Semantic search
Jump to navigation
Jump to search
Issue date | Title | Topic | |
---|---|---|---|
ML20198S194 | 30 November 1998 | Technical Evaluation Rept on Second 10-Year Interval Inservice Insp Program Plan,Southern Nuclear Operating Co, Vogtle Electric Generating Plant,Units 1 & 2 | Boric Acid Hydrostatic Nondestructive Examination VT-2 Incorporated by reference Dissimilar Metal Weld |
ML20101S041 | 30 November 1995 | Plant TER on Individual Plant Exam Back-End Analysis | Mission time Internal Flooding Fuel cladding |
ML20101S045 | 20 November 1995 | TER of IPE Submittal,Human Reliability Analysis, Final Rept | Internal Flooding Probabilistic Risk Assessment |
ML20101S038 | 15 November 1995 | Plant TER on Individual Plant Exam Front End Analysis | Safe Shutdown Packing leak Mission time Internal Flooding Probabilistic Risk Assessment |
ML20080A672 | 30 September 1994 | Technical Evaluation Rept,Evaluation of Util Response to Suppl 1 to NRC Bulletin 90-01:Vogtle-1/-2 | |
ML20091D275 | 22 August 1991 | Final Rept SAIC-91/6686, Technical Evaluation Electric Vogtle Electric Generating Plant Units 1 & 2 Station Blackout Evaluation | Safe Shutdown Battery sizing |
ML20043H926 | 31 March 1990 | Draft Rev 0 to, Vogtle Electric Generating Plant Risk-Based Insp Guide (Based on Generic Insights from Probabilistic Risk Assessments for Westinghouse Pwrs). | Probabilistic Risk Assessment |
ML20084T251 | 31 October 1989 | Technical Evaluation Rept on First 10-Yr Interval Inservice Insp Program Plan:Georgia Power Co,Vogtle Electric Generating Plant,Unit 1 | Weld Overlay Hydrostatic VT-2 Incorporated by reference Through-Wall Leak |
ML19332B614 | 31 October 1989 | Conformance to Generic Ltr 83-28,Item 2.2.1--Equipment Classification for All Other Safety-Related Components:Quad Cities 1 & 2, Final Technical Evaluation Rept | Safe Shutdown |
ML20248E212 | 16 August 1989 | Notification of Contract Execution,Mod 16,to Use of TVA Reactor Simulator Facilities at Chattanooga,Tn for Training on Browns Ferry,Sequoyah & Bellefonte Simulators. Contractor:Tva | |
ML20248E219 | 16 August 1989 | Mod 16,reflecting Return of Equipment to Tva,To Use of TVA Reactor Simulator Facilities at Chattanooga,Tn for Training on Browns Ferry,Sequoyah & Bellefonte Simulators | |
ML20247R385 | 16 May 1989 | Notification of Contract Execution,Mod 15,to Use of TVA Reactor Simulator Facilities at Chattanooga,Tn,For Training on Browns Ferry,Sequoyah & Bellefonte Simulators. Contractor:Tva | |
ML20247R394 | 16 May 1989 | Mod 15,extending Period of Performance,Providing Addl Work Re Training for NRC Inspectors & Supervisors,Changing NRC Project Officer & Adding TVA Project Manager & Increasing Contract Ceiling & Funding to Use of TVA Reactor.. | |
ML20246B815 | 30 April 1989 | Rev 1 to Conformance to Item 4.5.2 of Generic Ltr 83-28, Duane Arnold,Enrico Fermi-2,Hope Creek,Lasalle County 1 & 2, Limerick 1 & 2,Millstone 1,Monticello,Nine Mile Point 1 & 2 & Oyster Creek, Technical Evaluation Rept | |
ML20246B973 | 31 March 1989 | Conformance to Reg Guide 1.97:Byron 1/2 & Braidwood 1/2, Technical Evaluation Rept | Boric Acid |
ML20236B805 | 13 March 1989 | Monthly Progress Rept for Contract NRC-02-87-004 for Period 890204-890303.Financial Data Available in Central Files | |
ML20205N943 | 31 October 1988 | Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components: Millstone-1 | |
ML20011D101 | 31 July 1988 | Conformance to Generic Ltr 83-28,Item 2.2.1,Equipment Classification for All Other Safety-Related Components: Vogtle-1/-2, Technical Evaluation Rept | |
ML20155B739 | 1 June 1988 | Notification of Contract Execution,Mod 1,to Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee,Pilgrim & Seabrook Resident Sites. Contractor:New England Telephone Co | |
ML20155B753 | 1 June 1988 | Corrected Mod 1,restoring Funds That Was Deobligated & Providing Final Increment of Funding to Contract,To Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee, Pilgrim & Seabrook Resident Sites | |
ML20150D900 | 17 March 1988 | Notification of Contract Execution,Mod 1,to Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee,Pilgrim & Seabrook Resident Sites. Contractor:New England Telephone Co | |
ML20150D909 | 17 March 1988 | Mod 1,deobligating Funds from Total Obligated Amount of Contract & to Correct FIN Number,To Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee,Pilgrim & Seabrook Resident Sites | |
ML20196C164 | 4 February 1988 | Independent Assessment & Analysis, Monthly Progress Rept for Period Ending 880131 | |
