, IL 60048-1308 Decommissioning Plant Manager ZionSolutions, LLC John E. Matthews 101 Shiloh Boulevard Morgan, Lewis & Bockius LLP Zion, IL 60099 1111 Pennsylvania Avenue, NW Washington, DC 20004 Dan Shrum Senior VP Regulatory Affairs EnergySolutions 299 South Main Street, 17th Floor Salt Lake City, UT 84111 Russ Workman General Counsel EnergySolutions 299 South Main Street, 17th Floor Salt Lake City, UT 84111
Enclosure 2 Preflight Report for to ZS-20 15-0160
ZionSolutions, LLC ZS-2015-0160: Enclosure 2 Page 1 of 1 This document serves as preflight report for Enclosure 1 to the letter ZS-2015-0160. The following files do not pass pre-flight criteria or do not meet NRC criteria, but text is word searchable with clarity/legibility of high quality.
File Name Preflight Reso Status Rao TSD-14-028, Rev 0_Radiological Characterization Eror / Failed Document contains logos, color maps signatures, and Report scanned pages < 300 ppi, clear and legible Document contains logos, color maps (unembedded ZS-LT-0 1, Rev 4_QAPP for Characterization and FRS Error I Failed fonts), signatures, and scanned pages < 300 ppi, clear and legible Document contains logos, color maps (unembedded ZS-LT-02, Rev 3_Characterization Survey Plan Error I Failed fonts), signatures, and scanned pages < 300 ppi, clear and legible ZS-LT-03, Rev 1_Survey Plan-Non Impacted Open Err/Fie cne ae 30pi la n eil Land Survey UnitsEro/Fald Sandpgs<30piceradlgbe Document contains logos, color maps signatures, and 2006 Zion Station Historical Site Assessment Error / Failed scnepas<30piclradlgbe 2006 HSA Supplemental Documents Characterization Data Summary Report Passed Listing of Documents Reviewed Passed Listing of Survey Units Passed Summary of Results by Survey Passed
ZIO NSOL UTIONSLL An EnorgySolutonsCom~pany 10 CFR 50.83(b)
November 3, 2015 ZS-2015-0160 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-000 1 Zion Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-304
Subject:
Zion Station Partial Site Release References
References:
- 1) Gerard van Noordernen, ZionSolutions, Letter to U.S. Nuclear Regulatory Commission, "Zion Station Request for Partial Site Release," dated August 27, 2015 ZionSolutions, the licensee for Zion Nuclear Power Station, submitted a request to the Nuclear Regulatory Commission (NRC) to remove a portion of the site from the Part 50 licenses (License No s. DPR-39 and DPR-48) in accordance with 10 CFR 50.83 (b), "Release of a power reactor facility or site for unrestricted use," as documented in Reference 1. Following initial NRC review, an e-mail Request for Additional Information was received on October 30, 2015 requesting the following information in support of the ongoing review:
S"Zion Station Historical Site Assessment" (HSA) - September 2006 c ZionSolutions ZS-LT-02, "Characterization Survey Plan," Revision 3, July 6, 2015 ZionSolutionsZS-LT-0 1, "Quality Assurance Project Plan (for Characterization and FSS)" (QAPP), Revision 2, February 10, 2014 ZionSolutions ZS-LT-03, "Survey Plan, Non-Impacted Open Land Survey Units,"
Revision 1, June 11, 2013 ZionSolutions Technical Support Document 14-028, "Radiological Characterization Report," Revision 0, December 15, 2014 The QAPP has been revised since Reference 1 was submitted and the current document is Revision 4 dated October 16, 2015. The current revision is included in Enclosure 1 sent with this correspondence along with the remaining four documents. Enclosure 2 contains a preflight report identifying any noncompliance issues with NRC electronic submittal guidance that could not be resolved due to the source of the information being submitted. All submitted infornation is in legible format.
101 Shioh Boulevard, Zion ,L60099 (224) 789-4016 Fax: (224) 789-4008 *www.zionsoiutionscompany.com
ZionSolutions, LLC ZS-201 5-0160 Page 2 of 2 There are no regulatory commitments made in this submittal. If you should have any questions regarding this submittal, please contact Robert Yetter at (224) 789-4250.
