W3F1-2007-0037, License Amendment Request NPF-38-271 to Support Next Generation Fuel2 August 2007Entergy
Walsh K
Entergy Nuclear South
License Amendment Request NPF-38-271 to Support Next Generation FuelRequest
W3F1-2007-0038, Emergency Core Cooling System Performance Analysis9 August 2007Entergy
Walsh K
Entergy Nuclear South
Emergency Core Cooling System Performance AnalysisRequest
L-07-130, Submittal of Pressure and Temperature Limits Report, Revision 419 September 2007FirstEnergy
Sena P
Submittal of Pressure and Temperature Limits Report, Revision 4Request
W3F1-2007-0045, Supplement to the ECCS Performance Analysis Submittal in Support of Next Generation Fuel - 1999 EM Optional Steam Cooling Model Justification4 October 2007Entergy
Entergy Nuclear South
Murillo R
Supplement to the ECCS Performance Analysis Submittal in Support of Next Generation Fuel - 1999 EM Optional Steam Cooling Model JustificationRequest
W3F1-2008-0004, Supplement to Amendment Request NPF-38-271 to Support Next Generation Fuel17 January 2008Entergy
Entergy Nuclear South
Cook K
Supplement to Amendment Request NPF-38-271 to Support Next Generation FuelSupplement
ML08018028422 January 2008Kalyanam N
NRC/NRR/ADRO/DORL/LPLIV
Request for Additional Information on the Revised Emergency Core Cooling System Performance Analysis Supporting the Next Generation FuelRAI
ML0801600597 February 2008Kalyanam N
NRC/NRR/ADRO/DORL/LPLIV
Request for Additional Information Regarding Review of Supplemental Information to ECCS Performance Analysis in Support of Next Generation Fuel, Optional Spacer Grid Steam Cooling Transfer ModelRAI
ML08038043312 February 2008Kalyanam N
NRC/NRR/ADRO/DORL/LPLIV
Request for Additional Information License Amendment Request to Modify TS 6.9.1.11.1, Core Operating Limits, TS 3.5.1, Safety Injection Tanks, & TS 3.6.1.5, Containment Air Temperature to Support Next Generation FuelRAI
ML0805902623 March 2008Kent Howard
NRC/NRR/ADRO/DLR/REBB
Request for Additional Information, License Renewal Application (TAC Nos. MD6593 and MD6594)RAI
ML0806402165 March 2008Kent Howard
NRC/NRR/ADRO/DLR
RAI for the Review of the Beaver Valley Power Station, Units 1 and 2, LRARAI
ML0806010205 March 2008Kent Howard
NRC/NRR/ADRO/DLR
RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRARAI
W3F1-2008-0021, Supplement 2 RAI Response to Amendment Request NPF-38-271 to Support Next Generation Fuel10 March 2008Entergy
Entergy Nuclear South
Cook K
Supplement 2 RAI Response to Amendment Request NPF-38-271 to Support Next Generation FuelSupplement
ML08072028821 March 2008Kent Howard
NRC/NRR/ADRO/DLR
Request for Additional Information, Section B.2.35RAI
ML08084048424 March 2008Entergy
Robert Williams
E-mail from Ronald L. Williams, Entergy, to N. Kalyanam, NRC, RAI Response to On-Going Processes to Support Next Generation Fuel.Other
ML08079074426 March 2008Kent Howard
NRC/NRR/ADRO/DLR
Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application, for Sections B.2.6, B.2.19, and B.2.23RAI
L-08-122, Reply to Request for Additional Information for the Review of the License Renewal Application and Revisions to License Renewal Application Boundary Drawings31 March 2008FirstEnergy
Sena P
Reply to Request for Additional Information for the Review of the License Renewal Application and Revisions to License Renewal Application Boundary DrawingsResponse to RAI
ML0807903921 April 2008Kent Howard
NRC/NRR/ADRO/DLR
RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRARAI
ML0807905381 April 2008Kent Howard
NRC/NRR/ADRO/DLR
RAI for the Review of the Beaver Valley Power Station, Units 1 & 2, LRARAI
L-08-124, Reply to Request for Additional Information for Review of the License Renewal Application and License Renewal Application Amendment No. 52 April 2008FirstEnergy
Sena P
Reply to Request for Additional Information for Review of the License Renewal Application and License Renewal Application Amendment No. 5Response to RAI
ML0810003283 April 2008FirstEnergyDrawing Lr 1-14A-1, Rev. 7, Sample System.Other
ML0810002963 April 2008FirstEnergy
Sena P P
Reply to Request for Additional Information for the Review of License Renewal Application, Amendment No. 4, and Revised License Renewal Boundary DrawingsResponse to RAI
ML0810003223 April 2008FirstEnergyDrawing Lr 1-07-2, Rev. 4, Chemical and Volume Control System.Other
ML0810003313 April 2008FirstEnergyDrawing Lr 1-24-1, Rev. 6, Feedwater System.Other
L-08-123, Drawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System.3 April 2008FirstEnergyDrawing Lr 1-46-2, Rev. 5, Post DBA Hydrogen Analyzer System.Other