ML20205N953 | 31 January 1988 | Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components: Millstone-3 | Safe Shutdown |
ML20205N948 | 31 January 1988 | Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components - Millstone-2 | Safe Shutdown |
ML20149F169 | 11 January 1988 | Contract: Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee,Pilgrim & Seabrook Resident Sites, Awarded to New England Bell Telephone Co | |
ML20149F131 | 11 January 1988 | Notification of Contract Execution: Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee & Pilgrim & Seabrook Resident Sites, Awarded to New England Bell Telephone Co | |
ML20236T746 | 24 November 1987 | Mod 7,extending Period of Performance Through 880930,adding Addl GE Simulator to Contract & Scheduling Four Simulator Courses Through FY88,to Dresden & Perry Simulator | |
ML20236T737 | 24 November 1987 | Notification of Contract Execution,Mod 7,to Dresden & Perry Simulator. Contractor:Ge | |
ML18040B189 | 31 August 1987 | Selected Operating Reactors Issues:Stability Calculations for Grand Gulf 1 & Susquehanna 2 Bwrs. | |
ML20235V152 | 31 August 1987 | Technical Evaluation Rept,Reactor Trip Sys Reliability Conformance to Item 4.5.2 of Generic Ltr 83-28,Peach Bottom 2 & 3,Perry 1 & 2,Pilgrim 1,Quad Cities 1 & 2,River Bend 1, Shoreham,Susquehanna 1 & 2,Vermont Yankee & WNP-2 | |
ML20235M359 | 31 August 1987 | Preliminary Conformance to Reg Guide 1.97:Byron Units 1 & 2 & Braidwood Units 1 & 2, Technical Evaluation Rept | Boric Acid |
ML20237J062 | 19 August 1987 | Technical Evaluation Rept on Duke Power Co McGuire & Catawba Nuclear Stations Spds | Backfit |
ML20237J141 | 17 August 1987 | Facility Sys Analysis Support, Progress Rept 23 for 870713 -0807 | |
ML20236P218 | 10 August 1987 | Mod 1,increasing Total Amount of Contract,To Local Telephone Svc for Yankee Rowe,Vermont Yankee,Main Yankee, Pilgrim & Seabrook Resident Sites | |
ML20236P205 | 10 August 1987 | Notification of Contract Execution,Mod 1,to Local Telephone Svc for Yankee Rowe,Vermont Yankee,Main Yankee,Pilgrim & Seabrook Resident Sites. Contractor:New England Bell Telephone Co | |
ML17347A593 | 31 July 1987 | Retran Code:Transient Analysis Model Qualification, Technical Evaluation Rept | |
ML20236P640 | 31 July 1987 | Review of Recirculation Pump Trip Design for Brunswick Steam Electric Plants, Informal Rept | |
ML20236D918 | 31 July 1987 | Methodology and Application of Surrogate Plant PRA Analysis to the Rancho Seco Power Plant.Task 1 - Analysis of ANO-1 and Oconee PRAs | Probabilistic Risk Assessment Earthquake |
ML18052B193 | 30 June 1987 | Conformance to Item 2.1 (Part 2) of Generic Ltr 83-28, Reactor Trip Sys Vendor Interface,Calvert Cliffs-1 & -2, Millstone-2 & Palisades, Final Informal Rept | |
ML20235M420 | 30 June 1987 | Conformance to Generic Ltr 83-28,Item 2.2.2-Vendor Interface Programs for All Other Safety-Related Components: Vogtle 1 & 2, Informal Rept | |
ML20214R148 | 29 May 1987 | Notification of Contract Execution,Mod 12,to Use of TVA Reactor Simulator Facilities at Chattanooga,Tn for Training on Browns Ferry,Sequoyah & Bellefonte Simulators. Contractor:Tva | |
ML20214R156 | 29 May 1987 | Mod 12,providing Incremental Funds & Increasing Ceiling,To Use of TVA Reactor Simulator Facilities at Chattanooga,Tn for Training on Browns Ferry,Sequoyah & Bellefonte Simulators | |
ML20214Q898 | 30 April 1987 | Conformance to Item 2.1 (Part 2) of Generic Ltr 83-28, Reactor Trip Sys Vendor Interface,Hatch-1 & 2,Millstone-1, Final Rept | |
ML20214R068 | 30 April 1987 | Conformance to Item 2.1 (Part 2) of Generic Ltr 83-28, Reactor Trip Sys Vendor Interface,Arnold,Brunswick-1 & 2, Informal Rept | |
ML18152A583 | 30 April 1987 | Conformance to Item 2.1 (Part 2) of Generic Ltr 83-28, Reactor Trip Sys Vendor Interface,North Anna 1 & 2 & Surry 1 & 2. | |
ML18150A119 | 30 April 1987 | Conformance to Item 2.1 (Part 2) of Generic Ltr 83-28, Reactor Trip Sys Vendor Interface,North Anna 1 & 2 & Surry 1 & 2, Final Informal Rept | |
ML18150A188 | 30 April 1987 | Conformance to Generic Ltr 83-28,Item 2.2.2 - Vendor Interface Programs for All Other Safety-Related Components, North Anna Units 1 & 2 & Surry Units 1 & 2, Informal Rept | |
ML20206S713 | 8 April 1987 | Notification of Contract Execution,Mod 1,to Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee,Pilgrim & Seabrook Resident Sites. Contractor:New England Bell Telephone Co | |
ML20206F071 | 8 April 1987 | Flow-Pattern Results for Tmlb' Accident Sequence in Surry Plant Using Melprog |