Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML18016A90112 April 1999Part 21 Rept Re Defect in Component of DSRV-16-4,Enterprise DG Sys.Caused by Potential Problem with Connecting Rod Assemblies Built Since 1986,that Have Been Converted to Use Prestressed Fasteners.Affected Rods Should Be Inspected
ML20207M92312 March 1999Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results
ML20154E21728 September 1998Follow-up Part 21 Rept Re Defect with 1200AC & 1200BC Recorders Built Under Westronics 10CFR50 App B Program. Westronics Has Notified Bvps,Ano & RBS & Is Currently Making Arrangements to Implement Design Mods
ML20236X2355 August 1998Part 21 Rept Re Defect Associated W/Westronics 1200AC & 1200BC Recorders Built Under Westronics 10CFR50,App B Program.Beaver Valley,Arkansas Nuclear One & River Bend Station Notified.Design Mod Is Being Developed
ML20248F35321 May 1998Part 21 Rept Re Electronic Equipment Repaired or Reworked by Integrated Resources,Inc from Approx 930101-980501.Caused by 1 Capacitor in Each Unit Being Installed W/Reverse Polarity. Policy of Second Checking All Capacitors Is Being AdoptedReverse polarity
ML20217D57020 March 1998Part 21 Rept 40 Re Governor Valve Stems Made of Inconel 718 Matl Which Caused Loss of Governor Control.Control Problems Have Been Traced to Valve Stems Mfg by Bw/Ip.Id of Carbon Spacer Should Be Increased to at Least .5005/.5010
ML20203H98912 December 1997Part 21 Rept Re Potential Manufacturing Defect of Enterprise DSR-4 & DSRV-4 Edgs.Cooper Energy Svcs Supplied 1A-7840 Adjusting Screw to Affected Utils & Sites.River Bend Station Replaced W/Acceptable Assemblies
ML20140G4481 May 1997Part 21 Rept Re Potential Defect in Component of Dsrv & Dsr Enterprise Standby Diesel Generator Sys.Recommends That Springs Be Inspected on Periodic Basis,Such as During Refueling Outages
ML20137F32226 March 1997Part 21 Rept Re Perry Nuclear Power Plant Experiencing False Trip of K600S K-Line Low Voltage Circuit Breaker w/SS-5 Solid State Trip Device.Breaker Removed from Svc & Returned to Abb for Analysis
ML20133E8008 January 1997Deficiency Rept Re Nonconformance Related to Masterflow 713 Grout,Which Master Builders,Inc Has Supplied as Nuclear SR Product to 18 Npps.Cause Unknown.Requests That Listed Info Be Provided to Gain Insight as to Scope & Possible Cause
ML20134H3365 November 1996Part 21 Rept Re Defective Inner Thrust Bearing 1801461-01 Used in PSA 35 Mechanical Shock Arrestor Used as Restraint on Piping Sys for Nuclear Generating Plant.Lot of Defective Parts Located & Isolated to Three Customers
ML20115J39822 July 1996Interim Part 21 Rept Re 3/4 Schedule 80 Pipe Furnished to Consolidated Power Supply.Investigation Revealed Only One Nuclear Customer Involved in Sale of Matl
ML20115D2009 July 1996Part 21 Rept Re Mfg Defect of Enterprise DSR-4 & DSRV-4 Edgs,Originally Mfg by Calcon Corp.Amot Control Corp Purchased Calcon Product Line & Maintains Design & Production.Valves Returned to Cooper Energy Svcs on 960131
ML20117G46414 May 1996Part 21 Rept Re Cooper Bessemer Reciprocating Products,Div of Cooper Cameron Corp,Issued Ltr to Define Utils/Plants Containing Similar Equipment as Supplied on Cooper Bessemer Ksv & Enterprise Dsr EDGs
ML20085J65915 June 1995Potential Part 21 Rept Re Failure of Air Cylinder Mfg by Bellofram Corp at Ggns.Failure Discussed W/Mfg & Judged to Be Isolated Incident W/No Further C/A Required at Affected Utils or Cooper-Bessemer
ML20083R91026 April 1995Final Part 21 Rept Re Kepco,Inc Model RMX24-D-20804 Power Supplies in Which Transistors Q15 &/Or Q16 Failed to Open & R1 Was Open.Replacement of Transmitters w/XSIS-095 Along W/ Replacement of Electrolytic Capacitors Provides Solution
ML18038A8977 September 1994Part 21 Rept Re Defect in Latching Mechanism of Potter & Brumfield Relay on C&D High Voltage Shut Down Alarm Assembly Printed Circuit Boards.Pull Test on Relay Reset Button Incorporated Into Receiving Insp Procedures
ML20058K3849 December 1993Part 21 Rept Re Potential Defect in Component of Dsrv & Dsr Enterprise Standby DG Sys,Regarding Potential Problem W/ Subcover Assembled Atop Power Head
ML20059A71819 October 1993Part 21 Rept Re Defective Rocker Arms Supplied to TU & Clei. Rocker Arms Machined & Inspected to Incorrect Print & Discovered at Tu.Defective Rocker Arms Recalled from Nuclear Customers.No Corrective Action Required at Respective Utils
