ML23129A287 | 14 September 2022 | Fifth Ten-Year Interval ISI Program and Third Ten-Year Interval Containment Inservice Inspection Program, Revision 4 | Safe Shutdown Weld Overlay Internal Flooding Hydrostatic Probabilistic Risk Assessment Coatings Nondestructive Examination VT-2 Incorporated by reference Aging Management Pressure and Temperature Limits Report Scram Discharge Volume Large early release frequency Operability Determination Moisture barrier License Renewal Earthquake EVT-1 Liquid penetrant Through-Wall Leak Through-Wall Leakage Dissimilar Metal Weld Power Uprate |
ML21130A084 | 21 April 2021 | Fifth Ten-Year Interval Inservice Inspection Program and Third Ten-Year Interval Containment Inservice Inspection Program, Revision 3 | Weld Overlay Coatings Nondestructive Examination VT-2 Incorporated by reference Aging Management Pressure and Temperature Limits Report Scram Discharge Volume Moisture barrier Earthquake EVT-1 Liquid penetrant Through-Wall Leakage Dissimilar Metal Weld |
ML21130A085 | 21 April 2021 | 0 to Updated Final Safety Analysis Report, Appendix J, Inservice Inspection Program | Incorporated by reference |
NLS2021009, Inservice Inspection OAR-1 Owner'S Activity Report | 21 January 2021 | Inservice Inspection OAR-1 Owner'S Activity Report | |
NLS2019005, Inservice Inspection OAR-1 Owner'S Activity Report | 14 February 2019 | Inservice Inspection OAR-1 Owner'S Activity Report | |
NLS2017071, Inservice Inspection Program Fifth Ten-Year Interval 10 CFR 50.55a Relief Requests | 17 August 2017 | Inservice Inspection Program Fifth Ten-Year Interval 10 CFR 50.55a Relief Requests | |
NLS2017006, Inservice Inspection OAR-1 Owner'S Activity Report | 2 February 2017 | Inservice Inspection OAR-1 Owner'S Activity Report | Through Wall Leak |
NLS2015003, Inservice Inspection OAR-I Owner'S Activity Report | 28 January 2015 | Inservice Inspection OAR-I Owner'S Activity Report | |
NLS2013031, Inservice Inspection OAR-I Owner'S Activity Report | 27 February 2013 | Inservice Inspection OAR-I Owner'S Activity Report | Through Wall Leak |
NLS2011082, Inservice Inspection Owner'S Activity Report (OAR-1) Owner'S Activity Report | 5 August 2011 | Inservice Inspection Owner'S Activity Report (OAR-1) Owner'S Activity Report | |
NLS2010016, Inservice Inspection OAR-I Owner'S Activity Report for the Fall 2009 Refueling Outage | 2 February 2010 | Inservice Inspection OAR-I Owner'S Activity Report for the Fall 2009 Refueling Outage | Coatings Scram Discharge Volume Moisture barrier |
NLS2009006, 10 CFR 50.55a Request Number RI-21, Revision 0, and Request Number RI-22, Revision 0 | 16 February 2009 | 10 CFR 50.55a Request Number RI-21, Revision 0, and Request Number RI-22, Revision 0 | Dissimilar Metal Weld |
NLS2008065, Inservice Inspection Summary Report for the Spring 2008 Refueling Outage | 14 August 2008 | Inservice Inspection Summary Report for the Spring 2008 Refueling Outage | VT-2 EVT-1 |
NLS2008007, Correction to Inservice Inspection Summary Report | 17 January 2008 | Correction to Inservice Inspection Summary Report | |
NLS2007013, Inservice Inspection Summary Report | 20 February 2007 | Inservice Inspection Summary Report | |
NLS2006064, Response to NRC Request for Additional Information Regarding Relief Request RI-13 for the Fourth 10-Year Inservice Inspection Interval Cooper Nuclear Station | 1 August 2006 | Response to NRC Request for Additional Information Regarding Relief Request RI-13 for the Fourth 10-Year Inservice Inspection Interval Cooper Nuclear Station | |
NLS2006015, 10 CFR 50.55a Requests for Fourth Ten-Year Inservice Inspection Interval | 23 February 2006 | 10 CFR 50.55a Requests for Fourth Ten-Year Inservice Inspection Interval | Internal Flooding Hydrostatic Probabilistic Risk Assessment Nondestructive Examination VT-2 Scram Discharge Volume Large early release frequency Pressure Boundary Leakage Through-Wall Leak |
NLS2005074, Fourth Ten-Year Interval Pump and Valve Inservice Testing Program Relief Requests | 19 October 2005 | Fourth Ten-Year Interval Pump and Valve Inservice Testing Program Relief Requests | Reactor Vessel Water Level Stroke time |
NLS2005086, Inservice Inspection Relief Requests RI-21, Revision 2, and RI-36 and Withdrawal of Relief Request RI-20 | 28 September 2005 | Inservice Inspection Relief Requests RI-21, Revision 2, and RI-36 and Withdrawal of Relief Request RI-20 | |
NLS2005049, Inservice Inspection Summary Report | 16 May 2005 | Inservice Inspection Summary Report | Hydrostatic VT-2 EVT-1 |
NLS2004125, Inservice Inspection Relief Request RI-35 Cooper Nuclear Station | 25 October 2004 | Inservice Inspection Relief Request RI-35 Cooper Nuclear Station | Non-Destructive Examination Weld Overlay Hydrostatic Pressure Boundary Leakage Dissimilar Metal Weld |
NLS2004009, Inservice Inspection Relief Requests PR-03, RC-06, RC-07, R1-17, R1-31, R1-32, and R1-33 | 12 February 2004 | Inservice Inspection Relief Requests PR-03, RC-06, RC-07, R1-17, R1-31, R1-32, and R1-33 | Packing leak Coatings Nondestructive Examination VT-2 |
NLS2003059, Inservice Testing Program Relief Request RP-06, Revision 1 | 19 September 2003 | Inservice Testing Program Relief Request RP-06, Revision 1 | |
NLS2003080, Inservice Inspection (ISI) Summary Report for the Spring 2003 Refueling Outage at Cooper Nuclear Station | 21 July 2003 | Inservice Inspection (ISI) Summary Report for the Spring 2003 Refueling Outage at Cooper Nuclear Station | |
NLS2002111, Inservice Testing Program Relief Request RP-06, RP-07 | 14 November 2002 | Inservice Testing Program Relief Request RP-06, RP-07 | Incorporated by reference |
NLS2002040, Inservice Inspection Summary Report for Cooper Nuclear Station | 28 March 2002 | Inservice Inspection Summary Report for Cooper Nuclear Station | Anchor Darling VT-2 EVT-1 |