IR 05000400/202300430 January 2024Integrated Inspection Report 05000400/2023004
ML24025A15925 January 2024NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - Rvi AMP and Inspection Plan (L-2023-LLL-0016)
RA-23-0325, Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX8 January 2024Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEXPacking leak
Offsite Dose Calculation Manual
Operating Basis Earthquake
Exemption Request
Earthquake
Pressure Boundary Leakage
Grace period
Unidentified leakage
Operational leakage
RA-24-0006, 10 CFR 50.54(q) Evaluation4 January 202410 CFR 50.54(q) Evaluation
ML23341A1527 December 2023December 11, 2023 Public Meeting - RIPE Exemption Request - Licensee SlidesLarge early release frequency
Exemption Request
RA-23-0318, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation4 December 2023Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications ImplementationExemption Request
PMNS20231317, Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant Planned Exemption Request to Be Submitted the Under Risk-Informed Process for Evaluations (RIPE)21 November 2023Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant Planned Exemption Request to Be Submitted the Under Risk-Informed Process for Evaluations (RIPE)Exemption Request
RA-23-0284, RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation16 November 2023RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications ImplementationTime of Discovery
Fitness for Duty
Contraband
Condition Adverse to Quality
Safeguards Contingency Plan
Preemption Authority
Exemption Request
ML23356A13916 November 2023Marsh USA, Inc - Certificate of Liability Insurance
ML23317A34614 November 2023Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1Fire Protection Program
IR 05000400/20230039 November 2023Integrated Inspection Report 05000400/2023003Enforcement Discretion
Probabilistic Risk Assessment
Met Tower
Functionality Assessment
FLEX
Significance Determination Process
Operability Determination
Fire Protection Program
ML23326A0408 November 2023Comment (1) of Krystle Mcclain on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Energy Harbor Corp.; Energy Harbor Generation Llc.; Energy Harbor Nuclear Corp.; Perry Nuclear Power Plant, Unit 1License Renewal
Environmental Justice
RA-23-0276, Response to Request for Additional Information Regarding License Amendment Request to Align Certain Technical Specification Requirements with Industry Standards Provided in Improved Standard Technical Specific6 November 2023Response to Request for Additional Information Regarding License Amendment Request to Align Certain Technical Specification Requirements with Industry Standards Provided in Improved Standard Technical SpecificSafe Shutdown
Surveillance Frequency Control Program
RA-23-0281, Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes1 November 2023Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of ChangesExemption Request
Siren
ML23346A1326 October 2023Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently PublishedPandemic
COVID-19
Siren
ML23234A1703 October 2023Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical SpecificationsIncorporated by reference
ML23256A08825 September 2023Issuance of Alternative to Steam Generator WeldsHydrostatic
Probabilistic Risk Assessment
Incorporated by reference
Finite Element Analysis
RA-23-0218, Review Request for the Aging Management Program and Inspection Plan for the Shearon Harris Nuclear Power Plant, Unit 1, Reactor Vessel Internals21 September 2023Review Request for the Aging Management Program and Inspection Plan for the Shearon Harris Nuclear Power Plant, Unit 1, Reactor Vessel InternalsSafe Shutdown
Unanalyzed Condition
Non-Destructive Examination
Nondestructive Examination
Functionality Assessment
Aging Management
Stress corrosion cracking
Eddy Current Testing
License Renewal
Subsequent License Renewal
EVT-1
Power change
Power Uprate
Measurement Uncertainty Recapture
Thermal fatigue
RA-23-0225, Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes20 September 2023Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of ChangesMet Tower
Exemption Request
ML23195A07829 August 2023Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1Offsite Dose Calculation Manual
Annual Radioactive Effluent Release Report
Surveillance Frequency Control Program
Stress corrosion cracking
Pressure Boundary Leakage
Fire Protection Program
Unidentified leakage
Operational leakage
ML23241A00225 August 2023Paragon Final Part 21 Report on Defect with Eaton/Cutler Hammer Size 4 and 5 Freedom Series Contactors Modified by Paragon with Special Coils And/Or with RTV to Improve the Securing of Shading Coils
IR 05000400/202300523 August 2023Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005)Cyber Security
ML23234A25422 August 2023RQ Inspection Notification Letter
ML23221A3703 August 2023Paragon Energy Solutions, 10CFR Part 21 Initial Notification: P21-08032023-IN, Rev. 0
IR 05000400/202340226 July 2023Security Baseline Inspection Report 05000400/2023402
