ML20217J02413 October 1999Documents 991005 Telcon Between NRC & Util to Address All of Areas Identified in Reg Guide 1.179 & NUREG-1700 Re Final Survey Plan Except for One Area
ML20217N83713 October 1999Forwards Summary of Changes Made to Maine Yankee Defueled Security Plan,Iaw 10CFR50.54(p)(2).Without Encl
ML20217F12612 October 1999Forwards Update to Previously Submitted RELAP5 Analytical Assumptions for App R,Re RAI of 961104Safe Shutdown
BVY-99-130, Provides Clarification of Method for Determining MSIV Maximum & Minimum Pathway at Vermont Yankee Nuclear Power Station8 October 1999Provides Clarification of Method for Determining MSIV Maximum & Minimum Pathway at Vermont Yankee Nuclear Power Station
BVY-99-128, Submits Listed Addl Info in Support of 990414 Request for Clarification to SER Confirming Adequacy of Space Cooling for HPCI & RCIC Sys,Re Item II.K.3.24 of NUREG-0737.Copy of NEDE-24955,encl6 October 1999Submits Listed Addl Info in Support of 990414 Request for Clarification to SER Confirming Adequacy of Space Cooling for HPCI & RCIC Sys,Re Item II.K.3.24 of NUREG-0737.Copy of NEDE-24955,encl
ML20216J35329 September 1999Responds to NRC Re Violations Noted in Insp Rept 50-271/99-12 on 990628-0811.Corrective Actions:Based on RFO 20 Maint Rule Outage Performance Review,Task Was Generated to Clarify & Enhance SD Monitoring ProcessMaintenance Rule Program
BVY-99-122, Notifies of Intention to Reinstate Original Version of App F in FSAR & Correct Docket Re Assumption That Electrical Power Sys Are Designed IAW Requirements of GDC-1728 September 1999Notifies of Intention to Reinstate Original Version of App F in FSAR & Correct Docket Re Assumption That Electrical Power Sys Are Designed IAW Requirements of GDC-17
ML20212M24322 September 1999Expresses Concern Re NRC Consideration of Adoption of Policy Based on Requests from Licensees,To Allow as Part of Decommissioning of Nuclear Power Plants & Demolition of Onsite Structures at Reactor Plant Sites
BVY-99-113, Requests Approval to Perform Alternative Testing to That Specified by ASME Boiler & Pressure Vessel Code,Section XI & Asme/Ansi OM, Operation & Maint of Nuclear Power Plants. Attachment 1 Provides Justification for Alternative Testing21 September 1999Requests Approval to Perform Alternative Testing to That Specified by ASME Boiler & Pressure Vessel Code,Section XI & Asme/Ansi OM, Operation & Maint of Nuclear Power Plants. Attachment 1 Provides Justification for Alternative Testing
BVY-99-116, Informs of Determination That Wh Schulze,License SOP-10528-1,will No Longer Maintain License at Facility. Termination of License Requested21 September 1999Informs of Determination That Wh Schulze,License SOP-10528-1,will No Longer Maintain License at Facility. Termination of License Requested
BVY-99-114, Provides Notification That Licensee Completed Y2K Remediation Efforts Described in Util 990608 Response to NRC GL 98-01,Suppl 121 September 1999Provides Notification That Licensee Completed Y2K Remediation Efforts Described in Util 990608 Response to NRC GL 98-01,Suppl 1
BVY-99-121, Requests Extension Until 990929 to Respond to Violations Noted in Insp Rept 50-271/99-12,dtd 990819.Licensee Did Not Receive Rept Until 990830 & Addl Time Is Needed to Prepare & Allow for Adequate Review of Violation Response Submittal20 September 1999Requests Extension Until 990929 to Respond to Violations Noted in Insp Rept 50-271/99-12,dtd 990819.Licensee Did Not Receive Rept Until 990830 & Addl Time Is Needed to Prepare & Allow for Adequate Review of Violation Response Submittal
BVY-99-115, Forwards non-proprietary & Proprietary Responses to 990714 RAI Re Civil & Mechanical Engineering Considerations for Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355.Proprietary Encls Withheld16 September 1999Forwards non-proprietary & Proprietary Responses to 990714 RAI Re Civil & Mechanical Engineering Considerations for Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355.Proprietary Encls WithheldSafe Shutdown Earthquake
