ML20210L436 | 2 August 1999 | Cycle 9 12-Month SG Insp Rept | |
ML20210L445 | 31 July 1999 | Unit-2 Cycle 10 Voltage-Based Repair Criteria 90-Day Rept | |
ML20196H862 | 30 June 1999 | NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data, June 1999 Rept | High Radiation Area Power change |
ML20211F903 | 30 June 1999 | Cycle 9 Refueling Outage | |
ML20206J120 | 30 April 1999 | Redacted ME-98-001-00, Pressure Locking & Thermal Binding Test Program on Two Gate Valves with Limitorque Actuators | |
ML20205B663 | 28 February 1999 | Underground Storage Tank (Ust) Permanent Closure Rept, Sequoyah Nuclear Plant Security Backup DG Ust Sys | |
ML20206T799 | 31 January 1999 | Iodine Revolatizitation in Grand Gulf Loca | |
ML20198S730 | 31 December 1998 | Cycle 10 Voltage-Based Repair Criteria 90-Day Rept | |
ML20155F196 | 1 September 1998 | Engineering Rept for Evaluation of BWR CR Drive Mounting Flange Cap Screw | |
ML20206J127 | 30 April 1998 | Pressure Locking Thrust Evaluation Methodology for Flexible Wedge Gate Valves | FLEX |
ML20199J257 | 31 January 1998 | Cycle 9 Voltage-Based Repair Criteria 90-Day Rept | |
ML20199J244 | 29 January 1998 | Snp Unit 2 Cycle Refueling Outage Oct 1997 | |
L-97-215, SG Secondary Side Loose Object Safety Evaluation | 23 October 1997 | SG Secondary Side Loose Object Safety Evaluation | |
ML20203B959 | 18 September 1997 | Pressure Locking Summary & Evaluations Using Commonwealth Edison Methodology for Sqn | |
ML20210J176 | 31 July 1997 | Unit 1,Cycle 9 Alternate Plugging Criteria 90 Day Rept | Flow Induced Vibration |
ML20138D199 | 4 April 1997 | Special Project97-928S, Sequoyah Nuclear Plant Assessments | |
ML20138A204 | 31 March 1997 | Pre-SALP Rept for SALP Period 960225-970906 | Safe Shutdown Fitness for Duty High Radiation Area Non-Destructive Examination Grab sample Fire Barrier Hydrostatic Probabilistic Risk Assessment Nondestructive Examination Job Performance Measure Foreign Material Exclusion Process Control Program Maintenance Rule Program Downpower |
ML20138C537 | 24 March 1997 | Rev 0 to Pressurizer Level Event | Time of Discovery Scaffolding |
ML20217G240 | 3 March 1997 | Non-proprietary Rev 0 to SE of Reduced Thermal Design Flow | Shutdown Margin Ultimate heat sink Safe Shutdown Earthquake Fuel cladding Flow Induced Vibration Coast down |
ML20199G719 | 28 January 1997 | Rev 0 to Grand Gulf Nuclear Station Engineering Rept GGNS-97-0002 for GL 96-06 Evaluation of Drywall & Containment Penetrations | Finite Element Analysis Earthquake |
ML20117J361 | 1 August 1996 | SE of Safety Valve Setpoint Tolerance Relaxation | Ultimate heat sink Deep Dose Equivalent Fuel cladding |
ML20141A132 | 31 July 1996 | Prediction of Onset of Fission Gas Release from Fuel in Generic Bwr | |
ML20115A585 | 20 June 1996 | GGNS Engineering Rept for Evaluation of Ampacity Deratings for Thermo-Lag Fire Barrier Encl Cables in Fire Areas/Zones OC214,OC302,OC308 & 1A539 | Safe Shutdown Fire Barrier Fire Protection Program |
ML20108D086 | 30 April 1996 | Surveillance Specimen Program Evaluation for Grand Gulf Nuclear Station | |
ML20115A583 | 18 April 1996 | Engineering Rept for Evaluation of Ampacity Deratings for Thermo-Lag Fire Barrier Encl Cables in Fire Areas/Zones OC202,OC402,OC702 & 1A316 | Safe Shutdown Fire Barrier |
ML20117K946 | 5 March 1996 | Reliability Study | |
ML20117K951 | 29 February 1996 | Reliability Common Cause Assessment, for Feb 1996 | |
ML20100J862 | 22 February 1996 | Engineering Rept Safety/Relief Valves Safety Function Lift Setpoint Tolerance Relaxation Summary Rept | Feedwater Controller Failure Fuel cladding |