ML20056D70715 July 1993Part 21 Rept Re Reportable defect-75 PSIG Relief Check Valve 1 Npt,Emd 9521844,Kepner 416C-1-75
ML20127H23015 January 1993Part 21 Rept Re Potential Defeat in Component of Dsrv & Dsr Enterprise Standby DG Sys.Starting Air Distributor Housing Assemblies Installed as Replacement Parts at Listed Sites
ML20126B04217 December 1992Final Part 21 Rept Re Potential Problem W/Steel Cylinder Heads.Initially Reported on 921125.Caused by Inadequate Cast Wall Thickness at 3/4-inch-10 Bolt Hole.Stud at Location Indicated on Encl Sketch Should Be RemovedLoctite
ML20125C7167 December 1992Part 21 Rept Re Possibility for Malfunction of Declutching Mechanisms in SMB/SB-000 & SMB/SB/SBD-00 Actuators. Malfunction Only Occurs During Seismic Event.Balanced Levers May Be Purchased from Vendor.List of Affected Utils EnclStroke time
Anchor Darling
ML20127P58623 November 1992Followup to 921005 Part 21 Rept Re Potential Defect in SB/SBD-1 Housing Cover Screws.Procedure Re Replacement of SBD-1 Spring Cover Bolts Encl.All Fasteners Should Be Loosened & Removed.List of Affected Utils Encl
ML20118B43911 September 1992Part 21 Rept Re Degradation in Abb Type 27N Undervoltage Relays Used in Electrical Switchgear.Recommends That Users Review Applications Requiring Exposures Greater than 1E03 Rads TID W/Time Delay Function Option
ML20101R0648 July 1992Part 21 Rept Re Defect in Forged Elbow SA234 Wpc.Initially Reported by Util on 920625.Connex Will Audit Quality Sys Prior to Awarding Purchase Orders to Ram Forge to Verify Measurements Taken on Elbow
PY-CEI-NRR-1518, Corrected Part 21 Rept Re Defects in MSIV Poppets Supplied by Atwood & Morrill Co,Inc,Originally Submitted Via .Corrects Info in Corrective Action Section to Indicate That Poppet S/N 4 Not S/N 3 Installed at Facility1 July 1992Corrected Part 21 Rept Re Defects in MSIV Poppets Supplied by Atwood & Morrill Co,Inc,Originally Submitted Via .Corrects Info in Corrective Action Section to Indicate That Poppet S/N 4 Not S/N 3 Installed at Facility
ML17289A69726 June 1992Amend 1 to Part 21 Rept 158 Re gear-wear Induced Failures in engine-driven Jacket Water Pump in DSRV-16-4 Standby DG Sys. Initially Reported on 911029.Grand Gulf Station Observed Wear Characteristics in as Little as 500 Operating Hours
ML20101H52925 June 1992Part 21 Re Forged Elbow Purchased by Connex Pipe Sys.Elbow Return to Connex to Be Repaired.Elbow Returned to Gulf States Util River Bend Station Unit 1 Along W/Associated Documentation
ML20102B20724 June 1992Part 21 Rept Re Cracking of Stellite 21 Hardfacing on Guide Nose of Poppets Supplied as Part of MSIV Leakage Improvement Mod.Initially Reported by Clei on 920522. Recommends That Liquid Penetrant Exam Be PerformedLiquid penetrant
PY-CEI-NRR-1516, Part 21 Rept Re Defects in MSIV Poppets Supplied by Atwood & Morrill Co,Inc.Intially Reported on 920522.Measures Will Be Established to Ensure That Adequate Repair Methods Are Employed During Future Repairs of Modified MSIV Poppets19 June 1992Part 21 Rept Re Defects in MSIV Poppets Supplied by Atwood & Morrill Co,Inc.Intially Reported on 920522.Measures Will Be Established to Ensure That Adequate Repair Methods Are Employed During Future Repairs of Modified MSIV Poppets
ML20101G92119 June 1992Part 21 Rept Re Rotated Fuel Assemblies Sometimes Inappropriate for Modern Type Fuel Designs.Reevaluation Concluded That Inadvertently Rotated Fuel Assembly for BWR 4/5 C-lattice Plant Could Not Exceed TS Safety Limit MCPR
RBG-37042, Deficiency Rept:Employee Informed NRC of Defect in Forged Replacement Elbow Involving Numerous Areas Where Required Code & Design Min Wall Thickness Was Not Maintained.Licensee Returned Forged Elbow to Supplier18 June 1992Deficiency Rept:Employee Informed NRC of Defect in Forged Replacement Elbow Involving Numerous Areas Where Required Code & Design Min Wall Thickness Was Not Maintained.Licensee Returned Forged Elbow to Supplier
ML20097H15322 May 1992Part 21 Rept Re Defect in MSIV Poppets Supplied to Plant by Atwood & Morrill Co,Inc.Post Weld Heat Treatment Prescribed & Performed for Poppet to Alleviate Concerns Re Residual Stresses Present.Next Rept Will Be Submitted within 30 DaysTime of Discovery
Liquid penetrant
