ML16222A747: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 08/09/2016 | | issue date = 08/09/2016 | ||
| title = Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection | | title = Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection | ||
| author name = Masters A | | author name = Masters A | ||
| author affiliation = NRC/RGN-II/DRP/RPB7 | | author affiliation = NRC/RGN-II/DRP/RPB7 | ||
| addressee name = Henderson K | | addressee name = Henderson K | ||
Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVE N.E., SUITE 1200 | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVE N.E., SUITE 1200 ATLANTA, GEORGIA 30303 August 9, 2016 Mr. Kelvin Henderson Site Vice President Duke Energy Carolinas, LLC Catawba Nuclear Station 4800 Concord Road York, SC 29745-9635 | ||
Mr. Kelvin Henderson Site Vice President | |||
Duke Energy Carolinas, LLC Catawba Nuclear Station 4800 Concord Road | |||
York, SC 29745-9635 | |||
==SUBJECT:== | ==SUBJECT:== | ||
CATAWBA NUCLEAR STATION - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION FOR NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION | CATAWBA NUCLEAR STATION - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION FOR NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION | ||
==Dear Mr. Henderson:== | ==Dear Mr. Henderson:== | ||
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC) Region II staff will conduct a problem identification and resolution (PI&R) inspection at your Catawba Nuclear Station during the weeks of October 24 - 28 and November 7 - 10, 2016. | The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC) | ||
The inspection team will be led by Mrs. Jannette Worosilo, a Senior Project Engineer, from the | Region II staff will conduct a problem identification and resolution (PI&R) inspection at your Catawba Nuclear Station during the weeks of October 24 - 28 and November 7 - 10, 2016. | ||
The inspection team will be led by Mrs. Jannette Worosilo, a Senior Project Engineer, from the NRCs Region II office. This inspection will be conducted in accordance with the baseline inspection procedure, Procedure 71152, Problem Identification and Resolution, effective February 26, 2015. | |||
The biennial PI&R inspection and assessment of the licensees Corrective Action Program (CAP) complements and expands upon the resident baseline inspections of routine daily screening of all corrective action program issues, quarterly focused issue reviews, and semiannual trend PI&R reviews. | |||
On July 7, 2016, Mrs. Worosilo confirmed with Ms. Sherry Andrews, of your staff, arrangements for the two-week onsite inspection. | |||
The enclosure lists documents that will be needed prior to the inspection. Please have the referenced information available no later than September 26, 2016. Contact Mrs. Worosilo with any questions concerning the requested information. The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for inspection preparation. | |||
If additional documents are needed, they will be requested when identified. Prior to the onsite inspection, Mrs. Worosilo will discuss with your staff the following inspection support administrative details: Availability of knowledgeable plant engineering and licensing personnel to serve as points of contact during the inspection; method of tracking inspector requests during the inspection; access to licensee computers; working space; arrangements for site access; and other applicable information. | |||
K. Henderson 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number. | |||
Thank you for your cooperation in this matter. If you have any questions regarding the information requested or the inspection, please contact Mrs. Worosilo at (404) 997-4485. | |||
Sincerely, | |||
/RA/ | |||
Anthony D. Masters, Chief Reactor Projects Branch 7 Division of Reactor Projects Docket No. 50-413, 50-414 License No. NPF-35, NPF-52 | |||
==Enclosure:== | |||
Information Request for Catawba Nuclear Station Problem Identification and Resolution Inspections cc Distribution via ListServ | |||
ML16222A747 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE JGW1 RRR1 ADM2 NAME JWorosilo RRodriguez AMasters DATE 8/9/2016 8/9/2016 8/9/2016 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO | |||
K. Henderson 3 Letter to Kelvin Henderson from Anthony D. Masters dated August 9, 2016 | |||
==SUBJECT:== | ==SUBJECT:== | ||
CATAWBA NUCLEAR STATION - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION FOR NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION DISTRIBUTION | CATAWBA NUCLEAR STATION - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION FOR NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION DISTRIBUTION: | ||
D. Gamberoni, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMCatawba Resource | |||
INFORMATION REQUEST FOR CATAWBA NUCLEAR STATION PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION (October 24 - 28 and November 7 - 10, 2016) | |||
Note: Unless otherwise noted, the information requested below corresponds to documents generated since October 1, 2014. Please provide the requested documents in electronic format. If the information is not available in electronic format, please contact the inspection team leader to coordinate other available methods to provide the information. | |||