ML20094M524 | 20 November 1995 | Self Assessment SALP Period 940227-960224 | Fitness for Duty Non-Destructive Examination Grab sample Fire Barrier Missed surveillance Job Performance Measure Foreign Material Exclusion Earthquake Maintenance Rule Program |
ML20095J189 | 5 October 1995 | Design & Analysis of Weld Overlay Repair for Sequoyah Unit 1 CRDM Lower Canopy Seal Welds | Weld Overlay |
ML20081D383 | 12 March 1995 | Simulator Four Yr Test Rept for 950312 | Fuel cladding |
ML20078S135 | 8 February 1995 | SWS Operational Performance Insp (Swsopi) for Ggns | Safe Shutdown Ultimate heat sink Fire Barrier Hydrostatic Emergency Lighting Job Performance Measure Operability Determination Biofouling Through Wall Leak |
ML20083N952 | 16 November 1994 | 10CFR50.59 Rept to Nrc | Safe Shutdown Boric Acid Shutdown Margin High Radiation Area Safe Shutdown Earthquake Operating Basis Earthquake Nondestructive Examination Temporary Modification Condition Adverse to Quality |
ML20072C989 | 30 April 1994 | Survey of Melcor Assessment & Selected Applications, Third Draft | Loop seal Grab sample Hydrostatic Probabilistic Risk Assessment |
ML20063H779 | 31 December 1993 | 1993 Self Assessment | Fitness for Duty Half scram Job Performance Measure Systematic Assessment of Licensee Performance Earthquake Fire Protection Program Downpower |
ML20024H849 | 19 July 1993 | Evaluation of Ultrasonic Test Results from 1993 ISI on Underclad Flaw Indications in Sequoyah,Unit 1 Rv Nozzles. | |
ML20046A260 | 18 June 1993 | Safety Sys Functional Assessment, Low Pressure Core Spray & RCIC Sys. | Reactor Vessel Water Level Stroke time Temporary Modification |
ML18010B084 | 5 May 1993 | NRC Licensing Submittal Review of Licensing Conditions Imposed by NUREG-1216. | Safe Shutdown Boric Acid Shutdown Margin Loop seal Stroke time Temporary Modification Stress corrosion cracking Liquid penetrant Overspeed trip |
ML18010A952 | 30 November 1992 | NRC Licensing Submittal Review of Licensing Conditions Imposed by NUREG-1216. | Nondestructive Examination Liquid penetrant |
ML20116K800 | 13 November 1992 | Quarterly Status Rept for Period Ending 920930, 'Degraded Core Accident Hydrogen Control Program.' | |
ML20118D194 | 21 September 1992 | Technical Rept on Hydrogen Control Measures & Effects of Hydrogen Burns on Safety Equipment | |
ML20114A664 | 15 August 1992 | 920619 Self-Assessment. Several Hardware & Software Enhancements to Emergency Response Ctrs Completed During Reporting Period | Fire Barrier Coatings Condition Adverse to Quality Job Performance Measure Foreign Material Exclusion Systematic Assessment of Licensee Performance Fire Watch Downpower |
ML20095K095 | 30 April 1992 | Resolution of High Groundwater Levels at Grand Gulf Nuclear Station | Hydrostatic |
ML20141M134 | 27 March 1992 | Spent Fuel Pool Mod for Increased Storage Capacity | Operating Basis Earthquake Design basis earthquake Control of Heavy Loads Fuel cladding |
ML20086K474 | 31 October 1991 | Cycle 6 Plant Transient Analysis | Anticipated operational occurrence Feedwater Controller Failure |
ML20086K519 | 31 October 1991 | Nonproprietary Siemens Nuclear Power Corp Grand Gulf Unit 1 Reload XN-1.3,Cycle 4 Mechanical Design Rept Suppl 1 | Anticipated operational occurrence Power change |
ML20086K511 | 31 October 1991 | LOCA Analysis for Single Loop Operation | FLEX Fuel cladding |
ML20086K499 | 31 October 1991 | Cycle 6 Reload Analysis | Anticipated operational occurrence Fuel cladding |
ML20029C346 | 31 March 1991 | Simulator Certification Rept for Grand Gulf Nuclear Station. | |