ML20090L88018 March 1992Part 21 Re Cracked Piston Castings Received from Acme Foundry,Fairbanks Morse & General Casting.Magnetic Particle Insp of All Pistons Will Be Performed.List of Affected Plants Encl
ML20094L12713 March 1992Amend 1 to Part 21 Rept 159 Re Potential Defect in Power Cylinder Liner.Initially Reported on 920115.Caused by Liner/ Block Fit & Localized Matl Microstructure.All Drawings & Specs Revised to Address Matl Design Requirements
ML20081F60923 April 1991Part 21 Rept Re Edward Controlled Closure Check Valves & Testable Piston Check Valves Dashplate Bolt Failures Due to Rapid Valve Opening or Impulsive Differential Pressure Surge Across Dashplate.Design Changes Recommended
PY-CEI-NRR-1303, Part 21 Rept Re Finding That Nitrile Rather than Ethylene Propylene Diene Monomer (Epdm) Used as Seal Matl in Several E-sys Hydraulic Snubbers.Proper Seal Matl (Epdm) Used to Rebuild Snubbers & Leaking Valves Repaired4 February 1991Part 21 Rept Re Finding That Nitrile Rather than Ethylene Propylene Diene Monomer (Epdm) Used as Seal Matl in Several E-sys Hydraulic Snubbers.Proper Seal Matl (Epdm) Used to Rebuild Snubbers & Leaking Valves Repaired
ML20065T16619 December 1990Part 21 Rept Re Reportable Event Concerning Chilled Water Sys at Plant.Initially Reported on 901030 & 1130.Util Notified of Results of Evaluation & Reported Addl Details, Per 10CFR50.72
PY-CEI-NRR-1281, Part 21 Rept Re Failure of Several Asco Scram Solenoid Pilot Valves.Initially Reported on 901211.Faulty Valves Limited to Single Production Run.Installed Valves from Subj Production Run Replaced14 December 1990Part 21 Rept Re Failure of Several Asco Scram Solenoid Pilot Valves.Initially Reported on 901211.Faulty Valves Limited to Single Production Run.Installed Valves from Subj Production Run Replaced
ML17262A26230 November 1990Part 21 Rept Re Chilled Water Sys.Initially Reported on 901030.Evaluation of Perry Plant Will Be Sent by 901230
AECM-90-0196, Final Part 21 Rept Re Automatic Switch Co MSIVs Failing to Close Upon Demand from Automatic & Remote Manual Actuation Signals.Initially Reported on 890914.Dual Solenoid Valves Replaced W/Two Single Solenoid Valves21 November 1990Final Part 21 Rept Re Automatic Switch Co MSIVs Failing to Close Upon Demand from Automatic & Remote Manual Actuation Signals.Initially Reported on 890914.Dual Solenoid Valves Replaced W/Two Single Solenoid Valves
ML20043F3438 June 1990Part 21 Rept Re Circumferential Grove of Varying Depth Up to 0.200 Inches on Inside Surface of Journal Above Attachment Weld to Impeller.Failure of Journal Could Result in Major Damage to Pump.Disassembly Scheduled Over Next 18 Months
ML20043G76422 May 1990Part 21 Rept Re Potential Defect W/Speed Transmitter in Diesel Engine Control Panel of Dsrv Standby Diesel Generator.Estimate of Completion of Corrective Actions Not Possible,Since Correction Made by Other CompaniesOverspeed trip
ML20043A60927 April 1990Part 21 Rept Re Defective Axial Cracks in Pump Shaft in Region Immediately Above Impeller & in Reactor Recirculation Pumps.Probably Caused by Crack Growth as Thermal Fatigue. Technical Advisory Bulletin Will Be Sent to Each Util
ML20011F59722 February 1990Part 21 Rept Re Solder Connections in Abb 27/59 Relays Deteriorated Due to Thermal Stress,Causing Bonding of Printed Wiring Pattern to Glass Epoxy Circuit Board.Interim Circuit Board W/Larger Pads & Higher Wattage Will Be Used
ML20011F19422 February 1990Part 21 Rept Re Abb 27/59 Relay Catalog Series 211L.Solder Connections to Printed Wiring Runs on Bottom of Circuit Board Deteriorated Due to Thermal Stress.No Actual Failure Occurred & Relays to Be Changed at Next Outage
ML20005G6835 January 1990Part 21 Rept Re Installation Instructions for Grommet Use Range for Patel Conduit Seal P/N 841206.Conduit Seals in Environ Qualification Applications Inspected for Proper Wire Use Range & Grommets Replaced
ML19332E29722 November 1989Revised Part 21 Rept Re MSIV Failure to Close Due to Disk Matl for Dual Solenoid Valve Extruding Into Exhaust Port of Valve.Initially Reported on 890914.Dual Solenoid Valve Replaced or Refurbished Prior to Restart
ML19325E72720 October 1989Part 21 Rept Re Defect in Eight GE Type CR 2940 Control Switches at Plant.Initial Condition Found on 890930.Contacts 3 & 4 for All Switches in Plant Sys Verified to Be in Correct Position for Intended Application