Note: | |||
: 1. Copies of the corporate and site level procedures and sub-tier procedures associated with the corrective action program. This should include procedures related to: | : 1. Copies of the corporate and site level procedures and sub-tier procedures associated with the corrective action program. This should include procedures related to: | ||
a) | a) Corrective action process b) Cause evaluation c) Operating experience program d) Employee concerns program e) Self-assessment program f) Maintenance rule program and implementing procedures g) Operability determination process h) Degraded/non-conforming condition process (e.g., RIS 2005-20) i) System health process or equivalent equipment reliability improvement programs j) Preventive maintenance deferral If any of the procedures requested above were revised after October 1, 2014, please provide (or have available) copies of all revisions during the onsite inspection. | ||
: 2. List of top ten risk-significant systems, top ten risk-significant components for each one of the top ten risk-significant systems, and top ten risk-significant operator manual actions. | : 2. List of top ten risk-significant systems, top ten risk-significant components for each one of the top ten risk-significant systems, and top ten risk-significant operator manual actions. | ||
: 3. List of all Condition Reports (CRs) initiated including the following information for each CR: | : 3. List of all Condition Reports (CRs) initiated including the following information for each CR: | ||
a) CR number b) Brief, but complete problem description c) Priority or level d) Affected system e) Affected component f) Responsible plant department g) CR completion status If possible, provide this list in a format compatible with spreadsheet software (example shown below): | |||
CR # Problem Priority System Component Org Status CR001 A RHR Pump 2 RHR 2-RHR- ENG Open failed flow criteria PMP-A per SR 5.0.5.4 Enclosure | |||
2 | |||
: 4. List of outstanding corrective actions including the following information for each action: | |||
a) | a) Corrective action number b) Corrective action type (e.g., corrective action to prevent recurrence, enhancement, maintenance rule evaluation, etc) c) Brief, but complete corrective action description d) Associated CR number e) Corrective action initiation date f) Number of Extensions g) Corrective action due date h) Completion status If possible, provide this list in a format compatible with spreadsheet software (example shown below): | ||
Corrective Type Description CR Initiation Extensions Due Status Action # Date Date 25 CAPR Revise CR0058 01/05/12 2 06/15/12 Closed Procedure NGK-003-4585 | |||
: 5. List of control room deficiencies with a brief description and corresponding CR and/or work order (WO) number. | |||
: 6. List of operator workarounds and operator burdens with a brief description and corresponding CR number. | |||
: 7. List of all currently extended or overdue CRs, sorted by initiation date, with the following information: | |||
a) CR number b) Priority or Significance c) CR title and short description | |||
: 8. List of all CRs that have been voided or cancelled. Please provide the following information for each CR: | |||
a) CR number b) Brief, but complete problem description c) Reason voided or cancelled | |||
: 9. List of all structures, systems, and components (SSCs) which were classified as (a)(1) in accordance with the Maintenance Rule since October 2014. Please include the following information for each system in (a)(1): | |||
a) Date of classification in (a)(1) b) Reason for being placed in (a)(1) c) Planned actions and their status | |||
3 | |||
: 10. List of Maintenance Preventable Functional Failures (MPFFs) of risk-significant systems. | |||
Please include actions completed and current status. | |||
: | |||
: 11. List of corrective maintenance WOs. Please include the following information for each WO: | : 11. List of corrective maintenance WOs. Please include the following information for each WO: | ||
a) | a) WO number b) Brief, but complete work description c) Affected system and components d) Date of initiation e) Date of completion (if completed) | ||
If possible, provide this list in a format compatible with spreadsheet software (example shown below): | If possible, provide this list in a format compatible with spreadsheet software (example shown below): | ||
Work | Work Description System Component Initiation Due Status Order # Date Date WO01345 Replace breaker SI 2A-SI-PMP, 01/05/12 03/15/12 Closed 2A-BKR-08-BB4 for BKR-08-BB4 2A SI Pump. | ||
: 12. Corrective action closeout packages, including CRs with description of corrective actions, for all NRC findings/violations and all licensee identified violations (LIVs). Please include a cross reference linking NRC findings/violations and LIVs to appropriate CR numbers. | : 12. Corrective action closeout packages, including CRs with description of corrective actions, for all NRC findings/violations and all licensee identified violations (LIVs). | ||
