ML112430301: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 08/31/2011
| issue date = 08/31/2011
| title = Supplemental Information Regarding Relocation of the TS Surveillance Frequencies
| title = Supplemental Information Regarding Relocation of the TS Surveillance Frequencies
| author name = Sanders C J
| author name = Sanders C
| author affiliation = NRC/NRR/DORL/LPLI-2
| author affiliation = NRC/NRR/DORL/LPLI-2
| addressee name = Bartron W D
| addressee name = Bartron W
| addressee affiliation = Dominion Nuclear Connecticut, Inc
| addressee affiliation = Dominion Nuclear Connecticut, Inc
| docket = 05000423
| docket = 05000423

Revision as of 09:45, 29 June 2019

Supplemental Information Regarding Relocation of the TS Surveillance Frequencies
ML112430301
Person / Time
Site: Millstone Dominion icon.png
Issue date: 08/31/2011
From: Sanders C
Plant Licensing Branch 1
To: Bartron W
Dominion Nuclear Connecticut
Sandeers, Carleen, NRR/DORL, 415-1603
References
Download: ML112430301 (1)


Text

From: Sanders, Carleen Sent: Wednesday, August 31, 2011 12:33 PM To: 'William D Bartron'

Subject:

Millstone 3: Supplemental Information Regarding Request to Relocate the TS Surveillance Frequencies

Bill, Due to unforeseen circumstances (Hurricane Irene) over this past week, I understand that the equivalent of 3 business days were lost with respect to DNC's response to the request for supplemental information for the MPS3 acceptance review of LAR regarding relocation of TS surveillance frequencies. As such, I find it acceptable to extent the response date the equivalent of 3 business days. The new response date is September 12, 2011.

Thank you, Carleen Sanders Millstone Project Manager 301-415-1603