ML22339A001 | 22 December 2022 | Acceptance of Requested Licensing Action Amendment Request for Common Emergency Plan | |
IR 05000250/2022011 | 20 December 2022 | Design Basis Assurance Inspection (Programs) Inspection Report 05000250/2022011 and 05000251/2022011 | Safe Shutdown Internal Flooding Incorporated by reference Significance Determination Process Earthquake Power-Operated Valves Weak link |
OI 2-2022-016, Investigation Summary, Office of Investigations Case Number 2-2022-016 Dated 12/19/2022 | 19 December 2022 | Investigation Summary, Office of Investigations Case Number 2-2022-016 Dated 12/19/2022 | |
ML22322A181 | 15 December 2022 | Audit Plan for Turkey Point Digital I&C License Amendment Request (Public Version) | |
L-2022-185, Turkey Points, Units 3 & 4; Seabrook Station; and Point Beach, Units 1 and 2 - Supplement to License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 | 9 December 2022 | Turkey Points, Units 3 & 4; Seabrook Station; and Point Beach, Units 1 and 2 - Supplement to License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 | |
ML22327A240 | 8 December 2022 | Summary of October 27, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests | |
ML22336A026 | 7 December 2022 | December 7 2022 24-Month Fuel Cycle Public Meeting Licensee Slides | Surveillance Frequency Control Program Exemption Request Fuel cladding |
PMNS20221243, Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Florida Power & Light Company (FPL) to Discuss the Planned Digital Instrumentation and Controls License Amendment Request for Turkey Point Nuclear Generating, Unit Nos. 3 | 2 December 2022 | Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Florida Power & Light Company (FPL) to Discuss the Planned Digital Instrumentation and Controls License Amendment Request for Turkey Point Nuclear Generating, Unit Nos. 3 and | |
L-2022-181, Response to Request for Additional Information Regarding License Amendment Request for the Technical Specifications Conversion to NUREG-1431, Revision 5 | 1 December 2022 | Response to Request for Additional Information Regarding License Amendment Request for the Technical Specifications Conversion to NUREG-1431, Revision 5 | |
IR 05000250/2022010 | 29 November 2022 | Triennial Fire Protection Inspection Report 05000250/2022010 and 05000251/2022010 | Safe Shutdown Time Critical Operator Action Fire Protection Program Very Early Warning Fire Detection |
ML22307A115 | 28 November 2022 | Authorization of Relief Request No. 10 Part II Related to Repair of Intake Cooling Water Discharge Piping (EPID L-2022-LLR-0032) (Non-Proprietary) | Ultimate heat sink Coatings Through-Wall Leak |
ML23103A047 | 28 November 2022 | Comment (7) E-mail Regarding T.P. 3&4 Suppl Dseis | |
PMNS20221177, Pre-submittal Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Planned License Amendment Request for Transition to a 24-month Fuel Cycle Turkey Point Generating Unit Nos. 3 and 4 | 22 November 2022 | Pre-submittal Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Planned License Amendment Request for Transition to a 24-month Fuel Cycle Turkey Point Generating Unit Nos. 3 and 4 | |
ML22311A558 | 22 November 2022 | Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep | |
ML22321A323 | 18 November 2022 | License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Supplement | License Renewal Subsequent License Renewal Environmental Justice |
L-2022-182, Emergency Response Data System (Eros) Changes | 17 November 2022 | Emergency Response Data System (Eros) Changes | |
L-2022-180, CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums | 9 November 2022 | CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums | |
ML22312A573 | 8 November 2022 | Comment (2) of William Kenneth Dean on Notice of Intent to Prepare a Supplement to the Final Supplemental Environmental Impact Statement for the Subsequent License Renewal for Turkey Point Nuclear Generating Unit Nos. 3 and 4 | Aging Management Subsequent License Renewal Environmental Justice |
ML22311A475 | 7 November 2022 | NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - ITS | Incorporated by reference Power Uprate |
IR 05000250/2022402 | 7 November 2022 | Security Baseline Inspection Report 05000250 2022402 and 05000251 2022402 | |
ML23103A035 | 7 November 2022 | Comment (5) E-mail Regarding T.P. 3&4 Suppl Dseis | License Renewal Subsequent License Renewal |
ML23103A045 | 7 November 2022 | Comment (6) E-mail Regarding T.P. 3&4 Suppl Dseis | Aging Management Subsequent License Renewal Environmental Justice |
ML22312A576 | 7 November 2022 | Comment (4) of Anonymous on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Florida Power& Light Company Turkey Point Nuclear Generating Unit Nos. 3 and 4 | |
ML22312A574 | 7 November 2022 | Comment (3) of Caroline Reiser on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Florida Power& Light Company Turkey Point Nuclear Generating Unit Nos. 3 and 4 | License Renewal Subsequent License Renewal |
ML22314A095 | 7 November 2022 | Comment (5) of Talbert Cypress on Reauthorizing the Turkey Point Nuclear Generating Station Beyond Its Intended Life Creates Immediate Harm and Manifold Risks | COVID-19 |
PMNS20221132, Meeting with NextEra Energy/Florida Power & Light Company to Discuss the St. Lucie Plant, Units 1 and 2 and Turkey Point Nuclear Generating, Units 3 and 4 Improved Technical Specifications License Amendment Requests | 31 October 2022 | Meeting with NextEra Energy/Florida Power & Light Company to Discuss the St. Lucie Plant, Units 1 and 2 and Turkey Point Nuclear Generating, Units 3 and 4 Improved Technical Specifications License Amendment Requests | |
