|
|
Line 3: |
Line 3: |
| | issue date = 11/19/2007 | | | issue date = 11/19/2007 |
| | title = Review of Measurement Uncertainty Recapture Power Uprate Application | | | title = Review of Measurement Uncertainty Recapture Power Uprate Application |
| | author name = Wengert T J | | | author name = Wengert T |
| | author affiliation = NRC/NRR/ADRO/DORL/LPLIII-2 | | | author affiliation = NRC/NRR/ADRO/DORL/LPLIII-2 |
| | addressee name = Bezilla M B | | | addressee name = Bezilla M |
| | addressee affiliation = FirstEnergy Nuclear Operating Co | | | addressee affiliation = FirstEnergy Nuclear Operating Co |
| | docket = 05000346 | | | docket = 05000346 |
|
---|
Category:Letter
MONTHYEARML24303A3282024-10-29029 October 2024 Information Request for the Cyber Security Baseline Inspection Identification to Perform Inspection ML24281A0662024-10-0404 October 2024 EN 57363 - MPR Associates, Inc. Report in Accordance with 10 CFR Part 21 on Incomplete Dedication of Contactors Supplied as Basic Components IR 05000346/20244032024-09-27027 September 2024 Security Baseline Inspection Report 05000346/2024403 ML24269A0552024-09-25025 September 2024 Submittal of the Updated Final Safety Analysis Report, Revision 35 05000346/LER-2021-001-01, Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground2024-09-19019 September 2024 Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A2382024-09-16016 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24255A8032024-09-11011 September 2024 Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1602024-09-0505 September 2024 Information Request to Support Upcoming Material Control and Accounting Inspection at Davis-Besse Nuclear Power Station L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000346/20240052024-08-22022 August 2024 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000346/20240022024-08-0101 August 2024 Integrated Inspection Report 05000346/2024002 IR 05000346/20244012024-07-30030 July 2024 Security Baseline Inspection Report 05000346/2024401 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification L-24-032, Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report2024-07-15015 July 2024 Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report L-24-063, License Amendment Request to Remove the Table of Contents from the Technical Specifications2024-07-0808 July 2024 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-24-024, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-19019 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-214, Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2024-06-0505 June 2024 Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements L-24-019, Unit No.1 - Report of Facility Changes, Tests, and Experiments2024-05-22022 May 2024 Unit No.1 - Report of Facility Changes, Tests, and Experiments ML24142A3532024-05-21021 May 2024 Station—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-072, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 20232024-05-15015 May 2024 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 2023 L-24-111, Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-05-15015 May 2024 Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations L-24-031, Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage2024-05-14014 May 2024 Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage IR 05000346/20240012024-05-0303 May 2024 Integrated Inspection Report 05000346/2024001 L-24-069, Occupational Radiation Exposure Report for Year 20232024-04-30030 April 2024 Occupational Radiation Exposure Report for Year 2023 L-24-018, Submittal of Core Operating Limits Report, Cycle 24, Revision 02024-04-16016 April 2024 Submittal of Core Operating Limits Report, Cycle 24, Revision 0 ML24089A2582024-04-0101 April 2024 Request for Information for the NRC Quuadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000346/2024010 L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage ML24036A3472024-03-0707 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0076 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations ML24057A3362024-02-28028 February 2024 Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) IR 05000346/20230062024-02-28028 February 2024 Re-Issue Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 ML23293A0612023-11-0101 November 2023 Letter to the Honorable Marcy Kaptur, from Chair Hanson Responds to Letter Regarding Follow Up on Concerns Raised by Union Representatives During the June Visit to the Davis-Besse Nuclear Power Plant ML24045A0322023-10-26026 October 2023 L-23-221 Proposed Exam Submittal Cover Letter L-23-215, Changes to Emergency Plan2023-10-19019 October 2023 Changes to Emergency Plan ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments 2024-09-06
[Table view] |
Text
November 19, 2007 Mr. Mark B. Bezilla Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 - REVIEW OF MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE APPLICATION FOR DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 (TAC NO. MD5240)
Dear Mr. Bezilla:
By letter dated April 12, 2007, FirstEnergy Nucl ear Operating Company (FENOC) submitted an
amendment request for Davis-Besse Nuclear Power Station Unit No. 1 (DBNPS). The
proposed amendment, using a feedwater flow m easurement uncertainty recapture (MUR),
would change the DBNPS operating license to increase the maximum authorized power level by
approximately 1.6 percent above the current maximum authorized power level. The MUR
amendment request was scheduled for completion by November 18, 2007.
