Letter Sequence RAI |
---|
|
|
MONTHYEARML13058A0592013-02-22022 February 2013 Licesne Amendment Request to Update Pressure-Temperature Limit Curves No. 2012-10 Project stage: Other ML13165A1472013-06-21021 June 2013 Request for Additional Information Regarding Amendment Application Related to Reactor Coolant System Pressure and Temperature Limit Curves Project stage: RAI ML13259A1202013-09-10010 September 2013 Response to Request for Additional Information (RAI) Regarding License Amendment Request to Update Pressure-Temperature Limit Curves License Amendment Request (LAR) No. 2012-10, Supplement 1 Project stage: Supplement ONS-2013-016, Response to Request for Additional Information (RAI) Regarding License Amendment Request to Update Pressure-Temperature Limit Curves License Amendment Request (LAR) No. 2012-10, Supplement 22013-10-25025 October 2013 Response to Request for Additional Information (RAI) Regarding License Amendment Request to Update Pressure-Temperature Limit Curves License Amendment Request (LAR) No. 2012-10, Supplement 2 Project stage: Supplement ML13322B2762013-11-14014 November 2013 11/14/13 e-mail from B.Shingleton to R.Guzman PT Curves LAR Supplement 2 - ONS Unit 3 Lower Nozzle Belt Forging Reported in ANP-3127, Revision 2 Project stage: Supplement ML13305A1222013-11-25025 November 2013 Enclosure 3 - Areva Document No. 32-9212003-000, Lst Considering RCS Piping and RVCH Limit for B&W Plant Designs, September 2012 Project stage: Request ONS-2013-023, Response to Request for Additional Information (RAI) Regarding License Amendment Request to Update Pressure-Temperature Limit Curves License Amendment Request (LAR) No. 2012-10, Supplement 32013-11-29029 November 2013 Response to Request for Additional Information (RAI) Regarding License Amendment Request to Update Pressure-Temperature Limit Curves License Amendment Request (LAR) No. 2012-10, Supplement 3 Project stage: Supplement ML13342A0022013-12-0505 December 2013 12/5/13 E-mail from R.Guzman to B.Shingleton - Follow-up RAI to Pressure Temperature Curve LAR Supplement 3, Oconee Nuclear Station Units 1, 2, and 3 (TAC Nos. MF0763/64/65) Project stage: RAI ML13350A0982013-12-16016 December 2013 E-mail from B.Shingleton to R.Guzman Clarification of Upper Shelf Energy Values for ONS Pressure-Temperature Curve 54 EFPY LAR Project stage: Other ML14028A4822014-01-31031 January 2014 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML14041A0932014-02-27027 February 2014 Issuance of Amendments Regarding Revised Pressure-Temperature Limits Project stage: Approval 2013-12-05
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000269/20240032024-10-31031 October 2024 Integrated Inspection Report 05000269/2024003 and 05000270/2024003 and 05000287/2024003 (2) ML24255A3322024-10-16016 October 2024 SLRA - Revised SE Letter ML24297A6172024-10-11011 October 2024 PCA Letter to NRC Oconee Hurricane Helene ML24269A0912024-10-0909 October 2024 Request for Withholding Information from Public Disclosure ML24145A1782024-08-26026 August 2024 Issuance of Amendment Nos. 430, 432, and 431, to TS 5.5.2, Containment Leakage Rate Testing Program for a one-time Extension of the Type a Leak Rate Test Frequency IR 05000269/20240052024-08-26026 August 2024 Updated Inspection Plan for Oconee Nuclear Station, Units 1, 2 and 3 (Report 05000269/2024005, 05000270/2024005, and 05000287-2024005) 05000287/LER-2024-001, Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation2024-08-0202 August 2024 Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation IR 05000269/20240022024-07-25025 July 2024 Integrated Inspection Report 05000269/2024002 and 05000270/2024002 and 05000287/2024002 ML24192A1312024-07-15015 July 2024 Licensed Operator Positive Fitness-For-Duty Test ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24183A2352024-06-29029 June 2024 Update 3 to Interim Report Regarding a Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24179A1102024-06-27027 June 2024 Submittal of Updated Final Safety Analysis Report Revision 30, Technical Specifications Bases