Please include a cross reference linking NRC findings/violations and LIVs to appropriate CR numbers. | |||
: 13. Corrective action closeout packages, including CRs with description of corrective actions, for all licensee event reports (LERs) issued. Please include a cross reference linking LER number to appropriate CR number. | : 13. Corrective action closeout packages, including CRs with description of corrective actions, for all licensee event reports (LERs) issued. Please include a cross reference linking LER number to appropriate CR number. | ||
: 14. List of all NRC generic communications (e.g., Information Notices, Generic Letters, etc.) and industry operating experience (OE) documents (e.g., Part 21 reports, vendor information letters, information from other sites, etc.,) evaluated by the site for applicability to the station, regardless of the determination of applicability. Please include the reference number (e.g., CR number) for the documents that evaluated the aforementioned OE information. | : 14. List of all NRC generic communications (e.g., Information Notices, Generic Letters, etc.) | ||
and industry operating experience (OE) documents (e.g., Part 21 reports, vendor information letters, information from other sites, etc.,) evaluated by the site for applicability to the station, regardless of the determination of applicability. Please include the reference number (e.g., CR number) for the documents that evaluated the aforementioned OE information. | |||
: 15. Copies of all quality assurance audits and/or assessments issued, including the last two audits/assessments of the corrective action program. | : 15. Copies of all quality assurance audits and/or assessments issued, including the last two audits/assessments of the corrective action program. | ||
: 16. Copies of all department self-assessments. | : 16. Copies of all department self-assessments. | ||
: 17. Copy of the most recent integrated plant trend report, departmental trend report(s), and corrective action trend report(s), | : 17. Copy of the most recent integrated plant trend report, departmental trend report(s), and corrective action trend report(s), including any human performance and equipment reliability trends. | ||
4 | 4 | ||
: 19. Please provide a list of routine meetings involving the CAP to be held while team is onsite. 20. List of CRs related to equipment aging issues in the top ten risk significant systems since October 1, 2013, (e.g., system erosion and/or corrosion problems; electronic component aging or obsolescence of circuit boards, power supplies, relays, etc.; | : 18. Copy of the latest Corrective Action Program statistics (if exists) such as the number of CRs initiated by department, human performance errors by department, and others as may be available. | ||
: 19. Please provide a list of routine meetings involving the CAP to be held while team is onsite. | |||
: 20. List of CRs related to equipment aging issues in the top ten risk significant systems since October 1, 2013, (e.g., system erosion and/or corrosion problems; electronic component aging or obsolescence of circuit boards, power supplies, relays, etc.; | |||
environmental qualification). Please provide the following information for each CR: | environmental qualification). Please provide the following information for each CR: | ||
a) | a) CR number b) Priority c) CR problem description | ||
: 21. If performed, please provide any recent self-assessment of the site safety culture. | : 21. If performed, please provide any recent self-assessment of the site safety culture. | ||
: 22. Copies of corrective action program documents related to cross-cutting issues (human performance, problem identification and resolution, and safety conscious work environment) identified via trending, self-assessments, safety review committee or other oversight methods. | : 22. Copies of corrective action program documents related to cross-cutting issues (human performance, problem identification and resolution, and safety conscious work environment) identified via trending, self-assessments, safety review committee or other oversight methods. |
Latest revision as of 15:15, 30 October 2019
ML16222A747 | |
Person / Time | |
---|---|
Site: | Catawba |
Issue date: | 08/09/2016 |
From: | Masters A Reactor Projects Branch 7 |
To: | Henderson K Duke Energy Carolinas |
Betty Hitchuk | |
References | |
Download: ML16222A747 (8) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVE N.E., SUITE 1200 ATLANTA, GEORGIA 30303 August 9, 2016 Mr. Kelvin Henderson Site Vice President Duke Energy Carolinas, LLC Catawba Nuclear Station 4800 Concord Road York, SC 29745-9635
SUBJECT:
CATAWBA NUCLEAR STATION - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION FOR NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION
Dear Mr. Henderson:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a problem identification and resolution (PI&R) inspection at your Catawba Nuclear Station during the weeks of October 24 - 28 and November 7 - 10, 2016.