Hydrostatic
Operating Basis Earthquake
Earthquake
BVY-99-118, Responds to RAI Concerning GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions16 September 1999Responds to RAI Concerning GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions
ML20212B70114 September 1999Submits Comments & Raises Questions Re Generation of White Paper for Commission to Decide Merits of Rubberization
ML20211J50031 August 1999Forwards Proposed Rev 29 to Yankee Decomissioning QA Program, for NRC Info & Approval.Yaec Requests That Rev 29, Dtd May 1999 & Originally Transmitted in Be Withdrawn from Further Consideration by NRC Staff
BVY-99-110, Informs of Util Intent to Replace Commitments Made in Licensee & Subsequently Ack in NRC with Containment Insp Criteria Defined in 10CFR50.55a(b)(2)(vi),per Drywell Coating Insp31 August 1999Informs of Util Intent to Replace Commitments Made in Licensee & Subsequently Ack in NRC with Containment Insp Criteria Defined in 10CFR50.55a(b)(2)(vi),per Drywell Coating Insp
BVY-99-111, Informs That Encl TS Bases Page 91 Has Been Revised to Allow Reactivity Anomaly BOC Steady State Core Reactivity to Be Normalized Between off-line Uncorrected Solution & on-line 3D-Monicore Exposure Corrected Solution31 August 1999Informs That Encl TS Bases Page 91 Has Been Revised to Allow Reactivity Anomaly BOC Steady State Core Reactivity to Be Normalized Between off-line Uncorrected Solution & on-line 3D-Monicore Exposure Corrected Solution
ML20212E48427 August 1999Informs That at 990429 Meeting of Myap Community Advisory Panel,R Shadis,Asked If Given Lack of Resident Inspectors & Limited NRC-license Review Correspondence,If Shadis Could Take Part in Weekly NRC Conference Calls with Licensee
ML20216F18926 August 1999Forwards Copies of Maine Yankee & Yankee Rowe Refs Listed, Supporting Industry Position That Branch Technical Position Asb 9-2 Methodology over-estimates Spent Fuel Decay Heat
BVY-99-107, Submits Response to NRC RAI Re Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355 Fuel Assemblies26 August 1999Submits Response to NRC RAI Re Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355 Fuel AssembliesUltimate heat sink
BVY-99-108, Requests That Gv Bogue,Bj Croke,Vs Ferrizzi,Me French, Bk Mcnutt,Jf Meyer & DM Navarro Take BWR Gfes of OL Exam Administered on 991006.DA Daigler & ST Brown Will Have Access to Exams Before Tests Administered19 August 1999Requests That Gv Bogue,Bj Croke,Vs Ferrizzi,Me French, Bk Mcnutt,Jf Meyer & DM Navarro Take BWR Gfes of OL Exam Administered on 991006.DA Daigler & ST Brown Will Have Access to Exams Before Tests AdministeredGeneric Fundamentals Examination
ML20211C05919 August 1999Forwards Addl Justification for Proprietary Request Re 990809 Submittal Info on Maine Yankee License Termination Plan
BVY-99-103, Informs That Util Expects to Submit Approx Twenty Licensing Actions in FY00 & FY01,in Response to Administrative Ltr 99-0218 August 1999Informs That Util Expects to Submit Approx Twenty Licensing Actions in FY00 & FY01,in Response to Administrative Ltr 99-02
ML20212A59816 August 1999Expresses Appreciation for with Respect to e-mail Message Re Site Release Criteria Standards Can Never Be Verified Using Existing DatabaseFuel cladding
ML20210S06210 August 1999Forwards semi-annual fitness-for-duty Program Performance Data for six-month Period of 990101-990630,IAW 10CFR26.71(d)Fitness for Duty
ML20210Q7209 August 1999Forwards non-proprietary & Proprietary Draft Documents Re Info on Myap License Termination Plan & Diskette.Proprietary Info & Diskette Withheld
ML20211D7049 August 1999Forwards Rev 17 of Maine Yankee Defueled Safety Analysis Rept (Dsar), Per 10CFR50.71 & 10CFR50.4
ML20212B2276 August 1999Discusses Concerns Re Recent Incindent Involving Transport of Nuclear Matl from Maine Yankee