Revisions, Selected Licensee Commitment Revisions, 10 CFR 50.59 Evaluation Summary Report, and 10 CFR 54.37 Update, and Notification ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000269/20240012024-05-0303 May 2024 Integrated Inspection Report 05000269/2024001, 05000270/2024001 and 05000287/2024001 IR 05000269/20244022024-04-24024 April 2024 Security Baseline Inspection Report 05000269/2024402 and 05000270/2024402 and 05000287/2024402 ML24108A0792024-04-16016 April 2024 EN 57079 Paragon Energy Solutions Email Forwarding Part 21 Interim Report Re Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 IR 05000269/20244012024-03-28028 March 2024 – Security Baseline Inspection Report 05000269-2024401 and 05000270-2024401 and 05000287-2024401 ML24088A3052024-03-25025 March 2024 Fws to NRC, Agreement with Nlaa Determination for Tricolored Bat for Oconee Lr 05000270/LER-2023-001, Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition That Could Have Prevented Fulfillment of a Safety Function Licensee2024-02-29029 February 2024 Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition That Could Have Prevented Fulfillment of a Safety Function Licensee 05000287/LER-2023-002, Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications2024-02-29029 February 2024 Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications IR 05000269/20230062024-02-28028 February 2024 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 - (NRC Inspection Report 05000269/2023006, 05000270/2023006, and 05000287/2023006) ML24045A3042024-02-16016 February 2024 Ltr. to Lisa M. Collins Chief the Wassamasaw Tribe of Varnertown Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24030A0052024-02-16016 February 2024 Ltr. to Brian Harris, Chief, Catawba Indian Nation; Re., Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2942024-02-16016 February 2024 Ltr. to Carolyn Chavis Bolton Chief Pee Dee Indian Nation of Upper Sc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2962024-02-16016 February 2024 Ltr. to David Hill Principal Chief Muscogee Creek Nation Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2992024-02-16016 February 2024 Ltr. to Eric Pratt Chief the Santee Indian Organization Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3082024-02-16016 February 2024 Ltr. to Ralph Oxendine Chief Sumter Tribe of Cheraw Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3022024-02-16016 February 2024 Ltr. to Joe Bunch United Keetoowah Band of Cherokee Indians in Ok Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3072024-02-16016 February 2024 Ltr. to Pete Parr Chief Pee Dee Indian Tribe Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3032024-02-16016 February 2024 Ltr. to John Creel Chief Edisto Natchez-Kusso Tribe of Sc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3012024-02-16016 February 2024 Ltr. to Harold Hatcher Chief the Waccamaw Indian People Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2952024-02-16016 February 2024 Ltr. to Chuck Hoskin, Jr, Principal Chief Cherokee Nation Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2972024-02-16016 February 2024 Ltr. to Dexter Sharp Chief Piedmont American Indian Assoc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3052024-02-16016 February 2024 Ltr. to Louis Chavis Chief Beaver Creek Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3062024-02-16016 February 2024 Ltr. to Michell Hicks, Principal Chief Eastern Band of Cherokee Re Oconee Nuclear Station Units 1,2, and 3 Section 106 ML24019A1442024-02-13013 February 2024 Letter to Reid Nelson, Executive Director, Achp; Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24011A1532024-02-13013 February 2024 Letter to Tracy Watson EPA-Oconee Nuclear Sta, Unites 1, 2 & 3 Notice of Avail of the Draft Site-Specific Supp. 2, 2nd Renewal to the Generic EIS for Lic. Renew of Nuclear Plants ML24030A5212024-02-13013 February 2024 Letter to Elizabeth Johnson, Director, SHPO; Re Oconee Nuclear Stations Units 1, 2, and 3 Section 106 ML24011A1482024-02-13013 February 2024 Letter to Steven M. Snider-Oconee Nuclear