U-603082, Forwards Monthly Operating Rept for July 1998 for Clinton Power Station,Unit 1.Encl Rept Was Not Forwarded IAW TS Requirement Due to Administrative Error

From kanterella
(Redirected from U-603082)
Jump to navigation Jump to search
Forwards Monthly Operating Rept for July 1998 for Clinton Power Station,Unit 1.Encl Rept Was Not Forwarded IAW TS Requirement Due to Administrative Error
ML20151Y652
Person / Time
Site: Clinton Constellation icon.png
Issue date: 09/16/1998
From: Sipek J
ILLINOIS POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20151Y657 List:
References
U-603082, NUDOCS 9809180302
Download: ML20151Y652 (1)


Text

a e

. Ilknois Power Company Chnton Power Station P.O. Box 678 i Cknton,IL 61727 l Tel 217 935-8881 Joseph V. Sipek k Director - Licensing

--. c- ,,,,

8E.100c )

l September 16,1998 Docket No. 50-461 10CFR50.36 l l

,. U.S.-Nuclear Regulatory Commission Document Control Desk

, Washington, D.C. 20555

Subject:

Clinton Power Station, Unit 1 Facility Operating License NPF-62

- July 1998 Monthly Ooeratina Report  !

Dear Madam or Sir:

Please find in Attachment I the Monthly Operating Report for Clinton Power Station (CPS), Unit 1, for the period ending July 31,1998. Per CPS Technical l Specifications, the Monthly Operating Report is due no later than the fifteenth of each

month following the calendar month covered by the report The July 1998, CPS

! Monthly Operating Report was not forwarded in accordance with the Technical Specification requirement due to u administrative error.

sincerely yours, 4

9909180302 990916 PDR ADOCK 05000461

"~

e h-R PDR i~ Joseph V. Sipek Director - Licensing WED/lar Attachments -

hU l cc: NRC Region III Regional Administrator NRC Resident Office, V-690

. 1ggn49 iiiinois Department of Nuclear Sarety D. Zemel, T-31Z ~