| | issue date = 07/17/2018 | | | issue date = 07/17/2018 |
| | title = PSDAR Public Meeting the NRC Review Process | | | title = PSDAR Public Meeting the NRC Review Process |
| | author name = Broaddus D A | | | author name = Broaddus D |
| | author affiliation = NRC/NRR/DORL/LSPB | | | author affiliation = NRC/NRR/DORL/LSPB |
| | addressee name = | | | addressee name = |
Line 9: |
Line 9: |
| | docket = 05000219 | | | docket = 05000219 |
| | license number = DPR-016 | | | license number = DPR-016 |
| | contact person = Lamb J G, NRR/DORL/LSPB, 415-3100 | | | contact person = Lamb J, NRR/DORL/LSPB, 415-3100 |
| | case reference number = EPID L-2018-LRO-0022 | | | case reference number = EPID L-2018-LRO-0022 |
| | document type = Meeting Briefing Package/Handouts | | | document type = Meeting Briefing Package/Handouts |
Revision as of 00:56, 17 June 2019
Letter Sequence Meeting |
---|
EPID:L-2018-LRO-0022, Summary of 7/17/2018 Public Meeting in Forked River, Nj, to Receive Public Comments on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate (Approved, Closed) |
|
MONTHYEARML18149A0942018-06-0505 June 2018 FRN, Notice of Receipt, Public Meeting, Request for Comment, Post-Shutdown Decommissioning Activities Report Project stage: Meeting ML18149A0722018-06-0505 June 2018 Letter, Notice of Receipt, Public Meeting, and Request for Comment on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Meeting ML18201A2602018-06-13013 June 2018, 17 July 2018, 31 August 2018 Summary of 7/17/2018 Public Meeting in Forked River, Nj, to Receive Public Comments on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Request NRC-2018-0111, Comment (1) of Patrick Mulligan on Exelon Generation Company, LLC; Oyster Creek Nuclear Generating Station; Post-Shutdown Decommissioning Activities Report2018-06-29029 June 2018 Comment (1) of Patrick Mulligan on Exelon Generation Company, LLC; Oyster Creek Nuclear Generating Station; Post-Shutdown Decommissioning Activities Report Project stage: Request ML18201A2372018-07-17017 July 2018 Slides 7/17/2018 PSDAR Meeting Project stage: Meeting ML18201A3772018-07-17017 July 2018 Meeting Transcript for 7/17/2018 Public Meeting in Forked River, Nj, to Receive Public Comments on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Meeting ML18201A3072018-07-17017 July 2018 Post Shutdown Decommissioning Activities Report (PSDAR) Public Meeting Presentation Project stage: Meeting ML18201A2842018-07-17017 July 2018 PSDAR Public Meeting the NRC Review Process Project stage: Meeting ML18205A5502018-08-0606 August 2018 Memorandum to File - Public Feedback to 7/17/18 Public Meeting in Forked River, Nj, to Receive Public Comments on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Meeting ML18201A2632018-08-31031 August 2018 Summary of Public Meeting in Forked River, Nj, to Discuss Oyster Creek Nuclear Generating Station Post-Shutdown Decommissioning Activities Report Project stage: Meeting ML18256A0022018-09-12012 September 2018 NRR E-mail Capture - for Your Action: RAIs for Oyster Creek Post Shutdown Decommissioning Activities Report (PSDAR) Project stage: RAI RA-18-093, Request to Reinitiate Consultation Regarding the OCNGS Sea Turtle Incidental Take Statement2018-10-16016 October 2018 Request to Reinitiate Consultation Regarding the OCNGS Sea Turtle Incidental Take Statement Project stage: Request ML18241A0682018-12-17017 December 2018 Creek - Review of Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Approval 2018-06-05
[Table View] |
|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML19269B6892019-10-0303 October 2019 NEIMA Section 108 Public Meeting Slides - Oyster Creek - October 3, 2019 ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 ML18334A2162018-11-30030 November 2018 Presentation Slides: Exelon BWR MSIV (Boiling-Water Reactor - Main Steam Isolation Valve) Leakage Optimization for NRC Pre-Submittal Meeting of December 6, 2018 ML18319A1272018-11-19019 November 2018 Slides for 11/19/18 Public Meeting - Exelon Fleet LAR for Common Language for TS 5.7 High Radiation Areas ML18225A1752018-08-15015 August 2018 Decommissioning License Transfer Application NRC Pre-Submittal Meeting ML18201A2372018-07-17017 