Sta, Unites 1,2 & 3 Notice of Avail of the Draft Site-Specific Supp. 2, 2nd Renewal to the Generic EIS for Lic. Renew of Nuclear Plants IR 05000269/20230042024-02-13013 February 2024 Integrated Inspection Report 05000269/2023004, 05000270/2023004, and 05000287/2023004; and Inspection Report 07200040/2023001 ML23304A1422024-02-0101 February 2024 Issuance of Environmental Scoping Summary Report Associated with the U.S. Nuclear Regulatory Commission Staff’S Review of the Oconee Nuclear Station, Units 1, 2, & 3, Subsequent License Renewal Application ML24005A2492024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000269/20243012024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000269/2024301, 05000270/2024301, and 05000287/2024301 ML23331A7982023-12-14014 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report (01R32) ML23262A9672023-12-13013 December 2023 Alternative to Use RR-22-0174, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section XI, Division 1 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000269/20230032023-11-14014 November 2023 Integrated Inspection Report 05000269/2023003, 05000270/2023003, and 05000287/2023003; and IR 07200040/2023001; and Exercise of Enforcement Discretion ML23219A1402023-10-10010 October 2023 Audit Report Proposed Alternative to Use ASME Code Case N-752, Risk Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems XI, Division 1 ML23269A1102023-10-0606 October 2023 Letter to Steven Snider-Revised Schedule for the Environmental Review of the Oconee Nuclear Station, Unit 1, 2, and 3, Subsequent License Renewal Application ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds 2024-08-26
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24197A2302024-07-15015 July 2024 Request for Additional Information - Oconee SLRA - Annual Update ML24192A1312024-07-15015 July 2024 Licensed Operator Positive Fitness-For-Duty Test ML24190A0462024-07-0505 July 2024 Notification of Inspection and Request for Information ML24086A3772024-03-26026 March 2024 Request for Additional Information License Amendment Request to Revise Technical Specification 5.5.2 ML23284A3322023-10-11011 October 2023 Request for Additional Information Alternative Request (RA-22-0174) (L-2022-LLR-0060) ML23178A0682023-07-0303 July 2023 Audit Plan Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 & 3 Systems Section XI, Division 1 ML23156A2452023-06-0505 June 2023 Audit Summary and RAI-RCI - Revised Enclosure ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23095A0052023-04-0404 April 2023 002 Radiation Safety Baseline Inspection Information Request ML23086C0362023-03-27027 March 2023 Request for Additional Information Steam Generator Tube Inspection Report (03R31) ML23039A1632023-02-0808 February 2023 Requalification Program Inspection ML23038A1832023-02-0707 February 2023 Request for Additional Information Alternative Request (RA-22-0174) to Use ASME Code Case N-752 ML23037A0772023-02-0606 February 2023 402 Cyber Notification and RFI Letter Final ML22251A2902022-09-0808 September 2022 Request for Additional Information Additional Mode Change Limitations Applicable to the Adoption of Technical Specifications Tasks Force Traveler (TSTF) No. 359, Revision 9 ML22234A0052022-08-30030 August 2022 SLRA - Feedback for RAI B2.1.7-4a to Duke - August 16, 2022 ML22157A0042022-06-0606 June 2022 10 CFR 50.59 Inspection Initial Information Request ML22157A0012022-06-0101 June 2022 Email from NRC (Angela Wu) to Duke (Paul Guill) - Oconee SLRA - Additional NRC Comments on RAI 4.6.1-1a ML22154A2122022-06-0101 June 2022 SLRA - 2nd Round RAI B2.1.7-4b ML22124A1632022-05-0303 May 2022 (Public) Oconee SLRA - 2nd Round RAI B2.1.7-4a ML22124A1612022-05-0303 May 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round RAI B2.1.7-4a ML22122A0182022-04-28028 April 2022 Attachment: Oconee SLRA - 2nd Round RAI B2.1.9-2a ML22122A0192022-04-28028 April 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round RAI B2.1.9-2a ML22122A1312022-04-27027 April 2022 (Public) Oconee SLRA - 2nd Round RAIs - Trp 76 (Irradiation