MONTHYEARML23356A0072023-12-22022 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-122, Amendment No. 15 to Indemnity Agreement No. B-592023-11-29029 November 2023 Amendment No. 15 to Indemnity Agreement No. B-59 ML23291A0802023-11-16016 November 2023 Issuance of Conforming Amendments Regarding Direct Transfer of DPR-39 and DPR-48 Facility Operating Licenses from Zionsolutions, LLC to Constellation Energy Generation LLC ML23286A3132023-11-14014 November 2023 EPA Phase 2 Closure Letter 10-13-23 ML23286A3092023-11-0808 November 2023 Partial Site Release, Zion Nuclear Power Station, Units 1 and 2 ML23310A3132023-11-0808 November 2023 Cover Letter, S.Anderson, NRC to J.Sauger, Energysolutions, Remaining Final Status Surveys RS-23-116, Supplemental Information in Response to Order Consenting to License Transfers and Approval of Conforming License Amendments2023-11-0808 November 2023 Supplemental Information in Response to Order Consenting to License Transfers and Approval of Conforming License Amendments ML23310A1082023-11-0303 November 2023 Confirmatory Survey Report 2023 IR 05000295/20230012023-11-0202 November 2023 NRC Inspection Report No. 05000295/2023001(DRSS); 05000304/2023001 (Drss) - Zion Nuclear Power Station ML23251A0712023-09-0808 September 2023 Confirmatory Survey Extent of Condition Review ML23237B4132023-08-25025 August 2023 Response to Summary of May 4, 2023, Clarification Meeting Regarding the Partial Site Release Request ML23186A1902023-07-0606 July 2023 Review of Zion Solutions Responses to Requests for Additional Information Related to Zion Nuclear Power Station, Units 1 and 2 Decommissioning and Estimated Partial Site Release Review Schedule ZS-2023-0012, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-12012 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report ML23117A3692023-04-26026 April 2023 Annual Radioactive Effluent Release Report ML23116A2012023-04-24024 April 2023 Occupational Radiation Exposure Annual Report for 2022 ML23094A1292023-03-30030 March 2023 Annual Property Insurance Status Report ML23094A1322023-03-29029 March 2023 Decommissioning Funding Status Report for Shutdown Reactor ML23068A0122023-03-0303 March 2023 Withdrawal of Zion License Amendment Request for the License Termination Plan ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000295/20220012023-01-27027 January 2023 NRC Inspection Report 05000295/2022001 (Drss); 05000304/2022001 (Drss) ML23024A0122023-01-26026 January 2023 Letter to Energysolutions Transmitting Threshold Determination for Merger/Restructuring ML22308A1762022-11-17017 November 2022 J. Sauger Letter Regarding Zion License Transfer Order Fourth Extension ML22313A0562022-11-17017 November 2022 Audit Report - Letter to J Sauger ML22306A1342022-11-0909 November 2022 Receipt of Information and License Amendment Request for the Zion Nuclear Power Station, Units 1 and 2, Docket Nos. 50-295 and 50-304 RS-22-113, Updated ISFSI Decommissioning Funding Plan for Zion Nuclear Power Station2022-10-26026 October 2022 Updated ISFSI Decommissioning Funding Plan for Zion Nuclear Power Station ML22294A1622022-10-19019 October 2022 Request for Extension of Order Approving Transfer of the License for Zion Nuclear Power Station, Units 1 and 2, from Zionsolutions, LLC to Constellation Energy Company, LLC ML22293A4332022-10-17017 October 2022 Response to NRC Staff Questions Raised During the Regulatory Audit of RAI Responses Conducted July 19-20, 2022, and August 24-25, 2022 ML22273A1452022-10-0404 October 2022 U.S. NRC Analysis of Zion Solutions, LLC Decommissioning Funding Status Report for the Zion Nuclear Power Station Units 1 and 2 ML22279A9932022-09-30030 September 2022 Revised Final Status Survey Release Records, Final Reports, and Discrete Radioactive Particle Survey Report Technical Support Document ML22237A0952022-08-23023 August 2022 Revised Final Status Survey Release Records ML22200A0112022-07-19019 July 2022 Letter to J. Sauger, Zionsolutions, from K. Conway, NRC, - Regulatory Audit Plan Re Zionsolutions' Response to RAI Related to Partial Site Release and Recent Site Survey Activities