IR 05000250/2022003 | 31 October 2022 | Integrated Inspection Report 05000250/2022003 and 05000251/2022003 | Ultimate heat sink Internal Flooding Functionality Assessment FLEX Operability Determination Fire Protection Program |
ML22286A126 | 28 October 2022 | Review of the Fall 2021 Steam Generator Tube Inspections During Refueling Outage No. 32 | |
L-2022-168, and Point Beach Units 1 and 2 - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report | 26 October 2022 | and Point Beach Units 1 and 2 - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report | |
ML22303A042 | 20 October 2022 | Updated Final Safety Analysis Report, Appendix B, Questions and Responses Related to Initial NRC Review of Operating License Application | |
ML22303A034 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 12, Conduct of Operations | Grab sample Annual Radioactive Effluent Release Report Surveillance Frequency Control Program Process Control Program |
ML22303A027 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 5, Structures | Safe Shutdown Boric Acid Tornado Missile Safe Shutdown Earthquake Internal Flooding Hydrostatic Coatings Operating Basis Earthquake Finite Element Analysis FLEX Tornado-Generated Missile Aging Management Tornado Missile Protection Design basis earthquake Flooding Focused Evaluation License Renewal Subsequent License Renewal Earthquake Control of Heavy Loads Turbine Missile Liquid penetrant Power Uprate |
L-2022-171, 10 CFR 50.59(d)(2) Summary Report | 20 October 2022 | 10 CFR 50.59(d)(2) Summary Report | Temporary Modification |
L-2022-170, Updated Final Safety Analysis Report, Cover Sheet | 20 October 2022 | Updated Final Safety Analysis Report, Cover Sheet | |
ML22303A040 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 17, Aging Management Programs and Time-Limited Aging Analysis Activities | Boric Acid Ultimate heat sink Non-Destructive Examination Fire Barrier Weld Overlay Coatings Nondestructive Examination Incorporated by reference Aging Management Foreign Material Exclusion Moisture barrier License Renewal Subsequent License Renewal Control of Heavy Loads Biofouling EVT-1 Through-Wall Leakage Fire Protection Program Dissimilar Metal Weld Power Uprate |
ML22303A032 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion System | |
ML22303A038 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 15, Technical Specifications | |
ML22303A037 | 20 October 2022 | Updated Final Safety Analysis Report, Appendix 14A, Core Operating Limits Report (COLR) | Shutdown Margin |
ML22303A030 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 8, Electrical Systems | Safe Shutdown Boric Acid Fire Barrier Tornado-Generated Missile Surveillance Frequency Control Program Open Phase Condition License Renewal Earthquake |
ML22303A016 | 20 October 2022 | Updated Final Safety Analysis Report and License Renewal 10 CFR 54.37(b) Report | |
ML22303A033 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 11, Waste Disposal and Radiation Protection System | High Radiation Area Grab sample Offsite Dose Calculation Manual Anticipated operational occurrence Post Accident Monitoring Probabilistic Risk Assessment Fuel cladding Power Uprate Overexposure |
ML22303A041 | 20 October 2022 | Updated Final Safety Analysis Report, Appendix a, a Functional Evaluation of the Components of the Systems Which Are Shared by the Two Units | Boric Acid |
ML22303A039 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 16, Aging Management Programs and Time-Limited Aging Analyses Activities | Boric Acid Weld Overlay Aging Management Foreign Material Exclusion Moisture barrier Fire Protection Program |
ML22303A028 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 6, Engineered Safety Features | Boric Acid Stroke time Hydrostatic Earthquake Power Operated Valves Fuel cladding Liquid penetrant GOTHIC |
ML22303A031 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 9, Auxiliary and Emergency Systems | Safe Shutdown Boric Acid High winds Shutdown Margin Loop seal Ultimate heat sink Grab sample Anticipated operational occurrence Tornado Missile Internal Flooding Hydrostatic Probabilistic Risk Assessment Tornado Generated Missile Earthquake Control of Heavy Loads Fuel cladding Fire Protection Program Power change Coast down GOTHIC Power Uprate |
ML22303A024 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 2, Site and Environment | Offsite Dose Calculation Manual Safe Shutdown Earthquake Probabilistic Risk Assessment Operating Basis Earthquake Earthquake |
ML22303A022 | 20 October 2022 | Updated Final Safety Analysis Report, List of Effective Pages | |
ML22303A025 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 3, Reactor | Boric Acid Shutdown Margin Anticipated operational occurrence Hydrostatic Exemption Request Earthquake Fuel cladding Power change Flow Induced Vibration GOTHIC |
ML22303A023 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 1, Introduction and Summary | |
ML22303A029 | 20 October 2022 | Updated Final Safety Analysis Report, Chapter 7, Instrument and Control | Safe Shutdown Boric Acid Shutdown Margin Grab sample Offsite Dose Calculation Manual Anticipated operational occurrence Post Accident Monitoring Earthquake Fuel cladding Backfit Power change Power Uprate Measurement Uncertainty Recapture |