Structural) - FE 3.5.2.2.2.6 Redacted ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22112A0072022-04-20020 April 2022 Email from Marieliz Johnson (NRC) to Steve Snider (Duke) - Oconee SLRA - Request for Confirmation of Information 3.5.2.2.2.6-L ML22113A0092022-04-20020 April 2022 Attachment: Oconee SLRA - Final RAI 3.1.2-1 ML22081A0062022-03-21021 March 2022 Attachment: Oconee SLRA - 2nd Round RAI B4.1-3 ML22081A0052022-03-21021 March 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round RAI B4.1-3 ML22080A0772022-03-16016 March 2022 SLRA - RAI Set 4 (2nd Round Rais) ML22069A0012022-03-0808 March 2022 Attachment: Oconee SLRA - Final Requests for Confirmation of Information - Set 4 ML22063A4502022-03-0404 March 2022 Request for Additional Information Application to Revise TS 3.7.7, Low Pressure Service Water (LPSW) System, to Extend the Completion Time for One Required Inoperable LPSW Pump RA-22-0036, Responses to NRC Request for Additional Information Set 22022-02-14014 February 2022 Responses to NRC Request for Additional Information Set 2 ML22019A1032022-01-18018 January 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - Requests for Additional Information - Set 3 ML22019A2442022-01-18018 January 2022 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000269/2022010, 05000270/2022010, 05000287/2022010) and Request for Information (RFI) ML22019A1042022-01-18018 January 2022 Attachment: Oconee SLRA - Final Requests for Additional Information - Set 3 ML22012A0422022-01-11011 January 2022 SLRA - Final Requests for Additional Information - Set 2 ML22010A1132022-01-0505 January 2022 SLRA - RCIs - Set 3 ML21333A0392021-11-29029 November 2021 RP Inspection Document Request ML21327A2782021-11-23023 November 2021 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - Final RAIs (Set 1 and 2nd Round RAI B2.1.27-1a) ML21327A2792021-11-23023 November 2021 SLRA - Final Requests for Additional Information - Set 1 ML21327A2802021-11-23023 November 2021 SLRA - Final 2nd Round RAI - RAI B2.1.27-1a ML21330A0192021-11-23023 November 2021 Attachment: Oconee SLRA - Final Requests for Confirmation of Information - Set 2 ML21313A2342021-11-0404 November 2021 Attachment: Oconee SLRA - Final Requests for Confirmation of Information - Set 1 ML21274A0682021-10-0101 October 2021 Request for Additional Information Alternative Request (RA-20-0334) Regarding Use of an Alternative to the ASME Code Case N-853 Acceptance Criteria ML21273A0492021-09-30030 September 2021 Request for Additional Information Alternative Request (ON-RPI-OMN-28) to Use Code Case OMN-28 ML21271A5892021-09-28028 September 2021 SLRA - RAI B2.1.27-1 (Draft) ML21271A5902021-09-28028 September 2021 SLRA - RAI B2.1.27-1 (Final) ML21271A5882021-09-22022 September 2021 SLRA - Request for Additional Information B2.1.27-1 - Email from Angela Wu (NRC) to Steve Snider (Duke) ML21217A1912021-08-0505 August 2021 Request for Additional Information Alternative Request (RA-20-0334) Regarding Use of an Alternative to the ASME Code Case N-853 Acceptance Criteria 2024-07-05
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555"()001 June 21, 2013 Mr. Scott Batson Site Vice President Oconee Nuclear Station Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672-0752 OCONEE NUCLEAR STATION, UNITS 1,2, AND 3, REQUEST FOR ADDITIONAL INFORMATION REGARDING AMENDMENT APPLICATION RELATED TO REACTOR COOLANT SYSTEM PRESSURE AND TEMPERATURE LIMIT CURVES (TAC NOS. MF0763, MF0764, AND MF0765)
Dear Mr. Batson:
By letter dated February 22,2013, Duke Energy Carolinas, LLC (Duke), submitted an application for a proposed amendment for the Oconee Nuclear Station, Units 1,2, and 3, which would revise the Technical Specifications for the Reactor Coolant System pressure-temperature limit curves. The Nuclear Regulatory Commission (NRC) staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). On June 10, 2013, the Duke staff indicated that a response to the RAI would be provided within 60 days of the date of this letter. If you have any questions, please call me at 301-415-2901.