The inspection team will be led by Mrs. Jannette Worosilo, a Senior Project Engineer, from the NRCs Region II office. This inspection will be conducted in accordance with the baseline inspection procedure, Procedure 71152, Problem Identification and Resolution, effective February 26, 2015.
The biennial PI&R inspection and assessment of the licensees Corrective Action Program (CAP) complements and expands upon the resident baseline inspections of routine daily screening of all corrective action program issues, quarterly focused issue reviews, and semiannual trend PI&R reviews.
On July 7, 2016, Mrs. Worosilo confirmed with Ms. Sherry Andrews, of your staff, arrangements for the two-week onsite inspection.
The enclosure lists documents that will be needed prior to the inspection. Please have the referenced information available no later than September 26, 2016. Contact Mrs. Worosilo with any questions concerning the requested information. The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for inspection preparation.
If additional documents are needed, they will be requested when identified. Prior to the onsite inspection, Mrs. Worosilo will discuss with your staff the following inspection support administrative details: Availability of knowledgeable plant engineering and licensing personnel to serve as points of contact during the inspection; method of tracking inspector requests during the inspection; access to licensee computers; working space; arrangements for site access; and other applicable information.
K. Henderson 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
Thank you for your cooperation in this matter. If you have any questions regarding the information requested or the inspection, please contact Mrs. Worosilo at (404) 997-4485.
Sincerely,
/RA/
Anthony D. Masters, Chief Reactor Projects Branch 7 Division of Reactor Projects Docket No. 50-413, 50-414 License No. NPF-35, NPF-52
Enclosure:
Information Request for Catawba Nuclear Station Problem Identification and Resolution Inspections cc Distribution via ListServ
ML16222A747 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE JGW1 RRR1 ADM2 NAME JWorosilo RRodriguez AMasters DATE 8/9/2016 8/9/2016 8/9/2016 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO
K. Henderson 3 Letter to Kelvin Henderson from Anthony D. Masters dated August 9, 2016
SUBJECT:
CATAWBA NUCLEAR STATION - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION FOR NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION DISTRIBUTION:
D. Gamberoni, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMCatawba Resource
INFORMATION REQUEST FOR CATAWBA NUCLEAR STATION PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION (October 24 - 28 and November 7 - 10, 2016)
Note: Unless otherwise noted, the information requested below corresponds to documents generated since October 1, 2014. Please provide the requested documents in electronic format. If the information is not available in electronic format, please contact the inspection team leader to coordinate other available methods to provide the information.
- 1. Copies of the corporate and site level procedures and sub-tier procedures associated with the corrective action program. This should include procedures related to:
a) Corrective action process b) Cause evaluation c) Operating experience program d) Employee concerns program e) Self-assessment program f) Maintenance rule program and implementing procedures g) Operability determination process h) Degraded/non-conforming condition process (e.g., RIS 2005-20) i) System health process or equivalent equipment reliability improvement programs j) Preventive maintenance deferral If any of the procedures requested above were revised after October 1, 2014, please provide (or have available) copies of all revisions during the onsite inspection.
- 2. List of top ten risk-significant systems, top ten risk-significant components for each one of the top ten risk-significant systems, and top ten risk-significant operator manual actions.