IR 05000400/202300224 July 2023Integrated Inspection Report 05000400/2023002High winds
High Radiation Area
Temporary Modification
Functionality Assessment
Locked High Radiation Area
Operability Determination
Fire Protection Program
RA-23-0195, Notice of Intentions Regarding Apparent Violation Response; (EA-23-060)20 July 2023Notice of Intentions Regarding Apparent Violation Response; (EA-23-060)
RA-23-0136, Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)20 July 2023Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)Non-Destructive Examination
RA-23-0154, Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)20 July 2023Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)Non-Destructive Examination
Weld Overlay
Finite Element Analysis
IR 05000400/202344017 July 2023Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover LetterSignificance Determination Process
Affidavit
RA-23-0142, Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require7 July 2023Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance RequireIncorporated by reference
Surveillance Frequency Control Program
Operational leakage
ML23177A19926 June 2023NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-23-0005 - LAR to Align Certain TSs with ISTS (L-2023-LLA-0078)
ML23157A32026 June 2023Summary of April 26, 2023, Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant, Unit 1 Planned License Amendment Request Related to Turbine Control System and Reactor Protection System CircuitryHot Short
High winds
Probabilistic Risk Assessment
Large early release frequency
ML23172A01320 June 2023Duke Fleet - Correction to June 2, 2023, Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement FrequenciesSurveillance Frequency Control Program
RA-23-0135, Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory7 June 2023Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory
ML23153A1892 June 2023Duke Fleet - Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement FrequenciesSurveillance Frequency Control Program
ML23151A12331 May 2023Public Meeting Summary - 2022 Annual Assessment Meeting Regarding Shearon Harris Nuclear Plant
RA-23-0005, License Amendment Request to Align Certain Technical Specification Requirements with Industry Standards Provided in Improved Standard Technical Specifications31 May 2023License Amendment Request to Align Certain Technical Specification Requirements with Industry Standards Provided in Improved Standard Technical SpecificationsSafe Shutdown
Boric Acid
High Radiation Area
Offsite Dose Calculation Manual
Anticipated operational occurrence
Probabilistic Risk Assessment
Incorporated by reference
Locked High Radiation Area
Surveillance Frequency Control Program
Process Control Program
ML23151A34830 May 2023Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)Incorporated by reference
RA-23-0041, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations30 May 2023Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations
ML23142A27322 May 2023Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)Incorporated by reference
IR 05000400/202430115 May 2023Notification of Licensed Operator Initial Examination 05000400/2024301
IR 05000400/202300110 May 2023Integrated Inspection Report 05000400 2023001Internal Flooding
Enforcement Discretion
Temporary Modification
Functionality Assessment
FLEX
Significance Determination Process
Operability Determination
Fuel cladding
Fire Protection Program
Power change
IR 05000400/20234044 May 2023Cyber Security Inspection Report 05000400/2023404Cyber Security
Affidavit
ML23124A1214 May 2023Acceptance of Requested Licensing Action Duke Fleet Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)
ML23118A0761 May 2023Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XIIncorporated by reference
ML23118A13928 April 2023Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment ChangesSafe Shutdown
Boric Acid
Shutdown Margin
Ultimate heat sink
Fire Barrier
Anticipated operational occurrence
Tornado Missile
Internal Flooding
Hydrostatic
Past operability
Fire impairment
Nondestructive Examination
Incorporated by reference
Aging Management
Missed surveillance
Surveillance Frequency Control Program
Stress corrosion cracking
Operability Determination
License Renewal
Turbine Missile
Fuel cladding
Pressure Boundary Leakage
Offsite Circuit
Power change
Unidentified leakage
Overspeed trip
Operational leakage
RA-23-0049, Enclosure 1 - Shearon Harris Nuclear Power Plant, Unit 1, Updated Final Safety Analysis Report, Amendment 65 - Redacted Version (Publicly Available Information)28 April 2023Enclosure 1 - Shearon Harris Nuclear Power Plant, Unit 1, Updated Final Safety Analysis Report, Amendment 65 - Redacted Version (Publicly Available Information)
PMNS20230561, Annual Assessment Meeting26 April 2023Annual Assessment Meeting
ML23114A06726 April 2023April 26 2023 Public Meeting - RIPE LAR - Licensee SlidesHot Short
High winds
Internal Flooding
Probabilistic Risk Assessment
Large early release frequency