Line 2: |
Line 2: |
| | number = ML060890652 | | | number = ML060890652 |
| | issue date = 03/22/2006 | | | issue date = 03/22/2006 |
| | title = Perry, Response to a Request for Additional Information Associated with a Proposed License Amendment Request to Revise the Oscillation Power Range Monitors Enabled Region | | | title = Response to a Request for Additional Information Associated with a Proposed License Amendment Request to Revise the Oscillation Power Range Monitors Enabled Region |
| | author name = Pearce L W | | | author name = Pearce L |
| | author affiliation = FirstEnergy Nuclear Operating Co | | | author affiliation = FirstEnergy Nuclear Operating Co |
| | addressee name = | | | addressee name = |
Revision as of 22:04, 13 July 2019
Letter Sequence Response to RAI |
---|
|
|
MONTHYEARML0519402052005-07-0505 July 2005 License Amendment Request Pursuant to 10CFR50.90: Revision of Technical Specification Surveillance Requirement 3.3.1.3.5 Which Revises the Enabled Region for the Oscillation Power Range Monitors Project stage: Request ML0600604842006-01-17017 January 2006 RAI Related to Oscillation Power Range Monitors Project stage: RAI ML0608906522006-03-22022 March 2006 Response to a Request for Additional Information Associated with a Proposed License Amendment Request to Revise the Oscillation Power Range Monitors Enabled Region Project stage: Response to RAI ML0618700962006-06-30030 June 2006 Technical Specification, Modifies the Existing TS 3.3.1.3, Oscillation Power Range Monitor (OPRM) Instrumentation, Surveillance Requirement 3.3.1.3.5 Project stage: Other ML0611605772006-06-30030 June 2006 Amendment, Modifies the Existing TS 3.3.1.3, Oscillation Power Range Monitor (OPRM) Instrumentation, Surveillance Requirement 3.3.1.3.5 Project stage: Other 2006-01-17
[Table View] |
Similar Documents at Perry |
---|
Category:Letter
MONTHYEARIR 05000440/20230042024-01-30030 January 2024 Integrated Inspection Report 05000440/2023004 L-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative IR 05000440/20234022024-01-10010 January 2024 Cyber Security Inspection Report 05000440/2023402 ML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML23321A0472023-12-20020 December 2023 Letter to Rod L. Penfield - Perry Nuclear Power Plant, Unit 1 - License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000440/20230112023-11-28028 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000440/2023011 IR 05000440/20234032023-11-27027 November 2023 Security Baseline Inspection Report 05000440/2023403 ML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-052, Submittal of the Updated Safety Analysis Report, Revision 232023-10-27027 October 2023 Submittal of the Updated Safety Analysis Report, Revision 23 ML23292A2482023-10-19019 October 2023 Fws to NRC, Federal Agency Coordination Under ESA Section 7 for Perry Nuclear Plant, Unit 1, License Renewal, and Concurrence with Not Likely to Adversely Affect Determination for Northern Long-eared Bat ML23292A2472023-10-19019 October 2023 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected IR 05000440/20230032023-10-11011 October 2023 Integrated Inspection Report 05000440/2023003 ML23249A1032023-10-0303 October 2023 Letter to Rod L. Penfield, Site Vice President-Perry Nuclear Power Plant, Unit 1-Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML23261C3642023-09-25025 September 2023 License Renewal Application Online Reference Portal ML23261B0192023-09-25025 September 2023 Aging Management Audit Plan Regarding the License Renewal Application Review ML23256A3592023-09-22022 September 2023 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Energy Harbor Nuclear Corp. Application for License Renewal L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000440/20234012023-08-28028 August 2023 Public - Perry Nuclear Power Plant Security Baseline Inspection Report 05000440/2023401 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate ML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications IR 05000440/20230022023-08-0202 August 2023 Integrated Inspection Report 05000440/2023002 L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant IR 05000440/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection Report 05000440/2023010 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener ML23144A3562023-05-25025 May 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End of Cycle Plant Performance Assessment of Perry Nuclear Power Plant, Unit 1 L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) IR 05000440/20230012023-05-0404 May 2023 Integrated Inspection Report (05000440/2023001) L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report 2024-01-30
[Table view] |
Text
FENOC Perry Nuclear Powrer Station 1%10 Center Road FirstEnergy Nuclear Operating Company Perry Ohio 44081 L. William Pearce 440-280-5382 Vice President Fax: 440-280-8029 March 22, 2006 PY-CEI/NRR-2942L 10 CFR 50.90 United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Perry Nuclear Power Plant Docket No. 50-440-Response to a Request for Additional Information Associated with a Proposed License Amendment Request to Revise the Oscillation Power Range Monitors Enabled Region (TAC NO. MC7489)Ladies and Gentlemen:
This letter provides the response to the Nuclear Regulatory Commission Request for Additional Information dated January 17, 2006 pertaining to the Perry Nuclear Power Plant License Amendment Request (LAR) submitted on July 5, 2005 (PY-CEI/NRR-2853L).
The LAR would modify Technical Specification (TS) 3.3.1.3, 'Oscillation Power Range Monitor (OPRM) Instrumentation," Surveillance Requirement (SR) 3.3.1.3.5 by changing the thermal power level at which the OPRMs are "not bypassed" (enabled to perform their design function) from > 28.6% rated thermal power to 2 23.8% rated thermal power.There are no regulatory commitments contained in this letter or its attachment.