Sincerely, CJ:;
Manager Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and Request for Additional cc w/encl: Distribution via REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING TECHNICAL SPECIFICATION CHANGE REQUEST FOR PRESSURE-TEMPERATURE LIMIT CURVES DUKE ENERGY CAROLINAS, LLC OCONEE NUCLEAR STATION, UNITS 1,2, AND 3 DOCKET NOS. 50-269, 50-270 AND 50-287 Sy letter dated February 22,2013, Agencywide Documents Access and Management System Accession No. ML 130580060, Duke Energy Carolinas, LLC (Duke), submitted an application for a proposed amendment for the Oconee Nuclear Station, Units 1, 2, and 3, which would revise the Technical Specifications for the Reactor Coolant System pressure-temperature limit curves. The Nuclear Regulatory Commission (NRC) staff is reviewing the submittal and has the following questions:
RAI-1 (generic)
Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix G, Paragraph IV.A states that, "The pressure-retaining components of the reactor coolant pressure boundary [RCPBJ that are made of fem'tic materials must meet the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code [ASME Code, Section IIIJ, supplemented by the additional requirements set forth ... [in paragraph IV.A.2, "Pressure-Temperature (P-T) Limits and Minimum Temperature Requirements"]." Therefore, 10 CFR Part 50, Appendix G requires that P-T limits be developed for the ferritic materials in the reactor vessel (RV) beltline (neutron fluence 1 x 10 17 n/cm 2 , E> 1 MeV), as well as ferritic materials not in the RV beltline (neutron fluence < 1 x 10 17 n/cm 2 , E> 1 MeV). Further, 10 CFR Part 50, Appendix G requires that all RCPS components must meet the American Society of Mechanical Engineers Code (ASIVIE Code),Section III requirements.
The relevant ASME Code,Section III requirement that will affect the P-T limits is the lowest service temperature requirement for all reactor coolant pressure boundary (RCPB) components specified in Section III, NB-2332(b).
The P-T limit calculations for ferritic RCPS components that are not RV beltline shell materials may define P-T curves that are more limiting than those calculated for the RV beltline shell materials due to the following factors: RV nozzles, penetrations, and other discontinuities have complex geometries that may exhibit significantly higher stresses than those for the RV beltline shell region. These higher stresses can potentially result in more restrictive P-T limits, even if the reference temperature (RT NDT) for these components is not as high as that of RV beltline shell materials that have simpler geometries. Ferritic RCPS components that are not part of the RV may have initial RT NDT values, which may define a more restrictive lowest operating temperature in the P-T limits than those for the RV beltline shell materials.
Enclosure
-2 Consequently, please describe how the current P-T limit curves at 54 effective full power years (EFPY) for the Oconee units and the methodology used to develop these curves considered all RV materials (beltline and non-beltline) and the lowest service temperature of all ferritic RCPB materials, consistent with the requirements of 10 CFR Part 50, Appendix G in the proposed update. Your description shall include the following: Using a proposed composite heatup curve and a proposed cooldown curve as examples, point out the segments that were limited by closure head, outer nozzle, and beltline. Confirm availability of material data (initial RT NOT and copper and nickel contents) for all non-beltline materials for all three unit RPVs and demonstrate that none of them will become limiting under the 54 EFPY fluence. Confirm that the lowest service temperatures (LSTs) for all Ferritic RCPB components that are not part of the RV have been established for all three Oconee units, and the lowest temperature of 60 OF in the proposed P-T limits are higher than these LSTs. RAI-2 The fluence values at the one-quarter thickness (1/4T) and 3/4T of the RV in Table 3-1 of ANP-3127, Revision 1 (the ANP, Enclosure 2 of the February 22, 2013, submittal) appear to not be based on the same RV thickness for the same unit. Please confirm that you used Equation (3) in Regulatory Guide (RG) 1.99, Revision 2, "Radiation Embrittlement of Reactor Vessel Materials," to calculate the fluence at 1/4T and 3/4T of the RV. Please also provide the values that you used for "x" in Equation (3) in the ART calculations at 1/4T and 3/4T for the limiting materials shown in Table 3-1 and the RV radius that you used in the P-T limit calculations.