ML22111A1872022-04-0606 April 2022 Technical Support Document 2022-001, Discrete Radioactive Particle Survey Report, Revision 1 NMP1L3458, Constellation Energy Generation, LLC, Annual Property Insurance Status Report2022-04-0101 April 2022 Constellation Energy Generation, LLC, Annual Property Insurance Status Report ML22089A0982022-03-28028 March 2022 Revised Response to Request for Additional Information Related to Partial Site Release and Recent Site Survey Activities ML22089A0262022-03-28028 March 2022 Technical Support Document 2022-001, Discrete Radioactive Particle Survey Report, Revision 0 ZS-2022-0008, Report on Status of Decommissioning Funding for Shutdown Reactors2022-03-28028 March 2022 Report on Status of Decommissioning Funding for Shutdown Reactors ML22087A0052022-03-24024 March 2022 Annual Property Insurance Status Report ZS-2022-0001, License Amendment Request for the License Termination Plan2022-03-23023 March 2022 License Amendment Request for the License Termination Plan ML22068A0462022-03-14014 March 2022 Independent Spent Fuel Storage Installation Security Inspection Report 07201037/2022401 ML22069A3292022-03-0808 March 2022 Response to Request for Additional Information Related to Partial Site Release and Recent Site Survey Activities, and Notification of Foundation Pad Discovery RS-22-023, Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement2022-02-23023 February 2022 Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement IR 05000295/20210012022-02-22022 February 2022 NRC Inspection Report No. 05000295/2021001(DNMS); 05000304/2021001(DNMS) ML22021B6592022-02-0101 February 2022 Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000) (Letter) JAFP-22-0010, Supplemental Information in Response to Order Consenting to License Transfers and Approval of Draft Conforming License Amendments2022-01-24024 January 2022 Supplemental Information in Response to Order Consenting to License Transfers and Approval of Draft Conforming License Amendments ML22027A5752022-01-19019 January 2022 License Transfer to Constellation Energy Generation, LLC for Zion Nuclear Generating Station RS-21-121, Proposed Changes to Decommissioning Trust Agreements and Master Terms2021-12-15015 December 2021 Proposed Changes to Decommissioning Trust Agreements and Master Terms ML21277A2482021-11-16016 November 2021 Letter with Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (Public Version) ML21302A0692021-11-0808 November 2021 Letter to T. Rielly, Vista 360, from K. Conway, NRC, Re Exelon Notice of Disbursement from Decommissioning Trusts for Zion Units 1 and 2 2023-09-08
[Table view] Category:Schedule and Calendars
[Table view] |
Text
July 6, 2023 John T. Sauger, General Manager Zion Restoration Project ZionSolutions, LLC 101 Shiloh Boulevard Zion, IL 60099-2797
SUBJECT:
REVIEW OF ZIONSOLUTIONS RESPONSES TO REQUESTS FOR ADDITIONAL INFORMATION RELATED TO ZION NUCLEAR POWER STATION, UNITS 1 AND 2 DECOMMISSIONING AND ESTIMATED PARTIAL SITE RELEASE REVIEW SCHEDULE
Dear John Sauger:
The purpose of this letter is to provide the status of the U.S. Nuclear Regulatory Commission (NRC) staffs evaluation of the ZionSolutions, LLC (ZS or the Licensee) March 8, 2022, responses (Agencywide Documents Access and Management System Accession (ADAMS) No.
ML22069A329) to 11 requests for additional information (RAIs) issued on August 19, 2021, (ML21231A187) and October 14, 2021 (ML21238A067). Additionally, based on the currently available information, this letter provides the NRC plans for conducting a Confirmatory Survey.
This letter also provides the estimated review schedule which outlines the steps to complete the review of the ZS Partial Site Release (PSR) request dated June 5, 2020, (ML20164A096) for the Zion Nuclear Power Station, Units 1 and 2 (ZNPS).
Status of Responses to Request for Additional Information The RAIs, mentioned above, were issued because additional information was needed to complete the NRC staffs review of the Final Status Survey Reports (FSSRs) after the discrete radioactive particles (DRPs) were found during the April 2021 Confirmatory Survey at ZNPS.