ML20210M8175 August 1999Forwards Draft License Termination Plan/Amend Plan for Maine Yankee Atomic Power Co, to Enhance Dialogue Between Various Stakeholders & Provide Springboard for Clarifying Mutual Expectations.With Three Oversize Drawings
ML20210L2212 August 1999Forwards Two Copies of Objectives & Sequence of Events for Maine Yankee Emergency Preparedness Exercise for 990922. Without Encl
BVY-99-100, Forwards Revised Floor Response Spectra Diagrams,Originally Sent as Attachment 1 to Licensee to Nrc.Revised Diagrams Have More Legible Scale Markings2 August 1999Forwards Revised Floor Response Spectra Diagrams,Originally Sent as Attachment 1 to Licensee to Nrc.Revised Diagrams Have More Legible Scale Markings
ML20210M57930 July 1999Responds to NRC 990726 Telcon Re Status of Resolution for USI A-46 Outliers.Written Summary,By Equipment Category, Listed
ML20211E17028 July 1999Forwards Copy of Final Exercise Rept for 990427-29,full- Participation Plume Exposure & Ingestion Pathway Exercise of Offsite Radiological Emergency Response Plans site-specific to VYNPS
ML20210G42727 July 1999Forwards Testing Data & Associated Results for Fitness for Duty Program at Plant for 990101-0630Fitness for Duty
ML20210G50427 July 1999Responds to NRC 990301 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions. Licensee Will Submit Info Re Proposed Sys Mod by 990916
ML20210J30327 July 1999Submits Proposed Changes to Eals.Attachment 1 Provides Listing of Changes to EALs Along with Ref to Bases Documents Supporting ChangeFuel cladding
ML20210F36921 July 1999Submits Response to NRC Request for Clarification of Certain Details of Yaec Proposed Mods to Yankee Nuclear Power Station Defueled TS
ML20216D43119 July 1999Informs That Util Intends to Construct ISFSI Located on Owner Controlled Property Currently Part of Maine Yankee Reactor Site
ML20217M65719 July 1999Expresses Concern Re Verification of Cleanup Stds at Maine Yankee Atomic Power Co Power Station
ML20210C62715 July 1999Forwards Draft Site Characterization Summary in Support of 10CFR50 License Termination & Copy of Latest Decommissioning Schedule with Milestones Identified.Info Submitted Per License Termination Plan
ML20209J06014 July 1999Forwards Rev 11 to Vols 1-10 of State of Nh Radiological Emergency Response Plan & Vols 11-50 to Town Radiological Emergency Response Plans,In Support of Vermont Yankee & Seabrook Station.Vols 17-19 of Were Not Included
ML20209G15312 July 1999Discusses Util Setpoint Control Program Implementation Schedule,As Committed to in Licensee 990514 Response to Notice of Violation,Insp Rept 50-271/97-10Minimum Critical Power Ratio
ML20209D4889 July 1999Forwards Rev 29 to Decommissioning QA Program, for Info & NRC Approval,Iaw 10CFR50.54(a)(3).Attachment a Provides Listing of Changes,But Does Not Discuss All Refomatting, Grammatical,Editorial or Typographical ChangesNondestructive Examination
Condition Adverse to Quality
Liquid penetrant
ML20209C3151 July 1999Forwards Rev 9 to Security Plan,Reflecting Plant Decommissioning Activities & Continues to Provide Protection Against Radiological Sabotage.Rev Withheld
ML20209C3271 July 1999Forwards Rev 2 to Security Training & Qualification Plan.Rev Withheld
ML20209C77330 June 1999Responds to EDO Backfit Appeal Determination Re Emergency Plan Exemptions for Decommissioning PlantsExemption Request
Backfit
ML20210G39830 June 1999Discusses Review of Ltr Re Maine Yankee Backfit Appeal with Respect to Emergency Plan Exemptions for Decommissioning PlantsExemption Request
Backfit
ML20196J23230 June 1999Submits Input from Util Technical Staff Re Soil Disposal on-site Under 10CFR20.2002 & Expresses Interest in Pursuing Approval to Use Same Methodology (Implemented Through Util ODCM & Reported as Noted) If Possible
ML20196J74229 June 1999Informs NRC That Vygs Has Implemented Severe Accident Management,As Committed to in Licensee to NRC