On July 25, 2007, the U.S. Nuclear Regulatory Commission (NRC) staff submitted a request for
additional information (RAI) concerning the application. By letter dated September 18, 2007, FENOC provided responses to the RAI, which included a commitment to provide the setpoint
calculations for the high flux trip field instrumentation for NRC staff review by November 1, 2007. On November 8, 2007, FENOC informed the NRC that, due to insufficient staff resources
caused by the unexpected departure of two key engineers working on the calculation, FENOC
would not be able to provide that information until some time in January 2008.
To date the NRC staff has tracked the DBNPS MUR power uprate application review under
TAC No. MD5240. The NRC staff has completed a substantial portion of the review of your
application, but is unable to complete the review at this time because of a lack of information
concerning the high flux trip instrumentation. Therefore, in order to more efficiently manage
NRC staff resources, the NRC staff is closing TAC MD5240. Upon receipt of the information
necessary to support your application, the NRC staff will resume its review. A new TAC will be
established to track the NRC staff
=s reviews necessary to complete the review of your application. Closure of TAC No. MD5240 does not represent a denial of FENOC
=s license amendment request. Rather, the NRC considers this amendment to be on hold. Therefore, FENOC does not need to resubmit this request. However, we encourage FENOC to align its resources to supplement the MUR power uprate application with the outstanding information necessary for the NRC to complete its review.
M. Bezilla If you have any questions regarding this letter, please contact me at 301-415-4037.
Sincerely, /RA/ Thomas J. Wengert, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346 cc: See next page
ML073180358 NRR-106 OFFICE LPL3-2/PM LPL3-2/LA LPL3-2/BC DPR/PGCB/BC DORL/DD NAME TWengert EWhitt RGibbs MMurphy CHaney DATE 11/14/07 11/14/07 11/14/ 07 11/19/07 11/19/07 Davis-Besse Nuclear Power Station, Unit No. 1 cc: Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3065 5501 North State Route 2 Oak Harbor, OH 43449-9760 Director, Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P.O. Box 4009 Reynoldsburg, OH 43068-9009 Resident Inspector U.S. Nuclear Regulatory Commission 5503 North State Route 2 Oak Harbor, OH 43449-9760 Stephen Helmer Supervisor, Technical Support Section Bureau of Radiation Protection Ohio Department of Health 35 East Chestnut Street, 7 th Floor Columbus, OH 43215 Carol O=Claire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-2206 Zack A. Clayton DERR Ohio Environmental Protection Agency P.O. Box 1049 Columbus, OH 43266-0149 State of Ohio Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Attorney General Office of Attorney General 30 East Broad Street Columbus, OH 43216 President, Board of County Commissioners of Ottawa County Port Clinton, OH 43252 President, Board of County Commissioners of Lucas County One Government Center, Suite 800 Toledo, OH 43604-6506 The Honorable Dennis J. Kucinich United States House of Representatives Washington, D.C. 20515 The Honorable Dennis J. Kucinich United States House of Representatives 14400 Detroit Avenue Lakewood, OH 44107 Joseph J. Hagan President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-15 76 South Main Street Akron, OH 44308 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308
Davis-Besse Nuclear Power Station, Unit No. 1 cc: Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Richard Anderson Vice President, Nuclear Support FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 James H. Lash Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308