Respectfully, Gerard van Noordennen Vice President Regulatory Affairs
Enclosures:
- CD containing:
- "Zion Station Historical Site Assessment" (HSA) - September 2006
- ZionSolutions ZS-LT-02, "Characterization Survey Plan," Revision 3, July 6, 2015
- ZionSolutions ZS-LT-01, "Quality Assurance Project Plan (for Characterization and FS S)" (QAPP), Revision 4, October 16, 2015
- ZionSolutions ZS-LT-03, "Survey Plan, Non-Impacted Open Land Survey Units,"
Revision 1, June 11, 2013
- ZionSolutions Technical Support Document 14-028, "Radiological Characterization Report," Revision 0, December 15, 2014 : Preflight Report for Enclosure 1 cc: John Hickman, U.S. NRC Senior Project Manager (2 CDs of the enclosures)
Regional Administrator, U.S. NRC Region III (1 CD of the enclosures)
Service List (Cover letter only, no enclosures)
Zion Nuclear Power Station, Unit 1 and 2 License Transfer Service List cc:
Ken Robuck Alwyn C. Settles President Logistics Processing and Section Head, Nuclear Facility Inspection Disposal Group .NBureau of Nuclear Facility Safety EnergySolutions. Illinois Emergency Management Agency 299 South Main Street, 17th Floor 1011 Nordh Street, P0 Box 250 Salt Lake City, UT 84111 Mazon, IL 60444 John Sauger Kelly F. Grahn Executive VP & General Manager Senior Health Physicist, Unit Supervisor ZionSolutions, LLC Illinois Emergency Management Agency 101 Shiloh Boulevard Bureau of Radiation Safety, Environmental Zion, IL 60099 Management 245 W Roosevelt Road, Building 8, Suite 55 Gerard van Noordennen West Chicago, IL 60185 VP Regulatory Affairs ZionSolutions, LLC Kent McKenzie 101 Shiloh Boulevard Emergency Management Coordinator Zion, IL 60099 Lake County Emergency Management Agency 1303 N. Milwaukee Avenue Anthony Orawiec Libertyville, IL 60048-1308 Decommissioning Plant Manager ZionSolutions, LLC John E. Matthews 101 Shiloh Boulevard Morgan, Lewis & Bockius LLP Zion, IL 60099 1111 Pennsylvania Avenue, NW Washington, DC 20004 Dan Shrum Senior VP Regulatory Affairs EnergySolutions 299 South Main Street, 17th Floor Salt Lake City, UT 84111 Russ Workman General Counsel EnergySolutions 299 South Main Street, 17th Floor Salt Lake City, UT 84111
Enclosure 2 Preflight Report for to ZS-20 15-0160
ZionSolutions, LLC ZS-2015-0160: Enclosure 2 Page 1 of 1 This document serves as preflight report for Enclosure 1 to the letter ZS-2015-0160. The following files do not pass pre-flight criteria or do not meet NRC criteria, but text is word searchable with clarity/legibility of high quality.
File Name Preflight Reso Status Rao TSD-14-028, Rev 0_Radiological Characterization Eror / Failed Document contains logos, color maps signatures, and Report scanned pages < 300 ppi, clear and legible Document contains logos, color maps (unembedded ZS-LT-0 1, Rev 4_QAPP for Characterization and FRS Error I Failed fonts), signatures, and scanned pages < 300 ppi, clear and legible Document contains logos, color maps (unembedded ZS-LT-02, Rev 3_Characterization Survey Plan Error I Failed fonts), signatures, and scanned pages < 300 ppi, clear and legible ZS-LT-03, Rev 1_Survey Plan-Non Impacted Open Err/Fie cne ae 30pi la n eil Land Survey UnitsEro/Fald Sandpgs<30piceradlgbe Document contains logos, color maps signatures, and 2006 Zion Station Historical Site Assessment Error / Failed scnepas<30piclradlgbe 2006 HSA Supplemental Documents Characterization Data Summary Report Passed Listing of Documents Reviewed Passed Listing of Survey Units Passed Summary of Results by Survey Passed