If there are any questions or if additional information is required, please contact Mr. Gregory A. Dunn, Manager -FENOC Fleet Licensing, at (330) 315-7243.I declare under penalty of perjury that the foregoing is true and correct. Executed on March 22, 2006.L. W. Pearce
Attachment:
- 1. Response to a Request for Additional Information cc: NRC Project Manager NRC Resident Inspector NRC Region III State of Ohio ou (
--Attachment 1 PY-CEI/NRR-2942L Page 1 of 2 Response to a Request for Additional Information By letter dated January 17, 2006, the Nuclear Regulatory Commission (NRC) requested additional information relative to a license amendment request made by the FirstEnergy Nuclear Operating Company (FENOC) regarding a modification to Technical Specification (TS) 3.3.1.3, 'Oscillation Power Range Monitor (OPRM) Instrumentation," for the Perry Nuclear Power Plant (PNPP). This submittal provides the response to the NRC request.1. NRC Request: On page 1 of the cover letter, the second paragraph states that the Perry Nuclear Plant, Unit 1 (Perry) is currently operating with the oscillation power range monitors enabled at >23.8-percent rated thermal power. This is below the TS value of 28.6-percent rated thermal power. Please document the historical basis for the-- 238-percent rated thermal power value.1. Response: Licensing Topical Report NEDO-32465-A, "Reactor Stability Detect and Suppress Solutions Licensing Basis Methodology for Reload Applications," August 1996, requires the OPRM Trip function to be enabled when the power level is greater than 30% of rated and the core flow is less than 60% of rated. Below 30% rated thermal power or above 60% rated core flow, thermal hydraulic instabilities are not expected to occur. Above 30% rated thermal power and less than 60% rated core flow, the potential for thermal hydraulic instabilities exists; hence, the OPRMs must be capable of detecting and suppressing power oscillations to ensure the Minimum Critical Power Ratio (MCPR)Safety Limit is not exceeded should an instability event occur.In April 2000, a License Amendment Request (LAR) to incorporate the OPRM instrumentation into the Perry TS was submitted to the NRC for review and approval.The proposed OPRM Limiting Condition of Operability (LCO) Applicability was 225% rated thermal power. This value was chosen to be consistent with the Applicability conditions for the LCOs included in TS Section 3.2, "Power Distribution Limits." The power level proposed for enabling the OPRM trip function (capable of causing a Reactor Protection System channel trip) was > 30% rated thermal power.PNPP implemented a power uprate to 105% power during Summer 2000. In order to -maintain the percent of rated power values listed in the TS Applicability, Required Action, and Surveillance Requirement sections consistent with the pre-uprate thermal power levels, the percent of rated power values were adjusted by dividing the value by 1.05. For example, the LCO Applicability conditions of TS Section 3.2 were revised to 293.8% rated thermal power (25% divided by 1.05).In January 2001, a revision to the OPRM LAR was submitted to change the proposed OPRM LCO Applicability to 23.8% rated thermal power to maintain consistency with the Applicability conditions of TS Section 3.2. Additionally, the power level proposed for enabling the OPRM trip function was reduced to > 28.6% rated thermal power (30%divided by 1.05). The OPRM LAR was approved in February 2001 and implemented in March 2001.
Attachment 1 PY-CEI/NRR-2942L Page 2 of 2 Due to a number of issues associated with the OPRMs, General Electric issued a 10CFR21 notification regarding the operability of the OPRMs in June 2001. The resolution of these issues was to perform plant-specific OPRM calculations.
In August 2004, when the OPRMs were restored to operability, the power level used for enabling the OPRM trip function was 23.8% rated thermal power. This is conservative with respect to the current TS value of > 28.6% rated thermal power.2. NRC Request: On page 4 of Attachment 2, the fourth paragraph states that General Electric developed an analytical method which can be used to explain the interactive corrective action (ICA) and enabled regions. The methodology is called backup stability protection (BSP) analysis and is used to redraw the power to flow map.The BSP analysis uses plant-specific inputs to develop decay ratios. The decay ratios are then used to adjust the ICA regions in order to provide stability protection.
Please summarize the Perry-specific applicability for decay ratio.2. Response: The PNPP fuel and core designs are developed in accordance with the NRC-approved Licensing Topical Report NEDE-2401 1-P-A, "General Electric Standard Application for Reactor Fuel," (GESTAR II) (reference PNPP Updated Final Safety Analysis Report, Section 4.2). This topical report describes the processes by which the fuel vendor develops fuel and core designs, and how these designs are evaluated and limits are established.
GESTAR II, Section 1.2.8, Stability, states that new fuel designs and core designs will be evaluated for stability concerns.
To accomplish this, a decay ratio analysis will be performed using the ODYSY procedure and ODYSY computer code.The current version of the ODYSY procedure and ODYSY computer code are discussed in the NRC-approved Licensing Topical Report, NEDC-32992P-A, "ODYSY, Application for Stability Licensing Calculations," July 2001. This version of the ODYSY procedure and computer code was approved for incorporation into Amendment 27 of GESTAR II as documented in an NRC Safety Evaluation dated July 16, 2004.The Perry-specific decay ratio paramfietes ued in'the current PNPP Cycle 11 fuel and -core design stability evaluation were developed using this version of the ODYSY procedure and computer code.