Issue date | Title | Topic | |
---|---|---|---|
ML20071G211 | 28 June 1994 | Sys 80+ Emergency Operations Guidelines, Replacement Pp | |
ML20065M297 | 31 May 1994 | Draft Advanced Reactor Research & Development Programs 5-Yr Plan for Advanced Reactor Activities Under Energy Policy Act of 1992 | Safe Shutdown |
ML20065P803 | 9 April 1994 | Proposed Tech Specs Technical Revs Agreed Upon in 940405-06 Meeting | Safe Shutdown Time of Discovery Shutdown Margin High Radiation Area Ultimate heat sink Grab sample Offsite Dose Calculation Manual Anticipated operational occurrence Post Accident Monitoring Hydrostatic Pressure and Temperature Limits Report Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report Process Control Program Fuel cladding Pressure Boundary Leakage Offsite Circuit Fire Protection Program Power change Unidentified leakage |
ML20067D344 | 10 February 1994 | Rev 2 to NPX80-SQP-0101.0, Software Program Manualfor Nuplex 80+ | Post Accident Monitoring Coatings Weak link |
ML20058C306 | 10 November 1993 | Rev 1 to NPX80-SQP-0101.0, Software Program Manual for Nuplex 80+ | |
ML20058C325 | 10 November 1993 | Draft Rev to Sys 80+ Emergency Operations Guidelines, Functional Recovery Guideline | |
ML20059J911 | 5 November 1993 | Draft Sys 80+ Emergency Operations Guideline, Loss of All Feedwater Recovery | Shutdown Margin |
ML20059J941 | 5 November 1993 | Draft Sys 80+ Emergency Operations Guideline, SBO Recovery Guideline | Safe Shutdown Shutdown Margin |
ML20059J933 | 5 November 1993 | Draft Sys 80+ Emergency Operations Guideline, Excess Steam Demand Event Recovery | |
ML20059J919 | 5 November 1993 | Draft Sys 80+ Emergency Operations Guideline, Loss of Offsite Power Recovery Guideline | Shutdown Margin |
ML20059H593 | 3 November 1993 | SG Tube Rupture Recovery Guideline | Shutdown Margin |
ML20059H582 | 3 November 1993 | Diagnostic Actions | |
ML20059H553 | 3 November 1993 | Reactor Trip Recovery Guideline | |
ML20059H522 | 3 November 1993 | Standard Post Trip Actions Recovery Guideline | |
ML20059H599 | 3 November 1993 | LOCA Recovery Guideline | Boric Acid Shutdown Margin Fuel cladding |
ML20059B040 | 11 October 1993 | Proposed Tech Specs Identifying Differences from STS (NUREG-1432) & Basis for Differences | |
ML20058N094 | 30 September 1993 | Plant Designers Operational Support Info Plan for ABB-CE Sys 80+ (Tm) | Safe Shutdown Temporary Modification |
ML20058N085 | 29 September 1993 | Rev 2 to NPX80-IC-DP790-01, Human Factors Program Plan for Sys 80+ (Tm) Std Plant Design | Safe Shutdown Post Accident Monitoring Probabilistic Risk Assessment |
ML20056D815 | 11 August 1993 | Proposed STS 3.1.7, Standby Liquid Control Sys | Probabilistic Risk Assessment |
ML20127M425 | 31 January 1993 | Plant Designer Operational Support Info Plan for ABB-C-E Sys 80+ | |
ML20126F080 | 31 December 1992 | Rev 1 to Design Reliability Assuance Program Plan for Sys 80+ Standard Design | |
ML20113J108 | 31 July 1992 | Sys 80+ Probabilistic Risk Assessment Program Plan | Probabilistic Risk Assessment |
ML20096G066 | 14 May 1992 | Rev 0 to Sys 80+ Reactor Coolant Pump Seal Loss of Seal Cooling,Test Data Rept | |
ML20090D598 | 29 February 1992 | Description of Human Factors Program Plan for Sys 80+ (Tm) Standard Plant Design, for Plant Certification | Safe Shutdown Post Accident Monitoring Backfit |
ML20092B884 | 31 January 1992 | Draft Rev 0 to Reliability Assurance Program Plan for Sys 80+ Nuclear Power Plant | Probabilistic Risk Assessment |