July 2018 Slides 7/17/2018 PSDAR Meeting ML18201A2842018-07-17017 July 2018 PSDAR Public Meeting the NRC Review Process ML18201A3072018-07-17017 July 2018 Post Shutdown Decommissioning Activities Report (PSDAR) Public Meeting Presentation ML18054B3592018-02-27027 February 2018 Slide: NRC Pre-Submittal Meeting for Exelon Fleet LAR to Relocate TS Unit Staff Qualification ANSI Requirements to the QATR, February 27, 2018, Profile Info: Submitted by Frank Mascitelli ML17142A2382017-05-25025 May 2017 OEDO-17-00280 - Briefing Package for Drop-In Visit on June 9, 2017, by Senior Management of Exelon Generation Company, LLC with Chairman Svinicki, Commissioner Baran, and Commissioner Burns ML17062A5522017-03-0909 March 2017 E EMRV Failure Slides for Regulatory Conference Meeting Notice for 03/09/17 ML16314E4812016-11-14014 November 2016 Part 37 Applicability to Reactor Vessels and Associated Structures, Systems, and Components While in Safstor Awaiting Active Decommissioning Activities - November 14, 2016 ML16092A1402016-04-0606 April 2016 4/6/16, Meeting Slide for Pre-Submittal Meeting with NRC Regarding Oyster Creek Decommissioning Post-Shutdown Emergency Plan License Amendment Request ML16075A3292016-03-16016 March 2016 OEDO-16-00165 - Briefing Package for Drop-In Visit on March 23, 2016, by Senior Management of Exelon Generation Company, LLC with the NRC Executive Director for Operations ML15265A3592015-09-21021 September 2015 NRC Oyster Creek Decommissioning Pre-Submittal Meeting Slides 09-21-15 ML15118A8042015-05-0505 May 2015 Webinar 2015 Slides Presentation ML15265A3742015-02-21021 February 2015 NRC Pre-Submittal Meeting 09-21-15 - Decommissioning Submittal List ML12173A1322012-06-21021 June 2012 Summary of Public Meeting with Exelon Generation Company, LLC Regarding Items of Public Interest Related to Oyster Creek Nuclear Generating Station ML12110A3402012-04-19019 April 2012 Annual Assessment Meeting - 2011 ROP-NRC Slides ML1208701402012-03-27027 March 2012 Licensee Slides for Exelon Fleet Pre-Submittal Public Meeting 4-10-12 Licensed Operator Eligibility Requirements LAR ML1012300492010-05-0303 May 2010 Slides for the Oyster Creek Annual Assessment Public Meeting ML0934102382009-12-0404 December 2009 Meeting Presentation, ACRS Meeting with the U.S. Nuclear Regulator Commission ML0928701922009-10-0909 October 2009 FEMA Public Meeting at Oyster Creek Slides, October 2009 ML0919803632009-08-20020 August 2009 Summary of Licensing Counterparts Meeting with Exelon Generation Company, to Discuss Licensing Practices and Processes ML0919801452009-06-17017 June 2009 NRC Discussions with Nj DEP Engineers ML0919605452009-06-17017 June 2009 10/01/2008 Senior Management Briefing Oyster Creek License Renewal Regulatory Footprint, to Describe Current Regulatory Footprint, Additional Options & Actions, and Gov'T & Public Outreach Needs ML0919605462009-06-17017 June 2009 10/01/2008 Senior Management Briefing Oyster Creek License Renewal Regulatory Footprint, Working Discussion of Issues and Options in Response to RA Questions ML0919605472009-06-17017 June 2009 10/01/2008 Senior Management Briefing Oyster Creek License Renewal Regulatory Footprint, Working Discussion of Issues and Options in Response to RA Questions ML0919605572009-06-17017 June 2009 10/01/2008 Senior Management Briefing Oyster Creek License Renewal Regulatory Footprint, to Describe Current Regulatory Footprint, Additional Options & Actions, and Gov'T & Public Outreach Needs ML0919605582009-06-17017 June 2009 10/01/2008 Senior Management Briefing Oyster Creek License Renewal Regulatory Footprint, to Describe Current Regulatory Footprint, Additional Options & Actions, and Gov'T & Public Outreach Needs ML0919605592009-06-17017 June 2009 09/23/2008 DRS Management Briefing Oyster Creek License Renewal Regulatory Footprint, Working Discussion of Issues and Options in Response to RA Questions on a Lr Regulatory Foodprint ML0919605602009-06-17017 June 2009 09/23/2008 DRS Management Briefing Oyster Creek License Renewal Regulatory Footprint, Working Discussion of Issues and Options, in Response to RA Questions ML0919805202009-06-17017 June 2009 Brief for Ora Oyster Creek Commitment Inspection