Provide the same information for Units 2 and 3. RAI-3 Table 3-2 of the ANP indicated that the copper value of the lower nozzle belt to the upper shell circumferential weld of Heat 406L44 for Unit 2 is 0.27% and for the same type of weld of Heat 821T44 for Unit 3 is 0.24%, both are 0.01% lowerthan the corresponding values in the approved license renewal application.
Since the accumulative effect of several small changes over the years can be significant, please provide justification for the revision.
RAI-4 Section 4.2 of the ANP states that, "A % tNB (tNB -the thickness at the nozzle belt) deep corner flaw is postulated on the inside surface of the reactor vessel inlet and outlet nozzles and core flood nozzle corner." This suggests that your nozzle methodology is more complete than that of BAW-10046, Revision 2, which performed analysis on outlet nozzles only, based on the belief that the outlet nozzle is the most limiting nozzle. Please confirm that actual calculations have been performed on inlet, outlet, and core flood nozzles to determine the most limiting P-T limits for nozzles in this license amendment request (LAR).
Section 4.4 of the ANP states, "The Pressure-Temperature limits derived for the reactor vessel head-to-flange conservatively bounds the minimum required temperature requirements as given in Table 1 of the Appendix G to 10 CFR Part 50." Please use a figure from Figure 7-1 to Figure 7-9 to support and explain this statement.
RAI-6 Section 4.6 of the ANP indicated that both ramped and stepped transient definitions are modeled for normal operation heatup and cooldown.
Please confirm whether the thermal stresses are based on (1) the stepped transient, which is likely to be limiting, or (2) the stepped and the ramped transients depending on time. If Case (2) applies, please provide a discussion of why the stepped transient may not be limiting.
RAI-7 Section 6 of the ANP discussed pressure corrections with the LlP listed in Table 6-1. Please confirm whether this LlP should be added to or subtracted from the calculated pressure values based on the ASME Code,Section XI, Appendix G methodology.
Likewise, how do you adjust the calculated 1/4T metal temperature to the "indicated reactor coolant system (RCS) inlet temperature?" RAI-8 Figures 7-1 and 7-2 of the ANP illustrate the P-T limits for heatup and cooldown, along with pressure temperature pairs of typical pOints along the P-T limit curves (on the left side of Figures 7-1 and 7-2). To assist the NRC staff verify the proposed heatup and cooldown curves, please use these pressure temperature pairs as examples and provide the corresponding thermal stress intensity factors (KitS).
June 21, 2013 Mr. Scott Batson Site Vice President Oconee Nuclear Station Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672-0752 OCONEE NUCLEAR STATION, UNITS 1,2, AND 3, REQUEST FOR ADDITIONAL INFORMATION REGARDING AMENDMENT APPLICATION RELATED TO REACTOR COOLANT SYSTEM PRESSURE AND TEMPERATURE LIMIT CURVES (TAC NOS. MF0763, MF0764, AND MF0765)
Dear Mr. Batson:
By letter dated February 22,2013, Duke Energy Carolinas, LLC (Duke), submitted an application for a proposed amendment for the Oconee Nuclear Station, Units 1, 2, and 3, which would revise the Technical Specifications for the Reactor Coolant System pressure-temperature limit curves. The Nuclear Regulatory Commission (NRC) staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). On June 10, 2013, the Duke staff indicated that a response to the RAI would be provided within 60 days of the date of this letter. If you have any questions, please call me at 301-415-2901.
Sincerely, IRA! John P. Boska, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287
Enclosure:
Request for Additional Information cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsAcrsAcnw_MailCtr Resource RidsNrrDorlDpr Resource LPLlI-1 RlF RidsNrrLASFigueroa Resource RidsNrrDorlLp2-1 Resource RidsNrrPMOconee RidsRgn2MailCenter Resource RidsNrrDeEvib SSheng ADAMS Accession No.: ML13165A147
- See memo dated 5/30/13 OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/EVIB/BC*
NRR/LPL2-1/BC NRR/LPL2-1/PM NAME ,IBoska SFigueroa SRosenberg RPascarelii ,IBoska DATE 6/17113 6/19/13 5/30/13 6/21113 6/21/13 OFFICIAL RECORD COpy