ML22306A134

From kanterella
Jump to navigation Jump to search
Receipt of Information and License Amendment Request for the Zion Nuclear Power Station, Units 1 and 2, Docket Nos. 50-295 and 50-304
ML22306A134
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 11/09/2022
From: Kimberly Conway
Reactor Decommissioning Branch
To: Sauger J
ZionSolutions
References
Download: ML22306A134 (3)


Text

November 9, 2022 Mr. John Sauger General Manager Zion Restoration Project ZionSolutions, LLC 101 Shiloh Boulevard Zion, IL 60099-2797

SUBJECT:

RECEIPT OF INFORMATION AND LICENSE AMENDMENT REQUEST FOR THE ZION NUCLEAR POWER STATION, UNITS 1 AND 2, DOCKET NOS. 50-295 AND 50-304

Dear John Sauger:

By email dated February 8, 2022 (ML22040A116), based on the Zion Nuclear Power Station (ZNPS) schedule for remaining site work and surveys provided by EnergySolutions (the licensee), the NRC staff placed the review of ZNPS Final Status Survey Reports on hold pending receipt of all survey result reports from areas re-surveyed since April 2021, confirmation that all site work is finished, and receipt of complete and adequate responses to the 11 RAIs that were issued as a follow up to NRC's April 2021 inspection activities (ML21231A187 and ML21238A067).

By letter dated March 8, 2022 (ML22069A329) the licensee submitted its responses to the 11 RAIs. By letter dated March 23, 2022, the licensee also submitted a License Amendment Request (LAR) to the ZNPS License Termination Plan (ML22084A058). A follow-up letter dated September 30, 2022 (ML22279A993) transmitted the survey reports for areas where FSS was reperformed due to removal of subsurface concrete material and affirmed that all site work is complete.

Accordingly, the NRC staff acknowledges receipt of the items outlined in the February 8, 2022, email. The NRC staff intends to restart its reviews related to ZNPS on November 14, 2022, at which time the staff will begin review of the LAR with the goal of issuing an acceptance determination no later than January 13, 2023. Upon completion of the acceptance review, if the NRC determines that the submittal is sufficient to begin a detailed technical review of the LAR, a review schedule for the remaining actions associated with the ZNPS project completion will also be provided.

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs ADAMS. ADAMS is accessible from the NRC website at https://www.nrc.gov/reading-rm/adams.html.

J. Sauger If you have any questions, please call me at (301) 415-1335 or email me at Kimberly.Conway@nrc.gov.

Sincerely, Signed by Conway, Kimberly on 11/09/22 Kim Conway, Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Material Safety and Safeguards Docket Nos. 50-295 and 50-304 License Nos. DPR-39 and DPR-48 Cc: Zion ListServ

Ltr ML22306A134 OFFICE NMSS/DUWP/RDB NMSS/DUWP/RDB NMSS/DUWP/RDB NAME KConway KC SAnderson SA KConway KC DATE Nov 7, 2022 Nov 7, 2022 Nov 9, 2022