When evaluating these RAI responses, the NRC staff considered the information gained from the NRC 2022 audit (ML22313A053); the ZSs September 30, 2022 (ML22279A993) assertion that all ZS has submitted all documents for license termination, the October 17, 2022 (ML22293A431) revised RAI 1-g response, the ZS response to audit questions (ML22293A432), and the clarifying information provided by ZS at the May 4, 2023, NRC-ZS clarification meeting. At this time the NRC has no further questions on the RAI responses; however, the NRC may revisit them, as needed, based on the results of the Confirmatory Survey.
Confirmatory Survey NRC considered the RAI responses and other the information submitted by ZS, as described above, to risk-inform its next steps for the completion of the PSR review. The NRCs plans to conduct a Confirmatory Survey are summarized below. The NRC believes this approach will be effective and efficient to complete the PSR review by allowing the staff to analyze additional independent data. More coordination with ZS will be needed in the next month for logistic planning purposes. The estimated PSR review schedule then follows.
The Confirmatory Survey will identify areas where it believes there are remaining survey
information gaps and independently develop a sampling and analysis plan for DRPs to verify whether DRP identification and remediation at ZNPS were effective. The NRC plans to conduct both surface surveys and subsurface sampling. Subsurface data are necessary for dose compliance modeling demonstration. Also, sampling of certain areas of the subsurface will assist in verifying ZS contamination control practices. The NRC staff believes that the Confirmatory Survey will also serve to verify FSS survey results.
Concurrent with the Confirmatory Survey, the NRC intends to resume its review of all the submitted FSSRs for non-DRPs. The NRC will determine whether any survey units must be resurveyed for final status by ZS to address DRPs of concern or whether the NRC will revisit RAI responses 1 through 11, as informed by the results of the Confirmatory Survey.
Estimated PSR Review Schedule The estimated schedule for completing the PSR request is shown below. It includes NRC FSSR reviews, the Confirmatory Survey, and other necessary steps to complete the PSR request.
The NRC staff will try to complete the PSR review no later than February 28, 2024, with a full time equivalent (FTE) estimate of approximate 800 hours0.00926 days <br />0.222 hours <br />0.00132 weeks <br />3.044e-4 months <br />, not including the Confirmatory Survey.
Based on the results of the Confirmatory Survey, NRC will reevaluate whether the review schedule should be modified. If there are emergent complexities or challenges in our review, such unanticipated addition of scope to the review that would cause changes to the initial forecasted completion date, or delays in the Confirmatory Survey or requirement for ZS to re-perform FSS for certain survey units, the reasons for the changes, along with a new estimate, will be communicated during the routine interactions with the assigned project manager.
May - August: NRC Review of FSSRs for non-DRP and develop draft Safety Evaluation Reports (SERs) for FSS submittals May - June: Preparation for Confirmatory Survey June - August: Confirmatory Survey and Evaluation August: Evaluation of Information/Data Needs Provided No Additional Data Needs based on Confirmatory Survey(s)
June: Begin completing draft SER for PSR to include any update on waste disposition and insurance information September - Finalize SERs for FSSR Reviews December: As needed, Environmental Protection Agency-NRC Memorandum of Understanding Coordination and Finality on Decommissioning and Decontamination of Contaminated Sites (67 FR 65375, 65375-65379)
January- February 2024: Final SER for PSR During the review of FSSRs and development of Final SER (May-December 2023), there is likely a need for clarification calls or publicly noticed calls. This will require a high level of commitment to resources and quick turnaround on information requests so as not to impact the review schedule.
In accordance with 10 CFR 2.390 of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter is available for inspection at the Public Document Room Monday-Friday by appointment or electronically from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC Web site at https://www.nrc.gov/reading-rm/adams.html. To schedule an appointment to visit the Public Document Room, please email
PDR.Resource@nrc.gov or call 1-800-397-4209.
If you have any questions, please contact me by phone at 301-415-6822, or by email at Amy.Snyder@nrc.gov.
Sincerely, Signed by Snyder, Amy on 07/06/23 Amy M. Snyder, Senior Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Material Safety and Safeguards Docket Nos.: 50-295 and 50-304 A.C. Hazelhoff, Energy Solutions, achazelhoff@energysolutions.com Distribution: Zion Listserv
ML23186A190 OFFICE NMSS/DUWP/RDB NMSS/DUWP/RDB NMSS/DUWP/RDB NAME ASnyder SAnderson ASnyder DATE 6/8/23 7/5/23 7/6/23