- 3. List of all Condition Reports (CRs) initiated including the following information for each CR:
a) CR number b) Brief, but complete problem description c) Priority or level d) Affected system e) Affected component f) Responsible plant department g) CR completion status If possible, provide this list in a format compatible with spreadsheet software (example shown below):
CR # Problem Priority System Component Org Status CR001 A RHR Pump 2 RHR 2-RHR- ENG Open failed flow criteria PMP-A per SR 5.0.5.4 Enclosure
2
- 4. List of outstanding corrective actions including the following information for each action:
a) Corrective action number b) Corrective action type (e.g., corrective action to prevent recurrence, enhancement, maintenance rule evaluation, etc) c) Brief, but complete corrective action description d) Associated CR number e) Corrective action initiation date f) Number of Extensions g) Corrective action due date h) Completion status If possible, provide this list in a format compatible with spreadsheet software (example shown below):
Corrective Type Description CR Initiation Extensions Due Status Action # Date Date 25 CAPR Revise CR0058 01/05/12 2 06/15/12 Closed Procedure NGK-003-4585
- 5. List of control room deficiencies with a brief description and corresponding CR and/or work order (WO) number.
- 6. List of operator workarounds and operator burdens with a brief description and corresponding CR number.
- 7. List of all currently extended or overdue CRs, sorted by initiation date, with the following information:
a) CR number b) Priority or Significance c) CR title and short description
- 8. List of all CRs that have been voided or cancelled. Please provide the following information for each CR:
a) CR number b) Brief, but complete problem description c) Reason voided or cancelled
- 9. List of all structures, systems, and components (SSCs) which were classified as (a)(1) in accordance with the Maintenance Rule since October 2014. Please include the following information for each system in (a)(1):
a) Date of classification in (a)(1) b) Reason for being placed in (a)(1) c) Planned actions and their status
3
- 10. List of Maintenance Preventable Functional Failures (MPFFs) of risk-significant systems.
Please include actions completed and current status.
- 11. List of corrective maintenance WOs. Please include the following information for each WO:
a) WO number b) Brief, but complete work description c) Affected system and components d) Date of initiation e) Date of completion (if completed)
If possible, provide this list in a format compatible with spreadsheet software (example shown below):
Work Description System Component Initiation Due Status Order # Date Date WO01345 Replace breaker SI 2A-SI-PMP, 01/05/12 03/15/12 Closed 2A-BKR-08-BB4 for BKR-08-BB4 2A SI Pump.
- 12. Corrective action closeout packages, including CRs with description of corrective actions, for all NRC findings/violations and all licensee identified violations (LIVs).
Please include a cross reference linking NRC findings/violations and LIVs to appropriate CR numbers.
- 13. Corrective action closeout packages, including CRs with description of corrective actions, for all licensee event reports (LERs) issued. Please include a cross reference linking LER number to appropriate CR number.
- 14. List of all NRC generic communications (e.g., Information Notices, Generic Letters, etc.)
and industry operating experience (OE) documents (e.g., Part 21 reports, vendor information letters, information from other sites, etc.,) evaluated by the site for applicability to the station, regardless of the determination of applicability. Please include the reference number (e.g., CR number) for the documents that evaluated the aforementioned OE information.
- 15. Copies of all quality assurance audits and/or assessments issued, including the last two audits/assessments of the corrective action program.
- 16. Copies of all department self-assessments.
- 17. Copy of the most recent integrated plant trend report, departmental trend report(s), and corrective action trend report(s), including any human performance and equipment reliability trends.
4
- 18. Copy of the latest Corrective Action Program statistics (if exists) such as the number of CRs initiated by department, human performance errors by department, and others as may be available.
- 19. Please provide a list of routine meetings involving the CAP to be held while team is onsite.
- 20. List of CRs related to equipment aging issues in the top ten risk significant systems since October 1, 2013, (e.g., system erosion and/or corrosion problems; electronic component aging or obsolescence of circuit boards, power supplies, relays, etc.;
environmental qualification). Please provide the following information for each CR:
a) CR number b) Priority c) CR problem description
- 21. If performed, please provide any recent self-assessment of the site safety culture.
- 22. Copies of corrective action program documents related to cross-cutting issues (human performance, problem identification and resolution, and safety conscious work environment) identified via trending, self-assessments, safety review committee or other oversight methods.
- 23. List of all root cause evaluations with a brief description.
- 24. Copy of Probabilistic Risk Assessment importance measures report, if available.
- 25. System Health Reports, system design basis documents, and system description information for the top ten risk significant systems.