Results and Related Issues ML0916802102009-05-28028 May 2009 Oc Aam Public Feedback Form, 05/28/2009, 2008 Annual Assessment Meeting ML0913205742009-05-12012 May 2009 Meeting Slides, Oyster Creek Annual Assessment Meeting 2008 Reactor Oversight Process ML0912702392009-05-0404 May 2009 Calvert County Sheriff- Special Operations Team ML0912406092009-04-23023 April 2009 Meeting, Slides, New Jersey State Police Response to Hostile Action at Nuclear Power Plants, National Radiological Emergency Preparedness Conference ML0919801442008-12-22022 December 2008 Brief for Ora Oyster Creek Commitment Inspection Results and Related Issues with Handwritten Notes ML0919801392008-12-22022 December 2008 Brief for Ora Oyster Creek Commitment Inspection Results and Related Issues ML0919801402008-12-22022 December 2008 Brief for Ora Oyster Creek Commitment Inspection Results and Related Issues ML0919801422008-12-22022 December 2008 Brief for Ora Oyster Creek Commitment Inspection Results and Related Issues ML0919801432008-12-22022 December 2008 Brief for Ora Oyster Creek Commitment Inspection Results and Related Issues ML0812007842008-06-0202 June 2008 Meeting Slides, Nrc/Exelon Licensing Counterparts Meeting. ML0810606002008-04-15015 April 2008 Meeting Slides, NRC Annual Performance Assessment of Oyster Creek 2007 Reactor Oversight Program. ML0715204362007-05-23023 May 2007 Feedback Forms, List of Attendees, & Final Slides from the Oyster Creek 2007 Annual Assessment Meeting (Aam) ML0634206092006-11-0404 November 2006 Powerpoint: Oyster Creek 1R21 Outage Startup PORC Update on Drywell Shell Inspections November 4, 2006 (PA) ML0622301292006-07-12012 July 2006 Powerpoint Presentation Associated with Oyster Creek Draft EIS Public Meetings ML0610003702006-04-10010 April 2006 NRC Slides for Annual Assessment Public Meeting with Amergen Reference CY2005 Oyster Creek Station Performance ML0509800822005-04-0808 April 2005 05/12/2005 - Oyster Creek Annual Assessment Meeting Slides for Meeting with Amergen ML0430302762004-09-27027 September 2004 Attendance List for Oyster Creek EDG Cooling Fan Regulatory Conference 2019-10-03
[Table view] |
Text
Oyster Creek PSDARThe NRC Review ProcessJuly 17, 2018Forked River, New JerseyDouglas BroaddusChief, Special Projects and Process BranchOffice of the Nuclear Reactor Regulation
-Guidance for information to be included in a PSDAR
- Reviewed by technical staff in several areas
- Requests for additional information (RAIs)*Considers public commentsNRC's PSDAR Review Process
- Does the PSDAR contain the information required by regulation?
- Can the decommissioning be completed as described, and within 60 years?
- Can the radiological decommissioning be completed for the estimated cost?
- Do the decommissioning activities endanger public health and safety or the environment?NRC's PSDAR Review Process:Evaluation Criteria
- Site-specific Decommissioning Cost Estimate (DCE)-Provides reasonable assurance funds are available to complete decommissioning?
-Licensee has a means of adjusting the cost estimate and funding over the storage period?*Annual report of funding levels and changes from amounts in the DCE NRC's PSDAR Review Process: Decommissioning Cost Estimate
- Provides reasons for concluding that environmental impacts of site
-specific decommissioning activities are bounded by previous Environmental Impact Statement (EIS)
-NUREG-0586, "Final Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities
"-Consider site
-specific issues and changes not addressed in prior EIS
-Inspection programNRC's PSDAR Review Process: Environmental Review / NEPA
- Staff will notify licensee if no additional information is required
-NRC review does not approve the PSDAR
-Document the NRC review
-Addresses comments received
- Licensee may not begin major decommissioning activities until 90 days after NRC receives the PSDAR, per 10 CFR 50.82(a)(5)NRC's PSDAR Review Process
- This public meeting*Federal Rulemaking Web site:http://www.regulations.govSearch for Docket ID: NRC-2018-0111*By Mail: May MaOffice of Administration, Mail Stop:
TWFN-7-A60M U.S. Nuclear Regulatory CommissionWashington, DC 20555
-0001*Due September 10, 2018Comment on the PSDAR