Search by property
Jump to navigation
Jump to search
This page provides a simple browsing interface for finding entities described by a property and a named value. Other available search interfaces include the page property search, and the ask query builder.
List of results
- PNO-II-80-022, on 800208,w/both Units Operating,Both Seismic Recorders Activated.Checks Made W/Other Agencies Revealed No Seismic Activity.Licensee Implemented Emergency Procedure.Evidently Caused by Welding Activities + (ML20126B265)
- PNO-I-80-026, on 800125,27 & 0213,pinhole Leaks Found in Transfer Pipe from Condensate Storage Tank During Insp of Pipe.Contaminated Soil Was Removed & Pipe Replaced.Media Interest Expected + (ML20126B267)
- PNO-IV-85-027, on 850609,facility Achieved Mode 1.Plant Presently at 10% Power.Nrc Does Not Plan to Issue Press Release + (ML20126B268)
- ML20126B269 + (ML20126B269)
- PNO-II-80-023, on 800213,during Surveillance Test,Reactor Trip Occurred When Mechanic Accidentally Struck Instrument W/Wrench.Bldg Was Evacuated Due to Increased Radioactive Gas.Individual Has Small Contamination Level on Clothing + (ML20126B270)
- ML20126B271 + (ML20126B271)
- ML20126B272 + (ML20126B272)
- ML20126B273 + (ML20126B273)
- PNO-I-92-075, upon Investigation of Alarm Printed Out on Auxiliary Typewriter on 921213,operators Determined That Cpu for Overhead Annunciator (Oha) Had Failed to Perform, Resulting in Loss of Oha Sys for 1 H & 41 Minutes + (ML20126B275)
- ML20126B276 + (ML20126B276)
- ML20126B278 + (ML20126B278)
- ML20126B279 + (ML20126B279)
- ML20126B280 + (ML20126B280)
- ML20126B281 + (ML20126B281)
- ML20126B282 + (ML20126B282)
- ML20126B283 + (ML20126B283)
- ML20126B284 + (ML20126B284)
- ML20126B286 + (ML20126B286)
- ML20126B287 + (ML20126B287)
- ML20126B289 + (ML20126B289)
- ML20126B290 + (ML20126B290)
- IR 05000333/1992020 + (ML20126B291)
- ML20126B292 + (ML20126B292)
- ML20126B293 + (ML20126B293)
- ML20126B294 + (ML20126B294)
- ML20126B296 + (ML20126B296)
- 05000373/LER-1992-013-07, :on 921114,DG 1A Automatically Started While Disconnecting Test Equipment at Completion of Instrument Procedure.Caused by Actuation of Rosemount Level Transmitters.Dg Shut Down + (ML20126B297)
- ML20126B298 + (ML20126B298)
- ML20126B299 + (ML20126B299)
- ML20126B302 + (ML20126B302)
- 05000293/LER-1979-052-03, /03X-0:on 790705,fire Detector Alarm,Initiating from HPCI Turbine Compartment,Annunciated on Panel C114 in Control Room.No Fire Existed.Caused by Moisture in HPCI Area from Steam Leak + (ML20126B303)
- ML20126B304 + (ML20126B304)
- 05000293/LER-1979-053-04, /04X-0:on 790710 & 0807,temp Rise of Condenser Cooling Water Between Intake Structure & Discharge to Bay Exceeded 32 F.Caused by Seasonally High Ambient Water Temp. No Significant Adverse Effects to Marine Life + (ML20126B305)
- ML20126B306 + (ML20126B306)
- ML20126B307 + (ML20126B307)
- 05000293/LER-1979-054-03, /03X-0:on 790807,w/incoming Power unavailable,24 Kv Shutdown Transformer Tripped Off Line Via Undervoltage Relay Trip Operation.Caused by Blown Fuse & Relay Trip + (ML20126B308)
- ML20126B309 + (ML20126B309)
- ML20126B310 + (ML20126B310)
- IR 05000266/1992017 + (ML20126B312)
- ML20126B313 + (ML20126B313)
- TXX-4485, Deficiency Rept SDAR-178 Re Part 21 Notice from Westinghouse Indicating Core Exit Temp Monitoring Sys Thermocouple Signal May Produce Errors.Initially Reported 850510.Matter Not Reportable Under 10CFR50.55(e) + (ML20126B314)
- ML20126B316 + (ML20126B316)
- ML20126B317 + (ML20126B317)
- ML20126B321 + (ML20126B321)
- ML20126B322 + (ML20126B322)
- ML20126B323 + (ML20126B323)
- ML20126B324 + (ML20126B324)
- PNO-V-80-014, on 800225,earthquake Measuring 5.1 on Richter Scale Occurred.Epicenter Estimated Between Oceanside & San Clemente,Ca.All Facilities in Area Were Called.No Problems Identified + (ML20126B325)
- ML20126B327 + (ML20126B327)
- PNO-III-80-034, on 800220,industrial Accident Occurred at Const Site.Mobile Crane Got Stuck in Mud.Operator Raised Load to Try to Free Crane & It Tipped Over & Killed Him + (ML20126B328)
- ML20126B330 + (ML20126B330)