ML0810003233 April 2008FirstEnergyDrawing Lr 1-07-3, Rev. 6, Chemical and Volume Control System.Other
ML0810003243 April 2008FirstEnergyDrawing Lr 1-08-1, Rev. 4, Boron Recovery Degasifiers.Other
ML0810003263 April 2008FirstEnergyDrawing Lr 1-09-2, Rev. 4, Vent and Drain System.Other
ML0807907353 April 2008Kent Howard
NRC/NRR/ADRO/DLR
RAI for the Reveiw of the Beaver Valley, Units 1 and 2, License Renewal ApplicationRAI
ML0810003273 April 2008FirstEnergyDrawing Lr 1-12-1, Rev. 5, Containment Vacuum and Leakage Monitoring System.Other
ML0810003293 April 2008FirstEnergyDrawing Lr 1-14A-2, Rev. 5, Sample System.Other
ML0810003303 April 2008FirstEnergyDrawing Lr 1-19-1, Rev. 5, Gaseous Waste Disposal System.Other
ML0810003323 April 2008FirstEnergyDrawing Lr 1-30-1, Rev. 5, River Water System.Other
ML08088001515 April 2008Kalyanam N
NRC/NRR/ADRO/DORL/LPLIV
Tech Spec Pages for Amendment 214, Request to Support Next Generation Fuel; Review and Approval of ECCS Performance Analysis; and Review and Approval of Supplement to ECCS Performance AnalysisOther
ML08088001415 April 2008Kalyanam N
NRC/NRR/ADRO/DORL/LPLIV
License Amendment 214, Request to Support Next Generation Fuel; Review and Approval of ECCS Performance Analysis; and Review and Approval of Supplement to ECCS Performance AnalysisApproval
ML08098048317 April 2008Kent Howard
NRC/NRR/ADRO/DLR
Request for Additional Information, Review of License Renewal ApplicationRAI
ML08105033317 April 2008Kent Howard
NRC/NRR/ADRO/DLR
Request for Additional Information, Review of License Renewal ApplicationRAI
L-08-143, Reply to Request for Additional Information for Review of License Renewal Application and License Renewal Application Amendment No. 618 April 2008FirstEnergy
Sena P
Reply to Request for Additional Information for Review of License Renewal Application and License Renewal Application Amendment No. 6Response to RAI
L-08-144, Reply to Request for Additional Information for the Review of License Renewal Application25 April 2008FirstEnergy
Sena P
Reply to Request for Additional Information for the Review of License Renewal ApplicationResponse to RAI
ML08113039428 April 2008Kent Howard
NRC/NRR/ADRO/DLR
Request for Additional Information, Review of License Renewal ApplicationRAI
L-08-146, Reply to Request for Additional Information for Review, License Renewal Application and License Renewal Application Amendment No. 730 April 2008FirstEnergy
Sena P
Reply to Request for Additional Information for Review, License Renewal Application and License Renewal Application Amendment No. 7Response to RAI
ML08105027030 April 2008Kent Howard
NRC/NRR/ADRO/DLR
Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal ApplicationRAI
L-08-174, Request for Revised Submittal Date for Reply to Request for Additional Information for the Review of the License Renewal Application2 May 2008FirstEnergy
Sena P
Request for Revised Submittal Date for Reply to Request for Additional Information for the Review of the License Renewal ApplicationResponse to RAI
L-08-149, Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application5 May 2008FirstEnergy
Sena P
Reply to Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal ApplicationResponse to RAI
ML0814104168 May 2008FirstEnergy
Sena P P
Transmittal of Correction to Reply to RAI for the Review of License Renewal Application, License Renewal Application Amendment No. 8 & Revised License Renewal Boundary DrawingsRequest
ML0810505438 May 2008Kent Howard
NRC/NRR/ADRO/DLR
Request for Additional Information, Sections 3.5.2.2, B.2.1, B.2.3 and 4.6 of License Renewal ApplicationRAI
ML0811604678 May 2008Kent Howard
NRC/NRR/ADRO/DLR
Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal ApplicationRAI
ML0812009208 May 2008Kent Howard
NRC/NRR/ADRO/DLR
Request for Additional Information for the Review of the Beaver Valley Power Station, Units 1 and 2, License Renewal Application (TAC MD6593 and MD6594)RAI
ML0812605359 May 2008Kalyanam N
NRC/NRR/ADRO/DORL/LPLIV
Correction to Amendment 214 Request to Support Next Generation Fuel; Review & Approval of Revised ECCS Performance Analysis; & Review & Approval of Supplement to ECCS Performance Analysis (Tac Nos. MD6299, MD6363, & MD6954)Other
ML0812700369 May 2008NRC/NRR/ADRO/DORL/LPLIVTech Spec Page for Correction to Amendment 214 Request to Support Next Generation Fuel; Review & Approval of Revised ECCS Performance Analysis; & Review & Approval of Supplement to ECCS Performance AnalysisOther
ML08112053915 May 2008Kent Howard
NRC/NRR/ADRO/DLR
Request for Additional Information, License Renewal Application (TAC Nos. MD6593 and MD6594)RAI